Data Sheet No. DCS_Display_Control_Server_Spec_Sheet




EZcall™ Enterprise
DCS – Display Control Server
Description

The Display Control Server is the core component of an EZcall™ system. The Display Control Server receives
and processes all alarms, events and schedule activity on an EZcall™ system. A DCS may be operated as a
stand-alone application directly connected to a single input system and a single output system, or
complemented with various input, display and output client applications. The DCS may be expanded to
accept numerous output client applications by adding an MDS (Message Dispatch Server) which allows
several different output connections to reside on a single system as well as adds group, naming alias, Email
and message centre networking capabilities.

All display, RTLS, and alarm input clients network with the DCS over a standard Ethernet LAN or WAN
network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised client
connections of each type, and a single MDS connection over a network allowing over 10,000 alarm systems
more than 10,000 messaging/output systems and over 10,000 display clients to be networked into a single-
node EZcall™ installation. Multiple DCS servers may be networked into a central DCS server for multi-site
applications. Watchdog signals are used between the DCS and all client applications to ensure reliable
communications.

The Display Control server is a hardware agnostic platform that can interface and integrate various types and
brands of alarm systems into a single system to share alarms, reporting and dispatching. The DCS also
provides added functionality to basic alarm systems, by adding user features such as dementia monitoring,
door control and other similar features to simple alarm or i/o systems.

Features

   •   TCP/IP, UDP/IP, RS232, RS485 communications support
   •   Secure encrypted server communications
   •   Rapid setup and deployment for small or large systems
   •   HL7 (Health Level 7) integration support
   •   Multi-site support, or multi-node server support
   •   Fail-Over/Standby high availability options
   •   May be run as an application or a supervised Windows service
   •   Virtual COM port support
   •   Support for standard and proprietary protocols including XML, SOAP, SNMP, HTML
   •   Integrated simulator for testing & troubleshooting
   •   Direct output or networked output support
   •   Wireless coverage test tool built-in supports coverage testing using any system
   •   3-click device swap provides user-friendly device replacement for repairing hardware
   •   Direct input, networked input, or combined/mixed input
   •   Remote client control with built-in remote-access engine
   •   Integrated error logging and reporting
   •   Integrated database maintenance utility, with support for SQL, MSDE
   •   Configurable login schemes; per user, per access level, or per function
   •   Large button touch-screen support
   •   Skin’ able desktop allows the operator interface to be customized
   •   Multiple language support, c/w English, Dutch, French, Chinese (simplified)
                                                                                                                              1939 144 Street
                                                                                                                                       th
   •   Integrated history reporting utility
                                                                                                                           Surrey, BC V4A 7M7
   •   Provides primary output, secondary and backup
                                                                                                                        T. 604.812.SOFT (7638)
   •   Support for static, dynamic, or scheduled assignments
                                                                                                                             E. sales@qbsoft.ca
                                                                                                                             W. www.qbsoft.ca

Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                        All trademarks, and trade names shown here are the property of their relative owners.
•    Configurable assignment options; by area, by room, by ward, global
   •    Easy-to-use schedules; day, evening and night shifts may be individually configured
   •    Smart SAM (Sensor Activity Monitor) ensures device sensors are always operational
   •    PC Watchdog card support & integrated software watchdog
   •    Configurable icons
   •    Global priority standardization, up to 9999 system priorities
   •    Packaged with; Paging Encoder Emulator, Virtual Null Modem Application, EZtext server, Time Sync Client, EZstart
        application launcher and Ascom OAP emulator utilities
   •    Extensive log reports simplify system troubleshooting

Supported Applications

EDC – Event Display Client                           TDC – Target Display Client                                TPH – Touch-Panel Host
AIC – Alarm Input Client                             NWC – Network Watchdog Client                              BBC – Button Bar Client
PDC – Popup Display Client                           MDS – Message Dispatch Server                              EGW – EZcall™ GuardRFID Wrapper
VKC – Virtual Keypad Client                          TTC – Text Talker Client                                   EEW - EZcall™ Ekahau Wrapper
WAC – Web Access Client                              iServer™ – Inovonics Wireless Server
EWC – EZcall™ Wireless Client                        SAS – Spider Alert Server
FCC – Facility Control Client                        TMC – Text Messaging Client
VAC – Virtual Alarm Client                           EZtext™/LoginOut™ Server


Supported Direct Output Protocols

Visiplex paging output                 Globestar ConnexAll TMDP (Text Message Dispatch Protocol)
COMP2 paging output                    TAP (Telocator Alphanumeric Protocol) 1.8 paging direct serial output
Ascom enhanced TAP output              TAP 1.8 dial-up paging output

Supported Direct Input Protocols

Hill-Rom LightCom nurse call system network
Maxivox Maxicomm I nurse call system network
Maxivox Maxicomm II nurse call system network
GE/Dukane StaffCall Pro nurse call system network
Raw Data input

Added Applications/Functions

Staff location/presence
Dementia monitoring w/Artificial Intelligence auto-configuration
Staff rounds monitoring
Guard tour monitoring
Patient/Resident check-in
Service requirements
Door monitoring and alarm w/access control support
CCTV popup and control support
RTLS equipment location monitoring and alarm support

System Requirements

CPU:          Intel Xeon Quad Core or Equivalent, >200MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    160Gb
Interface:    RS232 db9/Ethernet (alarm and paging system dependent)

                                                                                                                                   1939 144 Street
                                                                                                                                            th


                                                                                                                                Surrey, BC V4A 7M7
                                                                                                                              T. 604.812.SOFT (7638)
                                                                                                                                  E. sales@qbsoft.ca
                                                                                                                                  W. www.qbsoft.ca
Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                        All trademarks, and trade names shown here are the property of their relative owners.
Data Sheet No. MDS_Message_Dispatch_Server_Spec_Sheet




EZcall™ Enterprise
MDS – Message Dispatch
Server
Description

The Message Dispatch Server is an expansion module to an EZcall™ DCS (Display Control Server) that allows multiple
output clients to be used and provides additional features. In addition to adding the ability for multiple output client
connections, the MDS has a built-in Email and LED message board interface. By adding an MDS to an existing DCS,
additional EZcall™ features are enabled, including output device group creation and output device aliasing. The Message
Dispatch Server networks directly with an EZcall™ DCS over a standard Ethernet LAN or WAN network using the TCP/IP
protocol. The Message Dispatch Server supports up to 10,000 of any type of output client connection, allowing the system
to be very expandable. Every DCS may only be linked to one MDS and typically reside on the same server computer.
Watchdog signals are used between the DCS and the MDS applications to ensure reliable communications.

Features

   •    SMTP, POP3, TCP/IP, UDP/IP, RS232, RS485 communications support
   •    Secure encrypted server communications
   •    Rapid setup and deployment
   •    Standard or secure Email server support, with MIME, HTML, and UUencoding support
   •    May be run as an application or a supervised Windows service
   •    Virtual COM port support
   •    Supports direct connection to LED message centres
   •    Output device group creation and alias naming adds versatility to a DCS server
   •    Instant Email SMS message output capability supported by mobile devices
   •    Prioritized Email output capability
   •    Integrated simulator for testing & troubleshooting
   •    Extensive log reports simplify system troubleshooting

Supported Systems/Products

Application Connections                              LED Message Centers                       Email Output
TPC – Telephone Paging Client (up to 9999)           Edwards Message Centre                    SMTP
SPC – Serial Paging Client (up to 9999)              Alpha PrintPak                            POP3
CAC – Command Argument Client (up to 9999)           Alpha EZkey II                            MIME
OCC – Output Control Client (up to 9999)             Alpha EZ95                                UUencoding
DCS – Display Control Server (1 connection)          Pro-Lite ver. 5.25
                                                     Pro-Lite ver.6


System Requirements

CPU:          Intel Xeon Quad Core or Equivalent, >200MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    120Gb
Interface:    RS232 db9/Ethernet (output system dependent)

                                                                                                                             1939 144 Street
                                                                                                                                      th


                                                                                                                          Surrey, BC V4A 7M7
                                                                                                                        T. 604.812.SOFT (7638)
                                                                                                                            E. sales@qbsoft.ca
                                                                                                                            W. www.qbsoft.ca


Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                        All trademarks, and trade names shown here are the property of their relative owners.
Data sheet No. WAC_Web_Access_Client_Spec_Sheet




EZcall™ Enterprise
WAC – Web Access Client
Description

The Web Access Client is a powerful EZcall™ server application that allows EZcall™ DCS functions to be accessed using
any standard web browser. The Web Access Client prevents the need of installing and supporting numerous client
program installations on user computers. By allowing browser access to most EZcall™ functions, a large facility
deployment may be completed in a fraction of the time needed by using dedicated client programs. The browser interface
also allows an EZcall™ deployment to be operating system independent. No matter what O.S. or web browser is being
used in the facility (Linux, Unix, MAC, Windows), all will function in the same manner using their standard web browsers as
the user interface. The Web Access Client is also supported by all popular standard and mobile browsers including;
Firefox, Windows Internet Explorer, Apple Safari, Opera, Google Chrome.

Features

   •       Standard HTTP 1.0 and 2.0 support ensures reverse compatibility
   •       Secure password protection login
   •       Secure encrypted server communications
   •       Built-in FGA Web Server does not rely or use IIS
   •       Reliable FGA Web Server not susceptible to HTTP virus attacks, spoofing or malware
   •       Rapid setup and deployment; no HTML language required
   •       May be run as an application or a supervised Windows service
   •       Alarm text and graphical map display
   •       Manual text messaging to any EZcall™ output device
   •       Alarm history display
   •       Call Routing Assignments
   •       On-Screen Virtual Call Buttons
   •       Staff Presence location display
   •       Reconfigurable skins allows graphics to be customized to the site/customer
   •       Mobile browser support (iPhone, BlackBerry, Android, Windows Mobile)
   •       Extensive log reports simplify system troubleshooting

System Requirements

Clients:         Web browsers that support HTTP 1.0

CPU:             Intel Xeon Quad Core or Equivalent, >180MHz
OS:              Windows XP, 7, Server 2003, Vista Ultimate
Memory:          2GB minimum (4GB recommended)
LAN/WAN:         10/100 (Gigabit recommended)
Hard Disk:       >120GB @ 7200RPM (> 10,000RPM recommended)




                                                                                                                                 1939 144 Street
                                                                                                                                          th


                                                                                                                               Surrey, BC V4A 7M7
                                                                                                                            T. 604.812.SOFT (7638)
                                                                                                                                E. sales@qbsoft.ca
                                                                                                                                 W. www.qbsoft.ca
Specifications subject to change without notice. © Copyright 2010 – QBsoft Solutions

                        All trademarks, and trade names shown here are the property of their relative owners.
Data Sheet No. IWS_iServer_Inovonics_Wireless_Server_Spec_Sheet




EZcall™ Enterprise
IWS – iServer™ Inovonics
Wireless Server
Description

The EZcall™ iServer™ is a fully functional integrated RTLS system that can network with an EZcall™ system. The iServer™
uses the Inovonics EchoStream hardware to function as a wireless duress, locating and nurse call solution. The iServer™
communicates directly to the Inovonics EchoStream hardware to allow all EchoStream alarms to be received and
processed by EZcall™, as well as allowing the iServer™ to function as a stand-alone alarm system. Every IWS can network
(optional) to an EZcall™ DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP
protocol. A single EZcall™ DCS will support up to 10,000 supervised EGW client connections over a network allowing that
many systems to be networked into an enterprise EZcall™ installation. Watchdog signals are used between the DCS and
all EGW applications to ensure reliable communications.

Features

   •   TCP/IP, UDP/IP, RS232, RS485 communications support
   •   Secure encrypted server communications
   •   Fully functional stand-alone wired/wireless duress/alarm system
   •   Rapid setup and deployment
   •   Real-time location and alarm information monitoring using proprietary RTLE™ algorithms
   •   Integrated web-server for alarm and history display, as well as transmitter management
   •   May be run as an application or a supervised Windows service
   •   User configurable priorities and messages
   •   Supports direct connection to numerous pocket paging systems
   •   Supports WWC wireless wizard client connections for system maintenance
   •   Integrated transmitter simulator for testing & troubleshooting
   •   Extensive log reports simplify system troubleshooting

Supported Systems/Products

Inovonics EchoStream serial receiver, repeaters and transmitters
EZcall™ DCS server (optional)
WWC wireless wizard client
Standard HTTP 1.0 capable web browsers

System Requirements

CPU:          Intel Core2 Duo or Equivalent, >180MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    160Gb
Interface:    Inovonics proprietary protocol


                                                                                                                          1939 144 Street
                                                                                                                                   th


                                                                                                                       Surrey, BC V4A 7M7
                                                                                                                    T. 604.812.SOFT (7638)
                                                                                                                         E. sales@qbsoft.ca
                                                                                                                         W. www.qbsoft.ca
Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                       EchoStream and Inovonics are registered trademarks of Inovonics Inc..
Data Sheet No. EEW_EZcall_Ekahau_Wrapper_Spec_Sheet




EZcall™ Enterprise
EEW – EZcall™ Ekahau
Wrapper
Description

The EZcall™ Ekahau Wrapper is a bi-directional interface between an EZcall™ system and an Ekahau RTLS system. The
EEW integrates directly with an Ekahau RTLS server using the proprietary Ekahau XML-based protocol to allow all Ekahau
alarms to be received and processed by EZcall™, as well as allowing an EZcall™ system to dispatch alarm messages to
Ekahau WiFi badge tags. Every EEW networks to an EZcall™ DCS (Display Control Server) over a standard Ethernet LAN
or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised EEW client
connections over a network allowing that many systems to be networked into an enterprise EZcall™ installation. Watchdog
signals are used between the DCS and all EEW applications to ensure reliable communications.

Features

   •   TCP/IP, UDP/IP, RS232, RS485 communications support
   •   Secure encrypted server communications
   •   Secure encrypted RTLS server communications
   •   Rapid setup and deployment
   •   Real-time location and alarm information monitoring
   •   Message dispatching to badge tags
   •   May be run as an application or a supervised Windows service
   •   User configurable priorities and messages
   •   Integrated badge tag simulator for testing & troubleshooting
   •   Extensive log reports simplify system troubleshooting

Supported Systems/Products

Ekahau RTLS server
EZcall™ DCS server

System Requirements

CPU:          Intel Core2 Duo or Equivalent, >180MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    60Gb
Interface:    TCP/IP XML-based protocol




                                                                                                               1939 144 Street
                                                                                                                        th


                                                                                                             Surrey, BC V4A 7M7
                                                                                                          T. 604.812.SOFT (7638)
                                                                                                              E. sales@qbsoft.ca
                                                                                                               W. www.qbsoft.ca
Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                              Ekahau is a trademark of Ekahau Corporation Inc.
Data Sheet No. EGW_EZcall_GuardRFID_Wrapper_Spec_Sheet




EZcall™ Enterprise
EGW – EZcall™ GuardRFID
Wrapper
Description

The EZcall™ GuardRFID Wrapper is a bi-directional interface between an EZcall™ system and a GuardRFID RTLS system.
The EGW integrates directly with an GuardRFID Argus server using the proprietary GuardRFID XML-based protocol to
allow all GuardRFID SafeGuard, TotGuard and AllGuard alarms to be received and processed by EZcall™, as well as
allowing an EZcall™ system to dispatch alarm messages to GuardRFID staff tags. Every EGW networks to an EZcall™
DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™
DCS will support up to 10,000 supervised EGW client connections over a network allowing that many systems to be
networked into an enterprise EZcall™ installation. Watchdog signals are used between the DCS and all EGW applications
to ensure reliable communications.

Features

   •   TCP/IP, UDP/IP, RS232, RS485 communications support
   •   Secure encrypted server communications
   •   Secure encrypted Argus server communications
   •   Rapid setup and deployment
   •   Real-time location and alarm information monitoring
   •   Message dispatching to staff tags
   •   May be run as an application or a supervised Windows service
   •   User configurable priorities and messages
   •   Integrated badge tag simulator for testing & troubleshooting
   •   Extensive log reports simplify system troubleshooting

Supported Systems/Products

GuardRFID Argus server
EZcall™ DCS server

System Requirements

CPU:          Intel Core2 Duo or Equivalent, >180MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    60Gb
Interface:    TCP/IP XML-based protocol




                                                                                                                      1939 144 Street
                                                                                                                               th


                                                                                                                   Surrey, BC V4A 7M7
                                                                                                                 T. 604.812.SOFT (7638)
                                                                                                                     E. sales@qbsoft.ca
                                                                                                                     W. www.qbsoft.ca
Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                  TotGuard, Argus, SafeGuard, AllGuard and GuardRFID are trademarks of GuardRFID Inc.
Data Sheet No. TPH_Touch_Panel_Host_Spec_Sheet




EZcall™ Enterprise
TPH – Touch-Panel Host
Description

The Touch-Panel Host is an EZcall™ server application to monitor alarm information from networked or
serially-attached EZtouch™ panels. Various protocols are supported by the TPH client application that may
be received by a direct serial, or supervised TCP/IP connection. Every TPH client networks to an EZcall™
DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A
single EZcall™ DCS will support up to 10,000 supervised TPH client connections over a network allowing that
many EZtouch™ panels and systems to be networked into an enterprise EZcall™ installation. Watchdog
signals are used between the DCS and all TPH applications to ensure reliable communications.

The TPH client operates as a server that hosts any number of supervised EZtouch™ panels. All EZtouch™
events are logged by the TPH and instantly forwarded to the EZcall™ DCS server for immediate alarm
dispatching and archiving. A single TPH can host any combination or 2.8 inch and 4.3 inch EZtouch™
panels. A single TPH may be sued to host both serially attached or Ethernet networked EZtouch™ panels
providing flexibility of using home-run or daisy-chained cabling on a single system.

Features

   •   TCP/IP, UDP/IP, RS485 communications support
   •   Secure encrypted server communications
   •   Rapid setup and deployment
   •   May be run as an application or a supervised Windows service
   •   Supervised touch panel connections
   •   On-screen virtual touch-panel emulates the attached devices
   •   Integrated simulator for testing & troubleshooting
   •   Simple integration to an EZcall™ DCS server
   •   Supports any combination or PoE Ethernet and RS485-looped EZtouch ™ panels
   •   Customizable priorities and alerts

Supported Systems/Products

EZ-TP28E - 2.8” Color LCD PoE Ethernet EZtouch™ panels
EZ-TP28S - 2.8” Color LCD RS485 serial EZtouch™ panels
EZ-TP43S – 4.3” Color LCD RS485 serial EZtouch™ panels
EZcall™ DCS (Display Control Server)

System Requirements

CPU:          Intel Xeon Quad Core or Equivalent, >180MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    >120Gb @ 7200RPM (>10,000RPM recommended)
Interface:    RS232 db9/Ethernet (alarm system dependent)



                                                                                                                             1939 144 Street
                                                                                                                                      th


                                                                                                                           Surrey, BC V4A 7M7
                                                                                                                        T. 604.812.SOFT (7638)
                                                                                                                            E. sales@qbsoft.ca
                                                                                                                             W. www.qbsoft.ca
Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                      All trademarks, and trade names shown here are the property of their relative owners.
Data Sheet No. EZtouch_Panels_Spec_Sheet




EZcall™ Enterprise
EZtouch™ – Color Touch-
Screen Panels
Description

The EZtouch™ panels are a user-friendly wall-mounted touch-screen panel that provide configurable alarm buttons and
alarm display capabilities. EZtouch™ panels are available as PoE powered Ethernet devices and RS485 serial devices to
allow multiple cabling configurations to be used. Each EZtouch™ panel supports from zero to 40 call buttons and may
also be configured with an alarm display and/or door control & monitoring. Every EZtouch™ panel networks to an EZcall™
TPH (Touch Panel Host) over a standard Ethernet LAN/WAN network using the TCP/IP protocol or through an RS485 serial
link. A single EZcall™ TPH will support up to 100,000 supervised EZtouch™ panel connections on a single system.
Watchdog signals are used between the TPH and all EZtouch™ panels to ensure reliable supervised communications.

EZtouch™ panels are available in two sizes; 2.8” display and 4.3” display. EZtouch™ panels are water-resistant with an
IP65 rating and may be cleaned using standard cleaners. All EZtouch™ panels are designed to mount in industry-
standard North American electrical boxes and also have weatherproof surface-mount backboxes available for outdoor
mounting. These cost effective touch panels provide an attractive and cost effective alarm initiation or display device that
may be used virtually anywhere. EZtouch™ panels may be used as alarm initiation devices, to display alarms at strategic
locations or as workflow control devices. With EZtouch panels, you are free to select which buttons you need at all
locations and can add/remove buttons as required.

Features

   •   Intuitive user-friendly call buttons
   •   Timeout digital clock display helps reduce light emission during evenings.
   •   Supervised connection alerts EZcall™ whenever a panel is disconnected or offline
   •   PoE powered Ethernet and RS485 models available
   •   Ethernet and RS485 models may be intermixed on a single TPH
   •   Fully configurable and customizable buttons with icons
   •   Alarm display (optional)
   •   Door monitoring and control display (optional)
   •   Integrated clean-screen option allows the screen to be cleaned
   •   Quick and easy to setup
   •   ESD Protection to 4kV
   •   Wide operating temperature range from -20°C ~ 70°C
   •   IP65 Waterproof front panel
   •   Built-in alarm sounder (speaker on the EZ-TP43 models)
   •   Very low power consumption (<2.5W)
   •   5-Year warranty

System Requirements

EZcall™ TPH Touch Panel Host
12VDC power supply (RS485 models)
IEEE 802.3af class 1 PoE network switch (Ethernet models)




Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                  All trademarks, and trade names shown here are the property of their relative owners.
Physical Characteristics

EZ-TP28 panels have a 2.8” TFT LCD color touch-screen display. EZ-TP28E is a PoE powered Ethernet model and the EZ-
TP28S is an RS485 serially networked (up to 31 per loop) model. EZ-TP28S dimensions are similar to EZ-TP28E.




EZ-TP43S panels hand a 4/3” TFT LCD color touch-screen display and are networked with an RS485 loop (up to 31).




Specifications




                                                                                                       1939 144 Street
                                                                                                                th


                                                                                                    Surrey, BC V4A 7M7
                                                                                                  T. 604.812.SOFT (7638)
                                                                                                      E. sales@qbsoft.ca
                                                                                                      W. www.qbsoft.ca

Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions
Data Sheet No. AIC_Alarm_Input_Client_Spec_Sheet




EZcall™ Enterprise
AIC - Alarm Input Client
Description

The Alarm Input Client is the input gateway for an EZcall™ system to retrieve alarm information from virtually any alarm
system or hardware. Various protocols are supported by the AIC client application that may be received by a direct serial,
TCP/IP, or UDP/IP connection. Every AIC client networks to an EZcall™ DCS (Display Control Server) over a standard
Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised AIC
client connections over a network allowing that many systems to be networked into a single-node EZcall™ installation.
Watchdog signals are used between the DCS and all AIC applications to ensure reliable communications.

Features

   •      TCP/IP, UDP/IP, RS232, RS485 communications support
   •      Supports XLM, SOAP, TAP, and Proprietary protocols
   •      Secure encrypted server communications
   •      Rapid setup and deployment
   •      AIC hardware appliance; reduces setup/deployment time
   •      May be run as an application or a supervised Windows service
   •      Virtual COM port support
   •      Integrated simulator for testing & troubleshooting
   •      Built-in web-server provides instant alarm display & activity monitoring
   •      Extensive log reports simplify system troubleshooting

Supported Systems/Products
Fire Alarm Systems                              Nurse Call Systems                                      Intercom Systems
Edwards EST-3 serial interface                  Dukane Procare 6000 VM input                            Algo VoiceComm 3400 OAI input
Edwards Quick serial interface                  Dukane Procare 2000 network input                       Dukane Starcare OAI input
Simplex 4100U serial input                      Dukane Procare 6000 ARMS input                          Edwards AccuSound Network input
Simplex 5000 serial input                       Dukane Procare 6000 OAI input                           Maxivox MC1 network interface
Notifier AM2020 serial                          Dukane Procare 6000 TAP input                           Sentex Infinity
Mircom serial                                   Dukane StaffCall Pro Network input
Honeywell XLS-1000 serial                       GE Caregard modem input                                 Other Alarm Systems
                                                GE Telligence Telergy TAP input                         Andover Continuum ascii input
                                                GE Telligence SQL database interface                    Genetec Synergis/Omnicast
                                                Hill-Rom ComLite network input                          GE Facility Commander
Paging System Emulation                         Maxivox Maxicomm I network interface                    GE Summit Pro PET input
Ascom Wireless paging input                     Maxivox Maxicomm II network interface                   Kantech Enterprise/Global
Generic TAP server emulation                    Rauland Responder 3000 net-controller                   Keyscan
Visiplex pocket paging input                    Rauland Responder 4000 PIP OAI                          RBH Axiom
COMP1 / COMP2 paging input                      Rauland Responder IV TAP input                          Senstar Stellar StarNet
Globestar Formatted TAP input                   Tunstall CMS4000 OAI serial interface                   X-Mark Halo TAP input
Home Free AMS ElmoPage input                    Zettler Sentinel 500 TAP input                          X-Mark Hugs/MyCall/FintIt
Nordicom AL800 server                           West-Com Endeavour/Novus/Odyssey+                       X-Mark RoamAlert TAP input
Salcom paging server                            Tektone NC300 / NC300 II                                Visonic Eiris OAI input
Scope paging server                             Ascom TeleCARE / TelePROTECT                            Visonic Eiris 3.0 UDP capture
                                                Simplex EZcare TAP input                                ADAM-6000 I/O boards
                                                Austco APR protocol                                     Ontrak ADR2000 I/O boards


System Requirements

CPU:              Intel Core2 Duo or Equivalent, >200MHz
OS:               Windows XP, 7, Server 2003, Vista Ultimate
Memory:           2GB minimum (4GB recommended)
LAN/WAN:          10/100 (Gigabit recommended)
                                                                                                                                             1939 144 Street
                                                                                                                                                      th
Hard Disk:        120Gb
                                                                                                                                          Surrey, BC V4A 7M7
Interface:        RS232 db9/Ethernet (alarm system dependent)
                                                                                                                                        T. 604.812.SOFT (7638)
                                                                                                                                            E. sales@qbsoft.ca
                                                                                                                                            W. www.qbsoft.ca

Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                                 All trademarks, and trade names shown here are the property of their relative owners.
Data Sheet No. VKC_Virtual_Keypad_Client_Spec_Sheet




EZcall™ Enterprise
VKC – Virtual Keypad Client
Description

The Virtual Keypad Client is the input gateway for an EZcall™ system to retrieve alarm information from
various intrusion alarm systems. Various protocols are supported by the VKC client application that may be
received by a direct serial, TCP/IP, or UDP/IP connection. Every VKC client networks to an EZcall™ DCS
(Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single
EZcall™ DCS will support up to 10,000 supervised VKC client connections over a network allowing that many
intrusion alarm systems to be networked into a single-node EZcall™ installation. Watchdog signals are used
between the DCS and all VKC applications to ensure reliable communications.

The VKC client also includes a built-in web-server that allows operators to connect to the VKC and it’s
associated intrusion alarm system through any standard web browser. All intrusion alarm keypad functions
including arming, disarming, and bypassing zones are supported through the intuitive on-screen virtual
keypad that emulates the actual keypads functions.

Features

   •   TCP/IP, UDP/IP, RS232, RS485 communications support
   •   Secure encrypted server communications
   •   Rapid setup and deployment
   •   May be run as an application or a supervised Windows service
   •   Virtual COM port support
   •   On-screen virtual keypad emulates the attached system
   •   Integrated simulator for testing & troubleshooting
   •   Built-in web-server provides instant alarm display & system control
   •   Extensive log reports simplify system troubleshooting

Supported Systems/Products

DSC Maxsys
DSC Power864
GE NetworX
GE Concord
GE Advent
Honeywell/Ademco Vista
Paradox Esprit
Paradox Spectra

System Requirements

CPU:          Intel Xeon Quad Core or Equivalent, >180MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    >120Gb @ 7200RPM (>10,000RPM recommended)
Interface:    RS232 db9/Ethernet (alarm system dependent)

                                                                                                                               1939 144 Street
                                                                                                                                        th


                                                                                                                             Surrey, BC V4A 7M7
                                                                                                                          T. 604.812.SOFT (7638)
                                                                                                                              E. sales@qbsoft.ca
                                                                                                                               W. www.qbsoft.ca

Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                       All trademarks, and trade names shown here are the property of their relative owners.
Data Sheet No. BBC_Button_Bar_Client_Spec_Sheet




EZcall™ Enterprise
BBC – Button Bar Client
Description

The Button Bar Client is a unique input client used to generate alarms on an EZcall™ system from a PC desktop. The
Button Bar Client is fully customizable to provide any quantity and type of on-screen button with different functions. The
BBC provides a non-intrusive bar on a PC desktop that can be hidden away until needed. Ideal uses include nurse station
porter and cleaner requests, and non-conventional workflow requests. Buttons may be added or deleted from the bar and
configured individually on each desktop. Every BBC client networks to an EZcall™ DCS (Display Control Server) over a
standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000
supervised BBC client connections over a network allowing that many systems to be networked into a single-node EZcall™
installation. Watchdog signals are used between the DCS and all BBC applications to ensure reliable communications.

Features

   •   Attractive display does not take-up the entire screen
   •   Configurable wards or areas – only display the locations that are needed
   •   May be run as an application or a supervised Windows service
   •   Event list display
   •   Lockable to prevent shutting-down or relocating the window
   •   Extensive log reports simplify system troubleshooting

System Requirements

CPU:          Intel Core2 Duo or Equivalent, >180MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate, Linux Ubuntu 9.0
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    60Gb




                                                                                                                               1939 144 Street
                                                                                                                                        th


                                                                                                                            Surrey, BC V4A 7M7
                                                                                                                          T. 604.812.SOFT (7638)
                                                                                                                              E. sales@qbsoft.ca
                                                                                                                               W. www.qbsoft.ca
Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                     All trademarks, and trade names shown here are the property of their relative owners.
Data Sheet No. CAC_Command_Argument_Client_Spec_Sheet




EZcall™ Enterprise
CAC – Command Argument
Client
Description

The Command Argument Client is an output gateway for an EZcall™ system to output standard DOS-like commands to
control various specialized systems. The Command Argument Client may be fully customized to generate virtually any
command-line argument output needed. Every CAC client networks to an EZcall™ MDS (Message Dispatch Server) over a
standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ MDS will support up to 10,000
supervised CAC client connections over a network allowing that many systems to be networked into a single-node EZcall™
installation. Watchdog signals are used between the DCS and all CAC applications to ensure reliable communications.

Features

   •   Fully configurable & customizable command-line arguments
   •   Secure encrypted server communications
   •   Rapid setup and deployment
   •   May be run as an application or a supervised Windows service
   •   Virtual COM port support
   •   Integrated testing & troubleshooting utility
   •   Extensive log reports simplify system troubleshooting

System Requirements

CPU:          Intel Core2 Duo or Equivalent, >180MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    60Gb




                                                                                                                1939 144 Street
                                                                                                                         th


                                                                                                             Surrey, BC V4A 7M7
                                                                                                           T. 604.812.SOFT (7638)
                                                                                                               E. sales@qbsoft.ca
                                                                                                               W. www.qbsoft.ca
Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                             DOS is a registered trademark of Microsoft Corp.
 


    EZcall Enterprise
    EDC – Event Display Client
    Description

    The Event Display Client is an output client used to display alarm or status messages on a computer output display. The
    Event Display Client is fully configurable to display events from specific areas and/or specific call types and priorities.
    Some uses include centralized Code Blue annunciators, local annunciators, maintenance or housekeeper alarm displays.
    Every EDC client networks to an EZcall DCS (Display Control Server) over a standard Ethernet LAN or WAN network using
    the TCP/IP protocol. A single EZcall DCS will support up to 10,000 supervised EDC client connections over a network
    allowing that many systems to be networked into a single-node EZcall installation. Watchdog signals are used between
    the DCS and all EDC applications to ensure reliable communications.

    Features

           Skin’able border images allow for a customized appearance of the display
           Configurable wards or areas – only display the locations that are needed
           Selectable priorities – only display the events types that are required
           Configurable time – allows events to only generate popups at certain times-of-day
           Hidden mouse pointer support
           May be run as an application or a supervised Windows service
           Configurable fields and text size, color & font
           Date/Time display
           Configurable screen size and location with locking capability to ensure that
            the display is always shown at the same location every time it is started
           Multiple EDC support – run several EDC windows on the same computer to
            display various event types or areas on a single display
           Windows and Linux versions available
           Support for Microsoft Agent popup characters
           Extensive log reports simplify system troubleshooting

    System Requirements

    CPU:          Intel Core2 Duo or Equivalent, >180MHz
    OS:           Windows XP, 7, Server 2003, Vista Ultimate, Linux Ubuntu 9.0
    Memory:       2GB minimum (4GB recommended)
    LAN/WAN:      10/100 (Gigabit recommended)
    Hard Disk:    60Gb




                                                                                                                1939 144th Street
                                                                                                             Surrey, BC V4A 7M7
                                                                                                           T. 604.812.SOFT (7638)
                                                                                                               E. sales@qbsoft.ca
                                                                                                               W. www.qbsoft.ca

 
    Specifications subject to change without notice.  Copyright 2010 – QBsoft Solutions 
 


    EZcall Enterprise
    PDC – Popup Display Client
    Description

    The Popup Display Client is an output client used to display alarm or status messages on a computer output display. The
    Event Display Client is fully configurable to display events from specific areas and/or specific call types and priorities.
    Some uses include centralized Code Blue annunciators, local annunciators, maintenance or housekeeper alarm displays.
    Every EDC client networks to an EZcall DCS (Display Control Server) over a standard Ethernet LAN or WAN network using
    the TCP/IP protocol. A single EZcall DCS will support up to 10,000 supervised EDC client connections over a network
    allowing that many systems to be networked into a single-node EZcall installation. Watchdog signals are used between
    the DCS and all EDC applications to ensure reliable communications.

    Features

           Select from over 10 different window types
           Configurable wards or areas – only display the locations that are needed
           Selectable priorities – only display the events types that are required
           Configurable time – allows events to only generate popups at certain times-of-day
           May be run as an application or a supervised Windows service
           Configurable fields and text size, color & font
           Text-to-speech and sound file support allows sounds to be used in conjunction with a visual popup window
           Lockable to prevent operators from shutting-down the alarm display
           Extensive log reports simplify system troubleshooting

    System Requirements

    CPU:          Intel Core2 Duo or Equivalent, >180MHz
    OS:           Windows XP, 7, Server 2003, Vista Ultimate, Linux Ubuntu 9.0
    Memory:       2GB minimum (4GB recommended)
    LAN/WAN:      10/100 (Gigabit recommended)
    Hard Disk:    60Gb




                                                                                                                1939 144th Street
                                                                                                             Surrey, BC V4A 7M7
                                                                                                           T. 604.812.SOFT (7638)
                                                                                                               E. sales@qbsoft.ca
                                                                                                               W. www.qbsoft.ca

 
    Specifications subject to change without notice.  Copyright 2010 – QBsoft Solutions 
 


    EZcall Enterprise
    TTC – Text Talker Client
    Description

    The Text Talker Client is a Text-to-Speech output client that allows alarm messages to be verbally announced using a PC
    speaker output. The Text Talker Client is compatible with most industry-standard text-to-speech engines and voices and
    supports multi-language translation. A TTC client may be configured to output specific wards or areas or all areas to
    provide multiple output alarm messaging using standard spoken messages rather than pre-recorded alerts. Every TTC
    client networks to an EZcall MDS (Message Dispatch Server) over a standard Ethernet LAN or WAN network using the
    TCP/IP protocol. A single EZcall MDS will support up to 10,000 supervised TTC client connections over a network allowing
    that many systems to be networked into a single-node EZcall installation. Watchdog signals are used between the DCS
    and all TTC applications to ensure reliable communications.

    Features

           Fully configurable & customizable using several brands of text-to-speech voice
           Configurable time – allows events to only output at certain times-of-day
           Secure encrypted server communications
           Rapid setup and deployment
           May be run as an application or a supervised Windows service
           Supports text-to-speech, pre-recorded .WAV files or a combination of both
           Support for Microsoft Agent popup characters
           Built-in abbreviation and phonetic translator to ensure that all messages are understood
           Integrated testing & troubleshooting utility
           Extensive log reports simplify system troubleshooting

    System Requirements

    CPU:          Intel Core2 Duo or Equivalent, >180MHz
    OS:           Windows XP, 7, Server 2003, Vista Ultimate
    Memory:       2GB minimum (4GB recommended)
    LAN/WAN:      10/100 (Gigabit recommended)
    Hard Disk:    60Gb




                                                                                                             1939 144th Street
                                                                                                           Surrey, BC V4A 7M7
                                                                                                        T. 604.812.SOFT (7638)
                                                                                                            E. sales@qbsoft.ca
                                                                                                             W. www.qbsoft.ca
 
    Specifications subject to change without notice.  Copyright 2010 – QBsoft Solutions 
Data Sheet No. TDC_Target_Display_Client_Spec_Sheet




EZcall™ Enterprise
TDC – Target Display Client
Description

The Target Display Client is a unique output client used to display real-time staff response times or call activity. The Target
Display Client is fully configurable to display events from specific areas and allows you to set a specific target response
time. Only events outside the target time will increment the counter and be displayed. Ideal uses include manager heads-
up display for at-a-glance status reporting and worker incentive displays. Every TDC client networks to an EZcall™ DCS
(Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS
will support up to 10,000 supervised TDC client connections over a network allowing that many systems to be networked
into a single-node EZcall™ installation. Watchdog signals are used between the DCS and all TDC applications to ensure
reliable communications.

Features

   •    Attractive display does not take-up the entire screen
   •    Configurable wards or areas – only display the locations that are needed
   •    May be run as an application or a supervised Windows service
   •    Event list display
   •    Lockable to prevent shutting-down or relocating the window
   •    Extensive log reports simplify system troubleshooting

System Requirements

CPU:          Intel Core2 Duo or Equivalent, >180MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate, Linux Ubuntu 9.0
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    60Gb




                                                                                                                                1939 144 Street
                                                                                                                                         th


                                                                                                                             Surrey, BC V4A 7M7
                                                                                                                           T. 604.812.SOFT (7638)
                                                                                                                               E. sales@qbsoft.ca
                                                                                                                               W. www.qbsoft.ca
Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                      All trademarks, and trade names shown here are the property of their relative owners.
 


    EZcall Enterprise
    NWC – Network Watchdog
    Client
    Description

    The Network Watchdog Client is an input client that allows an EZcall system to supervise network software components
    and hardware. The Network Watchdog Client monitors other network devices by sending requests for their response. The
    NWC client will alert the DCS server of any network components that is unresponsive to generate a system alarm or
    perform other actions. Various protocols are supported by the NWC client application including; PING, SNMP, and MAC
    ID request. Every NWC client networks to an EZcall DCS (Display Control Server) over a standard Ethernet LAN or WAN
    network using the TCP/IP protocol. A single EZcall DCS will support up to 10,000 supervised NWC client connections over
    a network allowing that many intrusion alarm systems to be networked into a single-node EZcall installation. Watchdog
    signals are used between the DCS and all NWC applications to ensure reliable communications.

    Features

           TCP/IP, UDP/IP, SNMP, PING communications support
           Rapid setup and deployment
           May be run as an application or a supervised Windows service
           Receive alerts of unresponsive critical network components
           Integrated testing & troubleshooting utilities
           Extensive log reports simplify system troubleshooting

    System Requirements

    CPU:          Intel Core2 Duo or Equivalent, >180MHz
    OS:           Windows XP, 7, Server 2003, Vista Ultimate
    Memory:       2GB minimum (4GB recommended)
    LAN/WAN:      10/100 (Gigabit recommended)
    Hard Disk:    60Gb




                                                                                                             1939 144th Street
                                                                                                          Surrey, BC V4A 7M7
                                                                                                        T. 604.812.SOFT (7638)
                                                                                                            E. sales@qbsoft.ca
                                                                                                            W. www.qbsoft.ca

 
    Specifications subject to change without notice.  Copyright 2010 – QBsoft Solutions 
Data Sheet No. SPC_Serial_Paging_Client_Spec_Sheet




EZcall™ Enterprise
SPC – Serial Paging Client
Description

The Serial Paging Client is the output gateway for an EZcall™ system to forward alarm text messages to
various SMS and paging systems or serial printers. Various protocols are supported by the SPC client
application that may connect by a direct serial, TCP/IP, or UDP/IP connection. Every SPC client networks to
an EZcall™ MDS (Message Dispatch Server) over a standard Ethernet LAN or WAN network using the TCP/IP
protocol. A single EZcall™ MDS will support up to 10,000 supervised SPC client connections over a network
allowing that many systems to be networked into a single-node EZcall™ installation. Watchdog signals are
used between the DCS and all SPC applications to ensure reliable communications.

Features

   •   TCP/IP, UDP/IP, RS232, RS485 communications support
   •   Secure encrypted server communications
   •   Rapid setup and deployment
   •   SPC hardware appliance; reduces setup/deployment time
   •   May be run as an application or a supervised Windows service
   •   Virtual COM port support
   •   Built-in abbreviation translator to ensure that all messages fit the mobile device screens
   •   Integrated simulator for testing & troubleshooting
   •   Extensive log reports simplify system troubleshooting

Supported Protocols

COMP1 / COMP1                          Visonic SL-PTX                                          Poltys DCC output (Eiris emulation)
TAP/PET 1.8 (serial & dial-up)         Edwards EST-3 printer emulation                         Pelco P & D ascii output
Visiplex basic                         EZcall serial printer detailed                          Salcom paging protocol
Visiplex VS-40                         EZcall serial printer simple                            Scope paging protocol
Ascom Enhanced TAP                     Waveware protocol                                       SecureTech WAVE 2-way radio output
J-Tech Extended                        Zetron TAP (capcode support)
Austco APR                             Globestar formatted TAP
Nordicom AL800                         GE Telergy 7.1 TAP (GUID support)

System Requirements

CPU:          Intel Core2 Duo or Equivalent, >180MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    60Gb
Interface:    RS232 db9/Ethernet (paging system dependent)




                                                                                                                                1939 144 Street
                                                                                                                                         th


                                                                                                                              Surrey, BC V4A 7M7
                                                                                                                           T. 604.812.SOFT (7638)
                                                                                                                               E. sales@qbsoft.ca
                                                                                                                                W. www.qbsoft.ca

Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                        All trademarks, and trade names shown here are the property of their relative owners.
Data Sheet No. TPC_Telephone_Paging_Client_Spec_Sheet




EZcall™ Enterprise
TPC – Telephone Paging
Client
Description

The Telephone Paging Client is the output gateway for an EZcall™ system to forward alarm text messages to various wired
and wireless telephony systems. Various protocols are supported by the TPC client application that may connect by a
direct serial, TCP/IP, or UDP/IP connection. Every TPC client networks to an EZcall™ MDS (Message Dispatch Server)
over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ MDS will support up to 10,000
supervised TPC client connections over a network allowing that many systems to be networked into a single-node EZcall™
installation. Watchdog signals are used between the DCS and all TPC applications to ensure reliable communications.

Features

   •   TCP/IP, UDP/IP, RS232, RS485 communications support
   •   Secure encrypted server communications
   •   Rapid setup and deployment
   •   TPC hardware appliance; reduces setup/deployment time
   •   May be run as an application or a supervised Windows service
   •   Virtual COM port support
   •   Built-in abbreviation translator to ensure that all messages fit the mobile device screens
   •   Integrated simulator for testing & troubleshooting
   •   Extensive log reports simplify system troubleshooting

Supported Systems/Products

Nortel Companion
Polycom Spectralink Lin150/Link3000
Polycom Spectralink NetLink
Polycom Kirk
Ascom Analog
Ascom VoIP
Cisco 7900 series telephones
NEC OpenWorX
Panasonic KX-TDx
Generic TAPI/SAPI
Vocera

System Requirements

CPU:          Intel Core2 Duo or Equivalent, >180MHz
OS:           Windows XP, 7, Server 2003, Vista Ultimate
Memory:       2GB minimum (4GB recommended)
LAN/WAN:      10/100 (Gigabit recommended)
Hard Disk:    60Gb
Interface:    RS232 db9/Ethernet (telephony system dependent)


                                                                                                                             1939 144 Street
                                                                                                                                      th


                                                                                                                          Surrey, BC V4A 7M7
                                                                                                                        T. 604.812.SOFT (7638)
                                                                                                                            E. sales@qbsoft.ca
                                                                                                                            W. www.qbsoft.ca
Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions

                       All trademarks, and trade names shown here are the property of their relative owners.

E zcall all_spec_sheets

  • 1.
    Data Sheet No.DCS_Display_Control_Server_Spec_Sheet EZcall™ Enterprise DCS – Display Control Server Description The Display Control Server is the core component of an EZcall™ system. The Display Control Server receives and processes all alarms, events and schedule activity on an EZcall™ system. A DCS may be operated as a stand-alone application directly connected to a single input system and a single output system, or complemented with various input, display and output client applications. The DCS may be expanded to accept numerous output client applications by adding an MDS (Message Dispatch Server) which allows several different output connections to reside on a single system as well as adds group, naming alias, Email and message centre networking capabilities. All display, RTLS, and alarm input clients network with the DCS over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised client connections of each type, and a single MDS connection over a network allowing over 10,000 alarm systems more than 10,000 messaging/output systems and over 10,000 display clients to be networked into a single- node EZcall™ installation. Multiple DCS servers may be networked into a central DCS server for multi-site applications. Watchdog signals are used between the DCS and all client applications to ensure reliable communications. The Display Control server is a hardware agnostic platform that can interface and integrate various types and brands of alarm systems into a single system to share alarms, reporting and dispatching. The DCS also provides added functionality to basic alarm systems, by adding user features such as dementia monitoring, door control and other similar features to simple alarm or i/o systems. Features • TCP/IP, UDP/IP, RS232, RS485 communications support • Secure encrypted server communications • Rapid setup and deployment for small or large systems • HL7 (Health Level 7) integration support • Multi-site support, or multi-node server support • Fail-Over/Standby high availability options • May be run as an application or a supervised Windows service • Virtual COM port support • Support for standard and proprietary protocols including XML, SOAP, SNMP, HTML • Integrated simulator for testing & troubleshooting • Direct output or networked output support • Wireless coverage test tool built-in supports coverage testing using any system • 3-click device swap provides user-friendly device replacement for repairing hardware • Direct input, networked input, or combined/mixed input • Remote client control with built-in remote-access engine • Integrated error logging and reporting • Integrated database maintenance utility, with support for SQL, MSDE • Configurable login schemes; per user, per access level, or per function • Large button touch-screen support • Skin’ able desktop allows the operator interface to be customized • Multiple language support, c/w English, Dutch, French, Chinese (simplified) 1939 144 Street th • Integrated history reporting utility Surrey, BC V4A 7M7 • Provides primary output, secondary and backup T. 604.812.SOFT (7638) • Support for static, dynamic, or scheduled assignments E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 2.
    Configurable assignment options; by area, by room, by ward, global • Easy-to-use schedules; day, evening and night shifts may be individually configured • Smart SAM (Sensor Activity Monitor) ensures device sensors are always operational • PC Watchdog card support & integrated software watchdog • Configurable icons • Global priority standardization, up to 9999 system priorities • Packaged with; Paging Encoder Emulator, Virtual Null Modem Application, EZtext server, Time Sync Client, EZstart application launcher and Ascom OAP emulator utilities • Extensive log reports simplify system troubleshooting Supported Applications EDC – Event Display Client TDC – Target Display Client TPH – Touch-Panel Host AIC – Alarm Input Client NWC – Network Watchdog Client BBC – Button Bar Client PDC – Popup Display Client MDS – Message Dispatch Server EGW – EZcall™ GuardRFID Wrapper VKC – Virtual Keypad Client TTC – Text Talker Client EEW - EZcall™ Ekahau Wrapper WAC – Web Access Client iServer™ – Inovonics Wireless Server EWC – EZcall™ Wireless Client SAS – Spider Alert Server FCC – Facility Control Client TMC – Text Messaging Client VAC – Virtual Alarm Client EZtext™/LoginOut™ Server Supported Direct Output Protocols Visiplex paging output Globestar ConnexAll TMDP (Text Message Dispatch Protocol) COMP2 paging output TAP (Telocator Alphanumeric Protocol) 1.8 paging direct serial output Ascom enhanced TAP output TAP 1.8 dial-up paging output Supported Direct Input Protocols Hill-Rom LightCom nurse call system network Maxivox Maxicomm I nurse call system network Maxivox Maxicomm II nurse call system network GE/Dukane StaffCall Pro nurse call system network Raw Data input Added Applications/Functions Staff location/presence Dementia monitoring w/Artificial Intelligence auto-configuration Staff rounds monitoring Guard tour monitoring Patient/Resident check-in Service requirements Door monitoring and alarm w/access control support CCTV popup and control support RTLS equipment location monitoring and alarm support System Requirements CPU: Intel Xeon Quad Core or Equivalent, >200MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 160Gb Interface: RS232 db9/Ethernet (alarm and paging system dependent) 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 3.
    Data Sheet No.MDS_Message_Dispatch_Server_Spec_Sheet EZcall™ Enterprise MDS – Message Dispatch Server Description The Message Dispatch Server is an expansion module to an EZcall™ DCS (Display Control Server) that allows multiple output clients to be used and provides additional features. In addition to adding the ability for multiple output client connections, the MDS has a built-in Email and LED message board interface. By adding an MDS to an existing DCS, additional EZcall™ features are enabled, including output device group creation and output device aliasing. The Message Dispatch Server networks directly with an EZcall™ DCS over a standard Ethernet LAN or WAN network using the TCP/IP protocol. The Message Dispatch Server supports up to 10,000 of any type of output client connection, allowing the system to be very expandable. Every DCS may only be linked to one MDS and typically reside on the same server computer. Watchdog signals are used between the DCS and the MDS applications to ensure reliable communications. Features • SMTP, POP3, TCP/IP, UDP/IP, RS232, RS485 communications support • Secure encrypted server communications • Rapid setup and deployment • Standard or secure Email server support, with MIME, HTML, and UUencoding support • May be run as an application or a supervised Windows service • Virtual COM port support • Supports direct connection to LED message centres • Output device group creation and alias naming adds versatility to a DCS server • Instant Email SMS message output capability supported by mobile devices • Prioritized Email output capability • Integrated simulator for testing & troubleshooting • Extensive log reports simplify system troubleshooting Supported Systems/Products Application Connections LED Message Centers Email Output TPC – Telephone Paging Client (up to 9999) Edwards Message Centre SMTP SPC – Serial Paging Client (up to 9999) Alpha PrintPak POP3 CAC – Command Argument Client (up to 9999) Alpha EZkey II MIME OCC – Output Control Client (up to 9999) Alpha EZ95 UUencoding DCS – Display Control Server (1 connection) Pro-Lite ver. 5.25 Pro-Lite ver.6 System Requirements CPU: Intel Xeon Quad Core or Equivalent, >200MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 120Gb Interface: RS232 db9/Ethernet (output system dependent) 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 4.
    Data sheet No.WAC_Web_Access_Client_Spec_Sheet EZcall™ Enterprise WAC – Web Access Client Description The Web Access Client is a powerful EZcall™ server application that allows EZcall™ DCS functions to be accessed using any standard web browser. The Web Access Client prevents the need of installing and supporting numerous client program installations on user computers. By allowing browser access to most EZcall™ functions, a large facility deployment may be completed in a fraction of the time needed by using dedicated client programs. The browser interface also allows an EZcall™ deployment to be operating system independent. No matter what O.S. or web browser is being used in the facility (Linux, Unix, MAC, Windows), all will function in the same manner using their standard web browsers as the user interface. The Web Access Client is also supported by all popular standard and mobile browsers including; Firefox, Windows Internet Explorer, Apple Safari, Opera, Google Chrome. Features • Standard HTTP 1.0 and 2.0 support ensures reverse compatibility • Secure password protection login • Secure encrypted server communications • Built-in FGA Web Server does not rely or use IIS • Reliable FGA Web Server not susceptible to HTTP virus attacks, spoofing or malware • Rapid setup and deployment; no HTML language required • May be run as an application or a supervised Windows service • Alarm text and graphical map display • Manual text messaging to any EZcall™ output device • Alarm history display • Call Routing Assignments • On-Screen Virtual Call Buttons • Staff Presence location display • Reconfigurable skins allows graphics to be customized to the site/customer • Mobile browser support (iPhone, BlackBerry, Android, Windows Mobile) • Extensive log reports simplify system troubleshooting System Requirements Clients: Web browsers that support HTTP 1.0 CPU: Intel Xeon Quad Core or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: >120GB @ 7200RPM (> 10,000RPM recommended) 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. © Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 5.
    Data Sheet No.IWS_iServer_Inovonics_Wireless_Server_Spec_Sheet EZcall™ Enterprise IWS – iServer™ Inovonics Wireless Server Description The EZcall™ iServer™ is a fully functional integrated RTLS system that can network with an EZcall™ system. The iServer™ uses the Inovonics EchoStream hardware to function as a wireless duress, locating and nurse call solution. The iServer™ communicates directly to the Inovonics EchoStream hardware to allow all EchoStream alarms to be received and processed by EZcall™, as well as allowing the iServer™ to function as a stand-alone alarm system. Every IWS can network (optional) to an EZcall™ DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised EGW client connections over a network allowing that many systems to be networked into an enterprise EZcall™ installation. Watchdog signals are used between the DCS and all EGW applications to ensure reliable communications. Features • TCP/IP, UDP/IP, RS232, RS485 communications support • Secure encrypted server communications • Fully functional stand-alone wired/wireless duress/alarm system • Rapid setup and deployment • Real-time location and alarm information monitoring using proprietary RTLE™ algorithms • Integrated web-server for alarm and history display, as well as transmitter management • May be run as an application or a supervised Windows service • User configurable priorities and messages • Supports direct connection to numerous pocket paging systems • Supports WWC wireless wizard client connections for system maintenance • Integrated transmitter simulator for testing & troubleshooting • Extensive log reports simplify system troubleshooting Supported Systems/Products Inovonics EchoStream serial receiver, repeaters and transmitters EZcall™ DCS server (optional) WWC wireless wizard client Standard HTTP 1.0 capable web browsers System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 160Gb Interface: Inovonics proprietary protocol 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions EchoStream and Inovonics are registered trademarks of Inovonics Inc..
  • 6.
    Data Sheet No.EEW_EZcall_Ekahau_Wrapper_Spec_Sheet EZcall™ Enterprise EEW – EZcall™ Ekahau Wrapper Description The EZcall™ Ekahau Wrapper is a bi-directional interface between an EZcall™ system and an Ekahau RTLS system. The EEW integrates directly with an Ekahau RTLS server using the proprietary Ekahau XML-based protocol to allow all Ekahau alarms to be received and processed by EZcall™, as well as allowing an EZcall™ system to dispatch alarm messages to Ekahau WiFi badge tags. Every EEW networks to an EZcall™ DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised EEW client connections over a network allowing that many systems to be networked into an enterprise EZcall™ installation. Watchdog signals are used between the DCS and all EEW applications to ensure reliable communications. Features • TCP/IP, UDP/IP, RS232, RS485 communications support • Secure encrypted server communications • Secure encrypted RTLS server communications • Rapid setup and deployment • Real-time location and alarm information monitoring • Message dispatching to badge tags • May be run as an application or a supervised Windows service • User configurable priorities and messages • Integrated badge tag simulator for testing & troubleshooting • Extensive log reports simplify system troubleshooting Supported Systems/Products Ekahau RTLS server EZcall™ DCS server System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb Interface: TCP/IP XML-based protocol 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions Ekahau is a trademark of Ekahau Corporation Inc.
  • 7.
    Data Sheet No.EGW_EZcall_GuardRFID_Wrapper_Spec_Sheet EZcall™ Enterprise EGW – EZcall™ GuardRFID Wrapper Description The EZcall™ GuardRFID Wrapper is a bi-directional interface between an EZcall™ system and a GuardRFID RTLS system. The EGW integrates directly with an GuardRFID Argus server using the proprietary GuardRFID XML-based protocol to allow all GuardRFID SafeGuard, TotGuard and AllGuard alarms to be received and processed by EZcall™, as well as allowing an EZcall™ system to dispatch alarm messages to GuardRFID staff tags. Every EGW networks to an EZcall™ DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised EGW client connections over a network allowing that many systems to be networked into an enterprise EZcall™ installation. Watchdog signals are used between the DCS and all EGW applications to ensure reliable communications. Features • TCP/IP, UDP/IP, RS232, RS485 communications support • Secure encrypted server communications • Secure encrypted Argus server communications • Rapid setup and deployment • Real-time location and alarm information monitoring • Message dispatching to staff tags • May be run as an application or a supervised Windows service • User configurable priorities and messages • Integrated badge tag simulator for testing & troubleshooting • Extensive log reports simplify system troubleshooting Supported Systems/Products GuardRFID Argus server EZcall™ DCS server System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb Interface: TCP/IP XML-based protocol 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions TotGuard, Argus, SafeGuard, AllGuard and GuardRFID are trademarks of GuardRFID Inc.
  • 8.
    Data Sheet No.TPH_Touch_Panel_Host_Spec_Sheet EZcall™ Enterprise TPH – Touch-Panel Host Description The Touch-Panel Host is an EZcall™ server application to monitor alarm information from networked or serially-attached EZtouch™ panels. Various protocols are supported by the TPH client application that may be received by a direct serial, or supervised TCP/IP connection. Every TPH client networks to an EZcall™ DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised TPH client connections over a network allowing that many EZtouch™ panels and systems to be networked into an enterprise EZcall™ installation. Watchdog signals are used between the DCS and all TPH applications to ensure reliable communications. The TPH client operates as a server that hosts any number of supervised EZtouch™ panels. All EZtouch™ events are logged by the TPH and instantly forwarded to the EZcall™ DCS server for immediate alarm dispatching and archiving. A single TPH can host any combination or 2.8 inch and 4.3 inch EZtouch™ panels. A single TPH may be sued to host both serially attached or Ethernet networked EZtouch™ panels providing flexibility of using home-run or daisy-chained cabling on a single system. Features • TCP/IP, UDP/IP, RS485 communications support • Secure encrypted server communications • Rapid setup and deployment • May be run as an application or a supervised Windows service • Supervised touch panel connections • On-screen virtual touch-panel emulates the attached devices • Integrated simulator for testing & troubleshooting • Simple integration to an EZcall™ DCS server • Supports any combination or PoE Ethernet and RS485-looped EZtouch ™ panels • Customizable priorities and alerts Supported Systems/Products EZ-TP28E - 2.8” Color LCD PoE Ethernet EZtouch™ panels EZ-TP28S - 2.8” Color LCD RS485 serial EZtouch™ panels EZ-TP43S – 4.3” Color LCD RS485 serial EZtouch™ panels EZcall™ DCS (Display Control Server) System Requirements CPU: Intel Xeon Quad Core or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: >120Gb @ 7200RPM (>10,000RPM recommended) Interface: RS232 db9/Ethernet (alarm system dependent) 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 9.
    Data Sheet No.EZtouch_Panels_Spec_Sheet EZcall™ Enterprise EZtouch™ – Color Touch- Screen Panels Description The EZtouch™ panels are a user-friendly wall-mounted touch-screen panel that provide configurable alarm buttons and alarm display capabilities. EZtouch™ panels are available as PoE powered Ethernet devices and RS485 serial devices to allow multiple cabling configurations to be used. Each EZtouch™ panel supports from zero to 40 call buttons and may also be configured with an alarm display and/or door control & monitoring. Every EZtouch™ panel networks to an EZcall™ TPH (Touch Panel Host) over a standard Ethernet LAN/WAN network using the TCP/IP protocol or through an RS485 serial link. A single EZcall™ TPH will support up to 100,000 supervised EZtouch™ panel connections on a single system. Watchdog signals are used between the TPH and all EZtouch™ panels to ensure reliable supervised communications. EZtouch™ panels are available in two sizes; 2.8” display and 4.3” display. EZtouch™ panels are water-resistant with an IP65 rating and may be cleaned using standard cleaners. All EZtouch™ panels are designed to mount in industry- standard North American electrical boxes and also have weatherproof surface-mount backboxes available for outdoor mounting. These cost effective touch panels provide an attractive and cost effective alarm initiation or display device that may be used virtually anywhere. EZtouch™ panels may be used as alarm initiation devices, to display alarms at strategic locations or as workflow control devices. With EZtouch panels, you are free to select which buttons you need at all locations and can add/remove buttons as required. Features • Intuitive user-friendly call buttons • Timeout digital clock display helps reduce light emission during evenings. • Supervised connection alerts EZcall™ whenever a panel is disconnected or offline • PoE powered Ethernet and RS485 models available • Ethernet and RS485 models may be intermixed on a single TPH • Fully configurable and customizable buttons with icons • Alarm display (optional) • Door monitoring and control display (optional) • Integrated clean-screen option allows the screen to be cleaned • Quick and easy to setup • ESD Protection to 4kV • Wide operating temperature range from -20°C ~ 70°C • IP65 Waterproof front panel • Built-in alarm sounder (speaker on the EZ-TP43 models) • Very low power consumption (<2.5W) • 5-Year warranty System Requirements EZcall™ TPH Touch Panel Host 12VDC power supply (RS485 models) IEEE 802.3af class 1 PoE network switch (Ethernet models) Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 10.
    Physical Characteristics EZ-TP28 panelshave a 2.8” TFT LCD color touch-screen display. EZ-TP28E is a PoE powered Ethernet model and the EZ- TP28S is an RS485 serially networked (up to 31 per loop) model. EZ-TP28S dimensions are similar to EZ-TP28E. EZ-TP43S panels hand a 4/3” TFT LCD color touch-screen display and are networked with an RS485 loop (up to 31). Specifications 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions
  • 11.
    Data Sheet No.AIC_Alarm_Input_Client_Spec_Sheet EZcall™ Enterprise AIC - Alarm Input Client Description The Alarm Input Client is the input gateway for an EZcall™ system to retrieve alarm information from virtually any alarm system or hardware. Various protocols are supported by the AIC client application that may be received by a direct serial, TCP/IP, or UDP/IP connection. Every AIC client networks to an EZcall™ DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised AIC client connections over a network allowing that many systems to be networked into a single-node EZcall™ installation. Watchdog signals are used between the DCS and all AIC applications to ensure reliable communications. Features • TCP/IP, UDP/IP, RS232, RS485 communications support • Supports XLM, SOAP, TAP, and Proprietary protocols • Secure encrypted server communications • Rapid setup and deployment • AIC hardware appliance; reduces setup/deployment time • May be run as an application or a supervised Windows service • Virtual COM port support • Integrated simulator for testing & troubleshooting • Built-in web-server provides instant alarm display & activity monitoring • Extensive log reports simplify system troubleshooting Supported Systems/Products Fire Alarm Systems Nurse Call Systems Intercom Systems Edwards EST-3 serial interface Dukane Procare 6000 VM input Algo VoiceComm 3400 OAI input Edwards Quick serial interface Dukane Procare 2000 network input Dukane Starcare OAI input Simplex 4100U serial input Dukane Procare 6000 ARMS input Edwards AccuSound Network input Simplex 5000 serial input Dukane Procare 6000 OAI input Maxivox MC1 network interface Notifier AM2020 serial Dukane Procare 6000 TAP input Sentex Infinity Mircom serial Dukane StaffCall Pro Network input Honeywell XLS-1000 serial GE Caregard modem input Other Alarm Systems GE Telligence Telergy TAP input Andover Continuum ascii input GE Telligence SQL database interface Genetec Synergis/Omnicast Hill-Rom ComLite network input GE Facility Commander Paging System Emulation Maxivox Maxicomm I network interface GE Summit Pro PET input Ascom Wireless paging input Maxivox Maxicomm II network interface Kantech Enterprise/Global Generic TAP server emulation Rauland Responder 3000 net-controller Keyscan Visiplex pocket paging input Rauland Responder 4000 PIP OAI RBH Axiom COMP1 / COMP2 paging input Rauland Responder IV TAP input Senstar Stellar StarNet Globestar Formatted TAP input Tunstall CMS4000 OAI serial interface X-Mark Halo TAP input Home Free AMS ElmoPage input Zettler Sentinel 500 TAP input X-Mark Hugs/MyCall/FintIt Nordicom AL800 server West-Com Endeavour/Novus/Odyssey+ X-Mark RoamAlert TAP input Salcom paging server Tektone NC300 / NC300 II Visonic Eiris OAI input Scope paging server Ascom TeleCARE / TelePROTECT Visonic Eiris 3.0 UDP capture Simplex EZcare TAP input ADAM-6000 I/O boards Austco APR protocol Ontrak ADR2000 I/O boards System Requirements CPU: Intel Core2 Duo or Equivalent, >200MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) 1939 144 Street th Hard Disk: 120Gb Surrey, BC V4A 7M7 Interface: RS232 db9/Ethernet (alarm system dependent) T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 12.
    Data Sheet No.VKC_Virtual_Keypad_Client_Spec_Sheet EZcall™ Enterprise VKC – Virtual Keypad Client Description The Virtual Keypad Client is the input gateway for an EZcall™ system to retrieve alarm information from various intrusion alarm systems. Various protocols are supported by the VKC client application that may be received by a direct serial, TCP/IP, or UDP/IP connection. Every VKC client networks to an EZcall™ DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised VKC client connections over a network allowing that many intrusion alarm systems to be networked into a single-node EZcall™ installation. Watchdog signals are used between the DCS and all VKC applications to ensure reliable communications. The VKC client also includes a built-in web-server that allows operators to connect to the VKC and it’s associated intrusion alarm system through any standard web browser. All intrusion alarm keypad functions including arming, disarming, and bypassing zones are supported through the intuitive on-screen virtual keypad that emulates the actual keypads functions. Features • TCP/IP, UDP/IP, RS232, RS485 communications support • Secure encrypted server communications • Rapid setup and deployment • May be run as an application or a supervised Windows service • Virtual COM port support • On-screen virtual keypad emulates the attached system • Integrated simulator for testing & troubleshooting • Built-in web-server provides instant alarm display & system control • Extensive log reports simplify system troubleshooting Supported Systems/Products DSC Maxsys DSC Power864 GE NetworX GE Concord GE Advent Honeywell/Ademco Vista Paradox Esprit Paradox Spectra System Requirements CPU: Intel Xeon Quad Core or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: >120Gb @ 7200RPM (>10,000RPM recommended) Interface: RS232 db9/Ethernet (alarm system dependent) 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 13.
    Data Sheet No.BBC_Button_Bar_Client_Spec_Sheet EZcall™ Enterprise BBC – Button Bar Client Description The Button Bar Client is a unique input client used to generate alarms on an EZcall™ system from a PC desktop. The Button Bar Client is fully customizable to provide any quantity and type of on-screen button with different functions. The BBC provides a non-intrusive bar on a PC desktop that can be hidden away until needed. Ideal uses include nurse station porter and cleaner requests, and non-conventional workflow requests. Buttons may be added or deleted from the bar and configured individually on each desktop. Every BBC client networks to an EZcall™ DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised BBC client connections over a network allowing that many systems to be networked into a single-node EZcall™ installation. Watchdog signals are used between the DCS and all BBC applications to ensure reliable communications. Features • Attractive display does not take-up the entire screen • Configurable wards or areas – only display the locations that are needed • May be run as an application or a supervised Windows service • Event list display • Lockable to prevent shutting-down or relocating the window • Extensive log reports simplify system troubleshooting System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate, Linux Ubuntu 9.0 Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 14.
    Data Sheet No.CAC_Command_Argument_Client_Spec_Sheet EZcall™ Enterprise CAC – Command Argument Client Description The Command Argument Client is an output gateway for an EZcall™ system to output standard DOS-like commands to control various specialized systems. The Command Argument Client may be fully customized to generate virtually any command-line argument output needed. Every CAC client networks to an EZcall™ MDS (Message Dispatch Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ MDS will support up to 10,000 supervised CAC client connections over a network allowing that many systems to be networked into a single-node EZcall™ installation. Watchdog signals are used between the DCS and all CAC applications to ensure reliable communications. Features • Fully configurable & customizable command-line arguments • Secure encrypted server communications • Rapid setup and deployment • May be run as an application or a supervised Windows service • Virtual COM port support • Integrated testing & troubleshooting utility • Extensive log reports simplify system troubleshooting System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions DOS is a registered trademark of Microsoft Corp.
  • 15.
      EZcall Enterprise EDC – Event Display Client Description The Event Display Client is an output client used to display alarm or status messages on a computer output display. The Event Display Client is fully configurable to display events from specific areas and/or specific call types and priorities. Some uses include centralized Code Blue annunciators, local annunciators, maintenance or housekeeper alarm displays. Every EDC client networks to an EZcall DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall DCS will support up to 10,000 supervised EDC client connections over a network allowing that many systems to be networked into a single-node EZcall installation. Watchdog signals are used between the DCS and all EDC applications to ensure reliable communications. Features  Skin’able border images allow for a customized appearance of the display  Configurable wards or areas – only display the locations that are needed  Selectable priorities – only display the events types that are required  Configurable time – allows events to only generate popups at certain times-of-day  Hidden mouse pointer support  May be run as an application or a supervised Windows service  Configurable fields and text size, color & font  Date/Time display  Configurable screen size and location with locking capability to ensure that the display is always shown at the same location every time it is started  Multiple EDC support – run several EDC windows on the same computer to display various event types or areas on a single display  Windows and Linux versions available  Support for Microsoft Agent popup characters  Extensive log reports simplify system troubleshooting System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate, Linux Ubuntu 9.0 Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb 1939 144th Street Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca   Specifications subject to change without notice.  Copyright 2010 – QBsoft Solutions 
  • 16.
      EZcall Enterprise PDC – Popup Display Client Description The Popup Display Client is an output client used to display alarm or status messages on a computer output display. The Event Display Client is fully configurable to display events from specific areas and/or specific call types and priorities. Some uses include centralized Code Blue annunciators, local annunciators, maintenance or housekeeper alarm displays. Every EDC client networks to an EZcall DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall DCS will support up to 10,000 supervised EDC client connections over a network allowing that many systems to be networked into a single-node EZcall installation. Watchdog signals are used between the DCS and all EDC applications to ensure reliable communications. Features  Select from over 10 different window types  Configurable wards or areas – only display the locations that are needed  Selectable priorities – only display the events types that are required  Configurable time – allows events to only generate popups at certain times-of-day  May be run as an application or a supervised Windows service  Configurable fields and text size, color & font  Text-to-speech and sound file support allows sounds to be used in conjunction with a visual popup window  Lockable to prevent operators from shutting-down the alarm display  Extensive log reports simplify system troubleshooting System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate, Linux Ubuntu 9.0 Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb 1939 144th Street Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca   Specifications subject to change without notice.  Copyright 2010 – QBsoft Solutions 
  • 17.
      EZcall Enterprise TTC – Text Talker Client Description The Text Talker Client is a Text-to-Speech output client that allows alarm messages to be verbally announced using a PC speaker output. The Text Talker Client is compatible with most industry-standard text-to-speech engines and voices and supports multi-language translation. A TTC client may be configured to output specific wards or areas or all areas to provide multiple output alarm messaging using standard spoken messages rather than pre-recorded alerts. Every TTC client networks to an EZcall MDS (Message Dispatch Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall MDS will support up to 10,000 supervised TTC client connections over a network allowing that many systems to be networked into a single-node EZcall installation. Watchdog signals are used between the DCS and all TTC applications to ensure reliable communications. Features  Fully configurable & customizable using several brands of text-to-speech voice  Configurable time – allows events to only output at certain times-of-day  Secure encrypted server communications  Rapid setup and deployment  May be run as an application or a supervised Windows service  Supports text-to-speech, pre-recorded .WAV files or a combination of both  Support for Microsoft Agent popup characters  Built-in abbreviation and phonetic translator to ensure that all messages are understood  Integrated testing & troubleshooting utility  Extensive log reports simplify system troubleshooting System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb 1939 144th Street Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca   Specifications subject to change without notice.  Copyright 2010 – QBsoft Solutions 
  • 18.
    Data Sheet No.TDC_Target_Display_Client_Spec_Sheet EZcall™ Enterprise TDC – Target Display Client Description The Target Display Client is a unique output client used to display real-time staff response times or call activity. The Target Display Client is fully configurable to display events from specific areas and allows you to set a specific target response time. Only events outside the target time will increment the counter and be displayed. Ideal uses include manager heads- up display for at-a-glance status reporting and worker incentive displays. Every TDC client networks to an EZcall™ DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ DCS will support up to 10,000 supervised TDC client connections over a network allowing that many systems to be networked into a single-node EZcall™ installation. Watchdog signals are used between the DCS and all TDC applications to ensure reliable communications. Features • Attractive display does not take-up the entire screen • Configurable wards or areas – only display the locations that are needed • May be run as an application or a supervised Windows service • Event list display • Lockable to prevent shutting-down or relocating the window • Extensive log reports simplify system troubleshooting System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate, Linux Ubuntu 9.0 Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 19.
      EZcall Enterprise NWC – Network Watchdog Client Description The Network Watchdog Client is an input client that allows an EZcall system to supervise network software components and hardware. The Network Watchdog Client monitors other network devices by sending requests for their response. The NWC client will alert the DCS server of any network components that is unresponsive to generate a system alarm or perform other actions. Various protocols are supported by the NWC client application including; PING, SNMP, and MAC ID request. Every NWC client networks to an EZcall DCS (Display Control Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall DCS will support up to 10,000 supervised NWC client connections over a network allowing that many intrusion alarm systems to be networked into a single-node EZcall installation. Watchdog signals are used between the DCS and all NWC applications to ensure reliable communications. Features  TCP/IP, UDP/IP, SNMP, PING communications support  Rapid setup and deployment  May be run as an application or a supervised Windows service  Receive alerts of unresponsive critical network components  Integrated testing & troubleshooting utilities  Extensive log reports simplify system troubleshooting System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb 1939 144th Street Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca   Specifications subject to change without notice.  Copyright 2010 – QBsoft Solutions 
  • 20.
    Data Sheet No.SPC_Serial_Paging_Client_Spec_Sheet EZcall™ Enterprise SPC – Serial Paging Client Description The Serial Paging Client is the output gateway for an EZcall™ system to forward alarm text messages to various SMS and paging systems or serial printers. Various protocols are supported by the SPC client application that may connect by a direct serial, TCP/IP, or UDP/IP connection. Every SPC client networks to an EZcall™ MDS (Message Dispatch Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ MDS will support up to 10,000 supervised SPC client connections over a network allowing that many systems to be networked into a single-node EZcall™ installation. Watchdog signals are used between the DCS and all SPC applications to ensure reliable communications. Features • TCP/IP, UDP/IP, RS232, RS485 communications support • Secure encrypted server communications • Rapid setup and deployment • SPC hardware appliance; reduces setup/deployment time • May be run as an application or a supervised Windows service • Virtual COM port support • Built-in abbreviation translator to ensure that all messages fit the mobile device screens • Integrated simulator for testing & troubleshooting • Extensive log reports simplify system troubleshooting Supported Protocols COMP1 / COMP1 Visonic SL-PTX Poltys DCC output (Eiris emulation) TAP/PET 1.8 (serial & dial-up) Edwards EST-3 printer emulation Pelco P & D ascii output Visiplex basic EZcall serial printer detailed Salcom paging protocol Visiplex VS-40 EZcall serial printer simple Scope paging protocol Ascom Enhanced TAP Waveware protocol SecureTech WAVE 2-way radio output J-Tech Extended Zetron TAP (capcode support) Austco APR Globestar formatted TAP Nordicom AL800 GE Telergy 7.1 TAP (GUID support) System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb Interface: RS232 db9/Ethernet (paging system dependent) 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.
  • 21.
    Data Sheet No.TPC_Telephone_Paging_Client_Spec_Sheet EZcall™ Enterprise TPC – Telephone Paging Client Description The Telephone Paging Client is the output gateway for an EZcall™ system to forward alarm text messages to various wired and wireless telephony systems. Various protocols are supported by the TPC client application that may connect by a direct serial, TCP/IP, or UDP/IP connection. Every TPC client networks to an EZcall™ MDS (Message Dispatch Server) over a standard Ethernet LAN or WAN network using the TCP/IP protocol. A single EZcall™ MDS will support up to 10,000 supervised TPC client connections over a network allowing that many systems to be networked into a single-node EZcall™ installation. Watchdog signals are used between the DCS and all TPC applications to ensure reliable communications. Features • TCP/IP, UDP/IP, RS232, RS485 communications support • Secure encrypted server communications • Rapid setup and deployment • TPC hardware appliance; reduces setup/deployment time • May be run as an application or a supervised Windows service • Virtual COM port support • Built-in abbreviation translator to ensure that all messages fit the mobile device screens • Integrated simulator for testing & troubleshooting • Extensive log reports simplify system troubleshooting Supported Systems/Products Nortel Companion Polycom Spectralink Lin150/Link3000 Polycom Spectralink NetLink Polycom Kirk Ascom Analog Ascom VoIP Cisco 7900 series telephones NEC OpenWorX Panasonic KX-TDx Generic TAPI/SAPI Vocera System Requirements CPU: Intel Core2 Duo or Equivalent, >180MHz OS: Windows XP, 7, Server 2003, Vista Ultimate Memory: 2GB minimum (4GB recommended) LAN/WAN: 10/100 (Gigabit recommended) Hard Disk: 60Gb Interface: RS232 db9/Ethernet (telephony system dependent) 1939 144 Street th Surrey, BC V4A 7M7 T. 604.812.SOFT (7638) E. sales@qbsoft.ca W. www.qbsoft.ca Specifications subject to change without notice. Copyright 2010 – QBsoft Solutions All trademarks, and trade names shown here are the property of their relative owners.