Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
The work process is characterized by the following basic steps:
1) Identification and notification of a potential change
2) Preparation and verification of the change report
3) Review of change request by other affected areas
4) Review of change request by quality department
5) Approval of the change report
6) Approved change request
7) Rejected change request
8) Planning and implementation of change
9) Closure of change request
10) Follow up actions
Energy Consulting SDVOSB Transition PlanningLink Resources
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Energy Consulting SDVOSB Transition ManagementLink Resources
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
The work process is characterized by the following basic steps:
1) Identification and notification of a potential change
2) Preparation and verification of the change report
3) Review of change request by other affected areas
4) Review of change request by quality department
5) Approval of the change report
6) Approved change request
7) Rejected change request
8) Planning and implementation of change
9) Closure of change request
10) Follow up actions
Energy Consulting SDVOSB Transition PlanningLink Resources
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Energy Consulting SDVOSB Transition ManagementLink Resources
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Energy Consulting SDVOSB Human Capital ManagementLink Resources
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Energy Consulting SDVOSB Capability Statement CorporateLink Resources
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Product Guide I created for Telemarc Ltd who are specialists in Telemarketing services. I designed and put together the whole booklet and also wrote all copywrite.
I also created the brand identity for Telemarc along with logo development.
Monitoring and evaluation.
A presentation in Arabic/English prepared the Palestinian Center for Peace and Democracy (PCPD)
اعداد المركز الفلسطيني للسلام والديمقراطية
فلسطين , ديمقراطية , ديموقراطية , monitoring , elections, evaluation , politics
This is PMBOK Guide Monitor and Control Process Group - Part One. It includes three Knowledge Area - Project Integration Management, Project Scope Management, and Project Quality Management - with five processes - Monitor & Control Project Work, Perform Integrated Change Control, Validate Scope, Control Scope, Control Quality -.
Link Resources exhibiting at Tennessee Valley Authority’s 3rd Annual Supplier...Link Resources
Link Resources exhibiting at Tennessee Valley Authority’s 3rd Annual Supplier Diversity Outreach Summit Wednesday April, 29 2015 at the North Hall of the Von Braun Center in Huntsville, Alabama. We look forward to meeting with TVA, clients, and industry leaders from the region. We look forward to seeing you and telling you more about Link Resources at our booth in the North Hall!
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Energy Consulting SDVOSB Organizational AssessmentLink Resources
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Energy Consulting SDVOSB Merger Acquisition PlanningLink Resources
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Energy Consulting SDVOSB Biofuel ExperienceLink Resources
Link Resources: providing Energy Consulting, Management, Operations and Maintenance services across Fossil, Nuclear, and Bio Energy power plants globally. No SDVOSB has our energy credentials or competencies!
Link Resources Capabilities Statement 2013Link Resources
Link Resources Capabilities Statement
Link's interactive, distinctive, and branded approach to energy consulting and our nineteen years of success across the spectrum of the energy space enables clients to accelerate objectives, mitigate risks, and rejuvenate performance during transitions - - whether such transitions include start-up, commissioning, decommissioning, contractor turnover, reorganization, acquisition, process rejuvenation, or even transitioning from engineering to procurement to construction to operations. In the Federal space Link has experience with DOE, multiple Federal prime contractors, and has project resumes at Portsmouth, Hanford, LANL, INEL, and Oak Ridge. In the Commercial arena Link has extensive experience with electric utilities and independent energy producers across the country and offshore as well - - from waste coal to biomass to oil/gas to biofuels to desalinization to CHP and the majority of the renewable energy technologies. Unlike most consultants, Link has millions of man-hours in hands-on operations experience, including cradle-to-grave as well as full-scope accountability for output or outcome, with lifecycle lessons learned that can be applied to consulting assignments.
Link’s founders and indeed its core staff have nuclear
experience at their roots - - which Link has melded with
its fossil and renewable competencies. For instance,
the inherently safer Small Modular Reactor industry of
course must work within the legacy regulatory structures,
yet must evolve a more entrepreneurially based
infrastructure if SMRs are going to achieve the societal
benefits envisioned.
Reciprocally, next-generation biofuel plants using
genetically modified organisms or highly hazardous
chemicals (or even gas/oil hydraulic fracturing technologies)
can learn many lessons from the mature
nuclear industry, such as emergency response, owners
group self-regulation, verbatim compliance for certain
activities, shift-turnover procedures, and so forth.
At Techbox Square, in Singapore, we're not just creative web designers and developers, we're the driving force behind your brand identity. Contact us today.
Business Valuation Principles for EntrepreneursBen Wann
This insightful presentation is designed to equip entrepreneurs with the essential knowledge and tools needed to accurately value their businesses. Understanding business valuation is crucial for making informed decisions, whether you're seeking investment, planning to sell, or simply want to gauge your company's worth.
Recruiting in the Digital Age: A Social Media MasterclassLuanWise
In this masterclass, presented at the Global HR Summit on 5th June 2024, Luan Wise explored the essential features of social media platforms that support talent acquisition, including LinkedIn, Facebook, Instagram, X (formerly Twitter) and TikTok.
B2B payments are rapidly changing. Find out the 5 key questions you need to be asking yourself to be sure you are mastering B2B payments today. Learn more at www.BlueSnap.com.
Kseniya Leshchenko: Shared development support service model as the way to ma...Lviv Startup Club
Kseniya Leshchenko: Shared development support service model as the way to make small projects with small budgets profitable for the company (UA)
Kyiv PMDay 2024 Summer
Website – www.pmday.org
Youtube – https://www.youtube.com/startuplviv
FB – https://www.facebook.com/pmdayconference
The world of search engine optimization (SEO) is buzzing with discussions after Google confirmed that around 2,500 leaked internal documents related to its Search feature are indeed authentic. The revelation has sparked significant concerns within the SEO community. The leaked documents were initially reported by SEO experts Rand Fishkin and Mike King, igniting widespread analysis and discourse. For More Info:- https://news.arihantwebtech.com/search-disrupted-googles-leaked-documents-rock-the-seo-world/
Premium MEAN Stack Development Solutions for Modern BusinessesSynapseIndia
Stay ahead of the curve with our premium MEAN Stack Development Solutions. Our expert developers utilize MongoDB, Express.js, AngularJS, and Node.js to create modern and responsive web applications. Trust us for cutting-edge solutions that drive your business growth and success.
Know more: https://www.synapseindia.com/technology/mean-stack-development-company.html
LA HUG - Video Testimonials with Chynna Morgan - June 2024Lital Barkan
Have you ever heard that user-generated content or video testimonials can take your brand to the next level? We will explore how you can effectively use video testimonials to leverage and boost your sales, content strategy, and increase your CRM data.🤯
We will dig deeper into:
1. How to capture video testimonials that convert from your audience 🎥
2. How to leverage your testimonials to boost your sales 💲
3. How you can capture more CRM data to understand your audience better through video testimonials. 📊
Digital Transformation and IT Strategy Toolkit and TemplatesAurelien Domont, MBA
This Digital Transformation and IT Strategy Toolkit was created by ex-McKinsey, Deloitte and BCG Management Consultants, after more than 5,000 hours of work. It is considered the world's best & most comprehensive Digital Transformation and IT Strategy Toolkit. It includes all the Frameworks, Best Practices & Templates required to successfully undertake the Digital Transformation of your organization and define a robust IT Strategy.
Editable Toolkit to help you reuse our content: 700 Powerpoint slides | 35 Excel sheets | 84 minutes of Video training
This PowerPoint presentation is only a small preview of our Toolkits. For more details, visit www.domontconsulting.com
Improving profitability for small businessBen Wann
In this comprehensive presentation, we will explore strategies and practical tips for enhancing profitability in small businesses. Tailored to meet the unique challenges faced by small enterprises, this session covers various aspects that directly impact the bottom line. Attendees will learn how to optimize operational efficiency, manage expenses, and increase revenue through innovative marketing and customer engagement techniques.
Putting the SPARK into Virtual Training.pptxCynthia Clay
This 60-minute webinar, sponsored by Adobe, was delivered for the Training Mag Network. It explored the five elements of SPARK: Storytelling, Purpose, Action, Relationships, and Kudos. Knowing how to tell a well-structured story is key to building long-term memory. Stating a clear purpose that doesn't take away from the discovery learning process is critical. Ensuring that people move from theory to practical application is imperative. Creating strong social learning is the key to commitment and engagement. Validating and affirming participants' comments is the way to create a positive learning environment.
Personal Brand Statement:
As an Army veteran dedicated to lifelong learning, I bring a disciplined, strategic mindset to my pursuits. I am constantly expanding my knowledge to innovate and lead effectively. My journey is driven by a commitment to excellence, and to make a meaningful impact in the world.
Falcon stands out as a top-tier P2P Invoice Discounting platform in India, bridging esteemed blue-chip companies and eager investors. Our goal is to transform the investment landscape in India by establishing a comprehensive destination for borrowers and investors with diverse profiles and needs, all while minimizing risk. What sets Falcon apart is the elimination of intermediaries such as commercial banks and depository institutions, allowing investors to enjoy higher yields.
1. LINK RESOURCES INC.
DOE Experience
The following are examples of Link's experience for DOE, DOE Labs, or major DOE
contractors:
Los Alamos National Lab (LANL)
Scope: Formality of Operations Support in the NMSM-SMF Program Office
Provided support in the NMSM-SMF Program Office in the Formality of Operations programs at all Stockpile
Management Facilities (CMR, TA-55, TA-18, WETF, and SIGMA). Work included support of the CMR resumption
activities, Operability Assessments development of Corrective Action Plans, and implementation. Supported the
following areas:
LINK ACTIVITIES
IN THE FOLLOWING PROGRAMS
Analysis and Assessment
Quality Management Systems
Planning & Reviews
Safety Systems
Training
Facility Safety Basis
ISM Implementation
Work Authorization
Reporting and Issue Resolution
Work Control
Developing/Using Quality
Management System Tools
Conduct of Operations
Activities also included support of Readiness Assessments, Operational Readiness Reviews, Performance
Assurance, Corrective Action Planning and Implementation assurance, and support to Program Management
processes including DOE interface, prioritization of activities and problem resolution. Prepared draft materials and
stand-alone reports to support CMR resumption activities and Operability Assessments. In addition, deliverables
defined by LANL included analyses, calculations, review comments, monthly status reports, and participation in
LANL meetings and processes such as quality improvement teams. Assisted or developed and implemented specific
training packages as requested. Assisted in the development of the Safety Assessment Plan for CMR Facility
Operations.
125 TownPark Drive, Suite 300
Kennesaw, Georgia 30144
770-919-7070
2. Idaho Nuclear Technology and Engineering Center (INTEC)
Scope: Technical Service Support for INTEC Compliance
1. Introduction
The Idaho Nuclear Technology and Engineering Center (INTEC) required technical experts to assess/verify Conduct
of Operations and compliance issues at INTEC. Link evaluated Conduct of Operations implementation and
Procedure Compliance to define areas for improvement and readiness for ISMS Phase II verification. Also evaluated
the necessary organizational and/or cultural changes that needed to take place to ensure INTEC operated efficiently
and in compliance with applicable laws, regulations, and DOE Orders.
2. Scope/Technical Requirements
Link provided support to the INTEC Site Area Director, Site Area Deputy Director, and supporting managers. Link
efforts included the following task areas:
• Monitored operations at INTEC with the intent to provide guidance for improvements to
Conduct of Operations, communication, compliance, safety, quality, and efficiency.
• Interfaced with BBWI management at INTEC regarding interpretation, effectiveness, and
degree of compliance with respect to procedure requirements and other directives.
• Reviewed work at INTEC for compliance, and verify status and completion of performance
agreements, corrective actions, and procedure compliance.
• Provided oversight of work scope at INTEC and monitor performance.
• Selected Oversight Responsibilities will be delegated by the INTEC SAD.
3. Deliverables:
Link provided INTEC with the following:
• On-site subject matter participation, as requested by the INTEC Site Area Director.
• Monthly compliance status reports to include identification of issues, recommended action
plans, and final issue resolution.
125 TownPark Drive, Suite 300
Kennesaw, Georgia 30144
770-919-7070
3. Fluor
Scope: Technical Support as SNF Project Coach/Mentor for Operational
Readiness Review
l. Provided support for the FH SNF for Operational Readiness Review (ORR) support as the Coach Mentor.
2. Provided technical support services to the FH Office of the President in determining the effectiveness and the
degree of compliance by the Spent Nuclear Fuels Project with applicable laws, regulations, and DOE Orders
contained in FH manuals. The work was performed through the following task areas:
• Monitored the routine project operations with the intent to provide guidance for
improvements to safety, quality, and efficiency. Support IS also provided for planning
and conducting non-routine activities as necessary.
• Interfaced with DOE-RL and project management regarding interpretation and
implementation of regulatory commitments and other directives.
• Reviewed the project work for compliance, and verify status and completion of
performance agreements, Corrective Actions, and milestones.
• Provided Oversight of work scope and Performance Monitoring. Select oversight
responsibilities may be delegated from the FH Project Support Vice President.
• Integrated subproject activities within project by facilitating effective communications
and resolving issues among projects, ES&H, PHMC support organizations,
management, and DOE-RL clients.
• Provided the FH Office of the President with a field presence for project activities and
processes related to maintenance, operation, startup, and shutdown,
• Notified the FH Office of the President of any activities or practices requiring either
immediate or long-term corrective actions. Prepare periodic reports of field
monitoring and oversight activities as required by the FH Chief Operating Officer
• Readiness Support: Provide Coach/Mentoring to the facility for pre-ORR preparations.
BWXT Y-12
Scope: Restart of Enriched Uranium Operations
Link provided support to the restart of Enriched Uranium Operations (EUO) for Environmental Safety & Health
(ESH) disciplines with specific emphasis in areas of Conduct of Operations (COO) and Operational Readiness (OR).
This support encompassed Facility Safety, Fire Protection, Criticality Safety, Industrial Safety and Radiological
Controls that was effective and integrated into the Restart Planning for EUO. Link evaluated existing plans and
modified to specifically delineate needed controls, including activity-based startup processes.
Monthly summary reports of progress and issues
Written report of findings relative to the restart plans for EUO as the plans address ESH
Written report of recommendations for inclusion in restart plans
125 TownPark Drive, Suite 300
Kennesaw, Georgia 30144
770-919-7070
4. Fluor Hanford
Scope: Operational Readiness and Review Support- W-460 Project
Provided Operational Readiness Review support as required by the SRID team member and assistant Team Leader
for the Fluor Hanford (FH) Material Packaging Project.
Provided technical support services to the FH Materials Packaging Project in determining the Readiness to Start Up
the W-460 Plutonium Stabilization, Handling and Packaging Project by the Plutonium Finishing Plant (PFP). The
work performed included the following task areas:
• Reviewed assigned functional areas contained in the Plan of Action.
• Assessed Organizational Effectiveness in establishing and implementing programs that
achieved compliance with applicable laws, regulations, DOE Orders, and FH
requirements.
• Prepared documentation of Identified Adverse Conditions, and assist in the preparation and
issuance of the Formal Assessment Reports.
• Provided other general support as requested.
• Provided Cost Estimating and Support Scheduling for the work scope.
The deliverables included:
1. Assisted ORR Team Leader in preparing for review,
2. Operational review (maximum 5 days in the field
3. Preparation of final report,
4. Preparation and presentation of readiness post-review briefings as requested and as needed
to support required presentation schedules as determined by FH Material Packaging
Project.
5. Project support. Any comments incorporated into the final deliverable.
BWXT Y-12
Scope: Infrastructure Reduction
Provided support for Infrastructure Reduction for activities associated with the readiness to complete the Argon
Glovebox activities. Provided a senior readiness team to the project manager to ensure 9206 is ready to declare goahead for an Operational Readiness Review (ORR) that was required by the National Nuclear Security
Administration (NNSA). Developed an Activity-based Readiness Process to ensure that 9206 is ready in all aspects.
Supported development and institutionalization of the Y-12 site-wide readiness process (this was the same process
that is being utilized in 9206). Provided senior advisor team for the readiness activities associated with Beta 2E and
the actions to recover from the unsuccessful Readiness Assessment. Status and progress reports provided to the
project managers for these activities.
Provided procedures and other documentation to institutionalize the processes.
125 TownPark Drive, Suite 300
Kennesaw, Georgia 30144
770-919-7070
5. Los Alamos National Labs (LANL)
Scope: Conduct of Operations
LANL was Implementing Conduct of Operations (DOE O 5480.19) in accordance with Conduct
of Operations Implementation Plan - Los Alamos National Laboratory (FWO-DO:O1-100), to support
implementation of this effort, LANL/FWO requested and Link provided the following technical support for FY02.
Assisted the effort to Implement Conduct of Operations (COO) at LANL in accordance with the ambitious schedule
in the Implementation Plan (IP), as specified below:
1. Provided Technical Assistance to Facilities in conducting the Gap Analysis and Implementation Verification
(COO IP WBS 2.2) as specified by the OIC for COO Implementation through the UTR.
2. Provided Technical Assistance to the OIC in completing the Institutional Gap Analysis (COO IP WBS 1.8) as
specified by the OIC for COO Implementation through the UTR.
3. Provided Technical Assistance in formulating specific Corrective Action Plans (CAPs) for gaps in the
institutional implementation of COO for entry into ITRAC (COO IP WBS 1.9) as specified by the OIC for COO
Implementation through the UTR
4. Provided Technical Assistance to the OIC in the Institutional Analysis of Facility Level Implementation (Step 5
of the COO Implementation Notice dtd July 17, 2001) (COO IP WBS x.y) as specified by the OIC for COO
Implementation through the UTR.
Fluor Hanford
Scope: Technical Support to SNF Construction Projects, including ORR
The contract supported the SNF Construction Projects, Project Director in the conduct of
the Operational Readiness Review as required by DOE Orders, including DOE 0 5480.31
and DOE 0 425.1, and guided by the associated DOE-STD-306-95. The contractor was
required to provide personnel with the technical knowledge, required security clearances,
and experience to meet the qualification requirements specified in DOE Order 5480.31
and DOE 0 425.1 for subject matter technical experts and senior members.
The contractor provided support to prepare the facility to complete their Operational
Readiness Review that complied with DOE policy that readiness reviews be conducted
prior to the startup or restart of DOE nuclear facilities. Provided additional technical
support services to the SNF Construction Projects and as deemed necessary by the
Project Director, SNF Construction Projects, in determining the effectiveness and the
degree of compliance with applicable laws, regulations, and DOE Orders contained in FH
manuals. The work included the following task areas:
A. Monitored the routine project operations with the intent to provide guidance for
improvements to safety, quality, and efficiency. Support is also provided for planning and
conducting nonroutine activities as necessary.
125 TownPark Drive, Suite 300
Kennesaw, Georgia 30144
770-919-7070
6. B. Interfaced with DOE-RL and FH project management regarding interpretation and
implementation of regulatory commitments and other directives.
C. Reviewed the SNF Construction Projects work for compliance, and verified status and
completion of performance incentives.
D. Provided oversight of work scope and performance monitoring as delegated from the SNF
Construction Projects, Project Director
E. Monitored vendors’ performance at vendor’s place of business, as directed by the SNF
Construction Project, Project Director
F. Notified the SNF Construction Projects, Project Director of any activities or practices
requiring either immediate or long-term corrective actions.
G. Prepared periodic reports of field monitoring and oversight activities as required by the
SNF Construction Projects, Project Director.
H. Provided coach/mentor technical support as needed by SNF Construction Projects.
Bechtel BWXT Idaho
Scope: OU 7-10 GEM Project, Operations Readiness Technical Services
The OU 7-10 Glovebox Excavator Method Project was breaking new ground in the early involvement of Operations.
Part of the project's operational philosophy was that preparations for the Management Self-Assessment (MSA) and
the Operational Readiness Review (ORR) should begin with the commencement of the project. In order to meet the
objective of an expedited, effective MSA and ORR, Operations required the services of a subcontractor.
Link facilitated, augmented, and audited all preparations for an expedited MSA and ORR. The primary objective of
this scope is to reduce operational risk and operational costs.
Link reported to and received direction from the Pit-9 (GEM) Operations Department Manager, providing expert
level technical services in the following areas:
Provided expertise in nuclear plant start-up, especially as coupled with CERCLA
regulations.
Conducted an extended, expert-level, independent audit of operational readiness to ensure
consistent and adequate progress.
Assisted in the development of a Plan of Action required by Bechtel BWXT Idaho, LLC
(BBWI) MCP-2783.
Assisted with managing MSA and ORR operational risks and document mitigating actions.
Provided expertise to ensure that all MSA and ORR requirements are fulfilled, verified,
objectively documented, organized and controlled in a manner that demonstrates
accountability and supports an expedited MSA and ORR.
• Served as the ORR Team Leader, per appointment by the Pit-9 (GEM) Operations Manager.
Link provided level-of-effort technical services assistance in preparing all Operations MSA and ORR deliverables as
directed by the Pit-9 (GEM) Operations Manager.
125 TownPark Drive, Suite 300
Kennesaw, Georgia 30144
770-919-7070
7. Fluor
Scope: Startup Review Strategy for PFP Decommissioning
• Reviewed and updated Accelerated Decommissioning Plan including scope of work and
schedule.
• Reviewed current version of Startup Readiness (HNF-PRO-055).
• Develop and issue Startup Review Strategy for Accelerated PFP Decommissioning. The
strategy will support the accelerated project plan and be in full compliance with HNFPRO-055.
• The Startup Review Strategy will identify the type of review for a specific scope of work
such that all Decommissioning work is covered.
DELIVERABLES / SCHEDULE OR OBJECTIVE ACCEPTANCE CRITERIA
• Startup Review Strategy due January 17, 2003
• Startup Notification Technical Description and Score sheet for each identified startup due
January 17, 2003
LATA/Parallax Portsmouth, LLC (LPP)
Scope: Proposal Assistance, Transition Planning, and Transition Implementation
for the Portsmouth Gaseous Diffusion Facility
Background:
The Portsmouth Gaseous Diffusion Plant (part of the Portsmouth site) is a uranium enrichment plant that was
constructed in the mid 1950's and operated by the Department of Energy (DOE) and its predecessor agencies to
supply both high-and low-enriched uranium for defense purposes and commercial nuclear fuel sales. The uranium
enrichment program utilizing the gaseous diffusion process resulted in the generation of significant quantities of
radioactive, hazardous, and mixed waste, which is referred to as legacy waste, and other contaminants. Waste and
contaminants at the site include those regulated under the Resource Conservation and Recovery Act (RCRA), the
Toxic Substances Control Act (TSCA), and the Atomic Energy Act (AEA), including construction debris, sanitary
waste, hazardous waste (HW), radioactive low-level waste (LLW), and mixed low-level waste (MLLW).
LATA/Parallax Portsmouth developed and submitted a winning proposal to the Department of Energy in response to
Request for Proposal to replace the Bechtel Jacobs Company whose contract was expiring. The Scope included the
Clean Up and Remediation/Environmental Management Services at the Portsmouth Gaseous Diffusion Plant.
Link Scope:
In support of the requirements of LPP’ efforts to respond to DOE’s RFP and to execute the awarded contract:
Link provided an estimate of all employee and labor related transition costs in sufficient detail to be
included in the target cost of this contract. Provided support to LPP in determining other transition costs.
Proposed costs were broken down by the following major cost elements: direct labor (including labor
125 TownPark Drive, Suite 300
Kennesaw, Georgia 30144
770-919-7070
8. categories, and labor hours in each category), relocation, travel, materials, supplies, subcontracts, and all
other costs.
Link led the development of a Transition Plan, supported LPP to allow submittal within 3 days after any
award to LPP. Detail and scope had to be sufficient to meet the requirements of DOE. The objectives were:
(1) achieve an orderly transition; (2) be fair to incumbent employees and maintain a productive and flexible
work force; (3) minimize the cost of the transition and its impacts on other DOE programs; (4) promote
those practices which will result in stable collective bargaining relationships; (5) adhere to DOE’s
Workforce Restructuring Plan for the facility; (6) integrate ES&H into the transition phase to ensure safety
and regulatory compliance; and (7) ensure compliance with DOE’s Request for Proposal. The Plan had to
address LPP’s approach, methods and processes for the integration and interfaces with other contactors and
private corporations on site. This included LPP’s organizational structure, strategy and understanding of
respective site roles, methods of resolving disputes and addressing issues, and approach to transition
including continuation of remediation activities, seamless transition of human resources, and strategy for
assumption of the directed or any other subcontracts. It was also understood that Link’s main focus and
responsibility as it related to the Transition Plan was focused on employee and labor related transition
activities.
Link managed the Transition Team during the transition period to ensure all Transition Objectives were
achieved while also ensuring transition costs incurred are allowable, allocable, and reasonable. Transition
Objectives can be summarized as:
o
Informing incumbent employees about the transition and various stages of the review and hiring
process through various means of communication
o Engaging Union Labor leadership to achieve mutual understanding early in the transition
o Achieving seamless transition of payroll and benefits
o Initiating alignment with DOE (PPPO and POOG) and other site contractors through a series of
meetings and MOUs to ensure clarity of interfaces, jurisdictions, protocols, and continuity of
support
o Maintaining tight accountability of nuclear material and the security of all site assets
o Preparing to maintain safety envelope for all facilities and operations
o Ensuring readiness to maintain compliance with DOE Orders, local, state, and federal regulations,
and all remediation requirements
o Transitioning (“blue-sheeting”) all existing Policies & Procedures (several thousands) to ensure
compliance while streamlining and adapting to a new culture
o Setting the stage for future rejuvenation of people and processes to achieve DOE objectives.
Link assisted LPP in conducting labor relations in accordance with applicable laws and DOE’s intent that
labor relations policies and practices reflect the best experience of American industry in aiming to achieve
the stable labor-management relations essential to successful accomplishment of DOE’s programs at
reasonable cost. Link provided assistance in recruiting, interviewing, and selecting the LPP staff.
Thereafter, Link provided ongoing labor relations and HR consultation and advice as needed.
125 TownPark Drive, Suite 300
Kennesaw, Georgia 30144
770-919-7070
9. U.S. Department of Energy, Golden Field Office
Scope: Technical Support re: Recovery Act - Demonstration of
Integrated Biorefinery Operations; Renewable Energy Research and
Development
Background:
The Department of Energy, Office of Energy Efficiency and Renewable Energy (EERE), announced a notice of
availability of funding for financial assistance from the Office of the Biomass Program. DOE was funding
biorefinery technology development projects to meet two of the EERE performance goals: 1) dramatically reduce, or
even end, dependence on imported oil; and 2) spur the creation of the domestic bio-industry. DOE solicited
participation from industry experts to review offerings from interested parties and select the technologies and
companies who presented the most credible proposals for a path forward to commercially viable projects.
Link Scope:
Link was selected by DOE to review multiple and competing Proposals for the construction
of pilot programs, demonstration projects, test plants, and/or commercial facilities that met
the above performance goals. Link subsequently provided its conclusions and technical
advice via participation in multi-disciplined teams chartered to select the winning offerings.
Link’s experience in the following technologies and projects was critical to its award as well as the credibility of its
technical advice during the project:
Municipal Solid Waste (burning, gasification, and/or cellulosic conversion to ethanol)
Vegetable oils (to biodiesel)
Animal oils (to biodiesel),
Forest floor waste (charcoal conversion),
Wood chips/prunings (burning and gasification),
Waste sludge from paper mills (ethanol conversion from cellulosic component),
Lignin (burning),
Sewage sludge (burning),
Black/green liquor (boilers),
Waste coal (burning and gasification),
Low-grade petroleum products (boilers, turbines, and reciprocating engines),
Biochemical Conversion/Processes such:
o Transesterification of oils into biodiesel,
o Cellulosic ethanol conversion (primarily strong/weak acid conversion, but some
enzyme/bacterial),
o Combustion in fluid bed and conventional boilers,
o Pretreatment (including MSW sorting, washing, drying, acid treatment, deacidification,
distillation, bleaching, storage, material handling, conveyance, etc.)
125 TownPark Drive, Suite 300
Kennesaw, Georgia 30144
770-919-7070
10. CONTACT INFORMATION
CEO:
Kirk D. Belmont
kbelmont@linkresources.com
Office:
+1 (770) 919-7070
Fax:
+1 (770) 919-9200
President: Gary A. Sanden
gsanden@linkresources.com
Office:
+1 (770) 919-7070
Fax:
+1 (770) 919-9200
125 TownPark Drive, Suite 300
Kennesaw, Georgia 30144
770-919-7070