Flow of Activities for

DG Installation
Plant room
•

Plant room with clear height of 5.5 Meter clearance and the width as per the
service consultant drawing.

•

The final location of HSD tank and the routing of fuel pipe as per the service
consultant drawings.

•

The Cable / Buss bar routing as per the service consultants.

•

A clear space for the Crain to enter the plant room to shift the DG sets from
trucks to the proper location.

•

The plant room to be fully equipped with the fire extinguishers as lot of
insulating material and fire hard material will be used during the installation of
complete system.

•

No water should stop in the Plant room and for that all the drainage system to
be ready before DG set arrive to the plant room
Civil works

DG Installation
DG Set plat form casting
HSD Tank location

Plant Room IPS
White wash to the entire plant room
DG set plat form

IPS @ plant room
HSD Tank Construction
•

As per the service consultants drawing the required height for the
HSD tank …… Meters need to be constructed

•

Plat form for HSD tank

•

The concrete trench for fuel pipe and LT Cables

•

Concrete road for the fuel truck to come for refueling

Concrete wall for HSD tank

Plat form for HSD
tank

HSD tank
Cooling
Tower

HSD tank

Fuel
Tank
for DG

DG Installation Overview

  • 1.
    Flow of Activitiesfor DG Installation
  • 2.
    Plant room • Plant roomwith clear height of 5.5 Meter clearance and the width as per the service consultant drawing. • The final location of HSD tank and the routing of fuel pipe as per the service consultant drawings. • The Cable / Buss bar routing as per the service consultants. • A clear space for the Crain to enter the plant room to shift the DG sets from trucks to the proper location. • The plant room to be fully equipped with the fire extinguishers as lot of insulating material and fire hard material will be used during the installation of complete system. • No water should stop in the Plant room and for that all the drainage system to be ready before DG set arrive to the plant room
  • 3.
    Civil works DG Installation DGSet plat form casting HSD Tank location Plant Room IPS White wash to the entire plant room
  • 5.
    DG set platform IPS @ plant room
  • 6.
    HSD Tank Construction • Asper the service consultants drawing the required height for the HSD tank …… Meters need to be constructed • Plat form for HSD tank • The concrete trench for fuel pipe and LT Cables • Concrete road for the fuel truck to come for refueling Concrete wall for HSD tank Plat form for HSD tank HSD tank
  • 8.