The document provides background information on relevant acts and potential offenders related to illegal dumping and asbestos waste. It discusses prevention measures that should start at the source site, such as notifications to WorkCover and local councils. It outlines the differences between bonded and friable asbestos and how bonded asbestos can become friable. The document also discusses options for issuing cleanup notices, orders, and penalties to address illegal dumping situations and ensure proper removal and disposal of asbestos waste.
Environmental control measures
Storage.
1. Storage areas for fuels, oils and chemicals will be located away from heavily trafficked areas. If this is not possible the fuels, oils and chemicals will be protected from damage by vehicle impact.
2. Tanks for fuels, oils and chemicals will be bunded with all pipe work kept inside the bund. Bunds containing more than 200 litres of oil, fuel or other liquids will hold 110% of the largest tanks capacity. Fuel dispensing hoses should be fitted with automatic cut-off valves. The area around the tanks and bunds will be concreted and graded so that spills can be contained and easily cleaned up.
3. Drums will be kept in a bund or drip tray in a designated area, with a designated area for empty drums awaiting removal from site
4. Small containers of liquids will be kept in a location where they will not cause pollution if accidentally split
5. Bags and sacks of materials will be kept off the ground on pallets in a designated area and covered
6. All containers will be labelled with their contents and capacity
7. Training and information to be given to all operatives
Refuelling
1. Bulk refuelling of tanks will be supervised by a nominated and competent personnel
2. Levels in tanks will be checked before delivery to prevent overflowing
3. Training and information to be given to all operatives.
PAB Resolution
IN THE MATTER OF
WATER POLLUTION CONTROL
AND ABATEMENT CASE
DENR-PAB Case No. CAR-00836-12
- versus-
PHILEX MINING CORPORATION,
Respondent.
FOR: Violation of R.A. 9275 and Its
Implementing Rules and Regulations
25 February 2013
Commercial and residential trash removal, bulk hauling construction services. Clearing these mounds of years-old waste,
called legacy waste, DCC initiative west Recycle is the largest waste management solution in India.
12 daniel c. meess - 4955983 - side loading vault system and method for the...Mello_Patent_Registry
Daniel C. Meess, Bobby J. Jones, Raymond M. Mello, Thomas G. Weiss, Jr, James B. Wright - Side Loading Vault System and Method for the Disposal of Radioactive Waste
We are Exclusive world suppliers of Massive Landscape Specimen Baobab trees, these beautiful trees are being Salvage Harvested (Saved from being Destroyed) by us from massive Land Clearing operations. We export these around the world to Botanic Gardens, Zoo's, Public Gardens, High End Landscapes including Palaces, Embassies, Mansions and Mansionetts,Luxury Villas and
City Councils for Street plantings.
A workshop hosted by the South African Journal of Science aimed at postgraduate students and early career researchers with little or no experience in writing and publishing journal articles.
Delivering Micro-Credentials in Technical and Vocational Education and TrainingAG2 Design
Explore how micro-credentials are transforming Technical and Vocational Education and Training (TVET) with this comprehensive slide deck. Discover what micro-credentials are, their importance in TVET, the advantages they offer, and the insights from industry experts. Additionally, learn about the top software applications available for creating and managing micro-credentials. This presentation also includes valuable resources and a discussion on the future of these specialised certifications.
For more detailed information on delivering micro-credentials in TVET, visit this https://tvettrainer.com/delivering-micro-credentials-in-tvet/
More Related Content
Similar to Effective building site and pollution issues with asbestos
Environmental control measures
Storage.
1. Storage areas for fuels, oils and chemicals will be located away from heavily trafficked areas. If this is not possible the fuels, oils and chemicals will be protected from damage by vehicle impact.
2. Tanks for fuels, oils and chemicals will be bunded with all pipe work kept inside the bund. Bunds containing more than 200 litres of oil, fuel or other liquids will hold 110% of the largest tanks capacity. Fuel dispensing hoses should be fitted with automatic cut-off valves. The area around the tanks and bunds will be concreted and graded so that spills can be contained and easily cleaned up.
3. Drums will be kept in a bund or drip tray in a designated area, with a designated area for empty drums awaiting removal from site
4. Small containers of liquids will be kept in a location where they will not cause pollution if accidentally split
5. Bags and sacks of materials will be kept off the ground on pallets in a designated area and covered
6. All containers will be labelled with their contents and capacity
7. Training and information to be given to all operatives
Refuelling
1. Bulk refuelling of tanks will be supervised by a nominated and competent personnel
2. Levels in tanks will be checked before delivery to prevent overflowing
3. Training and information to be given to all operatives.
PAB Resolution
IN THE MATTER OF
WATER POLLUTION CONTROL
AND ABATEMENT CASE
DENR-PAB Case No. CAR-00836-12
- versus-
PHILEX MINING CORPORATION,
Respondent.
FOR: Violation of R.A. 9275 and Its
Implementing Rules and Regulations
25 February 2013
Commercial and residential trash removal, bulk hauling construction services. Clearing these mounds of years-old waste,
called legacy waste, DCC initiative west Recycle is the largest waste management solution in India.
12 daniel c. meess - 4955983 - side loading vault system and method for the...Mello_Patent_Registry
Daniel C. Meess, Bobby J. Jones, Raymond M. Mello, Thomas G. Weiss, Jr, James B. Wright - Side Loading Vault System and Method for the Disposal of Radioactive Waste
We are Exclusive world suppliers of Massive Landscape Specimen Baobab trees, these beautiful trees are being Salvage Harvested (Saved from being Destroyed) by us from massive Land Clearing operations. We export these around the world to Botanic Gardens, Zoo's, Public Gardens, High End Landscapes including Palaces, Embassies, Mansions and Mansionetts,Luxury Villas and
City Councils for Street plantings.
A workshop hosted by the South African Journal of Science aimed at postgraduate students and early career researchers with little or no experience in writing and publishing journal articles.
Delivering Micro-Credentials in Technical and Vocational Education and TrainingAG2 Design
Explore how micro-credentials are transforming Technical and Vocational Education and Training (TVET) with this comprehensive slide deck. Discover what micro-credentials are, their importance in TVET, the advantages they offer, and the insights from industry experts. Additionally, learn about the top software applications available for creating and managing micro-credentials. This presentation also includes valuable resources and a discussion on the future of these specialised certifications.
For more detailed information on delivering micro-credentials in TVET, visit this https://tvettrainer.com/delivering-micro-credentials-in-tvet/
Safalta Digital marketing institute in Noida, provide complete applications that encompass a huge range of virtual advertising and marketing additives, which includes search engine optimization, virtual communication advertising, pay-per-click on marketing, content material advertising, internet analytics, and greater. These university courses are designed for students who possess a comprehensive understanding of virtual marketing strategies and attributes.Safalta Digital Marketing Institute in Noida is a first choice for young individuals or students who are looking to start their careers in the field of digital advertising. The institute gives specialized courses designed and certification.
for beginners, providing thorough training in areas such as SEO, digital communication marketing, and PPC training in Noida. After finishing the program, students receive the certifications recognised by top different universitie, setting a strong foundation for a successful career in digital marketing.
This slide is special for master students (MIBS & MIFB) in UUM. Also useful for readers who are interested in the topic of contemporary Islamic banking.
The simplified electron and muon model, Oscillating Spacetime: The Foundation...RitikBhardwaj56
Discover the Simplified Electron and Muon Model: A New Wave-Based Approach to Understanding Particles delves into a groundbreaking theory that presents electrons and muons as rotating soliton waves within oscillating spacetime. Geared towards students, researchers, and science buffs, this book breaks down complex ideas into simple explanations. It covers topics such as electron waves, temporal dynamics, and the implications of this model on particle physics. With clear illustrations and easy-to-follow explanations, readers will gain a new outlook on the universe's fundamental nature.
it describes the bony anatomy including the femoral head , acetabulum, labrum . also discusses the capsule , ligaments . muscle that act on the hip joint and the range of motion are outlined. factors affecting hip joint stability and weight transmission through the joint are summarized.
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...NelTorrente
In this research, it concludes that while the readiness of teachers in Caloocan City to implement the MATATAG Curriculum is generally positive, targeted efforts in professional development, resource distribution, support networks, and comprehensive preparation can address the existing gaps and ensure successful curriculum implementation.
Thinking of getting a dog? Be aware that breeds like Pit Bulls, Rottweilers, and German Shepherds can be loyal and dangerous. Proper training and socialization are crucial to preventing aggressive behaviors. Ensure safety by understanding their needs and always supervising interactions. Stay safe, and enjoy your furry friends!
Biological screening of herbal drugs: Introduction and Need for
Phyto-Pharmacological Screening, New Strategies for evaluating
Natural Products, In vitro evaluation techniques for Antioxidants, Antimicrobial and Anticancer drugs. In vivo evaluation techniques
for Anti-inflammatory, Antiulcer, Anticancer, Wound healing, Antidiabetic, Hepatoprotective, Cardio protective, Diuretics and
Antifertility, Toxicity studies as per OECD guidelines
6. Protection of the Environment Operations Act
sections 143 and 144
Environment Planning and Assessment Act
sections 76,76A and 76B
Possible Offenders/Situations.
Owners of the waste - Source Site
Transporter of the waste
Location of Depositing of waste
13. BONDED ASBESTOS FRIABLE ASBESTOS
Asbestos fibres that are
bonded in a base
material. Typically this
is a cement type
material or a plastic
membrane.
White (Chrysotile)
Brown (Amosite)
Any material that
contains Asbestos in the
form of a powder or can
be crumbled, pulverised
or reduced to powder
by hand pressure when
dry.
Blue (Crocidolite)
15. When bonded material becomes extensively
damaged by fire it may become friable.
Water blasting Asbestos cement will cause
fibres to become liberated.
Extensive hail damage may cause the sheeting
to become friable.
Where weathering has caused the substrate to
break down and the bonded material can be
crushed by hand.
Mechanical damage has crushed the bonded
matrix to powder.
19. BONDED ASBESTOS IN SOIL
Bonded Asbestos in soil to be treated as bonded
material and can be cleaned by a bonded licenced
operator.
If bonded material has been reduced to powder, can
be crumbled by hand or there are free fibre bundles
detected in the soil then the soil is treated as having
Friable Asbestos in the soil.
Friable Asbestos in the soil has to be removed by a
Friable Licensed Contractor.
20. Asbestos cement
sheeting fragments on
the ground surfaces
within the subfloor of
the
building
Dust containing asbestos
cement sheeting fragments on
the upper surfaces of the timber
framework
21. The asbestos assessment of the site has
identified scattered fragments of AC to
building rubble piles in the front yard,
grassed areas in the front yard, within and
below the partially demolished residential
house, grassed areas down both sides of the
residential house, to the building rubble pile
at the rear of the house and remaining
asbestos cement sheeting to the internal
main bathroom, internal kitchen and gable
wall sheeting on both ends of the residential
house.
One bulk asbestos cement fragment from
the front yard building rubble pile returned
positive for asbestos, while one bulk
asbestos cement fragment returned negative
from the rear yard building rubble pile. Soil
sampling carried out for asbestos fibres did
not return any results,
However, due to the wide spread
contamination of asbestos cement fragments
from previous demolition works outside
and inside the residential house, the
contamination should be deemed as friable
from an asbestos risk management
perspective and associated asbestos
remediation activities. However the full
vertical extent to the soil is not known and
further investigation maybe be required.
22. WHEN CAN YOU LEAVE ASBESTOS MATERIAL IN THE SOIL
23. There is no legal requirement to remove insitu
Asbestos
Depending on the final use of a site, it may be
feasible to leave the material in situ.
On sensitive sites such as schools and Hospitals
all Asbestos material should be removed.
If Asbestos material is left in place after a
redevelopment Approval from the Appropriate
Regulatory Authority needs to be obtained.
24. Example
Overseas Developer bought
an old Pottery production
site.
Site was full of Asbestos
throughout the ground from
the old kilm
Wanted to develop site for
townhouses.
Selling Points –
Waterfrontage to smelly
drainage easement, 24 hour
views to Motorway with
heavy traffic noise.
The Winning option – Local
Council has new reserve.
25.
26. BURY OR MIX ASBESTOS
IN LANDFILL BURN ASBESTOS WASTE
27. Location Road, Wallacia
******************************
POI: N K @ N T
D.O.B: 20/09/1969
ADD 1: , Bass Hill
ADD 2: , Constitution Hill
CHARGES: PCA, Steal Motor Vehicle, Cargo theft, Assault, Traffic
INTELL: People smuggling, Firearms, Cargo theft x 7, B,E&S x 8,
*******************************
Occupants: L Family
Firearm Holder: B P L
D.O.B: 01/01/1956
Firearms: 1 x Single barrel shotgun and 1 x .22 Rifle.
Safe audit conducted and passed on 13th March 2013.
*******************************
Police have recently received information about the mentioned POI dumping asbestos at the above
location. The information obtained shows the POI is charging $1,000 per load of asbestos taken and
dumped at the above location.
In September 2013, the POI was involved in an GBH assault on two persons at the above mentioned
location.
This information has been passed onto Mr Darren RIDING from Regional Illegal Dumping Squad
who are aware of the POI and the location.
28. If Investigating a matter, ensure the Appropriate Authority is
investigating the matter
30. REQUIREMENTS OF CLEAN UP/PREVENTION NOTICE:
As an Authorised Officer of-------------, I direct you to take the
following clean-up / prevention actions:
Install and Maintain Soil and Sedimentation Erosion Control
Devices (in accordance to the Blue Book Forth Edition Published
by LANDCOM) around the entire development site which has
not been undertaken.
Install a suitable Stabilised Site Access (in accordance to the
Blue Book Forth Edition Published by LANDCOM).
Ensure the site is fully enclosed with a 1.8m high security fence
around the entire development site which has not been
undertaken including approved dust control netting.
31. Additionally to the above, with the removal of all demolition material
from-----------------------, Engage the services of a Suitable Qualified
Company or persons to undertake and submit full reports of the
material within the premise.
These reports are to include but not limited to:
Hygienist Report (HR) (AS 1199.2-2003, ISO 2859-2:1985) prior and
after removal this to include the entire ground surface and possible
underlining surfaces.
Asbestos Removal Control Plan
Asbestos Classification and Risk Assessment
Asbestos Air Monitoring and Clearance Inspection
Buried Asbestos Materials (Unexpected Finds Protocols)
Environment Impact Study (EIS)Environment Management Plan
(EMP)
Waste Management Plan (WMP) including locations and method of
disposal.
Waste Data File (WDF) including all receipts and vehicle movement
from the premise.
These reports have to be submitted to ------------Council in which
approval of these reports have to be obtained from -------------Council
prior to any material being removed from the premise. Once approved
copies are to be left at the premise during the removal of all material.
32. Once approval is obtained from ------------Council of
all reports, remove all waste/sedimentation/ fuel
and or liquid substances from the property/ies
All waste/sedimentation/ fuel and or liquid
substances to be conveyed to approved waste
facilities in which receipts for each load are to be
obtained in which a copy is to be attached to the
Waste Data File for inspection at any time by an
Authorised Officer.
Additionally copies of all receipts for the disposal of
the waste/sedimentation/ fuel and or liquid
substances from the waste facility to be forwarded
within 7 days of the waste/sedimentation/ fuel and
or liquid substances been taken to the waste facilities.
33. All work on or around------------------, are to be
undertaken during approved working hours
approved by --------------------------Council.
Any work requiring Approved Development
Applications are to be sought and approved
prior to any of the work to be undertaken.
Care shall be taken in the method of excavation
of the waste material from the premises thereof
to ensure the topography of the land remain in
the profile and the general condition in which
they were before the waste material was placed
on the premises and to prevention the flow of
dust and small particles into neighbour
properties and the public road reserve.
34. Remove all waste/sedimentation/ and or liquid substances
from the road, gutter, drains, storm water network and
creeks/streams surrounding the properties at-------------------
------------------------------.
Ensure the road, gutter, drains, storm water network and
creeks/streams within and surrounding the properties ------
----------------are clean and free of waste/sedimentation/
fuel and or liquid substances.
The removal of the all the above mentioned from -------------
-----------are to be completed by----------------.
If you have not complied with the requirements of this
Notice by the required date, you still have a continuing
obligation to comply with this Notice after that date
(subject to revocation or variation of this Notice by---------
----------------------------)
35. TERMS OF ORDER 12
Section 121B Environmental Planning & Assessment Act 1979
Order 12 (b): To do such things as are specified in the order to restore premises to the condition in which they were before building
was unlawfully erected or before work was unlawfully carried out. Work has been unlawfully carried out.
Terms of Order
Submit a report from a suitably qualified person detailing the extent of filling on the site. This report is to detail
the previous and current ground levels.
Timeframe
Thirty (30) days from the date of the Order
Submit a report from a suitably qualified person or company attesting to the type of material contained within the
unauthorised landfill throughout the whole of the premises including the identification of any contaminants
found.
The report must meet the AS 1199.2-2003 and ISO2859-2:1985 Standards.
The report must also stipulate how the site is to be remediated including the entire ground surface and possible
underlining surfaces as well as Unexpected Finds Protocols.
Timeframe
Thirty (30) days from the date of the Order
REASON FOR ORDER
The unauthorised fill material has the ability to impact on the property, surrounding properties and the environment
by the way of altered drainage patterns (flooding), possible land contamination and water pollution from
unestablished soil.
The report is required in compliance pursuant to Work, Health and safety Standards and Environmental Standards to
ensure safety and possible environment concerns not just for yourself but your family, contractors and the
surrounding neighbours.
From the report it will establish the manner in which the unauthorised land fill is to be removed and where the
appropriate location or facility of that material can be properly disposed of.
37. Safer Work sites
Ease of neighbouring
residents concerns
Limited media
concerns
Reduced Politician or
Councillor Concerns
Contractors on Notice