1. Applied for the Post of Contract Manager
CURRICULUM VITAE
Name : Iftikhar Hussain
Father’s Name : Mujtaba Hussan
Date of Birth / Age : 16 December 1972/42 years
CNIC No : 36302-9476292-1
Passport No : YQ6892921
Marital Status : Married
Phone : +92-300-0695399
Email : sqsiftikhar@gmail.com
Mailing Address : House No 20, Block-Y
Lane No 7, New Multan
Multan
Academic Qualification (1) Master of Business
Administration
(2) PGD (Software
Engineering)
(3) Diploma of Assistant
Engineer (Civil)
Computer Skill : Computer Skill in following
System Management
Programs:-
(1) Auto CAD
(2) Eagle Point (Ver 98)
(3) Microsoft Windows
(4) Microsoft Office
(5) Special working approach
in Microsoft Excel
2. Key Activities / Duties
(1) Responsible for managing all project costs from pitch to completion.
(2) Preparation / Verification of Project Estimation / Project Cost.
(3) Preparation / Verification of Interim Payment Certificates.
(4) Preparation / Verification of Escalation / Delay Payment Certificates.
(5) Preparation / Verification of Idling / Other Claims.
(6) Preparation of Prequalification / Enlistment / Up Gradation of Category
Documentation.
(7) Developing strong relationships with the clients and sub contractors.
(8) Undertaking costs analysis for construction projects.
(9) Writing reports and advising on construction costs.
(10) Attending meetings and liaising with stakeholders on commercial matters.
(11) Preparing tender and contract documents.
(12) Monitoring the cost of site resources.
(13) Providing advice and guidance to staff in the preparation and presentation of
works proposals, reviews and updates.
Experience 23 Years
Osmani and Company (Pvt) Ltd
(From January 2016 todate)
Serving in Consultants as a Senior Quantity Surveyor and working on
Construction of Metro Bus System from BZU to Chungi No 6 Package-1:-
Responsibilities
a. Preparation / Verification of Revised Project Cost / Variation Order.
b. Verification of Bills of Contractors.
c. Verification of Variation Orders,
d. Verification of Rate Analysis of Project Items, and
e. Other project relevant documents.
3. Zahir Khan and Brothers
(From June 2015 to January 2016)
Served in Contractor as a Contract Manager and worked on Construction of
Metro Bus Fly and Rotary from Chungi No 6 to Fish Market (4345 Million
Cost):-
Responsibilities
1. Provide necessary technical Guidance to staff in:-
a. Preparation of Interim Payment Certificates.
b. Verification of Bills of Sub Contractors.
c. Preparation of Variation Orders,
d. Preparation of Rate Analysis, and
e. Other project relevant documents.
2. Participating, as necessary, in developing the solicitation and writing the
draft documents. Contract administration must be considered during this
process.
3. Monitoring the contractor’s progress and performance.
4. Documenting significant events.
5. Maintaining appropriate records.
6. Meeting with the concerned authorities on a regular basis to review
progress, discuss problems and consider necessary changes.
Maaksons (Pvt) Ltd
(From November 2014 to June 2015)
Serving in Contractor as a Contract Manager and worked on following projects
of (1174 Million Cost):-
a. Construction of Main Sheikhupura Road, Sheikhupura.
b. Construction of Sharqpur Road, Sheikhupura.
Responsibilities
1. Provide necessary technical Guidance to staff in:-
a. Preparation of Interim Payment Certificates.
b. Verification of Bills of Sub Contractors.
4. c. Preparation of Variation Orders,
d. Preparation of Rate Analysis, and
e. Other project relevant documents.
2. Participating, as necessary, in developing the solicitation and writing the
draft documents. Contract administration must be considered during this
process.
3. Monitoring the contractor’s progress and performance.
4. Documenting significant events.
5. Maintaining appropriate records.
6. Meeting with the concerned authorities on a regular basis to review
progress, discuss problems and consider necessary changes.
Zeeruck ~ Loya (JV)
(From June 2014 to October 2014)
Serving in Supervisory Consultants as a Quantity Surveyor and worked on
following projects:-
a. Construction of Bosan Road, Multan
b. Construction of Fly Over at Chungi No 06, Multan
Responsibilities
a. Verification of Interim Payment Certificates.
b. Verification of Escalation Bills/Claim/Delay Payment Certificate.
c. Verification of Variation Orders, and Other project relevant documents.
Habib Rafiq Limited
(From August 2013 to May 2014)
Serving in Contractor as a Senior Quantity Surveyor and worked on following
projects:-
a. Construction of Gray Structure of Grand Hotel and Resort.
b. Construction of Gray Structure of Terraced 31 Residental Complex in
Bahria Town Phase-7
Responsibilities
a. Preparation of Interim Payment Certificates.
b. Verification of Bills of Sub Contractors.
5. c. Preparation of Variation Orders, Rate Analysis and Other project
relevant documents.
Frontier Works Organisation (FWO)
(From Apr 2012 to Aug 2013)
Serving in Contractor as a Cheif Quantity Surveyor and worked on following
projects:-
a. Construction of Shaheed Benazir Bhutto Bridge Linking N-5 with N-55 at
Chacharan (1.2 Km)
b. Construction of Additional Carriageway on Sehwan – Ratodero Section
(200 Km) Section – IV
Responsibilities
a. Vetting of IPCs/Escalations.
b. Project Execution Plan.
c. Verification of Bills of Sub Contractors.
d. Preparation of Variation Orders.
e. Other project related documents.
RMC Constructions
(From 19 Feb 2011 to Apr 2012)
Serving in Contractor as a Chief Quantity Surveyor and worked on
(1) Construction of Fly Over (Package-1) at Chowk Kumharan Wala, Multan
including approaches & roads.
(2) Construction of Tool Plaza Complex including offices & residential area.
Responsibilities
a. Vetting of IPCs/Escalations.
b. Verification of Bills of Sub Contractors.
c. Preparation of Variation Orders.
d. Preparation of Reply of letter of Sponsor and other departments.
e. Checking of Bills of Supplier and Sub-Contractor.
f. Other project related documents.
6. Limak JV ZKB
(From April 2010 to February 2011)
Served in Contractor as a Chief Quantity Surveyor and worked on 150 Km
Road Project from Qila Saifullah to Zhob (24 Bridges and 800 Culverts).
Responsibilities
a. Vetting of IPCs/Escalations.
b. Verification of Bills of Sub Contractors.
c. Preparation of Final Bill of last 50 Km project from Muslim Bagh to Qila
Saifullah.
Asif Ali and Associates
(From December 2008 to April 2010)
Served in Consultants as a Quantity Surveyor and working on Project
Dualization / Strengthing of Road (Six Lane) from Vehari Chowk to Chowk
Kumharan Wala Project.
Responsibilities
a. Vetting of IPCs/Escalations.
b. Preparation of Project Estimates.
c. Vetting of Escalation Claims.
d. Preparation Project Report for Sponsor (NHA).
e. Other project related documents.
Frontier Works Organisation (FWO)
(From January 1993 to December 2008)
Served as a Quantity Surveyor and worked on following projects:-
(1) Construction of Ratto Dero ~ Ghaus Pur Road
(2) Big City Development Package, Bahawalpur.
(3) Construction of Dual Carriageway (N-5) Rahim Yar Khan to Taranda
Muhammad Pannah.
(4) WAPDA Employees Cooperative Housing Scheme Phase-I (Ext) and
Phase-II.
(5) Dualization of Railway Track from Khanewal to Raiwind
7. Responsibilities
a. Preparation and Vetting of IPC.
b. Preparation of Execution Plan.
c. Preparation Escalation Claims.
d. Preparation Project Report.
e. Checking of Bills of Supplier and Sub-Contractor.
f. Other project related documents.