SlideShare a Scribd company logo
Terror Lake: A Horror Amusement Park 
Section 080, Group 07 
 
Group members 
Talaial Alina, tba28@drexel.edu 
Gabriel LeVee, gbl29@drexel.edu 
Joey Massa, ​jvm54@drexel.edu 
 
Abstract 
 
The proposal to build the Terror Lake haunted amusement park excluded the construction 
of Green Stormwater Infrastructure (GSI), and also failed to include any bathrooms or sewage 
system. The purpose of this project is to design those missing components so that they could 
fulfill the requirements of this park’s ordinance. Indeed, the project designed the GSI and sewage 
system, and a budget for their construction. Sewage filtration and gravel­style stormwater 
filtration techniques were employed in designing these systems. The project helped successfully 
create green alternatives to the county ordinance, and aspirations that future building projects can 
include our designs to fuel a cleaner world. 
 
Introduction 
 
This project involved designing of a Green Stormwater Infrastructure (GSI) and sewer 
system for a haunted amusement park​ ​which borders both a forest and a lake. This required that 
team members extensively research fluid dynamics and filtration methods to better cultivate the 
group’s ability to design such a system. The first step involved creating the proposed layout for 
the park.  Then, the project involved designing a sewer system which connected all three 
available bathrooms to a single underground sewage filtration facility via gravity fed pipes which 
also led from the filtration plant to the lake carrying clean, filtered water. Finally, the project 
entailed the design of a runoff filtration system that borders the lake to prevent park pollution 
from seeping into the lake. This filtration system is the Green Stormwater Infrastructure because 
it cleans the stormwater before it reenters the environment. 
 
 
 
Sketches 
 
The overview pipeline layout sketch for the sewer system depicts all bathroom pipelines 
connecting into one major pipe that feeds into the underground facility while one pipe, filled 
with clean, filtered water, exits the facility. This not only helps cut down on the overall pipe 
required to build the sewer, but it also allows for easier maintenance if the system malfunctioned. 
Furthermore, building one overall pipeline easily makes it gravity­fed because the entire system 
can be tilted linearly, from the furthest bathroom down to the underground filtration facility. The 
underground filtration facility is the most important element because it allows this sewer system 
to be self­sustaining, and it can help an entrepreneurial fertilizer business effort in the future 
employ the filtered sewage product. This facility also ensures that the sewer system follows 
along with the green theme set by the GSI requirement. 
Furthermore, laying the three varied sizes of gravel to cover the depth of the lake border 
approximately 35ft deep ensures that only clean water enters into the lake and properly creates 
the filtration layer for stormwater runoff, as depicted in the sketch. Indeed, gradually increasing 
the fineness of gravel closer to the lake can help create one of the simplest and most effective 
natural filtration systems. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Figure 1: Sketch of Haunted Amusement Park 
 
Figure 2: Sketch of Haunted Amusement Park Sewage System and Green Stormwater 
System (GSI) 
Gantt chart 
 
The project Gantt Chart contains six major tasks to complete: gathering materials, 
installing sewage filtration station, installing PVC pipes and foundation for sewer, installing a 
filtration layer, installing bathroom systems, and creating a final report. The reasoning for those 
times are as follows. First, the materials, listed in the bill of materials, will be gathered from June 
1st until September 1st. Gathering these materials will take approximately three months due to 
the large quantities of materials and expenses required for the project. Next, the sewage filtration 
station will be installed from approximately September 2nd until November 12th. This station 
will be installed before the pipelines because it is the most crucial part of the sewer system and 
will take the most work to complete. The PVC pipes and foundation for the sewer will be 
installed in the subsequent time from November 13th until December 20th. Simultaneously, the 
filtration layer will be installed  from November 15th until January 7th. These will be installed at 
overlapping times because they will require similar areas of digging and work, and serve similar 
integrated purposes. Next, bathroom systems will be constructed from December 20th until 
January 18th. These will be installed after the sewer pipes because bathrooms require a 
functioning sewer prior to operation. Finally, a final report of all work, expenses, overall 
efficiency, and results will be developed from January 19th until February 16th, marking the 
completion of the actual project​. 
 
Figure 3: Haunted Amusement Park Gantt Chart  
 
Bill of Materials/Budget 
 
Parts one through eight in the first table are all used in conjunction with one another to 
create one large water filter. The concrete, part two, will be used to build the facility itself [10]. 
For this reason, it is necessary to spend around $10,000 to ensure the proper size. Part one, the 
two pumps, will be used to move water from the restrooms to the filtration facility [4]. Parts four 
through seven are all used as the physical filter. It starts with the largest particles, the pebbles 
that filter out the largest debris [1]. The water will then be sifted through the layers of coarse and 
fine silex as well as the activated carbon [11] [7] [8].  
The second table shows parts one through five of the sewage pipe system. Part five will 
be used as the main pipe connecting all of the various facilities in the park [17]. Part one will be 
used to help the drainage of the park [13]. Part one is a perforated PVC pipe that will lie under 
the surface of the park. It will be surrounded with parts two through four to ensure that water can 
enter the pipe [12] [16]. In theory, any excess runoff should flow into the perforated pipes which 
will guide it efficiently to the lake.  
The final table lays out the items used to reinforce the banks of the lake. Black Willow 
and Silver Maple trees have strong root systems that will help hold the soil in place [3] [14], but 
there is a large bank to the right of the park thus required many trees. Overall, trees alone will 
cost under $215,000. In addition to the trees, Big Bluestem, part three [2], is a wetland grass that 
not only supports the banks against erosion, but also helps to purify the water before it enters the 
lake. Parts four, five, and six are three different types of gravel [15] [6] [11]. When properly 
layered under the soil before the bank of the lake, this tree will help filter runoff before it enters 
the lake and protect against erosion. Preparing a sustainable and green bank for the lake will cost 
around $375,000 and will be the most expensive of the three segments in the bill of materials.  
 
Figure 4: Haunted Amusement Park Sewage System Bill of Materials  
Figure 5: Haunted Amusement Park Sewage System Budget  
 
 
Figure 5.1: Haunted Amusement Park Sewage System Budget (continued) 
 
 
 
 
Discussion 
 
Completing the haunted amusement park and the haunted amusement park sewage 
system designs involved numerous conceptual sketches of the haunted amusement park and its 
sewage system, development of a Green Stormwater Infrastructure (GSI) that harnesses both the 
local environment and environmentally sound materials, a sewage system comprised of several 
parts, creation of a Gantt Chart that illustrated the progression of the project, a bill of materials 
stating the material required for the project, and the entire budget for the green stormwater 
infrastructure detailing labor and material costs for the project.  
 
First, designing the sewage system of the haunted amusement park mandated delicately 
balancing the interests and desires of the county government with the strict, but important, 
construction requirements of the sewage system. This entailed concealing the park’s sewage 
system near the trees prevalent throughout the park while also recognizing the sewage system’s 
pollution on the local environment. The materials listed for the sewage system confronted this 
pollution concern through becoming a part of a filtration layer comprised of gravel, soil, and 
other materials, and a filtration system with an activated carbon filter. 
 
The project also envisioned that this sewage system would continuously flow water, rain 
or sewage water, throughout the structure. The filtration layer would collect runoff water from 
the rain and minimize the spread of harmful pollutants into the lake and elsewhere during intense 
rain periods, while the activated carbon layer in the sewage filtration station would absorb 
sewage. 
 
After planning these project goals through outlines and conceptual sketches, the next 
phase of the project involved determining how the project would be implemented. In this phase, 
a Gantt Chart illustrated sequential completion of the project over a period of eight months. This 
data also helped determine when a project staff member was needed, and the amount of material 
necessary to complete a specific Gantt Chart task on time. However, additional days should be 
added to each task in a Gantt Chart during an actual execution of this project to account for 
mishandled materials, delinquent employees, and weather changes. 
 
After developing a Gantt Chart, a Bill of Materials was produced detailing the 
comprehensive material costs of implementing the sewage system of the amusement park. This 
item explored the locations to purchase the required materials while accounting for their 
individual costs. In reality, the project contractor should clearly communicate with their client 
and discuss the potential flaws of the clients’s hopes for the project, including their desire to 
build with certain materials. As a result, the project will realistically realize the clients's 
aspirations. 
 
The final stage of the planning process for the haunted amusement park involves creating 
an extensive budget that details the project labor and material costs. In this budget, labor costs 
were calculated through determining the weekly salaries of each of the 169 employees required 
for the project and multiplying each of these values by 37 weeks, the number of weeks in the 
eight month period required to complete the project. To determine the total labor cost, this labor 
cost was added to each member’s travel expenses which were individually estimated to be 
$100/day for lodging, $10/day for airfare/train, $48.5/day for gas, and $1850 for meals and other 
transportation options. Interestingly, labor costs composed 50% of the entire budget, highlighting 
their significance in the project, and perhaps the importance of contractually obligating the 
contractor to hire temporary workers to complete a project on schedule if current workers leave a 
project. This may be where the 5% reserve funds in the budget allow emergency hirings of these 
temporary workers, or for missing materials.  
 
Beyond planning the procedures to construct the amusement park sewage system, the 
actual sewage system should be adaptable to local ecosystem changes or increases in park 
visitors. This involves coating the sewage filtration related materials with substances that can 
protect against weather changes or building adequate space around sewage lines to easily expand 
them in the future if needed, respectively. Similarly, the sewage filtration station should be built 
with regards to the potential for future expansion. In this station, a hired maintenance crew 
should also periodically cleanse the activated carbon filter and the other filtering materials to 
resupply the station with new materials and maintain its efficiency. Furthermore, a specialized 
team should periodically examine the the filtration layer of the green stormwater system to 
identify its continued effectiveness and replace its materials with more affordable and effective 
ones if the layer is breaking down. This team should also inspect the nearby lake to ensure that 
the park’s sewage system is properly filtering sewage, and not releasing deadly pollutants into 
the environment. Therefore, the sewage system project’s consideration of current and potential 
human and environmental concerns defines the park as an innovator in employing green 
technology to allow humans to coexist with the environment while also ensuring the park’s 
viability decades into the future. 
 
References 
 
[1] "Aqua Cove." ​Lyngso Garden​. Lyngso Garden Materials Inc, 2015. Web. 3 Dec. 2015. 
[2] "Big Bluestem." ​Jeinc.com​. Johnston Enterprises, Inc, 2015. Web. 03 Dec. 2015.   
[3] "Black Willow (Salix Nigra)." ​ColdStreamFarm.net​. Cold Stream Farm, 2015. Web. 03 
Dec. 2015.   
[4] "Complete Sewer Grinder Packages." ​Plumbing Supply​. Plumbing Supply, 2015. Web. 3 
Dec. 2015. 
[5] "DP290 3M Purification ­ Aqua­Pure Dual Port Manifold System W/Shut­Off."​JES 
Restaurant Equipment​. JES Restaurant Equipment, 2015. Web. 3 Dec. 2015. 
[6] "Earth First Indiana Price List." ​Indiana Price List Updated​ (2011): n. pag. ​Earth First​. 
Earth­First, 2013. Web. 3 Dec. 2015.   
[7] "Fine Silex (50 KG Bag)." ​EAqua.in​. EAqua.in, 2015. Web. 3 Dec. 2015. 
[8] "FLECK 2510AF AUTOMATIC BACKWASHING ACTIVATED CARBON FILTERS." ​Fleck 
2510AF Automatic Backwashing Activated Carbon Filters​. APS Water Services Inc, 3 Dec. 
2015. Web. 03 Dec. 2015. 
[9] "Full Time Private Industry Workers." ​U.S. Bureau of Labor Statistics​. U.S. Bureau of 
Labor Statistics, n.d. Web. 04 Dec. 2015.   
[10] "Goldenseal Unit Costs." ​Turtlesoft.com​. Turtle Creek Software, 2012. Web. 3 Dec. 2015. 
[11] "Quikrete 50 Lb. All­Purpose Gravel" ​The Home Depot​. Homer TLC, 2015. Web. 03 
Dec. 2015.   
[12] "Scotts 0.75­cu Ft Top Soil." ​Lowe's​. Lowe's Foundation LLC, 2015. Web. 3 Dec. 2015. 
[13] "Sewer Drain and Pipe Fittings." ​Lowe's​. Lowe's Foundation LLC, 2015. Web. 3 Dec. 
2015. 
[14] "Silver Maple." ​NatureHills.com​. Nature Hills Nursery Inc, 2015. Web. 03 Dec. 2015.   
[15] "Slag Rock #789 (Pea Gravel)." ​All Seasons Mulch​. All Seasons Mulch and Landscaping 
Supply, 05 Jan. 2013. Web. 04 Dec. 2015.   
[16] "TerraFill® Grounding Backfill, 50 Lb. Bag." ​AllTecGlobal.com​. ALLTEC LLC, 2015. 
Web. 3 Dec. 2015. 
[17] "4 In. X 10 Ft. Triplewall Pipe Solid." ​The Home Depot​. Homer TLC Inc, 2015. Web. 03 
Dec. 2015. 
[18] "9 Degrees of Freedom ­ Razor IMU." ​SparkFun.com​. SparkFun Electronics Inc, 2015. 
Web. 03 Dec. 2015. 

More Related Content

What's hot

Partnerships for Greening Atlanta - SF, DQ, CO
Partnerships for Greening Atlanta - SF, DQ, COPartnerships for Greening Atlanta - SF, DQ, CO
Partnerships for Greening Atlanta - SF, DQ, CO
Park Pride
 
The Rise of Blue-Green Infrastructure
The Rise of Blue-Green InfrastructureThe Rise of Blue-Green Infrastructure
The Rise of Blue-Green Infrastructure
Robert Brears
 
Nasa and Green Engineering
Nasa and Green EngineeringNasa and Green Engineering
Nasa and Green Engineering
Circular Economy Asia
 
Article on environment friendly technology in water industry
Article on environment friendly technology in water industryArticle on environment friendly technology in water industry
Article on environment friendly technology in water industry
Tejas Mairal
 
Stabilizer 101227102055-phpapp01
Stabilizer 101227102055-phpapp01Stabilizer 101227102055-phpapp01
Stabilizer 101227102055-phpapp01
sportechnic
 
Auraria Sustainable Campus Program
Auraria Sustainable Campus ProgramAuraria Sustainable Campus Program
Auraria Sustainable Campus ProgramVirginia Till
 
Concept Sketches
Concept SketchesConcept Sketches
Concept Sketches
Kim Mitchell
 
Nicole Avril - Ecoblock Qingdao
Nicole Avril - Ecoblock QingdaoNicole Avril - Ecoblock Qingdao
Nicole Avril - Ecoblock QingdaoShane Mitchell
 
Harrison Fraker- EcoBlocks
Harrison Fraker- EcoBlocksHarrison Fraker- EcoBlocks
Harrison Fraker- EcoBlocks
Geoffrey Lewis
 
Land, Water, People: New Parks in Practice
Land, Water, People: New Parks in PracticeLand, Water, People: New Parks in Practice
Land, Water, People: New Parks in PracticeRiverFirst Initiative
 
Solar Power Analysis and Design Specifications
 Solar Power Analysis and Design Specifications Solar Power Analysis and Design Specifications
Solar Power Analysis and Design SpecificationsCalifornia Free Solar
 
Benefits of Manure Digesters
Benefits of Manure DigestersBenefits of Manure Digesters
Benefits of Manure Digesters
lakeimprovement
 
A case for change transforming solid waste mangement in nova scotia
A case for change   transforming solid waste mangement in nova scotiaA case for change   transforming solid waste mangement in nova scotia
A case for change transforming solid waste mangement in nova scotia
Gord Helm
 
“EcoBlock” Neighborhoods The Right Scale for Zero Carbon Development?
“EcoBlock” Neighborhoods The Right Scale for Zero Carbon Development? “EcoBlock” Neighborhoods The Right Scale for Zero Carbon Development?
“EcoBlock” Neighborhoods The Right Scale for Zero Carbon Development?
Penn Institute for Urban Research
 
SWANA Atlantic Conference Final Presentation 27 april 2016
SWANA Atlantic Conference Final Presentation 27 april 2016SWANA Atlantic Conference Final Presentation 27 april 2016
SWANA Atlantic Conference Final Presentation 27 april 2016Gord Helm
 
The Critical Link Between Aquifer Exemptions and teh Sustainability of Water ...
The Critical Link Between Aquifer Exemptions and teh Sustainability of Water ...The Critical Link Between Aquifer Exemptions and teh Sustainability of Water ...
The Critical Link Between Aquifer Exemptions and teh Sustainability of Water ...
Dan Arthur
 
John Marshall, Georgia State University – “Large-scale Disasters and Federal...
 John Marshall, Georgia State University – “Large-scale Disasters and Federal... John Marshall, Georgia State University – “Large-scale Disasters and Federal...
John Marshall, Georgia State University – “Large-scale Disasters and Federal...EERI
 

What's hot (20)

Partnerships for Greening Atlanta - SF, DQ, CO
Partnerships for Greening Atlanta - SF, DQ, COPartnerships for Greening Atlanta - SF, DQ, CO
Partnerships for Greening Atlanta - SF, DQ, CO
 
The Rise of Blue-Green Infrastructure
The Rise of Blue-Green InfrastructureThe Rise of Blue-Green Infrastructure
The Rise of Blue-Green Infrastructure
 
Nasa and Green Engineering
Nasa and Green EngineeringNasa and Green Engineering
Nasa and Green Engineering
 
Article on environment friendly technology in water industry
Article on environment friendly technology in water industryArticle on environment friendly technology in water industry
Article on environment friendly technology in water industry
 
Stabilizer 101227102055-phpapp01
Stabilizer 101227102055-phpapp01Stabilizer 101227102055-phpapp01
Stabilizer 101227102055-phpapp01
 
Elements_Winter_2013
Elements_Winter_2013Elements_Winter_2013
Elements_Winter_2013
 
Auraria Sustainable Campus Program
Auraria Sustainable Campus ProgramAuraria Sustainable Campus Program
Auraria Sustainable Campus Program
 
CEN-winter-113
CEN-winter-113CEN-winter-113
CEN-winter-113
 
Concept Sketches
Concept SketchesConcept Sketches
Concept Sketches
 
Nicole Avril - Ecoblock Qingdao
Nicole Avril - Ecoblock QingdaoNicole Avril - Ecoblock Qingdao
Nicole Avril - Ecoblock Qingdao
 
Harrison Fraker- EcoBlocks
Harrison Fraker- EcoBlocksHarrison Fraker- EcoBlocks
Harrison Fraker- EcoBlocks
 
EPA poster
EPA posterEPA poster
EPA poster
 
Land, Water, People: New Parks in Practice
Land, Water, People: New Parks in PracticeLand, Water, People: New Parks in Practice
Land, Water, People: New Parks in Practice
 
Solar Power Analysis and Design Specifications
 Solar Power Analysis and Design Specifications Solar Power Analysis and Design Specifications
Solar Power Analysis and Design Specifications
 
Benefits of Manure Digesters
Benefits of Manure DigestersBenefits of Manure Digesters
Benefits of Manure Digesters
 
A case for change transforming solid waste mangement in nova scotia
A case for change   transforming solid waste mangement in nova scotiaA case for change   transforming solid waste mangement in nova scotia
A case for change transforming solid waste mangement in nova scotia
 
“EcoBlock” Neighborhoods The Right Scale for Zero Carbon Development?
“EcoBlock” Neighborhoods The Right Scale for Zero Carbon Development? “EcoBlock” Neighborhoods The Right Scale for Zero Carbon Development?
“EcoBlock” Neighborhoods The Right Scale for Zero Carbon Development?
 
SWANA Atlantic Conference Final Presentation 27 april 2016
SWANA Atlantic Conference Final Presentation 27 april 2016SWANA Atlantic Conference Final Presentation 27 april 2016
SWANA Atlantic Conference Final Presentation 27 april 2016
 
The Critical Link Between Aquifer Exemptions and teh Sustainability of Water ...
The Critical Link Between Aquifer Exemptions and teh Sustainability of Water ...The Critical Link Between Aquifer Exemptions and teh Sustainability of Water ...
The Critical Link Between Aquifer Exemptions and teh Sustainability of Water ...
 
John Marshall, Georgia State University – “Large-scale Disasters and Federal...
 John Marshall, Georgia State University – “Large-scale Disasters and Federal... John Marshall, Georgia State University – “Large-scale Disasters and Federal...
John Marshall, Georgia State University – “Large-scale Disasters and Federal...
 

Viewers also liked

Equipos de interconexión yuli
Equipos de interconexión yuliEquipos de interconexión yuli
Equipos de interconexión yuli
yulianaosorno82
 
Instalar software
Instalar softwareInstalar software
Instalar software
garcesjaramillo
 
Identificación de herramientas e insumos para mantenimiento preventivo
Identificación de herramientas e insumos para mantenimiento preventivoIdentificación de herramientas e insumos para mantenimiento preventivo
Identificación de herramientas e insumos para mantenimiento preventivo
yulianaosorno82
 
Giao an boi duong 8.1 kxh.docj.doc ket
Giao an boi duong 8.1   kxh.docj.doc ketGiao an boi duong 8.1   kxh.docj.doc ket
Giao an boi duong 8.1 kxh.docj.doc ket
Kiều Xuân Họa
 
Medios de transmision
Medios de transmisionMedios de transmision
Medios de transmision
yulianaosorno82
 
Definición de música
Definición de músicaDefinición de música
Definición de música
santiago bustos
 
Juego interactivo
Juego interactivoJuego interactivo
Juego interactivosoniiaop
 
Pinterest pecha kucha
Pinterest pecha kuchaPinterest pecha kucha
Pinterest pecha kucha
Heather Lentz
 
Ofimatica gubernamenta expo
Ofimatica gubernamenta expoOfimatica gubernamenta expo
Ofimatica gubernamenta expo
christianfloresguierrez
 
Todo sobre el SENA
Todo sobre el SENATodo sobre el SENA
Todo sobre el SENA
jsebastianamezquita
 
Psikologi sosial
Psikologi sosialPsikologi sosial
Psikologi sosial
Puryanto SS
 
διαμαντής αξιώτης
διαμαντής αξιώτηςδιαμαντής αξιώτης
διαμαντής αξιώτης
thomkef24
 
7. kesadaran berbangsa dan bernegara
7. kesadaran berbangsa dan bernegara7. kesadaran berbangsa dan bernegara
7. kesadaran berbangsa dan bernegara
Puryanto SS
 
Makri
MakriMakri
Makri
thomkef24
 
Retaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportRetaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportJoshua Yu
 
7. kesadaran berbangsa dan bernegara
7. kesadaran berbangsa dan bernegara7. kesadaran berbangsa dan bernegara
7. kesadaran berbangsa dan bernegara
Puryanto SS
 

Viewers also liked (20)

Equipos de interconexión yuli
Equipos de interconexión yuliEquipos de interconexión yuli
Equipos de interconexión yuli
 
Instalar software
Instalar softwareInstalar software
Instalar software
 
Identificación de herramientas e insumos para mantenimiento preventivo
Identificación de herramientas e insumos para mantenimiento preventivoIdentificación de herramientas e insumos para mantenimiento preventivo
Identificación de herramientas e insumos para mantenimiento preventivo
 
Giao an boi duong 8.1 kxh.docj.doc ket
Giao an boi duong 8.1   kxh.docj.doc ketGiao an boi duong 8.1   kxh.docj.doc ket
Giao an boi duong 8.1 kxh.docj.doc ket
 
Presentation15
Presentation15 Presentation15
Presentation15
 
Medios de transmision
Medios de transmisionMedios de transmision
Medios de transmision
 
Definición de música
Definición de músicaDefinición de música
Definición de música
 
Juego interactivo
Juego interactivoJuego interactivo
Juego interactivo
 
SEGRO_2015_Cover
SEGRO_2015_CoverSEGRO_2015_Cover
SEGRO_2015_Cover
 
Pinterest pecha kucha
Pinterest pecha kuchaPinterest pecha kucha
Pinterest pecha kucha
 
Ofimatica gubernamenta expo
Ofimatica gubernamenta expoOfimatica gubernamenta expo
Ofimatica gubernamenta expo
 
Melo presentacion
Melo presentacionMelo presentacion
Melo presentacion
 
Proyecto Abejas
Proyecto AbejasProyecto Abejas
Proyecto Abejas
 
Todo sobre el SENA
Todo sobre el SENATodo sobre el SENA
Todo sobre el SENA
 
Psikologi sosial
Psikologi sosialPsikologi sosial
Psikologi sosial
 
διαμαντής αξιώτης
διαμαντής αξιώτηςδιαμαντής αξιώτης
διαμαντής αξιώτης
 
7. kesadaran berbangsa dan bernegara
7. kesadaran berbangsa dan bernegara7. kesadaran berbangsa dan bernegara
7. kesadaran berbangsa dan bernegara
 
Makri
MakriMakri
Makri
 
Retaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportRetaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering Report
 
7. kesadaran berbangsa dan bernegara
7. kesadaran berbangsa dan bernegara7. kesadaran berbangsa dan bernegara
7. kesadaran berbangsa dan bernegara
 

Similar to engr101_grp07_FinPaper

Nicholas DiFrank - Professional Portfolio 2015
Nicholas DiFrank - Professional Portfolio 2015Nicholas DiFrank - Professional Portfolio 2015
Nicholas DiFrank - Professional Portfolio 2015
Nicholas DiFrank
 
AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002Dennis Palalay
 
Green infrastructure on the fair
Green infrastructure on the fairGreen infrastructure on the fair
Green infrastructure on the fairaslfadmin
 
An Absorbing Education: Stormwater Management to Begin Northeastern Illinois ...
An Absorbing Education: Stormwater Management to Begin Northeastern Illinois ...An Absorbing Education: Stormwater Management to Begin Northeastern Illinois ...
An Absorbing Education: Stormwater Management to Begin Northeastern Illinois ...
Mariah Green
 
CV Dog Park
CV Dog ParkCV Dog Park
CV Dog Park
Perla Arquieta
 
MASEFinalReport (2)
MASEFinalReport (2)MASEFinalReport (2)
MASEFinalReport (2)Sunil Satish
 
Hello 4. Through a google search, present one case study on Indirect.pdf
Hello 4. Through a google search, present one case study on Indirect.pdfHello 4. Through a google search, present one case study on Indirect.pdf
Hello 4. Through a google search, present one case study on Indirect.pdf
artimagein
 
2013 Uplift Report: Quantifying Ecological Uplift
2013 Uplift Report: Quantifying Ecological Uplift2013 Uplift Report: Quantifying Ecological Uplift
2013 Uplift Report: Quantifying Ecological Uplift
The Freshwater Trust
 
BWG Stormwater-Study
BWG Stormwater-StudyBWG Stormwater-Study
BWG Stormwater-Studyjpetr0s
 
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Fairfax County
 
Mission: Earth
Mission: EarthMission: Earth
Mission: Earth
AECOM
 
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water QualityNY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
Sotirakou964
 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715Max Kroschel
 
Spring Lake - A Case Study for Green Infrastructure & LID (part 1)
Spring Lake - A Case Study for Green Infrastructure & LID (part 1)Spring Lake - A Case Study for Green Infrastructure & LID (part 1)
Spring Lake - A Case Study for Green Infrastructure & LID (part 1)
Katie Pekarek
 
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINALPALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINALWilliam J. Pehaim
 
Underground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in WisconsinUnderground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in Wisconsin
Contech Engineered Solutions
 
2008 Engineering Excellence Awards
2008 Engineering Excellence Awards 2008 Engineering Excellence Awards
2008 Engineering Excellence Awards ACECSDES
 

Similar to engr101_grp07_FinPaper (20)

Nicholas DiFrank - Professional Portfolio 2015
Nicholas DiFrank - Professional Portfolio 2015Nicholas DiFrank - Professional Portfolio 2015
Nicholas DiFrank - Professional Portfolio 2015
 
AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002
 
Green infrastructure on the fair
Green infrastructure on the fairGreen infrastructure on the fair
Green infrastructure on the fair
 
An Absorbing Education: Stormwater Management to Begin Northeastern Illinois ...
An Absorbing Education: Stormwater Management to Begin Northeastern Illinois ...An Absorbing Education: Stormwater Management to Begin Northeastern Illinois ...
An Absorbing Education: Stormwater Management to Begin Northeastern Illinois ...
 
CV Dog Park
CV Dog ParkCV Dog Park
CV Dog Park
 
MASEFinalReport (2)
MASEFinalReport (2)MASEFinalReport (2)
MASEFinalReport (2)
 
DaybreakSRSPoster2Small
DaybreakSRSPoster2SmallDaybreakSRSPoster2Small
DaybreakSRSPoster2Small
 
MelissaMartinPortfolio2015
MelissaMartinPortfolio2015MelissaMartinPortfolio2015
MelissaMartinPortfolio2015
 
Hello 4. Through a google search, present one case study on Indirect.pdf
Hello 4. Through a google search, present one case study on Indirect.pdfHello 4. Through a google search, present one case study on Indirect.pdf
Hello 4. Through a google search, present one case study on Indirect.pdf
 
2013 Uplift Report: Quantifying Ecological Uplift
2013 Uplift Report: Quantifying Ecological Uplift2013 Uplift Report: Quantifying Ecological Uplift
2013 Uplift Report: Quantifying Ecological Uplift
 
BWG Stormwater-Study
BWG Stormwater-StudyBWG Stormwater-Study
BWG Stormwater-Study
 
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
 
Mission: Earth
Mission: EarthMission: Earth
Mission: Earth
 
AWRA_AWP_POSTER
AWRA_AWP_POSTERAWRA_AWP_POSTER
AWRA_AWP_POSTER
 
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water QualityNY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715
 
Spring Lake - A Case Study for Green Infrastructure & LID (part 1)
Spring Lake - A Case Study for Green Infrastructure & LID (part 1)Spring Lake - A Case Study for Green Infrastructure & LID (part 1)
Spring Lake - A Case Study for Green Infrastructure & LID (part 1)
 
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINALPALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
 
Underground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in WisconsinUnderground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in Wisconsin
 
2008 Engineering Excellence Awards
2008 Engineering Excellence Awards 2008 Engineering Excellence Awards
2008 Engineering Excellence Awards
 

More from Talaial Alina

Alina, Talaial_39x29 (1)
Alina, Talaial_39x29 (1)Alina, Talaial_39x29 (1)
Alina, Talaial_39x29 (1)Talaial Alina
 
ENGR103_section071_group07_designprocedure
ENGR103_section071_group07_designprocedureENGR103_section071_group07_designprocedure
ENGR103_section071_group07_designprocedureTalaial Alina
 
ENGR103_section071_group07_designproposal
ENGR103_section071_group07_designproposalENGR103_section071_group07_designproposal
ENGR103_section071_group07_designproposalTalaial Alina
 
engr103_grp07107_finRep
engr103_grp07107_finRepengr103_grp07107_finRep
engr103_grp07107_finRepTalaial Alina
 
Freshman Engineering Design Reports 1 2 3
Freshman Engineering Design Reports 1 2 3Freshman Engineering Design Reports 1 2 3
Freshman Engineering Design Reports 1 2 3Talaial Alina
 
PGW Presentation Research EDITED_V3 - Copy
PGW Presentation Research EDITED_V3 - CopyPGW Presentation Research EDITED_V3 - Copy
PGW Presentation Research EDITED_V3 - CopyTalaial Alina
 

More from Talaial Alina (6)

Alina, Talaial_39x29 (1)
Alina, Talaial_39x29 (1)Alina, Talaial_39x29 (1)
Alina, Talaial_39x29 (1)
 
ENGR103_section071_group07_designprocedure
ENGR103_section071_group07_designprocedureENGR103_section071_group07_designprocedure
ENGR103_section071_group07_designprocedure
 
ENGR103_section071_group07_designproposal
ENGR103_section071_group07_designproposalENGR103_section071_group07_designproposal
ENGR103_section071_group07_designproposal
 
engr103_grp07107_finRep
engr103_grp07107_finRepengr103_grp07107_finRep
engr103_grp07107_finRep
 
Freshman Engineering Design Reports 1 2 3
Freshman Engineering Design Reports 1 2 3Freshman Engineering Design Reports 1 2 3
Freshman Engineering Design Reports 1 2 3
 
PGW Presentation Research EDITED_V3 - Copy
PGW Presentation Research EDITED_V3 - CopyPGW Presentation Research EDITED_V3 - Copy
PGW Presentation Research EDITED_V3 - Copy
 

engr101_grp07_FinPaper