Which document describes how to create the WBS?
A. Project scope statement
B. Requirements traceability matrix
C. Scope management plan
D. Requirements management plan
HINT: Notice that only the project management plan provides
such guidelines.
QUESTION:
The correct answer is C.
Scope management plan
Correct. The scope management plan is a component of the project or
program management plan that describes how the scope will be
defined, developed, monitored, controlled, and verified.
The scope management plan specifies how to create the work
breakdown structure (WBS) from the detailed project scope statement
and how the WBS will be maintained and approved.
ANSWER:
All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.
We are a Project Management Institute (PMI)® Registered Education Provider.

Free CAPM® Exam Sample Question

  • 1.
    CAPM Exam Sample Q& A PMI®, PMP®, CAPM®, and PMBOK® Guide are trademarks of the Project Management Institute, Inc.PMI® has not endorsed and did not participate in the development of our products. OSP International LLC has been reviewed and approved by the PMI® Authorized Training Partner Program.Copyright 2020 OSP International LLC. All Rights Reserved.
  • 2.
    Which document describeshow to create the WBS? A. Project scope statement B. Requirements traceability matrix C. Scope management plan D. Requirements management plan HINT: Notice that only the project management plan provides such guidelines. QUESTION:
  • 3.
    The correct answeris C. Scope management plan Correct. The scope management plan is a component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and verified. The scope management plan specifies how to create the work breakdown structure (WBS) from the detailed project scope statement and how the WBS will be maintained and approved. ANSWER:
  • 4.
    All our questionsare updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a Project Management Institute (PMI)® Registered Education Provider.