SlideShare a Scribd company logo
Make the most of your energySM
Upgrade provides power supplier with superior
safety and communication devices
The Challenge
At the time, two pump-generator units were installed at the Bendeela and
Kangaroo Valley Power Stations. More than 30 years later, they needed to
upgrade the aging equipment.
In May 2008, Schneider Electric (formerly AREVA T&D Australian
Automation) received a request from Eraring Energy to provide panel
sections for the protection systems at both power stations. The project
required approval and coordinated effort from a number of stakeholders,
including: Eraring Energy (the customer); Aurecon (the consultant); AEMO
(grid regulators); Transgrid (the transmission utility); plus all subcontractors
and suppliers.
Site installation and pre-commissioning were completed over a period
of four weeks for each unit. Eraring Energy provided assistance onsite,
while Schneider Electric and their subcontractors completed the bulk
of the work.
Delivering a Complex System
Using local expertise, Schneider Electric assessed each site and proposed
to Eraring Energy a comprehensive solution – to replace their out-dated
equipment, with state-of-the-art numerical terminals.
Integrating new technology with the existing system was no easy task.
It required extensive design, engineering, system study and settings
report, plus technical assistance for approvals from the System Operator.
Schneider Electric’s solution included the provision of new protection
systems for generators, transformers and the transmission line, along
with replacement of cable communication carrier systems for turbine
inlet pipeline guard gate trips. This was carried out using DIP5000 (a
comprehensive, digital tele-protection system) and communication of
the relays on DNP3 to the SCADA system. In addition, Schneider Electric
was commissioned to install fault/disturbance recorders and a global
positioning satellite (GPS) system.
Unique Design and Engineering
Despite an innovative design, the upgrade required a solution that could
accommodate the challenges imposed by a 30-year-old system – namely
retrofitting the existing protection panels and creating an interface between
the old and the new systems. The units can run in both “generator” and
“pump” modes, and one of the main challenges arose while implementing
the negative-phase sequence protection on the generator, under these
modes. In “pump” mode, the Intelligent Electronic Device (IED) would
sense an unbalanced current in the system as in “Phase A” and
“Phase B” were reversed. In order to resolve the issue, the scheme had to
be designed so that the logics (programmed in the IEDs) could suitably
handle both modes of operation. Schneider Electric’s local expertise
and “creative engineering” were the keys to finding a solution for these
technical challenges.
Infrastructure Eraring Energy, Shoalhaven District, New South Wales
LOCATION
•	 Shoalhaven District, New South Wales.
OBJECTIVE
To provide Eraring Energy with superior safety
and communications devices.
How THIS WAS ACHIEVED
•	 replacement of generator and transformer
protection systems
•	 integration with existing systems
•	 operator and technician training
PrOjECT AT A GLANCE
•	 Protection panels including Schneider Electric
MiCOM & GE SR range of relays
•	 SCADA communication
•	 Site refurbishment
•	 3rd party coordination and approval
In 1977, the Electricity Commission of NSW commissioned their 16kV, two-stage,
pumped storage hydroelectric scheme in the Shoalhaven district.
©2012SchneiderElectric.AllRightsReserved.
Building the Protection Panels
There are two pump-generator units at each
of the locations. At Kangaroo Valley, both units
consist of a 16kV 93MVA synchronous motor-
generator. At Bendeela, the units consist of a
16kV 51.1MVA synchronous motor-generator.
The existing protection systems were primarily
made up from discrete electromechanical relays.
They were used as part of a retrofit, using an old
two-carrier communication system for the line
protection between the Bendeela and Kangaroo
Valley Power Stations. The electromechanical
relays were also integrated with the new
equipment. A new communication carrier system
was used to provide redundant tele-protection
for guard gate tripping, in the event of any fault
in the pipeline.
A total of eight panel sections have been
installed by Schneider Electric at the Bendeela
Power Station:
•	 2 x unit protection A panel sections
•	 2 x unit protection B panel sections
•	 1 x transformer and line protection A panel
section
•	 1 x transformer and line protection B panel
section and
•	 2 x station transformer panel sections.
A total of 11 panel sections were installed
by Schneider Electric at the Kangaroo Valley
Power Station:
•	 2 x unit protection A panel sections
•	 2 x unit protection B panel sections
•	 2 x transformer A panel sections
•	 2 x transformer B panel sections
•	 2 x station transformer panel sections and
•	 1 x standby generator panel section.
‘Schneider Electric’s local expertise and
“creative engineering” were the keys to finding
a solution for these technical challenges.’
Most of the protection equipment used, was Schneider Electric MiCOM
and GE Relays. The panel sections comprise:
•	 unit protection A panel section – (MiCOM P343, MiCOM P122)
•	 unit protection B panel section – (GE G60, MiCOM P122)
•	 transformer and line protection A panel section – (MiCOM P633,
MiCOM P543)
•	 transformer and line protection B panel section – (GE T60, GE L90)
•	 station transformer panel section – (MiCOM P141, MiCOM P122)
•	 standby generator panel section – (MiCOM P122)
The panel sections were successfully built and tested at Schneider
Electric’s testing facility. Eraring Energy also received extensive training
support for Operators and Technicians.
Communication Was the Key
The new protection equipment installed by Schneider Electric was
connected to the existing SCADA system. This setup enabled the customer
to access data communications in real time so relay settings, fault records
and event records could be accessed on demand. This was done through
the serial COM port of EKI-1522, on the second rear communication port
of the IEDs.
DIP5000 teleprotection units replaced the old analogue cable carrier
system that was used for the tripping of the guard gate system. The
DIP5000 was designed to transfer protection commands coming from
protective relays, to the remote location via either fibre optic cables (digital
mode) or pilot cables (analogue mode). Using the latest digital signalling
processing technology and advanced coding algorithms, the DIP5000
offers the highest level of security and speed of transfer for this
protection system.
Completing the Work
Protection upgrades to the Bendeela and Kangaroo Valley Power
Stations were, for the most part, completed in July 2009 and December
2011 respectively. The protection systems remain fully operational and
Schneider Electric is in the completion stage for any outstanding items, as
per the contract.
The Site-Specific Safety and Environment Plan was also prepared to
account for the activities that took place at the Kangaroo Valley and
Bendeela Power Stations. According to this plan, all work carried out by
Schneider Electric (and its subcontractors) was completed safely and with
no lost time due to workplace incidents.
Infrastructure Eraring Energy, Shoalhaven District, New South Wales
Schneider Electric (Australia) Pty Ltd 78 Waterloo Road, Macquarie Park, NSW 2113 Australia. Tel: 1300 369 233 Fax: 1300 369 288 www.schneider-electric.com.au
CLIPCOM 24735

More Related Content

What's hot

Arc Flash Considerations for Data Center IT Space
Arc Flash Considerations for Data Center IT SpaceArc Flash Considerations for Data Center IT Space
Arc Flash Considerations for Data Center IT Space
Schneider Electric
 
Bringing Sustainable Efficiency to Wind Power
Bringing Sustainable Efficiency to Wind PowerBringing Sustainable Efficiency to Wind Power
Bringing Sustainable Efficiency to Wind Power
Schneider Electric
 
Power Adapter Design for 400 V DC Power Distribution in Electronic Systems
Power Adapter Design for 400 V DC Power Distribution in Electronic SystemsPower Adapter Design for 400 V DC Power Distribution in Electronic Systems
Power Adapter Design for 400 V DC Power Distribution in Electronic Systems
Vicor Corporation
 
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
Schneider Electric
 
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS OperationEco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
Schneider Electric India
 
AccuSine pfv+
AccuSine pfv+ AccuSine pfv+
AccuSine pfv+
Schneider Electric
 
Schneider Electric Renewable Energies Catalog
Schneider Electric Renewable Energies CatalogSchneider Electric Renewable Energies Catalog
Schneider Electric Renewable Energies Catalog
Schneider Electric India
 
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
Sandia National Laboratories: Energy & Climate: Renewables
 
Evaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
Evaluating the Arc-Flash Protection Benefits of IEC 61850 CommunicationEvaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
Evaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
Schneider Electric
 
Impact of IEC 61508 Standards on Intelligent Electrial Networks and Safety Im...
Impact of IEC 61508 Standards on Intelligent Electrial Networks and Safety Im...Impact of IEC 61508 Standards on Intelligent Electrial Networks and Safety Im...
Impact of IEC 61508 Standards on Intelligent Electrial Networks and Safety Im...
Schneider Electric
 
ARC White paper: Schneider Electric Introduces First ePAC, Combines PAC with...
ARC White paper:  Schneider Electric Introduces First ePAC, Combines PAC with...ARC White paper:  Schneider Electric Introduces First ePAC, Combines PAC with...
ARC White paper: Schneider Electric Introduces First ePAC, Combines PAC with...
Schneider Electric
 
Iecon15 AMI
Iecon15 AMIIecon15 AMI
Iecon15 AMI
Juan C. Vasquez
 
[Pipeline Support Solutions] CLH Case Study
[Pipeline Support Solutions] CLH Case Study[Pipeline Support Solutions] CLH Case Study
[Pipeline Support Solutions] CLH Case Study
Schneider Electric
 
Operational Cost Avoidance through Harmonic Mitigation in Industrial Environm...
Operational Cost Avoidance through Harmonic Mitigation in Industrial Environm...Operational Cost Avoidance through Harmonic Mitigation in Industrial Environm...
Operational Cost Avoidance through Harmonic Mitigation in Industrial Environm...
Schneider Electric
 
[Pipeline Support Solutions] Kenya Pipeline Company Case Study
[Pipeline Support Solutions] Kenya Pipeline Company Case Study[Pipeline Support Solutions] Kenya Pipeline Company Case Study
[Pipeline Support Solutions] Kenya Pipeline Company Case Study
Schneider Electric
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
michaeljmack
 
Basic Concepts for an Integrated Steel Process Control System
Basic Concepts for an Integrated Steel Process Control SystemBasic Concepts for an Integrated Steel Process Control System
Basic Concepts for an Integrated Steel Process Control System
Schneider Electric
 
Modicon M580 MUCH MORE then a PLC…the first ePAC!
Modicon M580 MUCH MORE then a PLC…the first ePAC!Modicon M580 MUCH MORE then a PLC…the first ePAC!
Modicon M580 MUCH MORE then a PLC…the first ePAC!
Schneider Electric
 
Making the grid more efficient, flexible and secure
Making the grid more efficient, flexible and secureMaking the grid more efficient, flexible and secure
Making the grid more efficient, flexible and secure
Schneider Electric
 
Acti9 Communication System catalog
Acti9 Communication System catalogActi9 Communication System catalog
Acti9 Communication System catalog
Schneider Electric India
 

What's hot (20)

Arc Flash Considerations for Data Center IT Space
Arc Flash Considerations for Data Center IT SpaceArc Flash Considerations for Data Center IT Space
Arc Flash Considerations for Data Center IT Space
 
Bringing Sustainable Efficiency to Wind Power
Bringing Sustainable Efficiency to Wind PowerBringing Sustainable Efficiency to Wind Power
Bringing Sustainable Efficiency to Wind Power
 
Power Adapter Design for 400 V DC Power Distribution in Electronic Systems
Power Adapter Design for 400 V DC Power Distribution in Electronic SystemsPower Adapter Design for 400 V DC Power Distribution in Electronic Systems
Power Adapter Design for 400 V DC Power Distribution in Electronic Systems
 
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
 
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS OperationEco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
 
AccuSine pfv+
AccuSine pfv+ AccuSine pfv+
AccuSine pfv+
 
Schneider Electric Renewable Energies Catalog
Schneider Electric Renewable Energies CatalogSchneider Electric Renewable Energies Catalog
Schneider Electric Renewable Energies Catalog
 
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
 
Evaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
Evaluating the Arc-Flash Protection Benefits of IEC 61850 CommunicationEvaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
Evaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
 
Impact of IEC 61508 Standards on Intelligent Electrial Networks and Safety Im...
Impact of IEC 61508 Standards on Intelligent Electrial Networks and Safety Im...Impact of IEC 61508 Standards on Intelligent Electrial Networks and Safety Im...
Impact of IEC 61508 Standards on Intelligent Electrial Networks and Safety Im...
 
ARC White paper: Schneider Electric Introduces First ePAC, Combines PAC with...
ARC White paper:  Schneider Electric Introduces First ePAC, Combines PAC with...ARC White paper:  Schneider Electric Introduces First ePAC, Combines PAC with...
ARC White paper: Schneider Electric Introduces First ePAC, Combines PAC with...
 
Iecon15 AMI
Iecon15 AMIIecon15 AMI
Iecon15 AMI
 
[Pipeline Support Solutions] CLH Case Study
[Pipeline Support Solutions] CLH Case Study[Pipeline Support Solutions] CLH Case Study
[Pipeline Support Solutions] CLH Case Study
 
Operational Cost Avoidance through Harmonic Mitigation in Industrial Environm...
Operational Cost Avoidance through Harmonic Mitigation in Industrial Environm...Operational Cost Avoidance through Harmonic Mitigation in Industrial Environm...
Operational Cost Avoidance through Harmonic Mitigation in Industrial Environm...
 
[Pipeline Support Solutions] Kenya Pipeline Company Case Study
[Pipeline Support Solutions] Kenya Pipeline Company Case Study[Pipeline Support Solutions] Kenya Pipeline Company Case Study
[Pipeline Support Solutions] Kenya Pipeline Company Case Study
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Basic Concepts for an Integrated Steel Process Control System
Basic Concepts for an Integrated Steel Process Control SystemBasic Concepts for an Integrated Steel Process Control System
Basic Concepts for an Integrated Steel Process Control System
 
Modicon M580 MUCH MORE then a PLC…the first ePAC!
Modicon M580 MUCH MORE then a PLC…the first ePAC!Modicon M580 MUCH MORE then a PLC…the first ePAC!
Modicon M580 MUCH MORE then a PLC…the first ePAC!
 
Making the grid more efficient, flexible and secure
Making the grid more efficient, flexible and secureMaking the grid more efficient, flexible and secure
Making the grid more efficient, flexible and secure
 
Acti9 Communication System catalog
Acti9 Communication System catalogActi9 Communication System catalog
Acti9 Communication System catalog
 

Similar to Eraring_Energy_Case_Study

Schneider plc
Schneider plcSchneider plc
Schneider plc
Ghadak Mohammad
 
WM Siemens IEC 61850 Flyer 081914
WM Siemens IEC 61850 Flyer 081914WM Siemens IEC 61850 Flyer 081914
WM Siemens IEC 61850 Flyer 081914
Ryan Bolduc, PE
 
Iskra presentation 2016
Iskra presentation 2016Iskra presentation 2016
Iskra presentation 2016
Minka Grdesic
 
KPX Promotionnal Catalogue
KPX Promotionnal CatalogueKPX Promotionnal Catalogue
KPX Promotionnal Catalogue
CLEMENT Guillaume
 
FEEDER PROTECTION SYSTEM FROM EARTH FAULT, SHORT CIRCUIT AND OVERLOAD FAULTS
FEEDER PROTECTION SYSTEM FROM EARTH FAULT, SHORT CIRCUIT AND OVERLOAD FAULTSFEEDER PROTECTION SYSTEM FROM EARTH FAULT, SHORT CIRCUIT AND OVERLOAD FAULTS
FEEDER PROTECTION SYSTEM FROM EARTH FAULT, SHORT CIRCUIT AND OVERLOAD FAULTS
IRJET Journal
 
CB&I _ EATON NGSF SUCCESS STORY
CB&I _ EATON NGSF SUCCESS STORYCB&I _ EATON NGSF SUCCESS STORY
CB&I _ EATON NGSF SUCCESS STORY
Ray Caparas
 
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
Mahesh Chandra Manav
 
Nidec asi electric power solutions for ship to shore connection
Nidec asi electric power solutions for ship to shore connectionNidec asi electric power solutions for ship to shore connection
Nidec asi electric power solutions for ship to shore connection
Nidec Corporation
 
Josep Guerrero as Keynote Speaker at ENERGYCON2014
Josep Guerrero as Keynote Speaker at ENERGYCON2014Josep Guerrero as Keynote Speaker at ENERGYCON2014
Josep Guerrero as Keynote Speaker at ENERGYCON2014
Juan C. Vasquez
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
michaeljmack
 
E&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - WebE&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - Web
Amber Thomas
 
SMART GRID AND SMART TRANSFORMERS
SMART GRID AND SMART TRANSFORMERSSMART GRID AND SMART TRANSFORMERS
SMART GRID AND SMART TRANSFORMERS
Angel James
 
The meeco Group's product presentation of sun2live - solar and storage solution
The meeco Group's product presentation of sun2live - solar and storage solutionThe meeco Group's product presentation of sun2live - solar and storage solution
The meeco Group's product presentation of sun2live - solar and storage solution
The meeco Group
 
Techimp Products and Services Portfolio
Techimp Products and Services PortfolioTechimp Products and Services Portfolio
Techimp Products and Services Portfolio
Techimp HQ
 
Matimba Power Station
Matimba Power StationMatimba Power Station
Matimba Power Station
AGE Technologies
 
Article
ArticleArticle
Article
joeengi
 
Energy Projects Capability Statement
Energy Projects Capability StatementEnergy Projects Capability Statement
Energy Projects Capability Statement
CLEMENT Guillaume
 
gridFUTURE, A Concept
gridFUTURE, A ConceptgridFUTURE, A Concept
gridFUTURE, A Concept
John Schneider, Dr. Eng.
 
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
IRJET Journal
 
APsystems Value Proposition
APsystems Value PropositionAPsystems Value Proposition
APsystems Value Proposition
Clive Rippon
 

Similar to Eraring_Energy_Case_Study (20)

Schneider plc
Schneider plcSchneider plc
Schneider plc
 
WM Siemens IEC 61850 Flyer 081914
WM Siemens IEC 61850 Flyer 081914WM Siemens IEC 61850 Flyer 081914
WM Siemens IEC 61850 Flyer 081914
 
Iskra presentation 2016
Iskra presentation 2016Iskra presentation 2016
Iskra presentation 2016
 
KPX Promotionnal Catalogue
KPX Promotionnal CatalogueKPX Promotionnal Catalogue
KPX Promotionnal Catalogue
 
FEEDER PROTECTION SYSTEM FROM EARTH FAULT, SHORT CIRCUIT AND OVERLOAD FAULTS
FEEDER PROTECTION SYSTEM FROM EARTH FAULT, SHORT CIRCUIT AND OVERLOAD FAULTSFEEDER PROTECTION SYSTEM FROM EARTH FAULT, SHORT CIRCUIT AND OVERLOAD FAULTS
FEEDER PROTECTION SYSTEM FROM EARTH FAULT, SHORT CIRCUIT AND OVERLOAD FAULTS
 
CB&I _ EATON NGSF SUCCESS STORY
CB&I _ EATON NGSF SUCCESS STORYCB&I _ EATON NGSF SUCCESS STORY
CB&I _ EATON NGSF SUCCESS STORY
 
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
 
Nidec asi electric power solutions for ship to shore connection
Nidec asi electric power solutions for ship to shore connectionNidec asi electric power solutions for ship to shore connection
Nidec asi electric power solutions for ship to shore connection
 
Josep Guerrero as Keynote Speaker at ENERGYCON2014
Josep Guerrero as Keynote Speaker at ENERGYCON2014Josep Guerrero as Keynote Speaker at ENERGYCON2014
Josep Guerrero as Keynote Speaker at ENERGYCON2014
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
E&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - WebE&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - Web
 
SMART GRID AND SMART TRANSFORMERS
SMART GRID AND SMART TRANSFORMERSSMART GRID AND SMART TRANSFORMERS
SMART GRID AND SMART TRANSFORMERS
 
The meeco Group's product presentation of sun2live - solar and storage solution
The meeco Group's product presentation of sun2live - solar and storage solutionThe meeco Group's product presentation of sun2live - solar and storage solution
The meeco Group's product presentation of sun2live - solar and storage solution
 
Techimp Products and Services Portfolio
Techimp Products and Services PortfolioTechimp Products and Services Portfolio
Techimp Products and Services Portfolio
 
Matimba Power Station
Matimba Power StationMatimba Power Station
Matimba Power Station
 
Article
ArticleArticle
Article
 
Energy Projects Capability Statement
Energy Projects Capability StatementEnergy Projects Capability Statement
Energy Projects Capability Statement
 
gridFUTURE, A Concept
gridFUTURE, A ConceptgridFUTURE, A Concept
gridFUTURE, A Concept
 
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
 
APsystems Value Proposition
APsystems Value PropositionAPsystems Value Proposition
APsystems Value Proposition
 

Eraring_Energy_Case_Study

  • 1. Make the most of your energySM Upgrade provides power supplier with superior safety and communication devices The Challenge At the time, two pump-generator units were installed at the Bendeela and Kangaroo Valley Power Stations. More than 30 years later, they needed to upgrade the aging equipment. In May 2008, Schneider Electric (formerly AREVA T&D Australian Automation) received a request from Eraring Energy to provide panel sections for the protection systems at both power stations. The project required approval and coordinated effort from a number of stakeholders, including: Eraring Energy (the customer); Aurecon (the consultant); AEMO (grid regulators); Transgrid (the transmission utility); plus all subcontractors and suppliers. Site installation and pre-commissioning were completed over a period of four weeks for each unit. Eraring Energy provided assistance onsite, while Schneider Electric and their subcontractors completed the bulk of the work. Delivering a Complex System Using local expertise, Schneider Electric assessed each site and proposed to Eraring Energy a comprehensive solution – to replace their out-dated equipment, with state-of-the-art numerical terminals. Integrating new technology with the existing system was no easy task. It required extensive design, engineering, system study and settings report, plus technical assistance for approvals from the System Operator. Schneider Electric’s solution included the provision of new protection systems for generators, transformers and the transmission line, along with replacement of cable communication carrier systems for turbine inlet pipeline guard gate trips. This was carried out using DIP5000 (a comprehensive, digital tele-protection system) and communication of the relays on DNP3 to the SCADA system. In addition, Schneider Electric was commissioned to install fault/disturbance recorders and a global positioning satellite (GPS) system. Unique Design and Engineering Despite an innovative design, the upgrade required a solution that could accommodate the challenges imposed by a 30-year-old system – namely retrofitting the existing protection panels and creating an interface between the old and the new systems. The units can run in both “generator” and “pump” modes, and one of the main challenges arose while implementing the negative-phase sequence protection on the generator, under these modes. In “pump” mode, the Intelligent Electronic Device (IED) would sense an unbalanced current in the system as in “Phase A” and “Phase B” were reversed. In order to resolve the issue, the scheme had to be designed so that the logics (programmed in the IEDs) could suitably handle both modes of operation. Schneider Electric’s local expertise and “creative engineering” were the keys to finding a solution for these technical challenges. Infrastructure Eraring Energy, Shoalhaven District, New South Wales LOCATION • Shoalhaven District, New South Wales. OBJECTIVE To provide Eraring Energy with superior safety and communications devices. How THIS WAS ACHIEVED • replacement of generator and transformer protection systems • integration with existing systems • operator and technician training PrOjECT AT A GLANCE • Protection panels including Schneider Electric MiCOM & GE SR range of relays • SCADA communication • Site refurbishment • 3rd party coordination and approval In 1977, the Electricity Commission of NSW commissioned their 16kV, two-stage, pumped storage hydroelectric scheme in the Shoalhaven district.
  • 2. ©2012SchneiderElectric.AllRightsReserved. Building the Protection Panels There are two pump-generator units at each of the locations. At Kangaroo Valley, both units consist of a 16kV 93MVA synchronous motor- generator. At Bendeela, the units consist of a 16kV 51.1MVA synchronous motor-generator. The existing protection systems were primarily made up from discrete electromechanical relays. They were used as part of a retrofit, using an old two-carrier communication system for the line protection between the Bendeela and Kangaroo Valley Power Stations. The electromechanical relays were also integrated with the new equipment. A new communication carrier system was used to provide redundant tele-protection for guard gate tripping, in the event of any fault in the pipeline. A total of eight panel sections have been installed by Schneider Electric at the Bendeela Power Station: • 2 x unit protection A panel sections • 2 x unit protection B panel sections • 1 x transformer and line protection A panel section • 1 x transformer and line protection B panel section and • 2 x station transformer panel sections. A total of 11 panel sections were installed by Schneider Electric at the Kangaroo Valley Power Station: • 2 x unit protection A panel sections • 2 x unit protection B panel sections • 2 x transformer A panel sections • 2 x transformer B panel sections • 2 x station transformer panel sections and • 1 x standby generator panel section. ‘Schneider Electric’s local expertise and “creative engineering” were the keys to finding a solution for these technical challenges.’ Most of the protection equipment used, was Schneider Electric MiCOM and GE Relays. The panel sections comprise: • unit protection A panel section – (MiCOM P343, MiCOM P122) • unit protection B panel section – (GE G60, MiCOM P122) • transformer and line protection A panel section – (MiCOM P633, MiCOM P543) • transformer and line protection B panel section – (GE T60, GE L90) • station transformer panel section – (MiCOM P141, MiCOM P122) • standby generator panel section – (MiCOM P122) The panel sections were successfully built and tested at Schneider Electric’s testing facility. Eraring Energy also received extensive training support for Operators and Technicians. Communication Was the Key The new protection equipment installed by Schneider Electric was connected to the existing SCADA system. This setup enabled the customer to access data communications in real time so relay settings, fault records and event records could be accessed on demand. This was done through the serial COM port of EKI-1522, on the second rear communication port of the IEDs. DIP5000 teleprotection units replaced the old analogue cable carrier system that was used for the tripping of the guard gate system. The DIP5000 was designed to transfer protection commands coming from protective relays, to the remote location via either fibre optic cables (digital mode) or pilot cables (analogue mode). Using the latest digital signalling processing technology and advanced coding algorithms, the DIP5000 offers the highest level of security and speed of transfer for this protection system. Completing the Work Protection upgrades to the Bendeela and Kangaroo Valley Power Stations were, for the most part, completed in July 2009 and December 2011 respectively. The protection systems remain fully operational and Schneider Electric is in the completion stage for any outstanding items, as per the contract. The Site-Specific Safety and Environment Plan was also prepared to account for the activities that took place at the Kangaroo Valley and Bendeela Power Stations. According to this plan, all work carried out by Schneider Electric (and its subcontractors) was completed safely and with no lost time due to workplace incidents. Infrastructure Eraring Energy, Shoalhaven District, New South Wales Schneider Electric (Australia) Pty Ltd 78 Waterloo Road, Macquarie Park, NSW 2113 Australia. Tel: 1300 369 233 Fax: 1300 369 288 www.schneider-electric.com.au CLIPCOM 24735