SlideShare a Scribd company logo
1 of 20
Shane Mathew
Fossil Hydro Operations
Engineering Co-op Program
12/03/2019
About Me
■ University of South Florida
– Junior
– Mechanical Engineering
– May 2021
■ First Rotation with Duke Energy
– Bartow CC
2
Co-op Session Information
■ Bartow Combined Cycle Plant
– St. Petersburg, FL
■ Manager: Clide Forte
■ Mentor: Ron Major
 4-on-1
 Able to run simple or combined cycle
-Rare plant with two stacks per CT
 Auxiliaries such as PAG, Evap Coolers,
and Duct Burners add over 110MW and
are available year round
Project List Overview
■ Heat Recovery Steam Generator (HRSG)
Inspection & Training with Vogt Power
■ Permanent Tank Farm Sump Pump Installation
■ Steam Valve Replacement- Thermodynamic
Analysis
■ Discharge Water Canal Permanent power
■ Closed Cooling Water (CCW) Loss Mitigation
4
CCW Fundamentals
■ Plant equipment are exposed to high heat that,
if left uncooled, keep giving off heat, hence the
importance of an external cooling agent such
as CCW
■ The heat absorbed by CCW from the
equipment cycles through the CCW heat
exchangers where the heat is given off to the
cool water from Tampa Bay via the circulating
water system
■ The CCW system has a head tank that ensures
adequate suction head to the pumps and
accounts for thermal changes in system volume
■ Demineralized water is the makeup of CCW
Problem
■ The CCW head tank level loss
rate has substantially increased
since September 2017
■ The average time period between head
tank refills
– November 2016: 9 days
– November 2017: 20 hours
– November 2018: 11 hours
– November 2019: 9.5 hours
■ The average gallons per minute water lost over this time period has
increased to 1.4 gallons per minute (gpm), or about 2,000 gallons per
day.
■ The source of the loss is unknown and not visually apparent
Project Objective
■ Locate the source of CCW losses and mitigate
– This will reduce the costs of refilling the head tank and return the
closed cooling system to normal operation with normal losses
■ 0.02 gpm is the target gpm loss rate- according to historical data this is
considered a normal loss rate
Solution A: System Isolation
■ Equipment in the power block receiving CCW were strategically tested by closing the
supply and return CCW valves separately for 24 hours
■ After 24 hours, the valves are opened back up and the next section is isolated while
head tank level data is analyzed
■ If the head tank level ceases to
decline at the current loss rate,
then the individual system
closed off may be the sole or
contributing factor to CCW loss
and will be repaired after further
evaluation
System Isolation Scope
■ The units tested include:
– vacuum priming skid
– condenser vacuum skid
– chemical labs
■ These units were of special
interest due to the fact that
there is piping path for CCW
to flow without falling to the
ground
System Isolation Results
■ The resulting loss rate
after each isolated test
remained the constant
1.4 gpm loss
■ Thus, losses above
ground were ruled out
and it was concluded
the loss is likely below
ground
Solution B: Acoustic Testing
■ The CCW flow path was analyzed on Navisworks and through Fusion design
drawings to scope the test path of underground piping
■ The Ultrasound Detection Equipment (UE) device was calibrated to 40 KHZ at
a sensitivity value of 70 to detect the underground leak
■ Acoustic testing was performed along the CCW routes around 4Alpha once
every foot distance
Acoustic Testing Results
■ A damp ground indication led to further investigation into the CCW
lines between 4Alpha and 4Bravo HRSGs. A slight uptick in sound
was detected near the site of the damp ground
■ After analyzing the path of CCW relative to the damp ground and
validating through PI that the loss rate has increased, the decision
was made to excavate at the site of a CCW joint between 4Alpha
and 4Bravo
■ The source of CCW losses was founded to be at the site of a
fractured pipe and repaired using a leak repair clamp
Leak Source
Repair Clamp
Project Challenges
■ System Isolation for underground CCW lines were not
possible due to an uninterrupted return line to the head
tank that could not be closed off
■ A different approach to underground testing had to be
researched
First option:
■ Flush the CCW system out, pressurize the pipes
with Helium using available vents, and monitor
above ground for helium hotspots using a helium
detector device
■ This would be labor intensive and at the time did not
fit the outage schedule
Second option:
■ Acoustic testing which was feasible and outage-
schedule friendly
Project Results/ Turnover
■ The loss rate for CCW is
currently at 0.01 gpm,
surpassing the goal of 0.02 gpm
■ This zero-loss rate has been
maintained since the day of
repair on 11/21/2019
■ Hence, the head tank level has
maintained 60’’ of CCW.
Frequent head tank level refills
are no longer required.
Project Budget and Cost Savings
■ Both system isolation and acoustic tests
required $0.00 in additional expenses
other than the labor costs to conduct
these tests
■ The expense of frequent refilling of the
head tank about 2.5x per day will be
averted for the foreseeable future
Project Auxiliary Benefits
■ Relieves environment of exposure to
Demineralized water
■ Due to the loss, corrosion inhibitor injections had
to be halted
– Corrosion inhibitors prevent damage of the piping
system from corrosion
Skills and Knowledge Acquired
■ Fusion
■ PI Processing
■ Heat Transfer Fundamentals
■ Multi-dimensional Problem Solving (There is always another
way)
Looking Ahead
■ Complete last 3 semesters at USF
■ Return for a second rotation
■ Pass FE exam Spring 2021
■ Graduate from USF May 2021
Questions?
20

More Related Content

What's hot

Hot water-plumbing-system
Hot water-plumbing-systemHot water-plumbing-system
Hot water-plumbing-systemnhmurad
 
Steam Systems Management by John Herbert
Steam Systems Management by John HerbertSteam Systems Management by John Herbert
Steam Systems Management by John HerbertJohn A Herbert
 
Solar Sipper Presentation
Solar Sipper PresentationSolar Sipper Presentation
Solar Sipper PresentationSignarama Dtc
 
The Energy Network: Energy Upgrade California Home Upgrade
The Energy Network: Energy Upgrade California Home UpgradeThe Energy Network: Energy Upgrade California Home Upgrade
The Energy Network: Energy Upgrade California Home UpgradeThe Energy Network
 
Up on the Rooftop: Updating HVAC Rooftop UnitPerformance
Up on the Rooftop: Updating HVAC Rooftop UnitPerformanceUp on the Rooftop: Updating HVAC Rooftop UnitPerformance
Up on the Rooftop: Updating HVAC Rooftop UnitPerformanceE Source Companies, LLC
 
Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3Nicholas Naing
 
Rebuilding the World Trade Center
Rebuilding the World Trade CenterRebuilding the World Trade Center
Rebuilding the World Trade CenterChristopher Tso
 
Presentation - Sustainable Control Systems
Presentation - Sustainable Control SystemsPresentation - Sustainable Control Systems
Presentation - Sustainable Control SystemsJordan Robinson
 
Integriertes Wasserressourcenmanagement in Zentralasien , Modelregion Mongol...
Integriertes Wasserressourcenmanagement in Zentralasien , Modelregion  Mongol...Integriertes Wasserressourcenmanagement in Zentralasien , Modelregion  Mongol...
Integriertes Wasserressourcenmanagement in Zentralasien , Modelregion Mongol...tuvshin111
 
Cold water supply system & Components
Cold water supply system & ComponentsCold water supply system & Components
Cold water supply system & Componentsashikin
 

What's hot (17)

Final year project
Final year projectFinal year project
Final year project
 
Hot water-plumbing-system
Hot water-plumbing-systemHot water-plumbing-system
Hot water-plumbing-system
 
Cooling Tower Applications
Cooling Tower ApplicationsCooling Tower Applications
Cooling Tower Applications
 
Steam Systems Management by John Herbert
Steam Systems Management by John HerbertSteam Systems Management by John Herbert
Steam Systems Management by John Herbert
 
Solar Sipper Presentation
Solar Sipper PresentationSolar Sipper Presentation
Solar Sipper Presentation
 
Innovations in Multifamily Building Energy Savings
Innovations in Multifamily Building Energy SavingsInnovations in Multifamily Building Energy Savings
Innovations in Multifamily Building Energy Savings
 
The Energy Network: Energy Upgrade California Home Upgrade
The Energy Network: Energy Upgrade California Home UpgradeThe Energy Network: Energy Upgrade California Home Upgrade
The Energy Network: Energy Upgrade California Home Upgrade
 
tanajib
tanajibtanajib
tanajib
 
Water submetering
Water submeteringWater submetering
Water submetering
 
Up on the Rooftop: Updating HVAC Rooftop UnitPerformance
Up on the Rooftop: Updating HVAC Rooftop UnitPerformanceUp on the Rooftop: Updating HVAC Rooftop UnitPerformance
Up on the Rooftop: Updating HVAC Rooftop UnitPerformance
 
Air cooled condensers
Air cooled condensersAir cooled condensers
Air cooled condensers
 
Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3
 
Fire irrig ps
Fire irrig psFire irrig ps
Fire irrig ps
 
Rebuilding the World Trade Center
Rebuilding the World Trade CenterRebuilding the World Trade Center
Rebuilding the World Trade Center
 
Presentation - Sustainable Control Systems
Presentation - Sustainable Control SystemsPresentation - Sustainable Control Systems
Presentation - Sustainable Control Systems
 
Integriertes Wasserressourcenmanagement in Zentralasien , Modelregion Mongol...
Integriertes Wasserressourcenmanagement in Zentralasien , Modelregion  Mongol...Integriertes Wasserressourcenmanagement in Zentralasien , Modelregion  Mongol...
Integriertes Wasserressourcenmanagement in Zentralasien , Modelregion Mongol...
 
Cold water supply system & Components
Cold water supply system & ComponentsCold water supply system & Components
Cold water supply system & Components
 

Similar to Locating a CCW Loss in Underground Piping

Case study -4 Mort Street
Case study -4 Mort StreetCase study -4 Mort Street
Case study -4 Mort StreetShamitha Reddy
 
Power-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion PaperPower-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion PaperBowen
 
Report Out Presentation - Summer 2016
Report Out Presentation - Summer 2016Report Out Presentation - Summer 2016
Report Out Presentation - Summer 2016Jonathan Thomas
 
Energy Systems & Maintenance - Class Presentation
Energy Systems & Maintenance - Class PresentationEnergy Systems & Maintenance - Class Presentation
Energy Systems & Maintenance - Class PresentationTahaUzair2
 
Chernobyl Timeline
Chernobyl TimelineChernobyl Timeline
Chernobyl Timelinesmmiller166
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillDeanGarratt
 
Farook Presentation for Chief Engineer
Farook Presentation for Chief EngineerFarook Presentation for Chief Engineer
Farook Presentation for Chief EngineerFarook Pallikkalakath
 
Remediation of DNAPL in fractured bedrock
Remediation of DNAPL in fractured bedrockRemediation of DNAPL in fractured bedrock
Remediation of DNAPL in fractured bedrockIES / IAQM
 
Cem 350 gilbane corp mep retrofit systems overview 4 2011
Cem 350 gilbane corp mep retrofit systems overview  4 2011Cem 350 gilbane corp mep retrofit systems overview  4 2011
Cem 350 gilbane corp mep retrofit systems overview 4 2011miresmaeil
 
March3 2009-workshop-slides
March3 2009-workshop-slidesMarch3 2009-workshop-slides
March3 2009-workshop-slidesSWITCHOntario
 
Performance and Optimization of Residential Condensing Combi Systems
Performance and Optimization of Residential Condensing Combi SystemsPerformance and Optimization of Residential Condensing Combi Systems
Performance and Optimization of Residential Condensing Combi SystemsCenter for Energy and Environment
 
Louis Bosch AMSA VDBP
Louis Bosch AMSA VDBPLouis Bosch AMSA VDBP
Louis Bosch AMSA VDBP7391456
 
The Institute of Rural Research And Development (IRRAD)-Architecture case study
The Institute of Rural Research And Development (IRRAD)-Architecture case studyThe Institute of Rural Research And Development (IRRAD)-Architecture case study
The Institute of Rural Research And Development (IRRAD)-Architecture case studyShailja km
 

Similar to Locating a CCW Loss in Underground Piping (20)

Case study -4 Mort Street
Case study -4 Mort StreetCase study -4 Mort Street
Case study -4 Mort Street
 
Power System Restoration Drill
Power System Restoration DrillPower System Restoration Drill
Power System Restoration Drill
 
Power-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion PaperPower-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion Paper
 
Report Out Presentation - Summer 2016
Report Out Presentation - Summer 2016Report Out Presentation - Summer 2016
Report Out Presentation - Summer 2016
 
COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 
Energy Systems & Maintenance - Class Presentation
Energy Systems & Maintenance - Class PresentationEnergy Systems & Maintenance - Class Presentation
Energy Systems & Maintenance - Class Presentation
 
Chernobyl Timeline
Chernobyl TimelineChernobyl Timeline
Chernobyl Timeline
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
Oliver Grievson - WWEM - Experiences of a MCERTS Remedial Works Programme
Oliver Grievson - WWEM - Experiences of a MCERTS Remedial Works ProgrammeOliver Grievson - WWEM - Experiences of a MCERTS Remedial Works Programme
Oliver Grievson - WWEM - Experiences of a MCERTS Remedial Works Programme
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
Farook Presentation for Chief Engineer
Farook Presentation for Chief EngineerFarook Presentation for Chief Engineer
Farook Presentation for Chief Engineer
 
Remediation of DNAPL in fractured bedrock
Remediation of DNAPL in fractured bedrockRemediation of DNAPL in fractured bedrock
Remediation of DNAPL in fractured bedrock
 
Used fuel andrew sowder - epri
Used fuel   andrew sowder - epriUsed fuel   andrew sowder - epri
Used fuel andrew sowder - epri
 
Cem 350 gilbane corp mep retrofit systems overview 4 2011
Cem 350 gilbane corp mep retrofit systems overview  4 2011Cem 350 gilbane corp mep retrofit systems overview  4 2011
Cem 350 gilbane corp mep retrofit systems overview 4 2011
 
March3 2009-workshop-slides
March3 2009-workshop-slidesMarch3 2009-workshop-slides
March3 2009-workshop-slides
 
Performance and Optimization of Residential Condensing Combi Systems
Performance and Optimization of Residential Condensing Combi SystemsPerformance and Optimization of Residential Condensing Combi Systems
Performance and Optimization of Residential Condensing Combi Systems
 
Louis Bosch AMSA VDBP
Louis Bosch AMSA VDBPLouis Bosch AMSA VDBP
Louis Bosch AMSA VDBP
 
Fire irrig ps
Fire irrig psFire irrig ps
Fire irrig ps
 
Wp mp-update-camp pendleton.-april_25_2013
Wp   mp-update-camp pendleton.-april_25_2013Wp   mp-update-camp pendleton.-april_25_2013
Wp mp-update-camp pendleton.-april_25_2013
 
The Institute of Rural Research And Development (IRRAD)-Architecture case study
The Institute of Rural Research And Development (IRRAD)-Architecture case studyThe Institute of Rural Research And Development (IRRAD)-Architecture case study
The Institute of Rural Research And Development (IRRAD)-Architecture case study
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 

Locating a CCW Loss in Underground Piping

  • 1. Shane Mathew Fossil Hydro Operations Engineering Co-op Program 12/03/2019
  • 2. About Me ■ University of South Florida – Junior – Mechanical Engineering – May 2021 ■ First Rotation with Duke Energy – Bartow CC 2
  • 3. Co-op Session Information ■ Bartow Combined Cycle Plant – St. Petersburg, FL ■ Manager: Clide Forte ■ Mentor: Ron Major  4-on-1  Able to run simple or combined cycle -Rare plant with two stacks per CT  Auxiliaries such as PAG, Evap Coolers, and Duct Burners add over 110MW and are available year round
  • 4. Project List Overview ■ Heat Recovery Steam Generator (HRSG) Inspection & Training with Vogt Power ■ Permanent Tank Farm Sump Pump Installation ■ Steam Valve Replacement- Thermodynamic Analysis ■ Discharge Water Canal Permanent power ■ Closed Cooling Water (CCW) Loss Mitigation 4
  • 5. CCW Fundamentals ■ Plant equipment are exposed to high heat that, if left uncooled, keep giving off heat, hence the importance of an external cooling agent such as CCW ■ The heat absorbed by CCW from the equipment cycles through the CCW heat exchangers where the heat is given off to the cool water from Tampa Bay via the circulating water system ■ The CCW system has a head tank that ensures adequate suction head to the pumps and accounts for thermal changes in system volume ■ Demineralized water is the makeup of CCW
  • 6. Problem ■ The CCW head tank level loss rate has substantially increased since September 2017 ■ The average time period between head tank refills – November 2016: 9 days – November 2017: 20 hours – November 2018: 11 hours – November 2019: 9.5 hours ■ The average gallons per minute water lost over this time period has increased to 1.4 gallons per minute (gpm), or about 2,000 gallons per day. ■ The source of the loss is unknown and not visually apparent
  • 7. Project Objective ■ Locate the source of CCW losses and mitigate – This will reduce the costs of refilling the head tank and return the closed cooling system to normal operation with normal losses ■ 0.02 gpm is the target gpm loss rate- according to historical data this is considered a normal loss rate
  • 8. Solution A: System Isolation ■ Equipment in the power block receiving CCW were strategically tested by closing the supply and return CCW valves separately for 24 hours ■ After 24 hours, the valves are opened back up and the next section is isolated while head tank level data is analyzed ■ If the head tank level ceases to decline at the current loss rate, then the individual system closed off may be the sole or contributing factor to CCW loss and will be repaired after further evaluation
  • 9. System Isolation Scope ■ The units tested include: – vacuum priming skid – condenser vacuum skid – chemical labs ■ These units were of special interest due to the fact that there is piping path for CCW to flow without falling to the ground
  • 10. System Isolation Results ■ The resulting loss rate after each isolated test remained the constant 1.4 gpm loss ■ Thus, losses above ground were ruled out and it was concluded the loss is likely below ground
  • 11. Solution B: Acoustic Testing ■ The CCW flow path was analyzed on Navisworks and through Fusion design drawings to scope the test path of underground piping ■ The Ultrasound Detection Equipment (UE) device was calibrated to 40 KHZ at a sensitivity value of 70 to detect the underground leak ■ Acoustic testing was performed along the CCW routes around 4Alpha once every foot distance
  • 12. Acoustic Testing Results ■ A damp ground indication led to further investigation into the CCW lines between 4Alpha and 4Bravo HRSGs. A slight uptick in sound was detected near the site of the damp ground ■ After analyzing the path of CCW relative to the damp ground and validating through PI that the loss rate has increased, the decision was made to excavate at the site of a CCW joint between 4Alpha and 4Bravo ■ The source of CCW losses was founded to be at the site of a fractured pipe and repaired using a leak repair clamp
  • 14. Project Challenges ■ System Isolation for underground CCW lines were not possible due to an uninterrupted return line to the head tank that could not be closed off ■ A different approach to underground testing had to be researched First option: ■ Flush the CCW system out, pressurize the pipes with Helium using available vents, and monitor above ground for helium hotspots using a helium detector device ■ This would be labor intensive and at the time did not fit the outage schedule Second option: ■ Acoustic testing which was feasible and outage- schedule friendly
  • 15. Project Results/ Turnover ■ The loss rate for CCW is currently at 0.01 gpm, surpassing the goal of 0.02 gpm ■ This zero-loss rate has been maintained since the day of repair on 11/21/2019 ■ Hence, the head tank level has maintained 60’’ of CCW. Frequent head tank level refills are no longer required.
  • 16. Project Budget and Cost Savings ■ Both system isolation and acoustic tests required $0.00 in additional expenses other than the labor costs to conduct these tests ■ The expense of frequent refilling of the head tank about 2.5x per day will be averted for the foreseeable future
  • 17. Project Auxiliary Benefits ■ Relieves environment of exposure to Demineralized water ■ Due to the loss, corrosion inhibitor injections had to be halted – Corrosion inhibitors prevent damage of the piping system from corrosion
  • 18. Skills and Knowledge Acquired ■ Fusion ■ PI Processing ■ Heat Transfer Fundamentals ■ Multi-dimensional Problem Solving (There is always another way)
  • 19. Looking Ahead ■ Complete last 3 semesters at USF ■ Return for a second rotation ■ Pass FE exam Spring 2021 ■ Graduate from USF May 2021