SlideShare a Scribd company logo
1 of 15
Download to read offline
SEWERFIX WET WEATHER ALLIANCE
www.sydneywater.com.au/majorprojects
Technical Note
DATE 25/09/08 SUB PROJECT
Recalibration of East Esplanade Sub-
catchment
SUBJECT Northern Beaches Catchment Planning
Document No. NB SO-TN-001
Prepared by Faruk Kader
Reviewed by Glenn McDermott
BACKGROUND
The Manly SCAMP model was originally built and calibrated in 2001. The model was recalibrated
in 2004 following the recommendations of 2002 Needs Assessment Report to investigate the high
overflow frequency of four weirs in the Manly local government area. The recalibration of the model
used a new set of dedicated gauging data of 2004 and the subsequent analysis led to a realistic
assessment of the overflow frequency of the weirs far lower than that predicted by the 2001 model.
In 2007, SWC initiated a flow gauging program for the East Esplanade part of Manly SCAMP. The
data collected from this program was planned to be used to refine its calibration at sub-catchment
level for validation of the overflow frequency of the East Esplanade weir, located at the junction of
the Stuart St and East Esplanade RD. Figure 1 shows the East Esplanade sewer catchment and
flow gauging stations installed in 2007.
Accordingly, this modelling exercise was undertaken with the following objectives:
• To calibrate the East Esplanade sewer catchment model against the flow data gauged at three
locations, 8MAN58, 8MAN64 and 8MAN63, for the period Dec 2007-Aug 2008.
• To validate the wet weather parameters of the sewer catchment
SCOPE
• Extract East Esplanade sewer catchment model (MYN1) part from the previously calibrated
Manly SCAMP model (MYN)
• Extract and prepare model input data – rainfall, flow and outlet water level boundary data
• Analyse gauged flow data
• Select suitable dry and wet weather events for model calibration
• Calibrate the model for dry weather events
• Calibrate the model for wet weather events
• Validate the wet weather parameters
Figure 1: East Esplanade Sewer Catchment and Flow Gauging Stations
8MAN64
8MAN58
8MAN63
East Esplanade Overflow Weir
Flow Gauging Station
MODEL INPUT DATA
SWC installed three gauges (8MAN63, 8MAN64 and 8MAN58) to capture sufficient number of wet
weather events for use in calibration of the model, as shown in Figure1. Out of these, 8MAN58 is
located very close to the outlet of the sewer catchment to NSOOS. These three were all HVQ
stations, however, the most upstream gauge 8MAN63 was constricted.
Two closest permanent SWC rain gauges, 566100 (North Head STP) and 566089 (Manly CC),
were used to generate virtual rainfall time series data for East Esplanade for the gauging period:
The data of these two were found well correlated. Due to proximity of 566100 to East Esplanade,
this rain gauge was given more weightage in generating the data.
The following two dry weather and four wet weather events were considered for use in the model,
meeting SWC criteria as far as possible.
• Dry Weather Event 1 (DWE1): 06/05/2008 to 13/05/20008
• Dry Weather Event 2 (DWE2): 28/06/2008 to 05/07/20008
Page 2 of 15
S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical
NotesEast_Esplanade_Modelling_2008.doc
• Wet Weather Event 1(WWE1): 01/02/2008 to 13/02/2008
• Wet Weather Event 2(WWE2): 02/06/2008 to 11/06/2008
• Wet Weather Event 3(WWE3): 24/07/2008 to 02/08/2008
• Wet Weather Event 4(WWE4): 08/04/2008 to 11/04/2008
In the absence of continuous measured data, the outlet water level boundary conditions for the
East Esplanade model on NSOOS at Ashburner St (820001) was generated by correlation
between this gauging station and 820002 (Eustace St), which had continuous data.
Analysis of the captured flow data was done and a summary of flow analysis for the dominant
storm of the full/whole wet weather events is provided in Table 1.
Table 1: Summary of Flow Analysis
EVENTS
DWE1 DWE2 WWE1 WWE2 WWE3 WWE4
Gauge
Daily
Flow
(Kl/d)
Peak
Flow
l/s
Daily
Flow
(Kl/d)
Peak
Flow
l/s
Daily
Flow
(Kl/d)
Peak
Flow
l/s
Daily
Flow
(Kl/d)
Peak
Flow
l/s
Daily
Flow
(Kl/d)
Peak
Flow
l/s
Daily
Flow
(Kl/d)
Peak
Flow
l/s
8MAN63 226.0 11.97 197.0 11.03 1104.0 38.08 737.0 25.23 843.0 28.81 317.0 14.70
8MAN64 708.0 22.22 847.0 25.87 2741.0 81.22 2421.0 63.74 2940.0 83.81 1426.0 50.66
8MAN58 1005.0 29.25 1004.0 33.07 3406.0 100.17 2462.0 64.15 3098.0 83.81 1677.0 54.67
Almost identical flows monitored at 8MAN64 and 8MAN58
Significant flow difference between 8MAN64 and 8MAN58
Analysis shows that the water balance between 8MAN64 (u/s) and 8MAN64 (d/s) is not consistent
during the wet weather events. The flow volume difference between 8MAN64 and 8MAN58 is
significant during event WW1; 8MAN64 recorded 20% less volume than 8MAN58, while the flow
volume difference is 2 to 5% for events WW2 and WW3. An earlier investigation found problem in
gauging of 8MAN64 before March 2008 covering event WW1. Therefore, WW1 event was not used
for calibration of the sub-catchment gauged by 8MAN64.
For its catchment area, the flow captured at 8MAN63 looks less than expected. However, the
model results show that a major component of the flow from the upstream bypasses this gauge via
a bifurcation to the downstream gauge 8MAN64.
CALIBRATION
The East Esplanade model was basically calibrated for dry periods only. To arrive at a satisfactory
flow calibration during dry period, residential flow data of 140 to 150 l/EP/D was used. The existing
wet weather parameters were able to match flow volume, flow peak and flow depths within a
reasonable range of variation. Minor adjustment of pipe roughness was done upstream of flow
gauges to improve depth calibration. Given the uncertainty in flow data, it was deemed not
worthwhile to refine the existing wet weather parameters. Calibration results are summarized in
Table 2 below, while calibration plots are provided in Appendix.
Page 3 of 15
S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical
NotesEast_Esplanade_Modelling_2008.doc
SEWERFIX WET WEATHER ALLIANCE
www.sydneywater.com.au/majorprojects
Table 1: Summary of Calibration Results
8MAN63 (Constricted) 8MAN64 8MAN58Event
RQV RQP R R R R R R R R RQm DP DM QV QP Qm RDP DM RQV RQP Qm RDP DM
DWE1 0.98 0.60 0.98 NA NA 1.16 0.89 1.16 0.79 0.85 0.96 0.79 0.96 0.70 0.70
DWE2 1.17 0.71 1.17 NA NA 1.00 0.75 1.00 0.70 0.73 0.99 0.72 0.99 0.66 0.69
WWE1 0.61 0.67 0.61 NA NA 0.87 0.96 0.87 0.72 0.78 0.77 0.87 0.77 0.95 1.05
WWE2 0.80 0.77 0.80 NA NA 0.82 0.87 0.82 0.74 0.72 0.94 0.99 0.93 0.98 1.00
WWE3 0.89 0.89 0.89 NA NA 0.85 0.95 0.85 0.77 0.74 0.94 1.09 0.94 0.96 0.93
WWE4 1.33 1.13 1.33 NA NA 1.01 1.09 1.01 0.86 0.82 1.04 1.17 1.04 1.05 0.90
Note
RQV= Simulated Volume/Gauged Volume
RQP =Simulated Highest Peak Flow/Gauged Highest Peak Flow
RQM =Simulated Mean Flow/Gauged Mean Flow
RDP =Simulated Peak Flow Depth/Gauged Peak Flow Depth
RDM= Simulated Mean Flow Depth/Gauged Mean Flow Depth
The above ratios for wet weather events represent flow statistics for the dominant storm event within the whole storm event consisting of a number of bursts/events
SEWERFIX WET WEATHER ALLIANCE
www.sydneywater.com.au/majorprojects
CONCLUSIONS
It appears that the existing wet weather parameters for the East Esplanade part of the Manly SCAMP
are still valid within the allowable margin of error.
Prepared: Faruk Kader (SWWA) Date:
Checked:
Glenn McDermott
(SWWA) Date:
Approved: (SWC) Date:
Comments:
SEWERFIX WET WEATHER ALLIANCE
www.sydneywater.com.au/majorprojects
APPENDIX
Calibration Plots for Dry Weather and Wet Weather Events
SEWERFIX WET WEATHER ALLIANCE
Calibration Plot of Gauge 8MAN63 for DWE1
Calibration Plot of Gauge 8MAN63 for DWE2
www.sydneywater.com.au/majorprojects
Calibration Plot of Gauge 8MAN64 for DWE1
Calibration Plot of Gauge 8MAN64 for DWE2
Page 8 of 15
S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical
NotesEast_Esplanade_Modelling_2008.doc
S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical
NotesEast_Esplanade_Modelling_2008.doc
Calibration Plot of Gauge 8MAN58 for DWE1
Calibration Plot of Gauge 8MAN58 for DWE2
Page 9 of 15
S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical
NotesEast_Esplanade_Modelling_2008.doc
Calibration Plot of Gauge 8MAN63 for WWE1
Calibration Plot of Gauge 8MAN63 for WWE2
Page 10 of 15
S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical
NotesEast_Esplanade_Modelling_2008.doc
Calibration Plot of Gauge 8MAN63 for WWE3
Calibration Plot of Gauge 8MAN63 for WWE4
Page 11 of 15
S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical
NotesEast_Esplanade_Modelling_2008.doc
Calibration Plot of Gauge 8MAN64 for WWE2
Calibration Plot of Gauge 8MAN64 for WWE3
Page 12 of 15
S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical
NotesEast_Esplanade_Modelling_2008.doc
Calibration Plot of Gauge 8MAN64 for WWE4
Page 13 of 15
S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical
NotesEast_Esplanade_Modelling_2008.doc
Calibration Plot of Gauge 8MAN58 for WWE1
Calibration Plot of Gauge 8MAN58 for WWE2
Page 14 of 15
S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical
NotesEast_Esplanade_Modelling_2008.doc
Calibration Plot of Gauge 8MAN58 for WWE3
Calibration Plot of Gauge 8MAN58 for WWE4
Page 15 of 15

More Related Content

What's hot

Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology... Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...hydrologyproject001
 
Download-manuals-surface water-manual-sw-volume4fieldmanualhydrometrypartviii
 Download-manuals-surface water-manual-sw-volume4fieldmanualhydrometrypartviii Download-manuals-surface water-manual-sw-volume4fieldmanualhydrometrypartviii
Download-manuals-surface water-manual-sw-volume4fieldmanualhydrometrypartviiihydrologyproject001
 
Download-manuals-surface water-manual-sw-volume4designmanualhydrometry
 Download-manuals-surface water-manual-sw-volume4designmanualhydrometry Download-manuals-surface water-manual-sw-volume4designmanualhydrometry
Download-manuals-surface water-manual-sw-volume4designmanualhydrometryhydrologyproject001
 
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology... Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...hydrologyproject001
 
Statistical analysis software article - jan 2016
Statistical analysis software article  - jan 2016Statistical analysis software article  - jan 2016
Statistical analysis software article - jan 2016Peter Elvingdal
 
Download-manuals-surface water-manual-sw-volume3referencemanualhydro-meteoro...
 Download-manuals-surface water-manual-sw-volume3referencemanualhydro-meteoro... Download-manuals-surface water-manual-sw-volume3referencemanualhydro-meteoro...
Download-manuals-surface water-manual-sw-volume3referencemanualhydro-meteoro...hydrologyproject001
 
ChoptankModelingPresentation
ChoptankModelingPresentationChoptankModelingPresentation
ChoptankModelingPresentationRyan Jones, P.E.
 
Concurrent session 7 hec rts
Concurrent session 7 hec rtsConcurrent session 7 hec rts
Concurrent session 7 hec rtsSikandar Ali
 
GIS PROCEDURE FOR PRELIMINARY EVALUATION OF POTENTIAL HYDROPOWER SITES
GIS PROCEDURE FOR PRELIMINARY EVALUATION OF POTENTIAL HYDROPOWER SITESGIS PROCEDURE FOR PRELIMINARY EVALUATION OF POTENTIAL HYDROPOWER SITES
GIS PROCEDURE FOR PRELIMINARY EVALUATION OF POTENTIAL HYDROPOWER SITESFrancis Mitchell
 
2011 ras for_managers_11-22
2011 ras for_managers_11-222011 ras for_managers_11-22
2011 ras for_managers_11-22Sanjaya Srilal
 
Inspect typical water monitoring equipment alan hooper
Inspect typical water monitoring equipment alan hooperInspect typical water monitoring equipment alan hooper
Inspect typical water monitoring equipment alan hooperInternational WaterCentre
 
Flood Mapping via HEC-RAS Model and ArcGIS
Flood Mapping via HEC-RAS Model and ArcGISFlood Mapping via HEC-RAS Model and ArcGIS
Flood Mapping via HEC-RAS Model and ArcGISLengthong KIM
 
Discharge and Sediment Transport Modeling Buck Creek Proposal
Discharge and Sediment Transport Modeling Buck Creek ProposalDischarge and Sediment Transport Modeling Buck Creek Proposal
Discharge and Sediment Transport Modeling Buck Creek ProposalJames Blumenschein
 
Probabilistic Analysis of a Desalination Plant with Major and Minor Failures ...
Probabilistic Analysis of a Desalination Plant with Major and Minor Failures ...Probabilistic Analysis of a Desalination Plant with Major and Minor Failures ...
Probabilistic Analysis of a Desalination Plant with Major and Minor Failures ...Waqas Tariq
 
High Resolution Site Characterization (#HRSC) of Gasoline LNAPL Plume Migrati...
High Resolution Site Characterization (#HRSC) of Gasoline LNAPL Plume Migrati...High Resolution Site Characterization (#HRSC) of Gasoline LNAPL Plume Migrati...
High Resolution Site Characterization (#HRSC) of Gasoline LNAPL Plume Migrati...John Fontana
 

What's hot (19)

Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology... Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 
Download-manuals-surface water-manual-sw-volume4fieldmanualhydrometrypartviii
 Download-manuals-surface water-manual-sw-volume4fieldmanualhydrometrypartviii Download-manuals-surface water-manual-sw-volume4fieldmanualhydrometrypartviii
Download-manuals-surface water-manual-sw-volume4fieldmanualhydrometrypartviii
 
Download-manuals-surface water-manual-sw-volume4designmanualhydrometry
 Download-manuals-surface water-manual-sw-volume4designmanualhydrometry Download-manuals-surface water-manual-sw-volume4designmanualhydrometry
Download-manuals-surface water-manual-sw-volume4designmanualhydrometry
 
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology... Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 
Statistical analysis software article - jan 2016
Statistical analysis software article  - jan 2016Statistical analysis software article  - jan 2016
Statistical analysis software article - jan 2016
 
Download-manuals-surface water-manual-sw-volume3referencemanualhydro-meteoro...
 Download-manuals-surface water-manual-sw-volume3referencemanualhydro-meteoro... Download-manuals-surface water-manual-sw-volume3referencemanualhydro-meteoro...
Download-manuals-surface water-manual-sw-volume3referencemanualhydro-meteoro...
 
Mandal
MandalMandal
Mandal
 
Lecture3
Lecture3Lecture3
Lecture3
 
ChoptankModelingPresentation
ChoptankModelingPresentationChoptankModelingPresentation
ChoptankModelingPresentation
 
Campbell iain
Campbell iainCampbell iain
Campbell iain
 
Concurrent session 7 hec rts
Concurrent session 7 hec rtsConcurrent session 7 hec rts
Concurrent session 7 hec rts
 
GIS PROCEDURE FOR PRELIMINARY EVALUATION OF POTENTIAL HYDROPOWER SITES
GIS PROCEDURE FOR PRELIMINARY EVALUATION OF POTENTIAL HYDROPOWER SITESGIS PROCEDURE FOR PRELIMINARY EVALUATION OF POTENTIAL HYDROPOWER SITES
GIS PROCEDURE FOR PRELIMINARY EVALUATION OF POTENTIAL HYDROPOWER SITES
 
2011 ras for_managers_11-22
2011 ras for_managers_11-222011 ras for_managers_11-22
2011 ras for_managers_11-22
 
Gec pest
Gec pestGec pest
Gec pest
 
Inspect typical water monitoring equipment alan hooper
Inspect typical water monitoring equipment alan hooperInspect typical water monitoring equipment alan hooper
Inspect typical water monitoring equipment alan hooper
 
Flood Mapping via HEC-RAS Model and ArcGIS
Flood Mapping via HEC-RAS Model and ArcGISFlood Mapping via HEC-RAS Model and ArcGIS
Flood Mapping via HEC-RAS Model and ArcGIS
 
Discharge and Sediment Transport Modeling Buck Creek Proposal
Discharge and Sediment Transport Modeling Buck Creek ProposalDischarge and Sediment Transport Modeling Buck Creek Proposal
Discharge and Sediment Transport Modeling Buck Creek Proposal
 
Probabilistic Analysis of a Desalination Plant with Major and Minor Failures ...
Probabilistic Analysis of a Desalination Plant with Major and Minor Failures ...Probabilistic Analysis of a Desalination Plant with Major and Minor Failures ...
Probabilistic Analysis of a Desalination Plant with Major and Minor Failures ...
 
High Resolution Site Characterization (#HRSC) of Gasoline LNAPL Plume Migrati...
High Resolution Site Characterization (#HRSC) of Gasoline LNAPL Plume Migrati...High Resolution Site Characterization (#HRSC) of Gasoline LNAPL Plume Migrati...
High Resolution Site Characterization (#HRSC) of Gasoline LNAPL Plume Migrati...
 

Viewers also liked

i101 Final Group Project - Active Database Solution for Local Nonprofit
i101 Final Group Project - Active Database Solution for Local Nonprofiti101 Final Group Project - Active Database Solution for Local Nonprofit
i101 Final Group Project - Active Database Solution for Local NonprofitJordan Wright
 
DO NGOC THANH MAI
DO NGOC THANH MAIDO NGOC THANH MAI
DO NGOC THANH MAIMai Do
 
Gdi presentation eng
Gdi presentation engGdi presentation eng
Gdi presentation engOle Jensen
 
Cosmo Trial Information APSEA
Cosmo Trial Information APSEACosmo Trial Information APSEA
Cosmo Trial Information APSEADavid Pillischer
 
Ecoregion chocó darién flora
Ecoregion chocó darién floraEcoregion chocó darién flora
Ecoregion chocó darién floraDimasEduardo
 
Protocolo de investigación
Protocolo de investigación Protocolo de investigación
Protocolo de investigación Mariana AG
 

Viewers also liked (13)

Mani resume
Mani resumeMani resume
Mani resume
 
Coping with Stress
Coping with StressCoping with Stress
Coping with Stress
 
i101 Final Group Project - Active Database Solution for Local Nonprofit
i101 Final Group Project - Active Database Solution for Local Nonprofiti101 Final Group Project - Active Database Solution for Local Nonprofit
i101 Final Group Project - Active Database Solution for Local Nonprofit
 
Mahesh_Jadhav
Mahesh_JadhavMahesh_Jadhav
Mahesh_Jadhav
 
DO NGOC THANH MAI
DO NGOC THANH MAIDO NGOC THANH MAI
DO NGOC THANH MAI
 
Gdi presentation eng
Gdi presentation engGdi presentation eng
Gdi presentation eng
 
Navnath CV
Navnath CVNavnath CV
Navnath CV
 
Cosmo Trial Information APSEA
Cosmo Trial Information APSEACosmo Trial Information APSEA
Cosmo Trial Information APSEA
 
Brochure institucional
Brochure institucionalBrochure institucional
Brochure institucional
 
Test
TestTest
Test
 
Ecoregion chocó darién flora
Ecoregion chocó darién floraEcoregion chocó darién flora
Ecoregion chocó darién flora
 
Protocolo de investigación
Protocolo de investigación Protocolo de investigación
Protocolo de investigación
 
CVColo2015Gen
CVColo2015GenCVColo2015Gen
CVColo2015Gen
 

Similar to East_Esplanade_Modelling_2008[1]

CWW-(El-Salloum New Marina) Drawing.pdf
CWW-(El-Salloum New Marina) Drawing.pdfCWW-(El-Salloum New Marina) Drawing.pdf
CWW-(El-Salloum New Marina) Drawing.pdfAhmedAbdelkader494171
 
Jaya r pudashine
Jaya r pudashineJaya r pudashine
Jaya r pudashineClimDev15
 
HWRS2014_Diermanse-Paper148
HWRS2014_Diermanse-Paper148HWRS2014_Diermanse-Paper148
HWRS2014_Diermanse-Paper148Rob Ayre
 
An Introduction to the Environment Agency extreme offshore wave, water level ...
An Introduction to the Environment Agency extreme offshore wave, water level ...An Introduction to the Environment Agency extreme offshore wave, water level ...
An Introduction to the Environment Agency extreme offshore wave, water level ...Stephen Flood
 
Climatic data utilization in major irrigation schemes.pptx
Climatic data utilization in major irrigation schemes.pptxClimatic data utilization in major irrigation schemes.pptx
Climatic data utilization in major irrigation schemes.pptxAyeshaHerath4
 
Hydrological Calibration in the Mount Lofty Ranges using Source Paramenter Es...
Hydrological Calibration in the Mount Lofty Ranges using Source Paramenter Es...Hydrological Calibration in the Mount Lofty Ranges using Source Paramenter Es...
Hydrological Calibration in the Mount Lofty Ranges using Source Paramenter Es...eWater
 
DSD-INT 2019 The FEWSPo system - actual state and new developments - Tonelli
DSD-INT 2019 The FEWSPo system - actual state and new developments - TonelliDSD-INT 2019 The FEWSPo system - actual state and new developments - Tonelli
DSD-INT 2019 The FEWSPo system - actual state and new developments - TonelliDeltares
 
Hydrological Model for Estimating Volume of Inflow into the Peppara Dam Reser...
Hydrological Model for Estimating Volume of Inflow into the Peppara Dam Reser...Hydrological Model for Estimating Volume of Inflow into the Peppara Dam Reser...
Hydrological Model for Estimating Volume of Inflow into the Peppara Dam Reser...IRJET Journal
 
IRJET-Analysis of Storm Water Drain in 1410 Acres, Palasamudram Site
IRJET-Analysis of Storm Water Drain in 1410 Acres, Palasamudram SiteIRJET-Analysis of Storm Water Drain in 1410 Acres, Palasamudram Site
IRJET-Analysis of Storm Water Drain in 1410 Acres, Palasamudram SiteIRJET Journal
 
Rainfall Runoff Modelling on the Lower Tapi Basin using HEC-HMS
Rainfall Runoff Modelling on the Lower Tapi Basin using HEC-HMSRainfall Runoff Modelling on the Lower Tapi Basin using HEC-HMS
Rainfall Runoff Modelling on the Lower Tapi Basin using HEC-HMSAnkit Balyan MBA, B.Tech.
 
AIP-Procceding-Article
AIP-Procceding-ArticleAIP-Procceding-Article
AIP-Procceding-ArticleMehdi Karimi
 
Power conversion system design for tidal stream generator by Oceanflow
Power conversion system design for tidal stream generator by OceanflowPower conversion system design for tidal stream generator by Oceanflow
Power conversion system design for tidal stream generator by OceanflowOptima Control Solutions
 
Space Systems & Space Subsystems Fundamentals Technical Training Course Sampler
Space Systems & Space Subsystems Fundamentals Technical Training Course SamplerSpace Systems & Space Subsystems Fundamentals Technical Training Course Sampler
Space Systems & Space Subsystems Fundamentals Technical Training Course SamplerJim Jenkins
 
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
 Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin... Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...hydrologywebsite1
 
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
 Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin... Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...hydrologyproject001
 
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
 Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin... Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...hydrologyproject001
 

Similar to East_Esplanade_Modelling_2008[1] (20)

CE573_Poster2
CE573_Poster2CE573_Poster2
CE573_Poster2
 
CWW-(El-Salloum New Marina) Drawing.pdf
CWW-(El-Salloum New Marina) Drawing.pdfCWW-(El-Salloum New Marina) Drawing.pdf
CWW-(El-Salloum New Marina) Drawing.pdf
 
Jaya r pudashine
Jaya r pudashineJaya r pudashine
Jaya r pudashine
 
HWRS2014_Diermanse-Paper148
HWRS2014_Diermanse-Paper148HWRS2014_Diermanse-Paper148
HWRS2014_Diermanse-Paper148
 
An Introduction to the Environment Agency extreme offshore wave, water level ...
An Introduction to the Environment Agency extreme offshore wave, water level ...An Introduction to the Environment Agency extreme offshore wave, water level ...
An Introduction to the Environment Agency extreme offshore wave, water level ...
 
Climatic data utilization in major irrigation schemes.pptx
Climatic data utilization in major irrigation schemes.pptxClimatic data utilization in major irrigation schemes.pptx
Climatic data utilization in major irrigation schemes.pptx
 
Modflow Nepal
Modflow NepalModflow Nepal
Modflow Nepal
 
Hydrological Calibration in the Mount Lofty Ranges using Source Paramenter Es...
Hydrological Calibration in the Mount Lofty Ranges using Source Paramenter Es...Hydrological Calibration in the Mount Lofty Ranges using Source Paramenter Es...
Hydrological Calibration in the Mount Lofty Ranges using Source Paramenter Es...
 
DSD-INT 2019 The FEWSPo system - actual state and new developments - Tonelli
DSD-INT 2019 The FEWSPo system - actual state and new developments - TonelliDSD-INT 2019 The FEWSPo system - actual state and new developments - Tonelli
DSD-INT 2019 The FEWSPo system - actual state and new developments - Tonelli
 
Hydrological Model for Estimating Volume of Inflow into the Peppara Dam Reser...
Hydrological Model for Estimating Volume of Inflow into the Peppara Dam Reser...Hydrological Model for Estimating Volume of Inflow into the Peppara Dam Reser...
Hydrological Model for Estimating Volume of Inflow into the Peppara Dam Reser...
 
IRJET-Analysis of Storm Water Drain in 1410 Acres, Palasamudram Site
IRJET-Analysis of Storm Water Drain in 1410 Acres, Palasamudram SiteIRJET-Analysis of Storm Water Drain in 1410 Acres, Palasamudram Site
IRJET-Analysis of Storm Water Drain in 1410 Acres, Palasamudram Site
 
Rainfall Runoff Modelling on the Lower Tapi Basin using HEC-HMS
Rainfall Runoff Modelling on the Lower Tapi Basin using HEC-HMSRainfall Runoff Modelling on the Lower Tapi Basin using HEC-HMS
Rainfall Runoff Modelling on the Lower Tapi Basin using HEC-HMS
 
AIP-Procceding-Article
AIP-Procceding-ArticleAIP-Procceding-Article
AIP-Procceding-Article
 
Power conversion system design for tidal stream generator by Oceanflow
Power conversion system design for tidal stream generator by OceanflowPower conversion system design for tidal stream generator by Oceanflow
Power conversion system design for tidal stream generator by Oceanflow
 
Space Systems & Space Subsystems Fundamentals Technical Training Course Sampler
Space Systems & Space Subsystems Fundamentals Technical Training Course SamplerSpace Systems & Space Subsystems Fundamentals Technical Training Course Sampler
Space Systems & Space Subsystems Fundamentals Technical Training Course Sampler
 
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
 Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin... Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
 
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
 Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin... Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
 
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
 Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin... Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
Download-manuals-surface water-manual-sw-volume8operationmanualdataprocessin...
 
Swat model
Swat model Swat model
Swat model
 
Mathematical modeling
Mathematical modelingMathematical modeling
Mathematical modeling
 

East_Esplanade_Modelling_2008[1]

  • 1. SEWERFIX WET WEATHER ALLIANCE www.sydneywater.com.au/majorprojects Technical Note DATE 25/09/08 SUB PROJECT Recalibration of East Esplanade Sub- catchment SUBJECT Northern Beaches Catchment Planning Document No. NB SO-TN-001 Prepared by Faruk Kader Reviewed by Glenn McDermott BACKGROUND The Manly SCAMP model was originally built and calibrated in 2001. The model was recalibrated in 2004 following the recommendations of 2002 Needs Assessment Report to investigate the high overflow frequency of four weirs in the Manly local government area. The recalibration of the model used a new set of dedicated gauging data of 2004 and the subsequent analysis led to a realistic assessment of the overflow frequency of the weirs far lower than that predicted by the 2001 model. In 2007, SWC initiated a flow gauging program for the East Esplanade part of Manly SCAMP. The data collected from this program was planned to be used to refine its calibration at sub-catchment level for validation of the overflow frequency of the East Esplanade weir, located at the junction of the Stuart St and East Esplanade RD. Figure 1 shows the East Esplanade sewer catchment and flow gauging stations installed in 2007. Accordingly, this modelling exercise was undertaken with the following objectives: • To calibrate the East Esplanade sewer catchment model against the flow data gauged at three locations, 8MAN58, 8MAN64 and 8MAN63, for the period Dec 2007-Aug 2008. • To validate the wet weather parameters of the sewer catchment SCOPE • Extract East Esplanade sewer catchment model (MYN1) part from the previously calibrated Manly SCAMP model (MYN) • Extract and prepare model input data – rainfall, flow and outlet water level boundary data • Analyse gauged flow data • Select suitable dry and wet weather events for model calibration • Calibrate the model for dry weather events • Calibrate the model for wet weather events
  • 2. • Validate the wet weather parameters Figure 1: East Esplanade Sewer Catchment and Flow Gauging Stations 8MAN64 8MAN58 8MAN63 East Esplanade Overflow Weir Flow Gauging Station MODEL INPUT DATA SWC installed three gauges (8MAN63, 8MAN64 and 8MAN58) to capture sufficient number of wet weather events for use in calibration of the model, as shown in Figure1. Out of these, 8MAN58 is located very close to the outlet of the sewer catchment to NSOOS. These three were all HVQ stations, however, the most upstream gauge 8MAN63 was constricted. Two closest permanent SWC rain gauges, 566100 (North Head STP) and 566089 (Manly CC), were used to generate virtual rainfall time series data for East Esplanade for the gauging period: The data of these two were found well correlated. Due to proximity of 566100 to East Esplanade, this rain gauge was given more weightage in generating the data. The following two dry weather and four wet weather events were considered for use in the model, meeting SWC criteria as far as possible. • Dry Weather Event 1 (DWE1): 06/05/2008 to 13/05/20008 • Dry Weather Event 2 (DWE2): 28/06/2008 to 05/07/20008 Page 2 of 15 S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical NotesEast_Esplanade_Modelling_2008.doc
  • 3. • Wet Weather Event 1(WWE1): 01/02/2008 to 13/02/2008 • Wet Weather Event 2(WWE2): 02/06/2008 to 11/06/2008 • Wet Weather Event 3(WWE3): 24/07/2008 to 02/08/2008 • Wet Weather Event 4(WWE4): 08/04/2008 to 11/04/2008 In the absence of continuous measured data, the outlet water level boundary conditions for the East Esplanade model on NSOOS at Ashburner St (820001) was generated by correlation between this gauging station and 820002 (Eustace St), which had continuous data. Analysis of the captured flow data was done and a summary of flow analysis for the dominant storm of the full/whole wet weather events is provided in Table 1. Table 1: Summary of Flow Analysis EVENTS DWE1 DWE2 WWE1 WWE2 WWE3 WWE4 Gauge Daily Flow (Kl/d) Peak Flow l/s Daily Flow (Kl/d) Peak Flow l/s Daily Flow (Kl/d) Peak Flow l/s Daily Flow (Kl/d) Peak Flow l/s Daily Flow (Kl/d) Peak Flow l/s Daily Flow (Kl/d) Peak Flow l/s 8MAN63 226.0 11.97 197.0 11.03 1104.0 38.08 737.0 25.23 843.0 28.81 317.0 14.70 8MAN64 708.0 22.22 847.0 25.87 2741.0 81.22 2421.0 63.74 2940.0 83.81 1426.0 50.66 8MAN58 1005.0 29.25 1004.0 33.07 3406.0 100.17 2462.0 64.15 3098.0 83.81 1677.0 54.67 Almost identical flows monitored at 8MAN64 and 8MAN58 Significant flow difference between 8MAN64 and 8MAN58 Analysis shows that the water balance between 8MAN64 (u/s) and 8MAN64 (d/s) is not consistent during the wet weather events. The flow volume difference between 8MAN64 and 8MAN58 is significant during event WW1; 8MAN64 recorded 20% less volume than 8MAN58, while the flow volume difference is 2 to 5% for events WW2 and WW3. An earlier investigation found problem in gauging of 8MAN64 before March 2008 covering event WW1. Therefore, WW1 event was not used for calibration of the sub-catchment gauged by 8MAN64. For its catchment area, the flow captured at 8MAN63 looks less than expected. However, the model results show that a major component of the flow from the upstream bypasses this gauge via a bifurcation to the downstream gauge 8MAN64. CALIBRATION The East Esplanade model was basically calibrated for dry periods only. To arrive at a satisfactory flow calibration during dry period, residential flow data of 140 to 150 l/EP/D was used. The existing wet weather parameters were able to match flow volume, flow peak and flow depths within a reasonable range of variation. Minor adjustment of pipe roughness was done upstream of flow gauges to improve depth calibration. Given the uncertainty in flow data, it was deemed not worthwhile to refine the existing wet weather parameters. Calibration results are summarized in Table 2 below, while calibration plots are provided in Appendix. Page 3 of 15 S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical NotesEast_Esplanade_Modelling_2008.doc
  • 4. SEWERFIX WET WEATHER ALLIANCE www.sydneywater.com.au/majorprojects Table 1: Summary of Calibration Results 8MAN63 (Constricted) 8MAN64 8MAN58Event RQV RQP R R R R R R R R RQm DP DM QV QP Qm RDP DM RQV RQP Qm RDP DM DWE1 0.98 0.60 0.98 NA NA 1.16 0.89 1.16 0.79 0.85 0.96 0.79 0.96 0.70 0.70 DWE2 1.17 0.71 1.17 NA NA 1.00 0.75 1.00 0.70 0.73 0.99 0.72 0.99 0.66 0.69 WWE1 0.61 0.67 0.61 NA NA 0.87 0.96 0.87 0.72 0.78 0.77 0.87 0.77 0.95 1.05 WWE2 0.80 0.77 0.80 NA NA 0.82 0.87 0.82 0.74 0.72 0.94 0.99 0.93 0.98 1.00 WWE3 0.89 0.89 0.89 NA NA 0.85 0.95 0.85 0.77 0.74 0.94 1.09 0.94 0.96 0.93 WWE4 1.33 1.13 1.33 NA NA 1.01 1.09 1.01 0.86 0.82 1.04 1.17 1.04 1.05 0.90 Note RQV= Simulated Volume/Gauged Volume RQP =Simulated Highest Peak Flow/Gauged Highest Peak Flow RQM =Simulated Mean Flow/Gauged Mean Flow RDP =Simulated Peak Flow Depth/Gauged Peak Flow Depth RDM= Simulated Mean Flow Depth/Gauged Mean Flow Depth The above ratios for wet weather events represent flow statistics for the dominant storm event within the whole storm event consisting of a number of bursts/events
  • 5. SEWERFIX WET WEATHER ALLIANCE www.sydneywater.com.au/majorprojects CONCLUSIONS It appears that the existing wet weather parameters for the East Esplanade part of the Manly SCAMP are still valid within the allowable margin of error. Prepared: Faruk Kader (SWWA) Date: Checked: Glenn McDermott (SWWA) Date: Approved: (SWC) Date: Comments:
  • 6. SEWERFIX WET WEATHER ALLIANCE www.sydneywater.com.au/majorprojects APPENDIX Calibration Plots for Dry Weather and Wet Weather Events
  • 7. SEWERFIX WET WEATHER ALLIANCE Calibration Plot of Gauge 8MAN63 for DWE1 Calibration Plot of Gauge 8MAN63 for DWE2 www.sydneywater.com.au/majorprojects
  • 8. Calibration Plot of Gauge 8MAN64 for DWE1 Calibration Plot of Gauge 8MAN64 for DWE2 Page 8 of 15 S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical NotesEast_Esplanade_Modelling_2008.doc
  • 9. S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical NotesEast_Esplanade_Modelling_2008.doc Calibration Plot of Gauge 8MAN58 for DWE1 Calibration Plot of Gauge 8MAN58 for DWE2 Page 9 of 15
  • 10. S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical NotesEast_Esplanade_Modelling_2008.doc Calibration Plot of Gauge 8MAN63 for WWE1 Calibration Plot of Gauge 8MAN63 for WWE2 Page 10 of 15
  • 11. S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical NotesEast_Esplanade_Modelling_2008.doc Calibration Plot of Gauge 8MAN63 for WWE3 Calibration Plot of Gauge 8MAN63 for WWE4 Page 11 of 15
  • 12. S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical NotesEast_Esplanade_Modelling_2008.doc Calibration Plot of Gauge 8MAN64 for WWE2 Calibration Plot of Gauge 8MAN64 for WWE3 Page 12 of 15
  • 14. S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical NotesEast_Esplanade_Modelling_2008.doc Calibration Plot of Gauge 8MAN58 for WWE1 Calibration Plot of Gauge 8MAN58 for WWE2 Page 14 of 15
  • 15. S:SWWAPlanningNorthernBeachesLocal SolutionsModellingTechnical NotesEast_Esplanade_Modelling_2008.doc Calibration Plot of Gauge 8MAN58 for WWE3 Calibration Plot of Gauge 8MAN58 for WWE4 Page 15 of 15