The correct answer is c. The quality of the information used to develop the tests is a factor that influences the test effort involved in most projects. Factors like requirements documentation, software size, life cycle model used, process maturity, time constraints, availability of skilled resources, and test results all impact the test effort.
This presentation gives you a walkthorugh on CTFL module 01.
Covers in detail about-
1. Fundamentals of testing
2. Terminologies in testing
3. Seven testing principles
4. Fundamental test process
Tool Support for Testing as Chapter 6 of ISTQB Foundation 2018. Topics covered are Tool Benefits, Test Tool Classification, Benefits of Test Automation, Risk of Test Automation, Selecting a tool for Organization, Pilot Project, Success factor for using a tool
This presentation gives you a walkthorugh on CTFL module 01.
Covers in detail about-
1. Fundamentals of testing
2. Terminologies in testing
3. Seven testing principles
4. Fundamental test process
Tool Support for Testing as Chapter 6 of ISTQB Foundation 2018. Topics covered are Tool Benefits, Test Tool Classification, Benefits of Test Automation, Risk of Test Automation, Selecting a tool for Organization, Pilot Project, Success factor for using a tool
INTRODUCTION TO ISTQB FOUNDATION LEVEL - CTFLRahul R Pandya
This Slideshare will give you the basics introduction of the ISTQB Foundation level testing certification.
ISTQB stands for the “International Software Testing Qualifications Board.”
ISTQB Certification is a universally acknowledged programming testing affirmation that is directed online by its Member Boards through a testing Exam Provider.
Chapter 3 of ISTQB Foundation 2018 syllabus with sample questions. Answers about what is static testing, what is review, types of review, informal review, walkthrough, technical review, inspection.
This is chapter 4 of ISTQB Specialist Performance Tester certification. This presentation helps aspirants understand and prepare the content of the certification.
Now to answer, “What is Testing?” we can go by the famous definition of Myers, which says, “Testing is the process of executing a program with the intent of finding errors”
Software testing is an investigation conducted to provide stakeholders with information about the quality of the product or service under test. I hope this ppt will help u to learn about software testing.
Test Management as Chapter 5 of ISTQB Foundation 2018. Topics covered are Test Organization, Test Planning and Estimation, Test Monitoring and Control, Test Execution Schedule, Test Strategy, Risk and Testing, Defect Management
Here are the preparation slides for chapter 1 from ISTQB Foundation Level Certification syllabus. Hope it is useful.
Here is link to my complete course ISTQB - Foundation Level Certification (CTFL) Training Udemy with 40% discount.
https://www.udemy.com/istqb-foundation-level-certification-ctfl-training/?couponCode=SAGARREF
Coupon code: SAGARREF
INTRODUCTION TO ISTQB FOUNDATION LEVEL - CTFLRahul R Pandya
This Slideshare will give you the basics introduction of the ISTQB Foundation level testing certification.
ISTQB stands for the “International Software Testing Qualifications Board.”
ISTQB Certification is a universally acknowledged programming testing affirmation that is directed online by its Member Boards through a testing Exam Provider.
Chapter 3 of ISTQB Foundation 2018 syllabus with sample questions. Answers about what is static testing, what is review, types of review, informal review, walkthrough, technical review, inspection.
This is chapter 4 of ISTQB Specialist Performance Tester certification. This presentation helps aspirants understand and prepare the content of the certification.
Now to answer, “What is Testing?” we can go by the famous definition of Myers, which says, “Testing is the process of executing a program with the intent of finding errors”
Software testing is an investigation conducted to provide stakeholders with information about the quality of the product or service under test. I hope this ppt will help u to learn about software testing.
Test Management as Chapter 5 of ISTQB Foundation 2018. Topics covered are Test Organization, Test Planning and Estimation, Test Monitoring and Control, Test Execution Schedule, Test Strategy, Risk and Testing, Defect Management
Here are the preparation slides for chapter 1 from ISTQB Foundation Level Certification syllabus. Hope it is useful.
Here is link to my complete course ISTQB - Foundation Level Certification (CTFL) Training Udemy with 40% discount.
https://www.udemy.com/istqb-foundation-level-certification-ctfl-training/?couponCode=SAGARREF
Coupon code: SAGARREF
Software Testing adds organizational value in quantitative and qualitative ways. Successful organizations recognize the importance of quality. Establishing a quality-oriented mindset is the responsibility of business leadership.
Fundamental test process (TESTING IMPLEMENTATION SYSTEM)Putri nadya Fazri
In this section, we will describe the fundamental test process and activities. These start with test planning and continue through to test closure. For each part of the test process, we'll discuss the main tasks of each test activity.
Putri Nadya Fazri.
Program Studi S1 Sistem Informasi.
Fakultas Sains dan Teknologi.
Universitas Islam Negeri Sultan Syarif Kasim Riau.
Types of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating systemTypes of operating system
COURSE IS NOW FULLY AVAILABLE AND LIVE HERE: https://goo.gl/gVukvc
This is the first section of six parts to cover what you need to learn about ISTQB foundations exam. Broken down into pieces and examples to pass. Check out more on my blog: https://www.rogeriodasilva.com/
In software engineering, the right architecture is essential for robust, scalable platforms. Wix has undergone a pivotal shift from event sourcing to a CRUD-based model for its microservices. This talk will chart the course of this pivotal journey.
Event sourcing, which records state changes as immutable events, provided robust auditing and "time travel" debugging for Wix Stores' microservices. Despite its benefits, the complexity it introduced in state management slowed development. Wix responded by adopting a simpler, unified CRUD model. This talk will explore the challenges of event sourcing and the advantages of Wix's new "CRUD on steroids" approach, which streamlines API integration and domain event management while preserving data integrity and system resilience.
Participants will gain valuable insights into Wix's strategies for ensuring atomicity in database updates and event production, as well as caching, materialization, and performance optimization techniques within a distributed system.
Join us to discover how Wix has mastered the art of balancing simplicity and extensibility, and learn how the re-adoption of the modest CRUD has turbocharged their development velocity, resilience, and scalability in a high-growth environment.
Code reviews are vital for ensuring good code quality. They serve as one of our last lines of defense against bugs and subpar code reaching production.
Yet, they often turn into annoying tasks riddled with frustration, hostility, unclear feedback and lack of standards. How can we improve this crucial process?
In this session we will cover:
- The Art of Effective Code Reviews
- Streamlining the Review Process
- Elevating Reviews with Automated Tools
By the end of this presentation, you'll have the knowledge on how to organize and improve your code review proces
Quarkus Hidden and Forbidden ExtensionsMax Andersen
Quarkus has a vast extension ecosystem and is known for its subsonic and subatomic feature set. Some of these features are not as well known, and some extensions are less talked about, but that does not make them less interesting - quite the opposite.
Come join this talk to see some tips and tricks for using Quarkus and some of the lesser known features, extensions and development techniques.
Climate Science Flows: Enabling Petabyte-Scale Climate Analysis with the Eart...Globus
The Earth System Grid Federation (ESGF) is a global network of data servers that archives and distributes the planet’s largest collection of Earth system model output for thousands of climate and environmental scientists worldwide. Many of these petabyte-scale data archives are located in proximity to large high-performance computing (HPC) or cloud computing resources, but the primary workflow for data users consists of transferring data, and applying computations on a different system. As a part of the ESGF 2.0 US project (funded by the United States Department of Energy Office of Science), we developed pre-defined data workflows, which can be run on-demand, capable of applying many data reduction and data analysis to the large ESGF data archives, transferring only the resultant analysis (ex. visualizations, smaller data files). In this talk, we will showcase a few of these workflows, highlighting how Globus Flows can be used for petabyte-scale climate analysis.
May Marketo Masterclass, London MUG May 22 2024.pdfAdele Miller
Can't make Adobe Summit in Vegas? No sweat because the EMEA Marketo Engage Champions are coming to London to share their Summit sessions, insights and more!
This is a MUG with a twist you don't want to miss.
Top Features to Include in Your Winzo Clone App for Business Growth (4).pptxrickgrimesss22
Discover the essential features to incorporate in your Winzo clone app to boost business growth, enhance user engagement, and drive revenue. Learn how to create a compelling gaming experience that stands out in the competitive market.
We describe the deployment and use of Globus Compute for remote computation. This content is aimed at researchers who wish to compute on remote resources using a unified programming interface, as well as system administrators who will deploy and operate Globus Compute services on their research computing infrastructure.
Software Engineering, Software Consulting, Tech Lead.
Spring Boot, Spring Cloud, Spring Core, Spring JDBC, Spring Security,
Spring Transaction, Spring MVC,
Log4j, REST/SOAP WEB-SERVICES.
Custom Healthcare Software for Managing Chronic Conditions and Remote Patient...Mind IT Systems
Healthcare providers often struggle with the complexities of chronic conditions and remote patient monitoring, as each patient requires personalized care and ongoing monitoring. Off-the-shelf solutions may not meet these diverse needs, leading to inefficiencies and gaps in care. It’s here, custom healthcare software offers a tailored solution, ensuring improved care and effectiveness.
In 2015, I used to write extensions for Joomla, WordPress, phpBB3, etc and I ...Juraj Vysvader
In 2015, I used to write extensions for Joomla, WordPress, phpBB3, etc and I didn't get rich from it but it did have 63K downloads (powered possible tens of thousands of websites).
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERRORTier1 app
Even though at surface level ‘java.lang.OutOfMemoryError’ appears as one single error; underlyingly there are 9 types of OutOfMemoryError. Each type of OutOfMemoryError has different causes, diagnosis approaches and solutions. This session equips you with the knowledge, tools, and techniques needed to troubleshoot and conquer OutOfMemoryError in all its forms, ensuring smoother, more efficient Java applications.
Understanding Globus Data Transfers with NetSageGlobus
NetSage is an open privacy-aware network measurement, analysis, and visualization service designed to help end-users visualize and reason about large data transfers. NetSage traditionally has used a combination of passive measurements, including SNMP and flow data, as well as active measurements, mainly perfSONAR, to provide longitudinal network performance data visualization. It has been deployed by dozens of networks world wide, and is supported domestically by the Engagement and Performance Operations Center (EPOC), NSF #2328479. We have recently expanded the NetSage data sources to include logs for Globus data transfers, following the same privacy-preserving approach as for Flow data. Using the logs for the Texas Advanced Computing Center (TACC) as an example, this talk will walk through several different example use cases that NetSage can answer, including: Who is using Globus to share data with my institution, and what kind of performance are they able to achieve? How many transfers has Globus supported for us? Which sites are we sharing the most data with, and how is that changing over time? How is my site using Globus to move data internally, and what kind of performance do we see for those transfers? What percentage of data transfers at my institution used Globus, and how did the overall data transfer performance compare to the Globus users?
Experience our free, in-depth three-part Tendenci Platform Corporate Membership Management workshop series! In Session 1 on May 14th, 2024, we began with an Introduction and Setup, mastering the configuration of your Corporate Membership Module settings to establish membership types, applications, and more. Then, on May 16th, 2024, in Session 2, we focused on binding individual members to a Corporate Membership and Corporate Reps, teaching you how to add individual members and assign Corporate Representatives to manage dues, renewals, and associated members. Finally, on May 28th, 2024, in Session 3, we covered questions and concerns, addressing any queries or issues you may have.
For more Tendenci AMS events, check out www.tendenci.com/events
Innovating Inference - Remote Triggering of Large Language Models on HPC Clus...Globus
Large Language Models (LLMs) are currently the center of attention in the tech world, particularly for their potential to advance research. In this presentation, we'll explore a straightforward and effective method for quickly initiating inference runs on supercomputers using the vLLM tool with Globus Compute, specifically on the Polaris system at ALCF. We'll begin by briefly discussing the popularity and applications of LLMs in various fields. Following this, we will introduce the vLLM tool, and explain how it integrates with Globus Compute to efficiently manage LLM operations on Polaris. Attendees will learn the practical aspects of setting up and remotely triggering LLMs from local machines, focusing on ease of use and efficiency. This talk is ideal for researchers and practitioners looking to leverage the power of LLMs in their work, offering a clear guide to harnessing supercomputing resources for quick and effective LLM inference.
Enhancing Research Orchestration Capabilities at ORNL.pdfGlobus
Cross-facility research orchestration comes with ever-changing constraints regarding the availability and suitability of various compute and data resources. In short, a flexible data and processing fabric is needed to enable the dynamic redirection of data and compute tasks throughout the lifecycle of an experiment. In this talk, we illustrate how we easily leveraged Globus services to instrument the ACE research testbed at the Oak Ridge Leadership Computing Facility with flexible data and task orchestration capabilities.
Into the Box Keynote Day 2: Unveiling amazing updates and announcements for modern CFML developers! Get ready for exciting releases and updates on Ortus tools and products. Stay tuned for cutting-edge innovations designed to boost your productivity.
Developing Distributed High-performance Computing Capabilities of an Open Sci...Globus
COVID-19 had an unprecedented impact on scientific collaboration. The pandemic and its broad response from the scientific community has forged new relationships among public health practitioners, mathematical modelers, and scientific computing specialists, while revealing critical gaps in exploiting advanced computing systems to support urgent decision making. Informed by our team’s work in applying high-performance computing in support of public health decision makers during the COVID-19 pandemic, we present how Globus technologies are enabling the development of an open science platform for robust epidemic analysis, with the goal of collaborative, secure, distributed, on-demand, and fast time-to-solution analyses to support public health.
3. After completing
this lesson, you
will be able to
understand:
1 Recognize the importance of independent
testing. (Kl)
2 List the benefits and drawbacks of
independent testing within an organization.
(K2)
3 Recognize the different team members to be
considered for the creation of a test team. (Kl)
4 Recall the tasks of typical test leaders and
testers. (Kl)
4. K Levels
5)Test Management: (K3)
Test organization (K2)
Test Plans, estimates and strategies (K3)
Test progress, monitoring and control (K2)
Configuration management (K2)
Risk and testing (K2)
Incident management (K3)
5. Roles and
responsibilities
of aTest Leader?
Initiation , Planning, Execution,
Monitoring and Controlling , Closing
phase
devise the test objectives, organizational
test policies, test strategies and test
plans.
Automation – Analysis
6. Roles and
responsibilities
of a Tester ?
Test case preparation
Requirement analysis
Testers execute and log the tests, evaluate
the results and document problems found.
They monitor the testing and the test
environment, often using tools for this task,
and often gather performance metrics.
Throughout the testing life cycle, they
review each other’s work, including test
specifications, defect reports and test
results.
7. WhatTest plan
does ?
Test plan is the project plan for the testing work to be
done. It is not a test design specification, a collection
of test cases or a set of test procedures
First, by writing a test plan it guides our thinking.
Second, the test planning process and the plan itself
serve as the means of communication with other
members of the project team, testers, peers, managers
and other stakeholders.
Third, the test plan helps us to manage change.
10. Fundamental
test process
(Revise)
What is in scope and what is out of scope for this testing effort?
What are the test objectives?
What are the important project and product risks?
What constraints affect testing (e.g., budget limitations, hard
deadlines, etc.)?
What is most critical for this product and project?
Which aspects of the product are more (or less) testable?
What should be the overall test execution schedule and how
should we decide the order in which to run specific tests?
11. Estimation
techniques
1. People with expertise on the tasks to
be done:
[WBS,Bottom-up, tool : MS Project]
2. Consulting the people who will do the
work
[team's wisdom to create theWBS]
12. Factors
affecting test
effort
Project Documentation
Increase in Software Application Size
Software Life Cycle
Maturity of Process
Time Constraints
Availability of Skilled Testers
Test Results
13. Test
approaches or
Test strategy
one of the most powerful factor in the success of the test effort
and the accuracy of the test plans and estimates.
Analytical [The risk-based strategy /requirement based strategy]
Model-based [You can build mathematical models for loading and
response for e commerce servers, and test based on that model]
Methodical [You might have a checklist that you have put
together over the years that suggests the major areas of testing to
run ]
Process – or standard-compliant [Process- or standard-compliant
strategies have in common reliance upon an externally developed
approach to testing]
Dynamic [Dynamic strategies, such as exploratory testing]
Regression-averse [Automated regression suite]
14. Test
monitoring
Provide the project team with visibility about the test results.
Measure the status of the testing, test coverage and test items
against the exit criteria to determine whether the test work is
done.
Gather data for use in estimating future test efforts.
15. Test control
Test control is about guiding and corrective actions to try to
achieve the best possible outcome for the project.
how test control affect testing ?
Example : A portion of the software under test will be delivered
late but market conditions dictate that we cannot change the
release date. At this point of time test control might involve re-
prioritizing the tests so that we start testing against what is
available now.
16. Configuration
management
Configuration management is about making sure that these items
[source code, test scripts, third-party software, hardware, data
and both development and test documentation.] are managed
carefully, thoroughly and attentively during the entire project and
product life cycle.
Ideally, when testers receive an organized, version-controlled test
release from a change-managed source code repository, it is along
with a test item trans-mittal report or release notes.
17. Risk in
software
testing?
In the future, a risk has some probability between 0%
and 100%; it is a possibility, not a certainty.
We can classify risks into following categories:
Product risk (factors relating to what is produced by
the work, i.e. the thing we are testing).
Project risk (factors relating to the way the work is
carried out, i.e. the test project)
18. What is
Product Risk
Product risk is the risk associated with the software or system, the
possibility that software or system may fail to satisfy end
user/customers expectations is known as product risk.
If the software skips some key function that the customers
specified, the users required or the stakeholders were promised.
If the software is unreliable and frequently fails to work.
If software fail in ways that cause financial or other damage to a
user or the company that user works for.
If the software has problems related to a particular quality
characteristic, which might not be functionality, but rather
security, reliability, usability, maintainability or performance.
19. What is Project
Risk in testing?
Risks associated with the testing activity which can endanger the
test project cycle is known as project risk.
Some of the risks associated with project are:
1. Delay in the test build to test team.
2. Unavailability of test environment.
3. Delay in fixing test environment due to lack of system admin.
4. Delay in fixing defects by development team.
5.Organizational problems which can be like shortage of staff.
Required skills etc.
6. Major changes in the SRS which invalidates the test cases and
requires changes in the test case.
In order to deal with project risks we need to apply concepts like
identifying, prioritizing and managing the project risks.
20. Actions to be
taken on Risk.
For any risk, project risk or product risk we have four typical
actions that we can take:
Mitigate:Take steps in advance to reduce the possibility and
impact of the risk.
Contingency: Have a plan in place to reduce the possibility of the
risk to become an outcome.
Transfer: Convince some other member of the team or project
stakeholder to reduce the probability or accept the impact of the
risk.
Ignore: Ignore the risk, which is usually a good option only when
there is little that can be done or when the possibility and impact
of that risk are low in the project.
21. Risk based
testing
Risk is the probability of occurrence of an undesirable outcome.
This outcome is also associated with an impact. Since there might
not be sufficient time to test all functionality, Risk based testing
involves testing the functionality which has the highest impact
and probability of failure.
Risk-based testing starts early in the project
Risk-based testing also involves measuring how well we are doing
at finding and removing defects in critical areas.
22. How to
perform risk
based testing?
Make a prioritized list of risks.
Perform testing that explores each risk.
As risks evaporate and new ones emerge, adjust your
test effort to stay focused on the current crop.
23. What is Risk
analysis?
One technique for risk analysis is a close reading of the
requirements specification, design specifications, user
documentation and other items.
Another technique is brainstorming with many of the project
stakeholders.
24. What is an
Incident in
software
testing?
While executing a test, you might observe that the actual results
vary from expected results.When the actual result is different
from the expected result then it is called as incidents, bugs,
defects, problems or issues.
An incident is basically any situation where the system exhibits
questionable behavior
[not necessarily a true defect]
It will be a good idea to log, report, track, and manage incidents
found during development and reviews because it gives useful
information about the early and cheaper defect detection and
removal activities.
26. Q &A
Lets try to answer few questions based
on chapter 05
27. Question 1 Why is independent testing important?
a. Independent testing is usually cheaper than testing your
own work.
b. Independent testing is more effective at finding defects.
c. Independent testers should determine the processes and
methodologies used.
d. Independent testers are dispassionate about whether the
project succeeds or fails.
28. Question 2 Which of the following is among the typical tasks
of a test leader?
a. Develop system requirements, design specifications and
usage models.
b. Handle all test automation duties.
c. Keep tests and test coverage hidden from programmers.
d. Gather and report test progress metrics.
29. Question 3 According to the ISTQB Glossary, what do we
mean when we call someone a test manager?
a. A test manager manages a collection of test leaders.
b. A test manager is the leader of a test team or teams.
c. A test manager gets paid more than a test leader.
d. A test manager reports to a test leader.
30. Question 4 What is the primary difference between the test plan, the test design
specification, and the test procedure specification?
a. The test plan describes one or more levels of testing, the test design specification
identifies the associated high-level test cases and a test procedure specification describes
the actions for executing a test.
b. The test plan is for managers, the test design specification is for programmers and the
test procedure specification is for testers who are automating tests.
c. The test plan is the least thorough, the test procedure specification is the most thorough
and the test design specification is midway between the two.
d. The test plan is finished in the first third of the project, the test design specification is
finished in the middle third of the project and the test procedure specification is finished in
the last third of the project
31. Question 4 Which of the following factors is an influence on the test effort
involved in most projects?
a. Geographical separation of tester and programmers.
b. The departure of the test manager during the project.
c. The quality of the information used to develop the tests.
d. Unexpected long-term illness by a member of the project team.
Editor's Notes
The Institute of Electrical and Electronics Engineers
Factors Affecting the Software Testing Efforts of a BusinessProject Documentation: Good and detailed documentation adds value to the software development project. But both time and efforts are required to create detailed documentation. Sometimes the meticulous documentation of specific test cases can delay the testing process. When the testing professionals are required to maintain detailed documentation during test execution, they have to invest additional time and effort. So they test data that are fragile or need to be maintained frequently will have an impact on the testing efforts.Increase in Software Application Size: To beat competition, enterprises keep adding new features and functionality to the software during different stages of development. These new features often increase the overall size of the project. Sometimes the increase in the project size also makes the business in increasing the size of the project team. The frequent increase in the size of the project and project team can affect the testing of large and complex software applications.Software Life Cycle: The development life cycles of the software can also have a direct impact on the testing efforts. Each time any new features or functionality is added to the product, the testers are required to conduct rigorous regression testing. Sometimes changes in the late stages of development require the business to incur additional regression testing cost.Maturity of Process: Like new processes, mature processes can also affect the overall software testing efforts. The testers have to manage changes in mature processes with additional care. Any changes in the mature process during the middle or end of the project also require the testers to repeat all tests, while keeping the test execution cost under control.Time Constraints: Each company to wants to beat competition by reducing the time to market. The shortening of time to market often affects the organization’s overall software testing strategies and test efforts. The time pressure also makes some testing professionals to take unwarranted risks. To eliminate the unwarranted risk factors, the test efforts need to be planned and organized at regular intervals.Availability of Skilled Testers: Along with tools and methods, people are also in integral part of the software testing process. Along with writing test cases, the testers will further execute the processes. So the testing efforts are impacted by the skills of individual testing professionals and the team. It is always important for the business to pick seasoned software testers, and align their skills according to the specific needs of the project.Test Results: The test results help managers in taking some key decisions about the software release. Sometimes the test results are also evaluated by various stakeholders to take the right decisions. So the testing strategy of an organization must aim to deliver relevant and accurate test results. However, the quality of the software will be affected if the bugs or flaws highlighted in the test results are not fixed at the earliest. Any defect in the software identified during the testing must be fixed in the same cycle. Otherwise, the defect will have a huge impact on the overall test efforts.