The document outlines the process for applying for building plan approval in these steps: 1) A consultant submits building plans to the local authority which checks that basic requirements are met. 2) If requirements are not met, a letter is issued; if met, the application is processed. 3) Plans are circulated to relevant departments for comments. 4) Plans are checked for compliance and may be referred to a committee; otherwise approval is granted and the consultant collects the approved plans.