CURRICULUM VITAE
Ahmed. J
Project Engineer (Electrical)
Mobile: +971552670123
Email: ahmedj.0202@gmail.com
Personal Information:
Sex: Male Nationality: Indian
Age: 26 Date of Birth: 02/02/1990
Marital Status: Married Mother Tongue: Tamil
Languages Known: English, Tamil, and Hindi Driving License: Yes
Objective:
To work in a creative and challenging environment using the experience gained in Electrical
Maintenance, Interior Fit Out, and Electrical Testing in Substation to add value to my organization’s
requirements while continuously improving my skills to grow as a professional in the field of Power
Transmission and Distribution.
Educational Qualification:
 Completed B.E in Electrical and Electronics from Anna
University (B.S.Abdur Rahman Crescent Engineering College,
Chennai)
2007-2011 71.1%
 Higher Secondary from Tamil Nadu State Board (A.R.R
Higher Secondary School, Kumbakonam)
2006-2007 84.5%
 S.S.L.C from Matriculation (A.R.R. Higher Secondary
School, Kumbakonam)
2004-2005 84.5%
Professional Experience:
 Having 5+ years of Professional experience in Testing & Commissioning,
Engineering of EHV substations up to 220kV Voltage level Turnkey projects, LV design
including Load Schedule Preparation, Execution of LV Turnkey Projects – Interior Fit
Out(Estimation & Execution), Operation & Maintenance of LV system.
 Presently working as an Electrical Engineer in ETA – Power Projects Division, Abu
Dhabi, United Arab Emirates.
ETA – POWER PROJECTS DIVISION ( MARCH’15 – till date)
 As Testing & Commissioning Engineer
Job Responsibility:
 33kV GIS
 Bus Bar Contact Resistance Measurement
 Pressure Gauge and Density Meter Calibration
 Circuit Breaker/Disconnector/Earth Switch Timing Test and Motor Current Measurement
 Testing of Current and Voltage Transformers (Using Omicron CPC 100)
 Calibration of Ammeters and Voltmeters (Using Sverker 760)
 Local Control Cubicle Scheme Checks and Trouble Shooting.
 Coordinated and assisted GIS OEM for 33kV GIS HV Test.
 Primary & Secondary Injection for CT’s.
 Power Transformers:
 Testing of Current Transformer using Omicron CPC 100.
 Testing of Bushing Capacitance & Winding Capacitance (Tan Delta) using Omicron CP –
TD1.
 Analysis of SFRA (Sweep Frequency Response Analysis) report.
 Insulation Resistance & Hi Pot Test on Cooling Fan & Auxiliary circuits.
 Measurement of Zero Sequence & Short Circuit Impedance by Voltmeter Method.
 Cooling Fan Operational Checks.
 OLTC operation and Functional Checks.
 Winding Temperature & Oil Temperature Checks along with Calibration using Oil bath Kit.
 Functional Checks on Protective Devices (PRD, Buchholz Relay etc.)
 Measurement of Winding Resistance and Winding Ratio by Omicron CPC 100.
 MV/LV Power Cable Testing:
 Phase Identification Checks.
 DC Voltage with stand Test for Sheath.
 Capacitance Voltage Test
 Conductor DC Resistance Test.
 Insulation Resistance Test.
 AC High Voltage Test (VLF) for Conductor.
 NER/NGBS:
 Contact Resistance Test.
 Insulation Resistance Test.
 AC High Voltage Test.
 Coordinated and assisted OEM representative (MDS) for 110V& 48V DC System Testing
ETA – ENGINEERING MAINTENANCE COMPANY (EMCO) ( SEP’11 – MARCH’15)
 As Site Electrical Engineer
Job Responsibility:
 Based on the Study of complete scope of works, drawings, and specifications to prepare the Bill of
Quantity (BOQ) and Quotation with respect to client requirement.
 Reviewing tenders for MEP pricing.
 Negotiating best MEP prices for Turnkey projects with Clients/Sub Contractors
 Site supervision for MEP subcontractors on company’s projects.
 Monitoring & Supervising of MEP works on site.
 Managing and Scheduling day to day activities for a Team of 10 technicians including Foreman
and Transport Management for the same.
 Organizing Men and Materials for Turnkey Projects to meet the Scheduled Project timeline.
 Updating the As Built Drawings as per the performed Turnkey Projects against MEP services.
 Successfully completed the committed task by organizing, scheduling and managing the provided
manpower.
 Budget Follow-up
 Initiating for Invoicing
 Submission of Invoice to the clients
 Collection of cash/cheque
 Maintenance of MDB’s, SMDB’s & DB’s by carrying out PPM.
 Testing Kits Handled.
 Omicron CPC 100 for CT/VT testing & BUS BAR Contact Resistance in GIS, POWER
TRAFO’S & AUX TRFO’S.
 CBT 400 for MV CB timing test.
 DLRO micro ohm meter for Contact Resistance & Conductor Resistance Measurement.
 Omicron CMC 256 Secondary Injection Kit.
 ODEN Primary Injection Kit.
 DC High Voltage Kit for Cable Sheath (Eg. Baur KPG 25, Kilovolt KPG 25kV,
Hipotronics 800PL)
 Universal VLF & DC HV test system (HVA DIAGONOSTICS 60)
 Sverker
 Meggar
 Projects Handled :
 Project: N6976B.1A, Supply and Installation of 132/22kV Substation for South
Shamkha Development, Consultant: SNC Lavalin, Client: TRANSCO
 Project: 9201, Operation and Maintenance of Electrical Equipments in Dubai Airport
Freezone Authority.
 Project: 9583, Operational Maintenance & Interior fit out for Offices in Dubai Airport
Freezone for various prestigious clients like ABBOTT LABORATORIES, BOEING,
REDBULL, AIRBUS, TE CONNECTIVITY, ACTAVIS, CATERPILLAR etc.
 Sharaf DG, Giordano, Baristo Coffee – LV design and Work execution.
 Thermography survey – Emirates HQ, DAMAS outlets, Discovery Gardens.
 Additional Certification:
 Infrared Thermography (Level 1 Certified by IRT, Liverpool)
 Software Proficiency
 MS Office, MS Projects, AutoCAD.
 Hobbies
 Involving in Social Activities.
 Playing Badminton & Cricket.
I hereby affirm that the information given above is accurate and true to the best of my knowledge.
Ahmed Jaffar
Certificates:

CURRICULUM VITAE UPDATED 07.01.17

  • 1.
    CURRICULUM VITAE Ahmed. J ProjectEngineer (Electrical) Mobile: +971552670123 Email: ahmedj.0202@gmail.com Personal Information: Sex: Male Nationality: Indian Age: 26 Date of Birth: 02/02/1990 Marital Status: Married Mother Tongue: Tamil Languages Known: English, Tamil, and Hindi Driving License: Yes Objective: To work in a creative and challenging environment using the experience gained in Electrical Maintenance, Interior Fit Out, and Electrical Testing in Substation to add value to my organization’s requirements while continuously improving my skills to grow as a professional in the field of Power Transmission and Distribution. Educational Qualification:  Completed B.E in Electrical and Electronics from Anna University (B.S.Abdur Rahman Crescent Engineering College, Chennai) 2007-2011 71.1%  Higher Secondary from Tamil Nadu State Board (A.R.R Higher Secondary School, Kumbakonam) 2006-2007 84.5%  S.S.L.C from Matriculation (A.R.R. Higher Secondary School, Kumbakonam) 2004-2005 84.5% Professional Experience:  Having 5+ years of Professional experience in Testing & Commissioning, Engineering of EHV substations up to 220kV Voltage level Turnkey projects, LV design including Load Schedule Preparation, Execution of LV Turnkey Projects – Interior Fit Out(Estimation & Execution), Operation & Maintenance of LV system.  Presently working as an Electrical Engineer in ETA – Power Projects Division, Abu Dhabi, United Arab Emirates.
  • 2.
    ETA – POWERPROJECTS DIVISION ( MARCH’15 – till date)  As Testing & Commissioning Engineer Job Responsibility:  33kV GIS  Bus Bar Contact Resistance Measurement  Pressure Gauge and Density Meter Calibration  Circuit Breaker/Disconnector/Earth Switch Timing Test and Motor Current Measurement  Testing of Current and Voltage Transformers (Using Omicron CPC 100)  Calibration of Ammeters and Voltmeters (Using Sverker 760)  Local Control Cubicle Scheme Checks and Trouble Shooting.  Coordinated and assisted GIS OEM for 33kV GIS HV Test.  Primary & Secondary Injection for CT’s.  Power Transformers:  Testing of Current Transformer using Omicron CPC 100.  Testing of Bushing Capacitance & Winding Capacitance (Tan Delta) using Omicron CP – TD1.  Analysis of SFRA (Sweep Frequency Response Analysis) report.  Insulation Resistance & Hi Pot Test on Cooling Fan & Auxiliary circuits.  Measurement of Zero Sequence & Short Circuit Impedance by Voltmeter Method.  Cooling Fan Operational Checks.  OLTC operation and Functional Checks.  Winding Temperature & Oil Temperature Checks along with Calibration using Oil bath Kit.  Functional Checks on Protective Devices (PRD, Buchholz Relay etc.)  Measurement of Winding Resistance and Winding Ratio by Omicron CPC 100.  MV/LV Power Cable Testing:  Phase Identification Checks.  DC Voltage with stand Test for Sheath.  Capacitance Voltage Test  Conductor DC Resistance Test.  Insulation Resistance Test.  AC High Voltage Test (VLF) for Conductor.  NER/NGBS:  Contact Resistance Test.  Insulation Resistance Test.  AC High Voltage Test.  Coordinated and assisted OEM representative (MDS) for 110V& 48V DC System Testing
  • 3.
    ETA – ENGINEERINGMAINTENANCE COMPANY (EMCO) ( SEP’11 – MARCH’15)  As Site Electrical Engineer Job Responsibility:  Based on the Study of complete scope of works, drawings, and specifications to prepare the Bill of Quantity (BOQ) and Quotation with respect to client requirement.  Reviewing tenders for MEP pricing.  Negotiating best MEP prices for Turnkey projects with Clients/Sub Contractors  Site supervision for MEP subcontractors on company’s projects.  Monitoring & Supervising of MEP works on site.  Managing and Scheduling day to day activities for a Team of 10 technicians including Foreman and Transport Management for the same.  Organizing Men and Materials for Turnkey Projects to meet the Scheduled Project timeline.  Updating the As Built Drawings as per the performed Turnkey Projects against MEP services.  Successfully completed the committed task by organizing, scheduling and managing the provided manpower.  Budget Follow-up  Initiating for Invoicing  Submission of Invoice to the clients  Collection of cash/cheque  Maintenance of MDB’s, SMDB’s & DB’s by carrying out PPM.  Testing Kits Handled.  Omicron CPC 100 for CT/VT testing & BUS BAR Contact Resistance in GIS, POWER TRAFO’S & AUX TRFO’S.  CBT 400 for MV CB timing test.  DLRO micro ohm meter for Contact Resistance & Conductor Resistance Measurement.  Omicron CMC 256 Secondary Injection Kit.  ODEN Primary Injection Kit.  DC High Voltage Kit for Cable Sheath (Eg. Baur KPG 25, Kilovolt KPG 25kV, Hipotronics 800PL)  Universal VLF & DC HV test system (HVA DIAGONOSTICS 60)  Sverker  Meggar
  • 4.
     Projects Handled:  Project: N6976B.1A, Supply and Installation of 132/22kV Substation for South Shamkha Development, Consultant: SNC Lavalin, Client: TRANSCO  Project: 9201, Operation and Maintenance of Electrical Equipments in Dubai Airport Freezone Authority.  Project: 9583, Operational Maintenance & Interior fit out for Offices in Dubai Airport Freezone for various prestigious clients like ABBOTT LABORATORIES, BOEING, REDBULL, AIRBUS, TE CONNECTIVITY, ACTAVIS, CATERPILLAR etc.  Sharaf DG, Giordano, Baristo Coffee – LV design and Work execution.  Thermography survey – Emirates HQ, DAMAS outlets, Discovery Gardens.  Additional Certification:  Infrared Thermography (Level 1 Certified by IRT, Liverpool)  Software Proficiency  MS Office, MS Projects, AutoCAD.  Hobbies  Involving in Social Activities.  Playing Badminton & Cricket. I hereby affirm that the information given above is accurate and true to the best of my knowledge. Ahmed Jaffar
  • 5.