Gas Treatment Plant
Team Alpha
Kyle Soumar
Stephanie Sampra
Chris Drouganis
Mariam Buari
Mentor: Jerry Palmer
Outline
1. Purpose
2. Objective
3. Design Basis
o Composition
o Simple One Block Flow Diagram
o Product Specifications
4. Overall Block Flow Diagram
5. Individual Processes
6. Economics
o Capital Cost/Total Installation cost
o Revenues
o Expenses
7. Constraints
o Safety Risks Mitigation
o Environmental Risk Mitigation
8. Recommendations
9. Outlook
10. Q & A
Purpose: What is Shale Gas?
● Energy independence
● Cleaner than coal or oil.
● Lower greenhouse gas
emissions.
It is natural gas trapped within shale formations.
Importance
Objective
● Process raw shale gas.
● Produce compressed natural gas.
● Supply methane for Ammonia Plant, Air Separations
and Syngas Plant, the Direct Iron Reduction Plant, and
Combined Heat/Power plant.
● Produce liquefied natural gas (LNG)
● Separate natural gas liquids (NGL) for market.
Block Flow Diagram
Design Basis: Raw Gas
Composition
Bakken-Rich Gas Composition
Component Mol%
H2O(Water) 0.02
N2 (Nitrogen) 5.21
CO2 (Carbon Dioxide) 0.57
H2S (Hydrogen Sulfide) 0.01 (100ppm)
C1 (Methane) 57.67
C2 (Ethane) 19.94
C3 (Propane) 11.33
I-C4 (Isobutane) 0.97
N-C4 (N-butane) 2.83
C5+ (Pentanes) 0.91
Feed Specifications
Flow Rate 310 MMSCFD
Temperature 200 F
Pressure 800 PSIg
Design Basis: Product
Specifications
Treated Natural Gas
Component Mol%
H2O 0.00
N2 4.00
CO2 0.02
H2S (Hydrogen Sulfide) (6.05 PPB)
C1 (Methane) 94.5
C2 (Ethane) 0.77
C3 (Propane) 0.00
C4 (butanes) 0.00
C5+ (Pentanes) 0.00
Production Rates
Ammonia Plant 19.13 MMSCFD
Syngas Plant 42.16 MMSCFD
Midrex Plant 19.58 MMSCFD
CHP facility 50.00 MMSCFD
Pipeline 2.70 MMSCFD
NGL 57233.4 BBL/D
LNG 16335.44 BBL/D
Sulfur Cake 60 LB/HR
Overall Block Flow Diagram
Gas Receiving
Major equipment: 3 horizontal knock out tanks.
Purpose:
●To protect against liquid surges from well
head.
●To remove liquids that will condense at high
temperature and low pressure.
●Ensures gas pressure nominal for process.
Sour Gas Treatment
Two-Step Process for Complete SOur Gas Treatment
MDEA Treatment
-Selectional removal of H2S and CO2
-Achieves H2S content to 1 ppm in sweetened gas stream
-Most economically viable option for design basis of gas feed flow rate
LO-CAT II Sulfur Production
-Cost effective solution for Hydrogen Sulfide
-Reduces H2S to a 60 wt% cake of elemental sulfur
-Revenues of approximately $25,000/year
-Low operating costs compared to other processes
-Effective way to handle H2S
-LO-CAT catalyst solution is corrosion resistant and recycled
Dehydration
Lean Gas Absorption
-TEG dehydration
-Glycol is cost effective
- Achieves water content down to 10 ppmv
-Glycol can be replaced continuously
-Does not remove CO2
Adsorption
-Mole sieve dehydration
-Adsorbent like molecular sieves are expensive
-Achieves water content to as low as 0.1ppmv
-Multiple adsorption beds are required for continuous use
-Removes C02
Membrane
-Yields water content between 20-100 ppmv
-Removes CO2
Demethanization
Mechanical Refrigeration Plant:
- limited to -24 to -40 F
- only 60% propane
Lean oil absorption:
- 40% ethane
- 90% propane
- 100% heavier hydrocarbons
- Heating and cooling required
- High operating cost
Turboexpander:
- 60-90% ethane
- 90-98% propane
-100% of heavier hydrocarbons
● Since high percent ethane recovery is required, this is the most
economical method
Heavy Hydrocarbon
Stabilization
Natural gas liquids have to be stabilized to a
point that it can be stored and transported
in low-pressurized vessels.
Enhances the safety in handling, and
improving the liquid's marketability.
Stabilizing the liquid reduces the volatility.
Nitrogen Rejection
Cryogenic Distillation
Requires flow rates <50 MMSCFD
Best recovery rate
Highest purity product
Most benefits from economy of scale
Pressure Swing Adsorption
Second Most Commonly used NRU
Not scalable economically above 50 MMscfd
High Compression Costs at high flow rates
Sorbent must be replaced every 3-years
Membrane Separation
Applicable up to 100 MMSCFD
Most widely applied below 10 MMscfd
Because of limitations of membrane size
scalability becomes difficult at very high flow
rates
Compression costs become very high above 100
MMscfd
Lower recovery rate can affect plant economics
Must replace membranes every 3-years
At this stage of analysis cryogenic distillation has been selected for its
● high recovery and high purity of product (Nitrogen stream contains 3 wt% methane)
o Literature suggests nitrogen stream can contain as low as 0.5 wt% methane.
● Ability to liquefy natural gas for LNG production.
● Scalable to high flow rates
● Chiller supplies additional cooling to demethanizer feed
Its recommend that further analysis go into other processes constraints on nitrogen content and then re-
examine the need for such a high amount of gas upgrading.
LNG Production
Major equipment:
Joule-Thomson valve and flash drum.
Purpose:
●To simply and efficiently produce liquefied
natural gas for sale.
Plant Layout
Economics
Revenues
Pipeline Gas $4,400,000
NGL $224,533,762
LNG $88,300,000
Sulfur Cake $23,547
Total $317,257,309
Operating Costs
Salaries and fringes $10,500,000
Maintenance (3% of TIC) $4,332,002
Wellhead Gas $379,000,000
sorbents $525,714
MDEA $500,000
Total $394,857,716
Total Installation Cost
Total Equipment Cost $41,257,159
Total Installed Cost $144,400,056
Constraints
• Issues include highly pressurized vessels, high temperatures,cryogenic
temperatures, poisonous by-products.
• Pressure relief valves would be installed on all pressure vessels to
direct excess gases to the flare.
• Safety training for operators working around high or low temperature
equipment, as well as proper insulation of equipment.
• Hydrogen sulfide, which is very toxic, is immediately converted to an
inert sulfur cake.
•Hydrogen sulfide has a LD50 of 600 PPM / 30 minutes
Recommendations
It's recommend that this plant go forward
1.It is an essential for supplying large
quantities of gas for other processes within
the complex.
2.Offers some flexibility in products being
produced.
Future Outlook: NGL Stabilization Economics
Gate 2 possibility:
Separation of individual Hydrocarbons for
revenue.
Assuming 17 year life
No inflation accounted for
Additional
Capital Cost
Additional
Revenue
Additional
Operating
Cost
NPV
Fractionation $33,000,000 $195,000,000 $4,941,000 $814,000,000
Q & A

Final Presentation

  • 1.
    Gas Treatment Plant TeamAlpha Kyle Soumar Stephanie Sampra Chris Drouganis Mariam Buari Mentor: Jerry Palmer
  • 2.
    Outline 1. Purpose 2. Objective 3.Design Basis o Composition o Simple One Block Flow Diagram o Product Specifications 4. Overall Block Flow Diagram 5. Individual Processes 6. Economics o Capital Cost/Total Installation cost o Revenues o Expenses 7. Constraints o Safety Risks Mitigation o Environmental Risk Mitigation 8. Recommendations 9. Outlook 10. Q & A
  • 3.
    Purpose: What isShale Gas? ● Energy independence ● Cleaner than coal or oil. ● Lower greenhouse gas emissions. It is natural gas trapped within shale formations. Importance
  • 4.
    Objective ● Process rawshale gas. ● Produce compressed natural gas. ● Supply methane for Ammonia Plant, Air Separations and Syngas Plant, the Direct Iron Reduction Plant, and Combined Heat/Power plant. ● Produce liquefied natural gas (LNG) ● Separate natural gas liquids (NGL) for market.
  • 5.
  • 6.
    Design Basis: RawGas Composition Bakken-Rich Gas Composition Component Mol% H2O(Water) 0.02 N2 (Nitrogen) 5.21 CO2 (Carbon Dioxide) 0.57 H2S (Hydrogen Sulfide) 0.01 (100ppm) C1 (Methane) 57.67 C2 (Ethane) 19.94 C3 (Propane) 11.33 I-C4 (Isobutane) 0.97 N-C4 (N-butane) 2.83 C5+ (Pentanes) 0.91 Feed Specifications Flow Rate 310 MMSCFD Temperature 200 F Pressure 800 PSIg
  • 7.
    Design Basis: Product Specifications TreatedNatural Gas Component Mol% H2O 0.00 N2 4.00 CO2 0.02 H2S (Hydrogen Sulfide) (6.05 PPB) C1 (Methane) 94.5 C2 (Ethane) 0.77 C3 (Propane) 0.00 C4 (butanes) 0.00 C5+ (Pentanes) 0.00 Production Rates Ammonia Plant 19.13 MMSCFD Syngas Plant 42.16 MMSCFD Midrex Plant 19.58 MMSCFD CHP facility 50.00 MMSCFD Pipeline 2.70 MMSCFD NGL 57233.4 BBL/D LNG 16335.44 BBL/D Sulfur Cake 60 LB/HR
  • 8.
  • 9.
    Gas Receiving Major equipment:3 horizontal knock out tanks. Purpose: ●To protect against liquid surges from well head. ●To remove liquids that will condense at high temperature and low pressure. ●Ensures gas pressure nominal for process.
  • 10.
    Sour Gas Treatment Two-StepProcess for Complete SOur Gas Treatment MDEA Treatment -Selectional removal of H2S and CO2 -Achieves H2S content to 1 ppm in sweetened gas stream -Most economically viable option for design basis of gas feed flow rate LO-CAT II Sulfur Production -Cost effective solution for Hydrogen Sulfide -Reduces H2S to a 60 wt% cake of elemental sulfur -Revenues of approximately $25,000/year -Low operating costs compared to other processes -Effective way to handle H2S -LO-CAT catalyst solution is corrosion resistant and recycled
  • 11.
    Dehydration Lean Gas Absorption -TEGdehydration -Glycol is cost effective - Achieves water content down to 10 ppmv -Glycol can be replaced continuously -Does not remove CO2 Adsorption -Mole sieve dehydration -Adsorbent like molecular sieves are expensive -Achieves water content to as low as 0.1ppmv -Multiple adsorption beds are required for continuous use -Removes C02 Membrane -Yields water content between 20-100 ppmv -Removes CO2
  • 12.
    Demethanization Mechanical Refrigeration Plant: -limited to -24 to -40 F - only 60% propane Lean oil absorption: - 40% ethane - 90% propane - 100% heavier hydrocarbons - Heating and cooling required - High operating cost Turboexpander: - 60-90% ethane - 90-98% propane -100% of heavier hydrocarbons ● Since high percent ethane recovery is required, this is the most economical method
  • 13.
    Heavy Hydrocarbon Stabilization Natural gasliquids have to be stabilized to a point that it can be stored and transported in low-pressurized vessels. Enhances the safety in handling, and improving the liquid's marketability. Stabilizing the liquid reduces the volatility.
  • 14.
    Nitrogen Rejection Cryogenic Distillation Requiresflow rates <50 MMSCFD Best recovery rate Highest purity product Most benefits from economy of scale Pressure Swing Adsorption Second Most Commonly used NRU Not scalable economically above 50 MMscfd High Compression Costs at high flow rates Sorbent must be replaced every 3-years Membrane Separation Applicable up to 100 MMSCFD Most widely applied below 10 MMscfd Because of limitations of membrane size scalability becomes difficult at very high flow rates Compression costs become very high above 100 MMscfd Lower recovery rate can affect plant economics Must replace membranes every 3-years At this stage of analysis cryogenic distillation has been selected for its ● high recovery and high purity of product (Nitrogen stream contains 3 wt% methane) o Literature suggests nitrogen stream can contain as low as 0.5 wt% methane. ● Ability to liquefy natural gas for LNG production. ● Scalable to high flow rates ● Chiller supplies additional cooling to demethanizer feed Its recommend that further analysis go into other processes constraints on nitrogen content and then re- examine the need for such a high amount of gas upgrading.
  • 15.
    LNG Production Major equipment: Joule-Thomsonvalve and flash drum. Purpose: ●To simply and efficiently produce liquefied natural gas for sale.
  • 16.
  • 17.
    Economics Revenues Pipeline Gas $4,400,000 NGL$224,533,762 LNG $88,300,000 Sulfur Cake $23,547 Total $317,257,309 Operating Costs Salaries and fringes $10,500,000 Maintenance (3% of TIC) $4,332,002 Wellhead Gas $379,000,000 sorbents $525,714 MDEA $500,000 Total $394,857,716 Total Installation Cost Total Equipment Cost $41,257,159 Total Installed Cost $144,400,056
  • 18.
    Constraints • Issues includehighly pressurized vessels, high temperatures,cryogenic temperatures, poisonous by-products. • Pressure relief valves would be installed on all pressure vessels to direct excess gases to the flare. • Safety training for operators working around high or low temperature equipment, as well as proper insulation of equipment. • Hydrogen sulfide, which is very toxic, is immediately converted to an inert sulfur cake. •Hydrogen sulfide has a LD50 of 600 PPM / 30 minutes
  • 19.
    Recommendations It's recommend thatthis plant go forward 1.It is an essential for supplying large quantities of gas for other processes within the complex. 2.Offers some flexibility in products being produced.
  • 20.
    Future Outlook: NGLStabilization Economics Gate 2 possibility: Separation of individual Hydrocarbons for revenue. Assuming 17 year life No inflation accounted for Additional Capital Cost Additional Revenue Additional Operating Cost NPV Fractionation $33,000,000 $195,000,000 $4,941,000 $814,000,000
  • 21.