This document discusses the impact of easing business regulations on building permissions in Mumbai. It outlines the obstacles in the previous lengthy approval process, including extensive paperwork, long report writing, file journeys between departments, compliance requirements, and delays in obtaining occupancy certificates. The document then details the state government's efforts to improve the process by making all permissions online. It outlines the staged approval process and highlights of the new procedure, including timelines for concurrent approvals. Potential repercussions are noted, such as higher upfront costs and responsibility placed on consultants. Lastly, it recommends real estate companies adopt standard operating procedures and appoint internal reviewers to manage risks under the revised system.