Project risk management:
                        why not favour schedule based assessment?

                                What is Scheduled FMEA?
    •   Originally introduced by Renault under the French name of AMDEC Planning (Bensoussan,
        early 90s), its purpose is to gather technical and non technical project team members around
        the same decision model. Time to market was already very critical in the automotive industry.
        If it is important to your project as well (penalties, missed sales, etc.) think of it!
    •   It considers that a schedule is a system1 made of tasks and dependencies. As such it must be
        reliable (e.g. close to existing benchmarked experience) and maintainable (e.g. resilience to
        re-baselining) in all the three dimensions:
               o Inherent or embedded: is the element ‘self supporting’?
               o Logistic: is the way the element has been designed/defined based on real experience
                   and objective enough to be considered as ‘safe’?
               o Propagation: in case of failure of the element, how far or quick other key points of the
                   schedule will be affected?
    •   It transfers the discipline of FME(C)A, a very popular technique in the car industry for
        addressing technical risks, to the body of knowledge of project management.

                   What are the benefits of Scheduled FMEA?

    •   Uses the clear structure of the project network to systematically identify risk
    •   Helps asking unpleasant questions up-front:
             o Politically correct task durations
             o Irrelevant decomposition of W/P into tasks or activities
             o Disagreement or ignorance of inputs-ouputs chains2
             o Skills of selected operators
    •   Promotes a more robust way to consolidate schedule impact of risks and opportunities
    •   Facilitates the involvement of all stakeholders as each participant thinks first of his part of the
        job, before questioning the quality or in-time delivery of inputs
    •   Assessment sessions can be arranged according to the usual clusters of the organisation:
        resource-based, time-frame based, expertise-based, etc.
    •   No duplication of effort with the project risk register
    •   An interesting preliminary step that speeds up Monte Carlo simulation


                                               Issues:

    •   Like FMEA, could be time consuming as it is based on a systematic questioning of tasks,
        links, competence of resources
    •   Avoid paralysis by analysis: rely on assessment of operations
    •   Do not create unnecessary conflict with operations: the project schedule does not reinvent or
        describe everything they do!
    •   Many topics are generic to the usual architecture of projects in your organisation. Replace
        thorough analysis by a sanity check wherever possible!
    •   Once the discipline is understood, it is easily supported by spreadsheets…and still robust


                                    How to implement it:
    •   Contributors individually think about their portion of the project work (in between major
        milestones they are responsible for)

1
  2 basic characteristics: the whole is more than the sum of its parts; an assembly of elements with a
purpose
2
  Remember RACI or LCR matrix that deal with this topic as well


© Marc Desrumaux www.d-rix.fr                                                                5 mars 2010
•   With reference to the coding system of tasks and dependencies, they use a FMEA-like
        register to record uncertainties
    •   The project risk management plan defines the weighting system to use for reliability and
        maintainability on one hand3, for inherent, logistic and propagation on the other hand
    •   Each dimension is rated by the contributor on a 1 to 4 scale. Numbers are then multiplied or
        added and a path or milestone rating can be computed.
    •   You can easily compare the rating of important elements with the float at design
        protective/preventive actions




                                    Reliability                                                 Maintainability
                     Inherent          Logistic         Propagation           Inherent              Logistic          Propagation
                  Is content        Any functional      Validation of       Are tasks            Extra resources     Effectiveness of
                  known or          analysis report     inputs?             modular or           available?          fall back
                  understood?       to qualify                              tailored?                                solutions
Tasks                               requirement?
                  Are all           What about          RAM and             Is content           Work                Flexibility of QCT
                  necessary         work loads?         competencies        negotiated?          authorisation       objectives?
                  tasks for W/P                         of                  Agreed?              System
                  included?                             stakeholders?
                  Are task          Availability of     Process to                                                   Can content be
                  owners            resources?          detect/                                                      re-negotiated?
                  capable?                              anticipate
                                                        changes?
                  Did we do it      Candidness of       Is early start of   flexibility level    Triggering          Re-baselining
                  that way          information?        tasks possible?     of content           counter actions     procedures
                  before?                                                                        to warnings
Dependencies      buffer or         Process flows       Early warnings?     schedule             Variance            Buffer
                  padding           known/ mature?      Dash boards?        elasticity           analysis            consumption?
                  included?                                                                      procedures
                  Contracts         Communication       Contingency         Fall back            Exception           Flexibility of
                  inputs-outputs,   channels:           reserves            positions            (crisis)            partnerships
                  incl’d?           effective, clear?                                            procedures
                                                        Work around or                                               Reserve & buffer
                                                        contingency                                                  Management
                                                        plans?




3
  For example reliability factor is 2 ; maintainability is 1 ; inherent 3, logistic 2, propagation 1. It would
mean that the project team favours more a robust schedule than a flexible one and that reference to
past experience is more important than resilience to failure of an element. Assume a given task gets
the respective scores of TRI=2; TRL=4; TRP=1; TMI=4; TML=1:TMP=2.The overall rating of the task will be
(2x3 + 4x2+ 1x1)x2 + (4x3 + 1x2 + 2x1)x1= 46. Rating of paths incorporate rating of dependencies.


© Marc Desrumaux www.d-rix.fr                                                                                      5 mars 2010
© Marc Desrumaux www.d-rix.fr   5 mars 2010

More Related Content

What's hot

Lengyel.david
Lengyel.davidLengyel.david
Lengyel.david
NASAPMC
 
Dan galorath
Dan galorathDan galorath
Dan galorath
NASAPMC
 
Doug brown
Doug brownDoug brown
Doug brown
NASAPMC
 
Jim.free
Jim.freeJim.free
Jim.free
NASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
NASAPMC
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
NASAPMC
 
Return on Investment for a Design for Reliability Program
Return on Investment for a Design for Reliability ProgramReturn on Investment for a Design for Reliability Program
Return on Investment for a Design for Reliability Program
Accendo Reliability
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
NASAPMC
 
Nichols.hornback.moses
Nichols.hornback.mosesNichols.hornback.moses
Nichols.hornback.moses
NASAPMC
 
Harvey elliott
Harvey elliottHarvey elliott
Harvey elliott
NASAPMC
 
Homayoon.dezfuli
Homayoon.dezfuliHomayoon.dezfuli
Homayoon.dezfuli
NASAPMC
 
gtnews TMS Buyers Guide
gtnews TMS Buyers Guidegtnews TMS Buyers Guide
gtnews TMS Buyers Guide
benpoolewriter
 
Rhodes.donna
Rhodes.donnaRhodes.donna
Rhodes.donna
NASAPMC
 
A Brief Introduction to the SCRUM Agile Methodology
A Brief Introduction to the SCRUM Agile MethodologyA Brief Introduction to the SCRUM Agile Methodology
A Brief Introduction to the SCRUM Agile Methodology
Taha Kass-Hout, MD, MS
 

What's hot (20)

Quantitative Risk Analysis - Preventing Project cost escalation
Quantitative Risk Analysis - Preventing Project cost escalationQuantitative Risk Analysis - Preventing Project cost escalation
Quantitative Risk Analysis - Preventing Project cost escalation
 
Lengyel.david
Lengyel.davidLengyel.david
Lengyel.david
 
Dan galorath
Dan galorathDan galorath
Dan galorath
 
Symons
SymonsSymons
Symons
 
CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...
CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...
CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...
 
Doug brown
Doug brownDoug brown
Doug brown
 
Jim.free
Jim.freeJim.free
Jim.free
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
IT GOVERNANCE CONSULTING
IT GOVERNANCE CONSULTINGIT GOVERNANCE CONSULTING
IT GOVERNANCE CONSULTING
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
 
Return on Investment for a Design for Reliability Program
Return on Investment for a Design for Reliability ProgramReturn on Investment for a Design for Reliability Program
Return on Investment for a Design for Reliability Program
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Nichols.hornback.moses
Nichols.hornback.mosesNichols.hornback.moses
Nichols.hornback.moses
 
Harvey elliott
Harvey elliottHarvey elliott
Harvey elliott
 
Macrosolutions Consulting Service: Applying Quantitative Methods and Risks Si...
Macrosolutions Consulting Service: Applying Quantitative Methods and Risks Si...Macrosolutions Consulting Service: Applying Quantitative Methods and Risks Si...
Macrosolutions Consulting Service: Applying Quantitative Methods and Risks Si...
 
Homayoon.dezfuli
Homayoon.dezfuliHomayoon.dezfuli
Homayoon.dezfuli
 
gtnews TMS Buyers Guide
gtnews TMS Buyers Guidegtnews TMS Buyers Guide
gtnews TMS Buyers Guide
 
Macrosolutions Consulting Service: Structuring the Risks Management Processes
Macrosolutions Consulting Service: Structuring the Risks Management ProcessesMacrosolutions Consulting Service: Structuring the Risks Management Processes
Macrosolutions Consulting Service: Structuring the Risks Management Processes
 
Rhodes.donna
Rhodes.donnaRhodes.donna
Rhodes.donna
 
A Brief Introduction to the SCRUM Agile Methodology
A Brief Introduction to the SCRUM Agile MethodologyA Brief Introduction to the SCRUM Agile Methodology
A Brief Introduction to the SCRUM Agile Methodology
 

Viewers also liked

Predicting Trends in Preventive Care Service Utilization Impacting Cardiovasc...
Predicting Trends in Preventive Care Service Utilization Impacting Cardiovasc...Predicting Trends in Preventive Care Service Utilization Impacting Cardiovasc...
Predicting Trends in Preventive Care Service Utilization Impacting Cardiovasc...
gpartha85
 
Divorzio 12 maggio alessandra moretti
Divorzio 12 maggio alessandra morettiDivorzio 12 maggio alessandra moretti
Divorzio 12 maggio alessandra moretti
Rita Ghedini
 
Prevention ppt
Prevention pptPrevention ppt
Prevention ppt
Sandhya M
 

Viewers also liked (10)

Predicting Trends in Preventive Care Service Utilization Impacting Cardiovasc...
Predicting Trends in Preventive Care Service Utilization Impacting Cardiovasc...Predicting Trends in Preventive Care Service Utilization Impacting Cardiovasc...
Predicting Trends in Preventive Care Service Utilization Impacting Cardiovasc...
 
Divorzio 12 maggio alessandra moretti
Divorzio 12 maggio alessandra morettiDivorzio 12 maggio alessandra moretti
Divorzio 12 maggio alessandra moretti
 
Preventive Knee Care Tips
Preventive Knee Care Tips Preventive Knee Care Tips
Preventive Knee Care Tips
 
Preventive Care
Preventive CarePreventive Care
Preventive Care
 
Preventive Care
Preventive CarePreventive Care
Preventive Care
 
Health prevention model
Health prevention modelHealth prevention model
Health prevention model
 
Level of prevention
Level of preventionLevel of prevention
Level of prevention
 
Preventive health care for women ppt
Preventive health care for women pptPreventive health care for women ppt
Preventive health care for women ppt
 
Prevention ppt
Prevention pptPrevention ppt
Prevention ppt
 
From Problems to Preventive Care
From Problems to Preventive CareFrom Problems to Preventive Care
From Problems to Preventive Care
 

Similar to Ft Amdec Planning

Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdfPrimavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
InSync2011
 
Lengyel dave
Lengyel daveLengyel dave
Lengyel dave
NASAPMC
 
Project management
Project managementProject management
Project management
Sameer Kumar
 
An Inside Look At Extreme Programming Essay
An Inside Look At Extreme Programming EssayAn Inside Look At Extreme Programming Essay
An Inside Look At Extreme Programming Essay
Sharon Roberts
 

Similar to Ft Amdec Planning (20)

Dec 2012 Evening Talk - Managing Complex Project
Dec 2012 Evening Talk - Managing Complex ProjectDec 2012 Evening Talk - Managing Complex Project
Dec 2012 Evening Talk - Managing Complex Project
 
Agile Intro for FCL
Agile Intro for FCLAgile Intro for FCL
Agile Intro for FCL
 
You don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pmYou don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pm
 
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdfPrimavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
 
Biju 2008 Pmi Whitepaper
Biju 2008 Pmi WhitepaperBiju 2008 Pmi Whitepaper
Biju 2008 Pmi Whitepaper
 
Lengyel dave
Lengyel daveLengyel dave
Lengyel dave
 
Project management
Project managementProject management
Project management
 
Agile Project Management
Agile Project Management Agile Project Management
Agile Project Management
 
Ohsms geotech risk_acg_fillseminar_june2013_alexatkins
Ohsms geotech risk_acg_fillseminar_june2013_alexatkinsOhsms geotech risk_acg_fillseminar_june2013_alexatkins
Ohsms geotech risk_acg_fillseminar_june2013_alexatkins
 
Disciplined Agile Delivery: An Introduction
Disciplined Agile Delivery: An IntroductionDisciplined Agile Delivery: An Introduction
Disciplined Agile Delivery: An Introduction
 
MCP1
MCP1MCP1
MCP1
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 
Jharna Software
Jharna SoftwareJharna Software
Jharna Software
 
Erp
ErpErp
Erp
 
An Inside Look At Extreme Programming Essay
An Inside Look At Extreme Programming EssayAn Inside Look At Extreme Programming Essay
An Inside Look At Extreme Programming Essay
 
How to choose and implement wms
How to choose and implement wmsHow to choose and implement wms
How to choose and implement wms
 
Fear and Loathing in Agility: Long Live the Accounting Department
Fear and Loathing in Agility: Long Live the Accounting DepartmentFear and Loathing in Agility: Long Live the Accounting Department
Fear and Loathing in Agility: Long Live the Accounting Department
 
Agile Project Management Methods of IT Projects
Agile Project Management Methods of IT ProjectsAgile Project Management Methods of IT Projects
Agile Project Management Methods of IT Projects
 
Agile - Agile Software Project Management Methodologies
Agile - Agile Software Project Management MethodologiesAgile - Agile Software Project Management Methodologies
Agile - Agile Software Project Management Methodologies
 
Asset Finance Agile Projects
Asset Finance Agile ProjectsAsset Finance Agile Projects
Asset Finance Agile Projects
 

Recently uploaded

anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 

Recently uploaded (20)

The Inspiring Personality To Watch In 2024.pdf
The Inspiring Personality To Watch In 2024.pdfThe Inspiring Personality To Watch In 2024.pdf
The Inspiring Personality To Watch In 2024.pdf
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Falcon Invoice Discounting Setup for Small Businesses
Falcon Invoice Discounting Setup for Small BusinessesFalcon Invoice Discounting Setup for Small Businesses
Falcon Invoice Discounting Setup for Small Businesses
 
12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf
12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf
12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf
 
Did Paul Haggis Ever Win an Oscar for Best Filmmaker
Did Paul Haggis Ever Win an Oscar for Best FilmmakerDid Paul Haggis Ever Win an Oscar for Best Filmmaker
Did Paul Haggis Ever Win an Oscar for Best Filmmaker
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
Easy Way to Download and Set Up Gen TDS Software on Your Computer
Easy Way to Download and Set Up Gen TDS Software on Your ComputerEasy Way to Download and Set Up Gen TDS Software on Your Computer
Easy Way to Download and Set Up Gen TDS Software on Your Computer
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
Understanding UAE Labour Law: Key Points for Employers and Employees
Understanding UAE Labour Law: Key Points for Employers and EmployeesUnderstanding UAE Labour Law: Key Points for Employers and Employees
Understanding UAE Labour Law: Key Points for Employers and Employees
 
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Team-Spandex-Northern University-CS1035.
Team-Spandex-Northern University-CS1035.Team-Spandex-Northern University-CS1035.
Team-Spandex-Northern University-CS1035.
 
USA classified ads posting – best classified sites in usa.pdf
USA classified ads posting – best classified sites in usa.pdfUSA classified ads posting – best classified sites in usa.pdf
USA classified ads posting – best classified sites in usa.pdf
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Special Purpose Vehicle (Purpose, Formation & examples)
Special Purpose Vehicle (Purpose, Formation & examples)Special Purpose Vehicle (Purpose, Formation & examples)
Special Purpose Vehicle (Purpose, Formation & examples)
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
India’s Recommended Women Surgeons to Watch in 2024.pdf
India’s Recommended Women Surgeons to Watch in 2024.pdfIndia’s Recommended Women Surgeons to Watch in 2024.pdf
India’s Recommended Women Surgeons to Watch in 2024.pdf
 

Ft Amdec Planning

  • 1. Project risk management: why not favour schedule based assessment? What is Scheduled FMEA? • Originally introduced by Renault under the French name of AMDEC Planning (Bensoussan, early 90s), its purpose is to gather technical and non technical project team members around the same decision model. Time to market was already very critical in the automotive industry. If it is important to your project as well (penalties, missed sales, etc.) think of it! • It considers that a schedule is a system1 made of tasks and dependencies. As such it must be reliable (e.g. close to existing benchmarked experience) and maintainable (e.g. resilience to re-baselining) in all the three dimensions: o Inherent or embedded: is the element ‘self supporting’? o Logistic: is the way the element has been designed/defined based on real experience and objective enough to be considered as ‘safe’? o Propagation: in case of failure of the element, how far or quick other key points of the schedule will be affected? • It transfers the discipline of FME(C)A, a very popular technique in the car industry for addressing technical risks, to the body of knowledge of project management. What are the benefits of Scheduled FMEA? • Uses the clear structure of the project network to systematically identify risk • Helps asking unpleasant questions up-front: o Politically correct task durations o Irrelevant decomposition of W/P into tasks or activities o Disagreement or ignorance of inputs-ouputs chains2 o Skills of selected operators • Promotes a more robust way to consolidate schedule impact of risks and opportunities • Facilitates the involvement of all stakeholders as each participant thinks first of his part of the job, before questioning the quality or in-time delivery of inputs • Assessment sessions can be arranged according to the usual clusters of the organisation: resource-based, time-frame based, expertise-based, etc. • No duplication of effort with the project risk register • An interesting preliminary step that speeds up Monte Carlo simulation Issues: • Like FMEA, could be time consuming as it is based on a systematic questioning of tasks, links, competence of resources • Avoid paralysis by analysis: rely on assessment of operations • Do not create unnecessary conflict with operations: the project schedule does not reinvent or describe everything they do! • Many topics are generic to the usual architecture of projects in your organisation. Replace thorough analysis by a sanity check wherever possible! • Once the discipline is understood, it is easily supported by spreadsheets…and still robust How to implement it: • Contributors individually think about their portion of the project work (in between major milestones they are responsible for) 1 2 basic characteristics: the whole is more than the sum of its parts; an assembly of elements with a purpose 2 Remember RACI or LCR matrix that deal with this topic as well © Marc Desrumaux www.d-rix.fr 5 mars 2010
  • 2. With reference to the coding system of tasks and dependencies, they use a FMEA-like register to record uncertainties • The project risk management plan defines the weighting system to use for reliability and maintainability on one hand3, for inherent, logistic and propagation on the other hand • Each dimension is rated by the contributor on a 1 to 4 scale. Numbers are then multiplied or added and a path or milestone rating can be computed. • You can easily compare the rating of important elements with the float at design protective/preventive actions Reliability Maintainability Inherent Logistic Propagation Inherent Logistic Propagation Is content Any functional Validation of Are tasks Extra resources Effectiveness of known or analysis report inputs? modular or available? fall back understood? to qualify tailored? solutions Tasks requirement? Are all What about RAM and Is content Work Flexibility of QCT necessary work loads? competencies negotiated? authorisation objectives? tasks for W/P of Agreed? System included? stakeholders? Are task Availability of Process to Can content be owners resources? detect/ re-negotiated? capable? anticipate changes? Did we do it Candidness of Is early start of flexibility level Triggering Re-baselining that way information? tasks possible? of content counter actions procedures before? to warnings Dependencies buffer or Process flows Early warnings? schedule Variance Buffer padding known/ mature? Dash boards? elasticity analysis consumption? included? procedures Contracts Communication Contingency Fall back Exception Flexibility of inputs-outputs, channels: reserves positions (crisis) partnerships incl’d? effective, clear? procedures Work around or Reserve & buffer contingency Management plans? 3 For example reliability factor is 2 ; maintainability is 1 ; inherent 3, logistic 2, propagation 1. It would mean that the project team favours more a robust schedule than a flexible one and that reference to past experience is more important than resilience to failure of an element. Assume a given task gets the respective scores of TRI=2; TRL=4; TRP=1; TMI=4; TML=1:TMP=2.The overall rating of the task will be (2x3 + 4x2+ 1x1)x2 + (4x3 + 1x2 + 2x1)x1= 46. Rating of paths incorporate rating of dependencies. © Marc Desrumaux www.d-rix.fr 5 mars 2010
  • 3. © Marc Desrumaux www.d-rix.fr 5 mars 2010