SlideShare a Scribd company logo
1 of 45
Download to read offline
Managing the Increase in ARRA-Focused
Projects: A Real Success Story with the
       Bayfront PMO Workbook

             Paul A. Capello, PMP
     Project Management Office Manager
           Bayfront Health Systems
                October 2010
Session Objectives

 How using a PMO Workbook will make a
 difference in the ARRA projects focused future.
Documentation, Documentation, Documentation!
       Project Scope.
       Project Change.
       Project Risk.
       Project Issues.
       Etc…….
 Bayfront Project Portfolio Success Metrics.
   “You can’t argue with Success”
Bayfront Health Systems founded in 1968, consists
  of the facilities listed below:
   • Bayfront Medical Center (BMC) St. Petersburg
   • Bayfront Medical Plaza St. Petersburg
   • Bayfront Convenient Care Clinics –Throughout
      Pinellas County(6 Locations)
   • Bayfront Family Health Center St. Petersburg
   • BayFlite- Largest Helicopter Fleet in the
      Southeast US.
   • Cerner Client since 2001
Cerner Team 2010
What is a Project At Bayfront Technology Services?



  A Bayfront Project is a “temporary”
  endeavor (consisting of greater than 40
           work)
  hours of work) undertaken to create a
  unique product, service or result, i.e., install
  new technology, upgrade or change existing
  technology.
  Projects are quantified by more than 15K in
  Capital Costs and need approval from the
  Bayfront Technology Steering Committee.
BHS Project Process
© Data from HIMSS AnalyticsTM Database   N = 5166   N = 5235

     7
American Recovery and Reinvestment Act of 2009
HR 1 -- 111th Congress
$787 Billion
Highly partisan vote

Healthcare gets $147.7 Billion
(HITECH Act)
 •$87B for Medicaid
 •$25B for support for extending COBRA
 •$10B for NIH              $19,000 Million
 •$19B directly for HIT
  8
New Project Work Breakdown Structure


        PPPD Approval Process
        Project Kickoff
        Define Software Resources
        Define Hardware Requirements
        Define Network Configuration(If applicable)
        Review Domain Strategy
        Update System Documentation
        Testing, Testing and More Testing
        On Going Training
        Production Implementation
        CLOSE-DOWN PROCESS BEGINS
PMO WORKBOOK HISTORY

In February 2004, Bayfront went Live with Cerner
from 7.8 to 2004.1(Phase 2 – 12 Nets including
ProFit!).
Subsequently, a formal PMO Methodology was
introduced which included the first rendition of the
PMO Workbook.
Cerner subsequent upgrades include:
   2005.02.46
   2005.02.54
   2007.12
   2007.19.03
ORGANIZATIONAL COMMITTMENT

One of the key foundations of Bayfront’s
 Methodology was establishing an
 effective Project Structure. Success
 requires the Bayfront's Leadership’s
 commitment to thorough planning and
 regular review and approval of Projects.
An experienced, knowledgeable and
 committed Project organization must be
 assembled and certain members
 designated as leaders.
Steering Committee

     The purpose of the Steering Committee is the
     following:
      Provide Executive Direction to the Project Team.
      Verify Projects are meeting Bayfront's Strategic
      Business objectives.
      Resolve Issues that are beyond the authority of the
      Project Team.
      Additionally, The Steering Committee will verify the
      project deliverables meet the business requirements
      of Bayfront. These meetings are conducted at key
      project milestone dates with the results
      communicated to the Project Team.
PROJECT ADMINISTRATION

Project monitoring and control procedures document
  the process and mechanisms for tracking the
  project. Proper monitoring of the project is
  dependent upon excellent communication
  throughout the project organization. This
  communication is the responsibility of the entire
  team, but
The Project Manager or Project Lead is the #1 Go To
  person on Communication.
Project Manager or Lead


Both BMC and Vendor project managers will be responsible for
  the following:
          Provide full-time project management as detailed in
          the contract.
          Monitoring project plans and implementation
          schedules to ensure upcoming tasks are identified
          and communicated to team members.
          Making task assignments and ensure task
          completion.
          Identifying and documenting potential problems or
          issues and ensuring these are communicated to the
          Project Director and Project Management Team.
          Reporting progress to the Project Director and other
          Team Leaders in status report meetings.
          Maintain the official project documentation.
Status Report for Week

Status Report
Customer:
Project:    For period: Starting:                     Ending:



Achievements This Period:

Planned Next Period:

Scope Status:

Budget Status: Original budgeted costs:   Expected final costs:

Schedule Status: Planned completion:      Expected completion:

Major Issues:
PROJECT DELIVERABLES

The key deliverables for the project are as follows:
  Visualize the final product
  Build a visual of the implemented application by posing the
  following questions to the team:
       When the system is in place, what will it look like to you?
       What does the application have to do to meet your
       critical business requirements?
       How will information get into the system?
       How will that information be updated, used, modified and
       distributed?
       What technical capabilities are essential for your
       environment?
       Will the system have to interact and/or integrate with
       other systems? If so, how will that occur?
  Milestones
       *Key deliverables
PROJECT WORK PLAN

  The project work plan is used to control the
  progress of the project on a day-to-day basis.
  The project work plan contains the detailed
  activities and tasks required to develop the
  project deliverables, to monitor progress
  compared to plan, and to assign tasks to
  project team members. The overall project
  work plan is updated weekly based on the
  accomplishments communicated at the project
  status review meetings, documented in project
  status reports, and discussion with project
  team members.
Meetings



    Project status review meetings serve to
    convey status, identify issues, and detect
    scope changes to the overall project.
    Additionally, these meetings serve as a
    tool to record and measure team
    progress and performance and ensure
    project objectives are being met. These
    meetings are conducted on a weekly or
    bi-weekly basis and typically include the
    Project Team.
Meetings

    The following agenda will be used:
          Brief summary of project to date
          Review of open issues
          Discussion of previous week’s tasks and
          accomplishments
          Review status and update project work plan
          Identify new issues, provide resolutions, or record
          on the project issue and project log forms and
          assign as appropriate
          Assign new tasks and action items for the next
          week
          The results of the meeting are summarized,
          activities recorded and minutes distributed to the
          Project Management Team. Team Leaders are
          responsible for communicating the results of
          these meetings to their sub-teams
Bayfront Technology Services
    Meeting Minutes Example
MEETING: Bayfront Change Management Meeting
DATE/PLACE/TIME: Monday March 22, 2010 Mangrove Conference room 1:00 pm
ATTENDEES: Paul Capello, Jennifer Greenman, Tony Curtis, Herman Gilyard, Denise Murphy, Mike Musallam, Denise Rafferty, Marge
Slater, Melanie McKee, Heather Morrison, Jason Barth, Helen Bruns, Dave Leclaire
          Agenda Item                     Discussion                     Action Items             Owner      Scheduled End
                                                                                                                  Date

Deactivate "beginning of year"    Some temporary code          Deactivate "beginning of year"     Melanie    TBD
hard code in programs:            exists in these              hard code in programs:             McKee
CUG100EX, CUG110EX,               programs that need to        CUG100EX, CUG110EX,
CUG140EX.                         be activated for the first   CUG140EX.
                                  run of the year, and
                                  then deactivated.
Personnel transaction custom      Not a critical item, but     Personnel transaction custom        Melanie   2/26/2010
programs needed to be             one that should be           programs needed to be modified to McKee
modified to submit the self-      cleaned up...                submit the self-service file update
service file update after the HR I have noticed several        after the HR file updates so that
file updates so that self-service people in the HR group       self-service would pick up the
would pick up the group           of self service that are     group associated with the new
associated with the new           not and never have           position. Programs to change are:
position. Programs to change      been in HR.                  CUGTRTR, CUGTRDM,
are:                              Additionally, that HR        CUGTRHI, CUGTRPR,
CUGTRTR, CUGTRDM,                 group has traditionally      CUGTRRH, CUGTRTR
CUGTRHI, CUGTRPR,                 been limited to a very
CUGTRRH, CUGTRTR                  small group of people.
                                  Not sure why it has
                                  been expanded to
                                  include people from
                                  Barely Sick etc.
Project Documentation

 Project Documentation is any material related
 to the project that provides an audit of the
 project. This includes the formal deliverables
 identified in the Project Work Plan, as well as
 project status reports, project and steering
 committee reports, supporting notes and
 memos, key decisions forms, meeting minutes,
 and other informal documentation kept by
 Project Team members to support their work
 and deliverables.
Project Documentation

• Project Documentation may be maintained in
  electronic form in designated project file
  directories, with those project documents
  requiring approval printed for distribution and
  signature. Project Leads will maintain team
  documentation, such as meeting minutes, in
  electronic and/or paper form and supply key
  deliverables to the Project Director when
  completed.
RISK MANAGEMENT
 Risk Management is the process of identifying areas of
 risk that could negatively impact the success of the
 project and proactively managing those areas. Risk is
 analyzed during the initial stages of the project to lay
 the foundation for success and on an ongoing basis
 during the project.
 Risk assessments are the means used to analyze risk.
 They highlight common areas of risk with the intent of
 identifying and controlling the risk. After high-risk
 areas are identified, risk control processes are selected
 and implemented.
 The following risk assessment describes potential high-
 risk areas of the project and documents the
 mechanisms established to control these areas.
Risk                                 Target                      Control Procedures

Business

Vendor involvement not at a level to   Vendor involvement at a level to   Vendor involvement not at a level to
insure success                         insure success                     insure success:
                                                                          •Implement regular status reporting
                                                                          •Detailed project management
                                                                          •Try to expand vendor involvement
                                                                          •Develop a very detailed project plan
                                                                          •Include frequent quality reviews




Project Environment

New system hardware required           No new system hardware required    New system hardware required:
                                                                          •Gain access to technical specialists
                                                                          •Integrate delivery and installation
                                                                          into project schedule
                                                                          •Purchase proven hardware
SECURITY / CONFIDENTIALITY

Data in all its forms (electronic, paper, or other), and throughout its life
cycle (creation, entry, storage, processing and disposal) will be protected
from unauthorized access, modification, destruction and disclosure,
whether accidental or intentional, at Bayfront Health System.
User Access Controls
     One of the key ingredients of information protection is user access
     controls over who can access the information and how they can
     access it. To ensure appropriate levels of access, security
     measures will be instituted for this project.
Security will be controlled by menu design as well as security levels
attached to individual items.
     A complete analysis of existing application access and security
     will be done and adjustments made to ensure all existing users
     have access specific to their job requirements.
Password Management
     Passwords are not displayed when entered.
Employee Awareness Programs
Monitoring/Reporting
Change Management

Change Management is the process of managing changes to
  previously agreed-upon areas of the project.
      Changes can affect many areas: the project resources,
      the project deliverables, the cost and time frame in
      which objectives must be achieved and even the
      project priority.
      Change will be viewed positively as long as its purpose
      is to ensure Bayfront's business needs are met.
      Change Management documentation preserves the
      integrity of the project definition document, provides a
      mechanism for handling change requests, and provides
      a means for retaining historical change/issue
      information to enhance future project management
      efforts.
Change Management

The following process is followed when a change to the
schedule, budget, or scope of the project is required.
Identify the Change: Determine if the change is within or
outside the scope of the project.
Record the Request: Complete the Change Request Form
and submit to the Project Manager.
Evaluate the Request: The Project Team will review the
proposed change and make a decision to approve,
disapprove, or alter the change request. The Steering
Committee will be contacted if a decision requires approval
at a higher level.
Implement the Change: If it is determined the change
should be incorporated into the project, the Project Work
Plan will be updated to reflect the change in tasks,
resource requirements, deliverables and/or timeframes.
Scope Change Request Form

Customer:

Project:

Requested by:

Description of the Change:



Justification for the Change:



Project Impacts          (Project Manager Use Only)



Budget and Schedule Impacts:(Project Manager Use Only)

New Project Completion Date:             Additional Project Costs:

Date:                                    Resolution Required by:

Signed (Project Manager):

Resolution:                  (Customer Use Only)

Approved          Rejected               Date:

Signed:

Name and Title:
Issue Management

An Issue is anything that arises which, if left unresolved, could
  delay or have an impact on the success of the project.
  All Issues are documented on the Project Issue Form. Each
  issue is prioritized, assigned an owner, and documented on
  the Project Issue Log. Issues the Project Team is unable to
  resolve are escalated to the Project Team Management for
  resolution or submission to the Steering Committee for
  resolution. Outstanding issues are reviewed at the project
  status review meeting.
  Any Issues that result in an increase in the project budget,
  time estimates, or scope must be documented on the Project
  Issue Form.
Issue Escalation Guidelines:

  Level I - Issues are resolved and documented by the Project Team
  and/or Work Team. Decision deadline: up to one (1) week.

  Level II - Issues which cannot be resolved at the Project Team
  Management level are submitted to the Project Director for review
  with the Project Team Management. Decision deadline: up to one
  (1) week.

  Level III - Issues which cannot be resolved at the Project Team
  Management level, or which are so sensitive as to require
  Executive approval, will be submitted to the Steering Committee,
  for resolution. Decision deadline: up to fourteen (14) days.

  Level IV - Issues which cannot be resolved at the Steering
  Committee level are submitted to the Project Sponsor for review
  with senior management. In addition, an issue can be escalated
  directly to Level IV based on issue criticality.
BAYFRONT MEDICAL CENTER
                                          2007.19.03 TESTING ISSUES


SR#     CWX or        DATE     APP           2007.19.03 TESTING ISSUES-              Reported              Daily Update
         SWX?                                        MOCK HPUX                          by

         CWX                            UPTIME (package installation)                           March 22nd to March 26th

                                        STEPS BEFORE GO-LIVE

      CWX-                   Fat clients Update nasp5102 with new code                       On your NAS share if you have no
      Mo, Tony                           warehouse.                                             Space issues then, rename your
                                                                                                current P5102 to P5102_VMS. Re-sync
                                                                                                the DBMIG (copy from RRD02 to NAS)
                                                                                                once done synching, create a new
                                                                                                copy of DBMIG folder and rename it to
                                                                                                P5102. Use that one for Prod Fat
                                                                                                client setup.


      CWX-       Mo          Fat clients Send new batch file for fat clients                    3-24 Mo copied to RRD02 DBMIG
                                         including setup.ini and group files


      BMC                    Fat clients David and Leonard will test upgrading fat
                                         clients before upgrade


      Mo and Tony                       BMCCitrix03- CPDI needs setup?

      Desktop                  PACS Upgrade PACS Viewing Stations for Citrix                    Almost done
                                    version 11.0
PROJECT PROFILE DOCUMENT


     I—
PART I—PROFILE IDENTIFICATION AND REGISTRATION
   1.Profile/Project
   1.Profile/Project Title
   2.Profile
   2.Profile Control Number
The PMO will register the PPP in the project control system.
   1.Profile
   1.Profile Preparation Team
        Name                   Specialty           Position




    1.Profile
    1.Profile Completion Date
    2.Business/Clinical
    2.Business/Clinical Case
       •Refer to an early stage SOC
       •Strategic Direction or Action Steps
       •Budgeted for Capital Year (Yes or No)
PART II—PROPOSED PROJECT DESCRIPTION AND
OUTLINE

     Project Scope
     Project Objectives
     Project Background/Linkage
     Project Assumptions
     Project Classification
     Recommended Project Start and
     Completion Dates
PART III—PROPOSED PROJECT MANAGEMENT PLAN
   Project Manager
   Project Management Team

        Name                Specialty          Position


 1.Project
 1.Project Phasing
 Project Phase-Workload Estimate Table
         Phase-


              Work          Recommended   Recommended     Estimated
Phase    Package/Activity     Schedule      Resource        Cost
PART IV—PROJECT EVALUATION AND VALIDATION



 4.1 Project Objectives
 4.2 Project Risks
 4.3 Project Structure
 4.4 Hardware Requirements (If applicable)
PROJECT TEAM REVIEW AND APPROVAL FORM


Document/Deliverable: Project Workbook

Date Presented:

Paul Capello, PMO Manager
Date_____________

Jennifer Greenman , Chief Information Officer
Date_____________
The Standish Group surveyed 365
  respondents covering 8,380 IT applications
 Project Success Statistics
  across several industries:
   • 16.2% of projects completed on-time
     and on-budget. .(Bayfront success rate
     is 95%)
   • 52.7% of projects completed over
     budget, over time, and with fewer
     features than originally specified.
   • 31.1% of projects canceled during the
     development cycle.
Bayfront Project Portfolio 2009-2010
                                                  Project Name
Pharmacy Clinical Intervention Documentation
Email antispyware / Antispam and Trend Antivirus / Antispyware systems
Explorer Menu Clean Up
Philips Xcelera upgrade for Cardiology
QoS/Traffic Shaping on Internet
RAD PACS and Cerner Labs for Heart Center/EP
WISM(Wireless Services Module)
Physician Progress Notes
Life Net Stemi for ED/Cardiac
Clinical Transformation - Post Partum Documentation
Clinical Transformation - Documentation( Phase 1 Form Roll Out and Phase 2 Form Design)
McKesson Accudose
PACS Cube
Point of Care(Arterial Blood Gases)
CLINICAL TRANSFORMATION - Handoffs & PAL & Hardware Assessment
IN BOX
ShoreTel Phone and Voicemail Migration
Cerner Provision Document Imaging(Patient Access Services)
Cerner Provision Document Imaging(Medical Records(HIM)
Cerner Provision Document Imaging(Pharmacy Order Management)
CBORD Upgrade
Optimal Radiology Interface
Sentry Data Systems
All Children's - OB Project - Baby Place
Health Line ECHO ASP for Med Staff Office
Nortel Conversion
Trauma Base
Kronos
Cerner 2007.19
PMO Value
   According to Forrester Research®,
companies that implemented a successful
PMO achieved an 80% ROI, 20% reduction
            in project time.

Companies without a PMO experienced a
74% project failure rate. That is a sobering
                 statistic.
                 statistic

Bayfront’s successful PMO is in its 7th year
               of existence.
Bayfront Active Projects
Project                     Project Name                          Status       Project Mgr
   #
   1      Cerner Provision Document Imaging(Lab)                   Active   Shari Goodwin
   2      CPOE                                                     Active   Paul Capello
   3      SurgiNet                                                 Active   John Amodeo
          CLINICAL TRANSFORMATION - Rehab Evaluation &
   4      Treatment Documentation                                  Active   Denise Murphy
   5      CLINICAL TRANSFORMATION- Medication Reconciliation       Active   Lee Ann Sahagun
   6      CLINICAL TRANSFORMATION- ED Documentation                Active   Lee Ann Sahagun
   7      CLINICAL TRANSFORMATION - Depart Process                 Active   John Amodeo
   8      NextGen Ambulatory EHR                                   Active   Heather Morrison
   9      Care Focus/ Mercury MD                                   Active   Heather Morrison
   10     INFOR AP and Material Mgt                                Active   Melanie McKee
   11     6 South Conversion                                       Active   Dale Graf
   12     Philips Xcelera and XPER Upgrade                         Active   Jason Barth



                                Active                              12
                               Complete                             222
                               Not Active                           59
                                                          Total     293
A Computer in the Patient Room?
     “That it will ever come into general use,
       notwithstanding its value, is extremely doubtful
       because its beneficial application requires much
       time and gives a good bit of trouble, both to the
       patient and to the practitioner because its hue
       and character are foreign and opposed to all our
       habits and associations.”

                          - The London Times, 1834
                          Commenting on the
44
                          “stethoscope”
Questions and Answers?
  Email: Paul.Capello@bayfront.org
Name: Paul Capello
  Phone: 727-893-6038
Email: Paul.Capello@bayfront.org

Phone: 727-893-6038

More Related Content

What's hot

Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11PMA Consultants
 
File 2 removed 5 words 1
File 2 removed 5 words 1File 2 removed 5 words 1
File 2 removed 5 words 1test prod1
 
File 2 removed word 1
File 2 removed word 1File 2 removed word 1
File 2 removed word 1test prod1
 
File 2 removed word 2
File 2 removed word 2File 2 removed word 2
File 2 removed word 2test prod1
 
File 2 extra slide 2
File 2 extra slide 2File 2 extra slide 2
File 2 extra slide 2test prod1
 
File 2 removed 4 slides 2
File 2 removed 4 slides 2File 2 removed 4 slides 2
File 2 removed 4 slides 2test prod1
 
File 2 removed 1 slide 2
File 2 removed 1 slide 2File 2 removed 1 slide 2
File 2 removed 1 slide 2test prod1
 
File 2 removed 1 word from 5 slides 2
File 2 removed 1 word from 5 slides 2File 2 removed 1 word from 5 slides 2
File 2 removed 1 word from 5 slides 2test prod1
 
File 2 original copy 1
File 2 original  copy 1File 2 original  copy 1
File 2 original copy 1test prod1
 
File 2 removed 5 words 2
File 2 removed 5 words 2File 2 removed 5 words 2
File 2 removed 5 words 2test prod1
 
File 2 four extra slides 2
File 2 four extra slides 2File 2 four extra slides 2
File 2 four extra slides 2test prod1
 
Observation Report-CRP-22July-2014
Observation Report-CRP-22July-2014Observation Report-CRP-22July-2014
Observation Report-CRP-22July-2014Rahmat Hashim, PMP
 
File 2 removed 4 slides 1
File 2 removed 4 slides 1File 2 removed 4 slides 1
File 2 removed 4 slides 1test prod1
 
File 2 removed 1 slide 1
File 2 removed 1 slide 1File 2 removed 1 slide 1
File 2 removed 1 slide 1test prod1
 
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management ProcessesKCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management ProcessesKing Consulting Services
 
File 2 removed 1 word from 5 slides 1
File 2 removed 1 word from 5 slides 1File 2 removed 1 word from 5 slides 1
File 2 removed 1 word from 5 slides 1test prod1
 
Ingoldsby.k.lee.y
Ingoldsby.k.lee.yIngoldsby.k.lee.y
Ingoldsby.k.lee.yNASAPMC
 

What's hot (17)

Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
File 2 removed 5 words 1
File 2 removed 5 words 1File 2 removed 5 words 1
File 2 removed 5 words 1
 
File 2 removed word 1
File 2 removed word 1File 2 removed word 1
File 2 removed word 1
 
File 2 removed word 2
File 2 removed word 2File 2 removed word 2
File 2 removed word 2
 
File 2 extra slide 2
File 2 extra slide 2File 2 extra slide 2
File 2 extra slide 2
 
File 2 removed 4 slides 2
File 2 removed 4 slides 2File 2 removed 4 slides 2
File 2 removed 4 slides 2
 
File 2 removed 1 slide 2
File 2 removed 1 slide 2File 2 removed 1 slide 2
File 2 removed 1 slide 2
 
File 2 removed 1 word from 5 slides 2
File 2 removed 1 word from 5 slides 2File 2 removed 1 word from 5 slides 2
File 2 removed 1 word from 5 slides 2
 
File 2 original copy 1
File 2 original  copy 1File 2 original  copy 1
File 2 original copy 1
 
File 2 removed 5 words 2
File 2 removed 5 words 2File 2 removed 5 words 2
File 2 removed 5 words 2
 
File 2 four extra slides 2
File 2 four extra slides 2File 2 four extra slides 2
File 2 four extra slides 2
 
Observation Report-CRP-22July-2014
Observation Report-CRP-22July-2014Observation Report-CRP-22July-2014
Observation Report-CRP-22July-2014
 
File 2 removed 4 slides 1
File 2 removed 4 slides 1File 2 removed 4 slides 1
File 2 removed 4 slides 1
 
File 2 removed 1 slide 1
File 2 removed 1 slide 1File 2 removed 1 slide 1
File 2 removed 1 slide 1
 
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management ProcessesKCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
 
File 2 removed 1 word from 5 slides 1
File 2 removed 1 word from 5 slides 1File 2 removed 1 word from 5 slides 1
File 2 removed 1 word from 5 slides 1
 
Ingoldsby.k.lee.y
Ingoldsby.k.lee.yIngoldsby.k.lee.y
Ingoldsby.k.lee.y
 

Similar to Paul Capello Cerner Health Conference

Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011tigcap
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management ProjectMary Stevenson
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxjessiehampson
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overviewcford1973
 
Project Scope StatementProject NameStudent NameDateI.docx
Project Scope StatementProject NameStudent NameDateI.docxProject Scope StatementProject NameStudent NameDateI.docx
Project Scope StatementProject NameStudent NameDateI.docxwkyra78
 
File 2 original copy 2
File 2 original  copy 2File 2 original  copy 2
File 2 original copy 2test prod1
 
File 2 original
File 2 originalFile 2 original
File 2 originaltest prod1
 
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdf
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdfCase Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdf
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdfsales88
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management MethodologyMohammed Al-Taee
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time ManagementSabrinaScott22
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1Imoh Etuk
 
project management plan.pptx
project management plan.pptxproject management plan.pptx
project management plan.pptxNimra zaman
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Renee Jones
 
ProjectManagementforNGOs
ProjectManagementforNGOsProjectManagementforNGOs
ProjectManagementforNGOswebuploader
 
Project management professional
Project management professionalProject management professional
Project management professionalReema
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project SummaryMinhas Kamal
 
Project management paradigm
Project management paradigmProject management paradigm
Project management paradigmGlen Alleman
 

Similar to Paul Capello Cerner Health Conference (20)

Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
Project Scope StatementProject NameStudent NameDateI.docx
Project Scope StatementProject NameStudent NameDateI.docxProject Scope StatementProject NameStudent NameDateI.docx
Project Scope StatementProject NameStudent NameDateI.docx
 
File 2 original copy 2
File 2 original  copy 2File 2 original  copy 2
File 2 original copy 2
 
File 2 original
File 2 originalFile 2 original
File 2 original
 
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdf
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdfCase Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdf
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdf
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management Methodology
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
project management plan.pptx
project management plan.pptxproject management plan.pptx
project management plan.pptx
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
ProjectManagementforNGOs
ProjectManagementforNGOsProjectManagementforNGOs
ProjectManagementforNGOs
 
Project management professional
Project management professionalProject management professional
Project management professional
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project Summary
 
Project management paradigm
Project management paradigmProject management paradigm
Project management paradigm
 

More from tigcap

HFMA Published article
HFMA Published articleHFMA Published article
HFMA Published articletigcap
 
The 9 Elements of Successful Health Care Consulting Whitepaper.Final
The 9 Elements of Successful Health Care Consulting Whitepaper.FinalThe 9 Elements of Successful Health Care Consulting Whitepaper.Final
The 9 Elements of Successful Health Care Consulting Whitepaper.Finaltigcap
 
The Value of A PMO
The Value of A PMOThe Value of A PMO
The Value of A PMOtigcap
 
PMO 2010 Research Report
PMO 2010 Research ReportPMO 2010 Research Report
PMO 2010 Research Reporttigcap
 
Pc 2011 Epmo Plan
Pc 2011 Epmo PlanPc 2011 Epmo Plan
Pc 2011 Epmo Plantigcap
 
Paul Capello CHC 2010 Final
Paul Capello CHC 2010 FinalPaul Capello CHC 2010 Final
Paul Capello CHC 2010 Finaltigcap
 

More from tigcap (6)

HFMA Published article
HFMA Published articleHFMA Published article
HFMA Published article
 
The 9 Elements of Successful Health Care Consulting Whitepaper.Final
The 9 Elements of Successful Health Care Consulting Whitepaper.FinalThe 9 Elements of Successful Health Care Consulting Whitepaper.Final
The 9 Elements of Successful Health Care Consulting Whitepaper.Final
 
The Value of A PMO
The Value of A PMOThe Value of A PMO
The Value of A PMO
 
PMO 2010 Research Report
PMO 2010 Research ReportPMO 2010 Research Report
PMO 2010 Research Report
 
Pc 2011 Epmo Plan
Pc 2011 Epmo PlanPc 2011 Epmo Plan
Pc 2011 Epmo Plan
 
Paul Capello CHC 2010 Final
Paul Capello CHC 2010 FinalPaul Capello CHC 2010 Final
Paul Capello CHC 2010 Final
 

Paul Capello Cerner Health Conference

  • 1. Managing the Increase in ARRA-Focused Projects: A Real Success Story with the Bayfront PMO Workbook Paul A. Capello, PMP Project Management Office Manager Bayfront Health Systems October 2010
  • 2. Session Objectives How using a PMO Workbook will make a difference in the ARRA projects focused future. Documentation, Documentation, Documentation! Project Scope. Project Change. Project Risk. Project Issues. Etc……. Bayfront Project Portfolio Success Metrics. “You can’t argue with Success”
  • 3. Bayfront Health Systems founded in 1968, consists of the facilities listed below: • Bayfront Medical Center (BMC) St. Petersburg • Bayfront Medical Plaza St. Petersburg • Bayfront Convenient Care Clinics –Throughout Pinellas County(6 Locations) • Bayfront Family Health Center St. Petersburg • BayFlite- Largest Helicopter Fleet in the Southeast US. • Cerner Client since 2001
  • 5. What is a Project At Bayfront Technology Services? A Bayfront Project is a “temporary” endeavor (consisting of greater than 40 work) hours of work) undertaken to create a unique product, service or result, i.e., install new technology, upgrade or change existing technology. Projects are quantified by more than 15K in Capital Costs and need approval from the Bayfront Technology Steering Committee.
  • 7. © Data from HIMSS AnalyticsTM Database N = 5166 N = 5235 7
  • 8. American Recovery and Reinvestment Act of 2009 HR 1 -- 111th Congress $787 Billion Highly partisan vote Healthcare gets $147.7 Billion (HITECH Act) •$87B for Medicaid •$25B for support for extending COBRA •$10B for NIH $19,000 Million •$19B directly for HIT 8
  • 9. New Project Work Breakdown Structure PPPD Approval Process Project Kickoff Define Software Resources Define Hardware Requirements Define Network Configuration(If applicable) Review Domain Strategy Update System Documentation Testing, Testing and More Testing On Going Training Production Implementation CLOSE-DOWN PROCESS BEGINS
  • 10.
  • 11. PMO WORKBOOK HISTORY In February 2004, Bayfront went Live with Cerner from 7.8 to 2004.1(Phase 2 – 12 Nets including ProFit!). Subsequently, a formal PMO Methodology was introduced which included the first rendition of the PMO Workbook. Cerner subsequent upgrades include: 2005.02.46 2005.02.54 2007.12 2007.19.03
  • 12. ORGANIZATIONAL COMMITTMENT One of the key foundations of Bayfront’s Methodology was establishing an effective Project Structure. Success requires the Bayfront's Leadership’s commitment to thorough planning and regular review and approval of Projects. An experienced, knowledgeable and committed Project organization must be assembled and certain members designated as leaders.
  • 13. Steering Committee The purpose of the Steering Committee is the following: Provide Executive Direction to the Project Team. Verify Projects are meeting Bayfront's Strategic Business objectives. Resolve Issues that are beyond the authority of the Project Team. Additionally, The Steering Committee will verify the project deliverables meet the business requirements of Bayfront. These meetings are conducted at key project milestone dates with the results communicated to the Project Team.
  • 14. PROJECT ADMINISTRATION Project monitoring and control procedures document the process and mechanisms for tracking the project. Proper monitoring of the project is dependent upon excellent communication throughout the project organization. This communication is the responsibility of the entire team, but The Project Manager or Project Lead is the #1 Go To person on Communication.
  • 15. Project Manager or Lead Both BMC and Vendor project managers will be responsible for the following: Provide full-time project management as detailed in the contract. Monitoring project plans and implementation schedules to ensure upcoming tasks are identified and communicated to team members. Making task assignments and ensure task completion. Identifying and documenting potential problems or issues and ensuring these are communicated to the Project Director and Project Management Team. Reporting progress to the Project Director and other Team Leaders in status report meetings. Maintain the official project documentation.
  • 16. Status Report for Week Status Report Customer: Project: For period: Starting: Ending: Achievements This Period: Planned Next Period: Scope Status: Budget Status: Original budgeted costs: Expected final costs: Schedule Status: Planned completion: Expected completion: Major Issues:
  • 17. PROJECT DELIVERABLES The key deliverables for the project are as follows: Visualize the final product Build a visual of the implemented application by posing the following questions to the team: When the system is in place, what will it look like to you? What does the application have to do to meet your critical business requirements? How will information get into the system? How will that information be updated, used, modified and distributed? What technical capabilities are essential for your environment? Will the system have to interact and/or integrate with other systems? If so, how will that occur? Milestones *Key deliverables
  • 18. PROJECT WORK PLAN The project work plan is used to control the progress of the project on a day-to-day basis. The project work plan contains the detailed activities and tasks required to develop the project deliverables, to monitor progress compared to plan, and to assign tasks to project team members. The overall project work plan is updated weekly based on the accomplishments communicated at the project status review meetings, documented in project status reports, and discussion with project team members.
  • 19. Meetings Project status review meetings serve to convey status, identify issues, and detect scope changes to the overall project. Additionally, these meetings serve as a tool to record and measure team progress and performance and ensure project objectives are being met. These meetings are conducted on a weekly or bi-weekly basis and typically include the Project Team.
  • 20.
  • 21. Meetings The following agenda will be used: Brief summary of project to date Review of open issues Discussion of previous week’s tasks and accomplishments Review status and update project work plan Identify new issues, provide resolutions, or record on the project issue and project log forms and assign as appropriate Assign new tasks and action items for the next week The results of the meeting are summarized, activities recorded and minutes distributed to the Project Management Team. Team Leaders are responsible for communicating the results of these meetings to their sub-teams
  • 22. Bayfront Technology Services Meeting Minutes Example MEETING: Bayfront Change Management Meeting DATE/PLACE/TIME: Monday March 22, 2010 Mangrove Conference room 1:00 pm ATTENDEES: Paul Capello, Jennifer Greenman, Tony Curtis, Herman Gilyard, Denise Murphy, Mike Musallam, Denise Rafferty, Marge Slater, Melanie McKee, Heather Morrison, Jason Barth, Helen Bruns, Dave Leclaire Agenda Item Discussion Action Items Owner Scheduled End Date Deactivate "beginning of year" Some temporary code Deactivate "beginning of year" Melanie TBD hard code in programs: exists in these hard code in programs: McKee CUG100EX, CUG110EX, programs that need to CUG100EX, CUG110EX, CUG140EX. be activated for the first CUG140EX. run of the year, and then deactivated. Personnel transaction custom Not a critical item, but Personnel transaction custom Melanie 2/26/2010 programs needed to be one that should be programs needed to be modified to McKee modified to submit the self- cleaned up... submit the self-service file update service file update after the HR I have noticed several after the HR file updates so that file updates so that self-service people in the HR group self-service would pick up the would pick up the group of self service that are group associated with the new associated with the new not and never have position. Programs to change are: position. Programs to change been in HR. CUGTRTR, CUGTRDM, are: Additionally, that HR CUGTRHI, CUGTRPR, CUGTRTR, CUGTRDM, group has traditionally CUGTRRH, CUGTRTR CUGTRHI, CUGTRPR, been limited to a very CUGTRRH, CUGTRTR small group of people. Not sure why it has been expanded to include people from Barely Sick etc.
  • 23. Project Documentation Project Documentation is any material related to the project that provides an audit of the project. This includes the formal deliverables identified in the Project Work Plan, as well as project status reports, project and steering committee reports, supporting notes and memos, key decisions forms, meeting minutes, and other informal documentation kept by Project Team members to support their work and deliverables.
  • 24. Project Documentation • Project Documentation may be maintained in electronic form in designated project file directories, with those project documents requiring approval printed for distribution and signature. Project Leads will maintain team documentation, such as meeting minutes, in electronic and/or paper form and supply key deliverables to the Project Director when completed.
  • 25. RISK MANAGEMENT Risk Management is the process of identifying areas of risk that could negatively impact the success of the project and proactively managing those areas. Risk is analyzed during the initial stages of the project to lay the foundation for success and on an ongoing basis during the project. Risk assessments are the means used to analyze risk. They highlight common areas of risk with the intent of identifying and controlling the risk. After high-risk areas are identified, risk control processes are selected and implemented. The following risk assessment describes potential high- risk areas of the project and documents the mechanisms established to control these areas.
  • 26. Risk Target Control Procedures Business Vendor involvement not at a level to Vendor involvement at a level to Vendor involvement not at a level to insure success insure success insure success: •Implement regular status reporting •Detailed project management •Try to expand vendor involvement •Develop a very detailed project plan •Include frequent quality reviews Project Environment New system hardware required No new system hardware required New system hardware required: •Gain access to technical specialists •Integrate delivery and installation into project schedule •Purchase proven hardware
  • 27. SECURITY / CONFIDENTIALITY Data in all its forms (electronic, paper, or other), and throughout its life cycle (creation, entry, storage, processing and disposal) will be protected from unauthorized access, modification, destruction and disclosure, whether accidental or intentional, at Bayfront Health System. User Access Controls One of the key ingredients of information protection is user access controls over who can access the information and how they can access it. To ensure appropriate levels of access, security measures will be instituted for this project. Security will be controlled by menu design as well as security levels attached to individual items. A complete analysis of existing application access and security will be done and adjustments made to ensure all existing users have access specific to their job requirements. Password Management Passwords are not displayed when entered. Employee Awareness Programs Monitoring/Reporting
  • 28. Change Management Change Management is the process of managing changes to previously agreed-upon areas of the project. Changes can affect many areas: the project resources, the project deliverables, the cost and time frame in which objectives must be achieved and even the project priority. Change will be viewed positively as long as its purpose is to ensure Bayfront's business needs are met. Change Management documentation preserves the integrity of the project definition document, provides a mechanism for handling change requests, and provides a means for retaining historical change/issue information to enhance future project management efforts.
  • 29. Change Management The following process is followed when a change to the schedule, budget, or scope of the project is required. Identify the Change: Determine if the change is within or outside the scope of the project. Record the Request: Complete the Change Request Form and submit to the Project Manager. Evaluate the Request: The Project Team will review the proposed change and make a decision to approve, disapprove, or alter the change request. The Steering Committee will be contacted if a decision requires approval at a higher level. Implement the Change: If it is determined the change should be incorporated into the project, the Project Work Plan will be updated to reflect the change in tasks, resource requirements, deliverables and/or timeframes.
  • 30. Scope Change Request Form Customer: Project: Requested by: Description of the Change: Justification for the Change: Project Impacts (Project Manager Use Only) Budget and Schedule Impacts:(Project Manager Use Only) New Project Completion Date: Additional Project Costs: Date: Resolution Required by: Signed (Project Manager): Resolution: (Customer Use Only) Approved Rejected Date: Signed: Name and Title:
  • 31.
  • 32. Issue Management An Issue is anything that arises which, if left unresolved, could delay or have an impact on the success of the project. All Issues are documented on the Project Issue Form. Each issue is prioritized, assigned an owner, and documented on the Project Issue Log. Issues the Project Team is unable to resolve are escalated to the Project Team Management for resolution or submission to the Steering Committee for resolution. Outstanding issues are reviewed at the project status review meeting. Any Issues that result in an increase in the project budget, time estimates, or scope must be documented on the Project Issue Form.
  • 33. Issue Escalation Guidelines: Level I - Issues are resolved and documented by the Project Team and/or Work Team. Decision deadline: up to one (1) week. Level II - Issues which cannot be resolved at the Project Team Management level are submitted to the Project Director for review with the Project Team Management. Decision deadline: up to one (1) week. Level III - Issues which cannot be resolved at the Project Team Management level, or which are so sensitive as to require Executive approval, will be submitted to the Steering Committee, for resolution. Decision deadline: up to fourteen (14) days. Level IV - Issues which cannot be resolved at the Steering Committee level are submitted to the Project Sponsor for review with senior management. In addition, an issue can be escalated directly to Level IV based on issue criticality.
  • 34. BAYFRONT MEDICAL CENTER 2007.19.03 TESTING ISSUES SR# CWX or DATE APP 2007.19.03 TESTING ISSUES- Reported Daily Update SWX? MOCK HPUX by CWX UPTIME (package installation) March 22nd to March 26th STEPS BEFORE GO-LIVE CWX- Fat clients Update nasp5102 with new code On your NAS share if you have no Mo, Tony warehouse. Space issues then, rename your current P5102 to P5102_VMS. Re-sync the DBMIG (copy from RRD02 to NAS) once done synching, create a new copy of DBMIG folder and rename it to P5102. Use that one for Prod Fat client setup. CWX- Mo Fat clients Send new batch file for fat clients 3-24 Mo copied to RRD02 DBMIG including setup.ini and group files BMC Fat clients David and Leonard will test upgrading fat clients before upgrade Mo and Tony BMCCitrix03- CPDI needs setup? Desktop PACS Upgrade PACS Viewing Stations for Citrix Almost done version 11.0
  • 35. PROJECT PROFILE DOCUMENT I— PART I—PROFILE IDENTIFICATION AND REGISTRATION 1.Profile/Project 1.Profile/Project Title 2.Profile 2.Profile Control Number The PMO will register the PPP in the project control system. 1.Profile 1.Profile Preparation Team Name Specialty Position 1.Profile 1.Profile Completion Date 2.Business/Clinical 2.Business/Clinical Case •Refer to an early stage SOC •Strategic Direction or Action Steps •Budgeted for Capital Year (Yes or No)
  • 36. PART II—PROPOSED PROJECT DESCRIPTION AND OUTLINE Project Scope Project Objectives Project Background/Linkage Project Assumptions Project Classification Recommended Project Start and Completion Dates
  • 37. PART III—PROPOSED PROJECT MANAGEMENT PLAN Project Manager Project Management Team Name Specialty Position 1.Project 1.Project Phasing Project Phase-Workload Estimate Table Phase- Work Recommended Recommended Estimated Phase Package/Activity Schedule Resource Cost
  • 38. PART IV—PROJECT EVALUATION AND VALIDATION 4.1 Project Objectives 4.2 Project Risks 4.3 Project Structure 4.4 Hardware Requirements (If applicable)
  • 39. PROJECT TEAM REVIEW AND APPROVAL FORM Document/Deliverable: Project Workbook Date Presented: Paul Capello, PMO Manager Date_____________ Jennifer Greenman , Chief Information Officer Date_____________
  • 40. The Standish Group surveyed 365 respondents covering 8,380 IT applications Project Success Statistics across several industries: • 16.2% of projects completed on-time and on-budget. .(Bayfront success rate is 95%) • 52.7% of projects completed over budget, over time, and with fewer features than originally specified. • 31.1% of projects canceled during the development cycle.
  • 41. Bayfront Project Portfolio 2009-2010 Project Name Pharmacy Clinical Intervention Documentation Email antispyware / Antispam and Trend Antivirus / Antispyware systems Explorer Menu Clean Up Philips Xcelera upgrade for Cardiology QoS/Traffic Shaping on Internet RAD PACS and Cerner Labs for Heart Center/EP WISM(Wireless Services Module) Physician Progress Notes Life Net Stemi for ED/Cardiac Clinical Transformation - Post Partum Documentation Clinical Transformation - Documentation( Phase 1 Form Roll Out and Phase 2 Form Design) McKesson Accudose PACS Cube Point of Care(Arterial Blood Gases) CLINICAL TRANSFORMATION - Handoffs & PAL & Hardware Assessment IN BOX ShoreTel Phone and Voicemail Migration Cerner Provision Document Imaging(Patient Access Services) Cerner Provision Document Imaging(Medical Records(HIM) Cerner Provision Document Imaging(Pharmacy Order Management) CBORD Upgrade Optimal Radiology Interface Sentry Data Systems All Children's - OB Project - Baby Place Health Line ECHO ASP for Med Staff Office Nortel Conversion Trauma Base Kronos Cerner 2007.19
  • 42. PMO Value According to Forrester Research®, companies that implemented a successful PMO achieved an 80% ROI, 20% reduction in project time. Companies without a PMO experienced a 74% project failure rate. That is a sobering statistic. statistic Bayfront’s successful PMO is in its 7th year of existence.
  • 43. Bayfront Active Projects Project Project Name Status Project Mgr # 1 Cerner Provision Document Imaging(Lab) Active Shari Goodwin 2 CPOE Active Paul Capello 3 SurgiNet Active John Amodeo CLINICAL TRANSFORMATION - Rehab Evaluation & 4 Treatment Documentation Active Denise Murphy 5 CLINICAL TRANSFORMATION- Medication Reconciliation Active Lee Ann Sahagun 6 CLINICAL TRANSFORMATION- ED Documentation Active Lee Ann Sahagun 7 CLINICAL TRANSFORMATION - Depart Process Active John Amodeo 8 NextGen Ambulatory EHR Active Heather Morrison 9 Care Focus/ Mercury MD Active Heather Morrison 10 INFOR AP and Material Mgt Active Melanie McKee 11 6 South Conversion Active Dale Graf 12 Philips Xcelera and XPER Upgrade Active Jason Barth Active 12 Complete 222 Not Active 59 Total 293
  • 44. A Computer in the Patient Room? “That it will ever come into general use, notwithstanding its value, is extremely doubtful because its beneficial application requires much time and gives a good bit of trouble, both to the patient and to the practitioner because its hue and character are foreign and opposed to all our habits and associations.” - The London Times, 1834 Commenting on the 44 “stethoscope”
  • 45. Questions and Answers? Email: Paul.Capello@bayfront.org Name: Paul Capello Phone: 727-893-6038 Email: Paul.Capello@bayfront.org Phone: 727-893-6038