SlideShare a Scribd company logo
INDUSTRIAL CASE STUDY
Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571
www.envirotechltd.co.uk info@envirotechltd.co.uk
COVENTRY UNIVERSITY
Project: Charles Ward Energy Centre
Date of Project: June 2014 - September 2014
Project Value: £2.2million
INDUSTRIAL CASE STUDY
Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571
www.envirotechltd.co.uk info@envirotechltd.co.uk
Project Description:- Charles ward energy centre
Work Elements:- New 6.5mw energy centre
Period of Works:- June 2014 - September 2014
Total time span:- 12 weeks including 5 week
asbestos strip out
Project value:- £2.2m
Overview:-
6.5mw of Heating load
Thermal store 34,000 litre
BIM model
NEW CHP
Revitt Modelling
Saving of 489 tonnes of carbon
off site fabrication
Temporary boiler plant for hot water
5 new 1200kw boilers
New flue system
Siemens Bons control
350kw air cooled chiller
"spill & fill" pressurisation units
Ongoing water
Carbon Reduction Measures
INDUSTRIAL CASE STUDY
Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571
www.envirotechltd.co.uk info@envirotechltd.co.uk
INDUSTRIAL CASE STUDY
Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571
www.envirotechltd.co.uk info@envirotechltd.co.uk
What did the project involve?
The project comprised the replacement of 5 boilers, 1 new chiller and 1 CHP unit that previously fed a
district heating circuit, and adding a further district heating branch to a local student accommodation
facility. Existing boilers were approximately 40 years old, one boiler had failed its annual insurance
inspection and the remaining four were well beyond their expected lifespan. The existing CHP unit was
12 years old, oversized, and replacement parts were hard to source. Total plantroom heating load is
approximately 6.5MW.
In addition to this, a large thermal store was installed to maximise CHP run hours and minimise
dumping. The systems pumping strategy was drastically rationalised from individual pumped circuits on
every branch (24 pumps in total) to main packaged pump arrangements, inverter driven, pressure
controlled and automatic zone control valves. The plantroom 10 years overdue a refurbishment and had
always been avoided due to the expectation that this was a project that could not be undertakenduring
a single summer break. A lengthy asbestos strip was required before any refurbishment could begin and
this required allboilers being switched off reducing programme evenfurther.
Stand out achievement
Programme was the main constraint of the project. With a maximum period of ‘heat off’ of 12
weeks and a 5 week asbestos strip reducing this to an actual plant room access time of 7 weeks, the
decision was made that the project required almost complete
off site fabrication. The plantroom was BIM modelled and the offsite fabrication produced from the BIM
model when plant room access was unavailable. Once available, only small stool pieces were required on
site to account for level changes within the existing floorslab.
Without off site fabrication and the BIM model, this project could not have been completed within the
heat off timeframe. The University are committed to a programme of carbon reduction and as one of its
largest campus boiler rooms saw this project as key to their ongoing commitment to energy efficiency.
Previously the CHP installation was oversized and as such dumped a lot of its heat. This system was linked
to a nearby accommodation block to allow additional run hours to be utilised and also involved the
installation of a 34,000L thermal store to recover heat outside of this and re-use if the following day.
INDUSTRIAL CASE STUDY
Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571
www.envirotechltd.co.uk info@envirotechltd.co.uk
BIM MODEL
ACTUAL INSTALL
Used as our presentation for the 2015 HVAC Awards in March
Coventry University Charles Ward Boiler House
(BIM model and Actual Build)
INDUSTRIAL CASE STUDY
Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571
www.envirotechltd.co.uk info@envirotechltd.co.uk
Environmental concerns.
The existing CHP system dumped a significant proportion of its heat. Calculations determined that the
improvements in boiler efficiency and the addition of a thermal store should save 240 tonnes of carbon
and the addition of the student accommodation block would save a further 249 tonnes resulting in a
total saving of 489 tonnes Carbon.
Improvements in pumping strategy and moving over to zone control and inverter driven pressure
controlled pumps will result in further energy savings. These are difficult to calculate, however we have
installed a significant energy metering system which over the next 12 months will monitor and report on
energy consumption against predictedusages.
Capitalizing on the projectsuccess
Due to the complexity and timescales involved with project, we took the decision to enter this project for
the 2015 H&V award for the “Building Services Project for theyear”.
To date ewe have been shortlisted from hundreds of entries and have reached the finals which take
place in April 2015
In addition to this we are able, through our relationship with the university to disseminate information
regarding this project through the Association of University Engineers (AUE). The AUE have over 200
members from nationwide universities, over 50 of these universities have existing CHP units that are
nearing the end of their lives and they would benefit from the knowledge gained from thisproject.
FINALIST
INDUSTRIAL CASE STUDY
Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571
www.envirotechltd.co.uk info@envirotechltd.co.uk
What differentiates us from our competitors?
We believe what differentiates us from our competitors is our overall approach to the project from the
start. From initial interview (pre-contract award) we devised a very detailed plan and programme to
achieve the vital heat on date. Post contract start, we had a dedicated team not only on the installation
but on the project management side with a full time on site manager along with a site based
procurement team. This ensured that the tight time frame became easier to manage and achieve.
In addition, by collaborating in detail with the specialist sub-contractors, i.e. controls and electrical
engineers, we were able to ensure all necessary milestones and key dates were achieved. In addition,
the use of the BIM modelling and off site fabrication meant that we could confidently demonstrate to
the client that we could deliver what we said we would.

More Related Content

What's hot

GSC meeting PM - Final
GSC meeting  PM - FinalGSC meeting  PM - Final
GSC meeting PM - FinalDavid Nderimo
 
Deep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building StandardsDeep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building Standards
SustainableEnergyAut
 
NZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean ArmstrongNZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean Armstrong
SustainableEnergyAut
 
Health Business Services, HSE NZEB approach by Brendan Reddington
Health Business Services, HSE NZEB approach by Brendan ReddingtonHealth Business Services, HSE NZEB approach by Brendan Reddington
Health Business Services, HSE NZEB approach by Brendan Reddington
SustainableEnergyAut
 
DURBAN PORT COMMITTEE - 20 April
 DURBAN PORT COMMITTEE - 20 April DURBAN PORT COMMITTEE - 20 April
DURBAN PORT COMMITTEE - 20 April
Marketing Durban Chamber
 
Itm Hannover Presentation
Itm Hannover PresentationItm Hannover Presentation
Itm Hannover Presentationmetalysis
 
3. Brochure Trilogy Swindon
3. Brochure Trilogy Swindon3. Brochure Trilogy Swindon
3. Brochure Trilogy SwindonMatthew Warr
 
Greenergy Facility Presentation
Greenergy Facility PresentationGreenergy Facility Presentation
Greenergy Facility Presentation
MichaelVentre
 
NZEB Office Building including renewable energy ratio calculation orla coyle
NZEB Office Building including renewable energy ratio calculation  orla coyleNZEB Office Building including renewable energy ratio calculation  orla coyle
NZEB Office Building including renewable energy ratio calculation orla coyle
SustainableEnergyAut
 
Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...
Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...
Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...
Granit Architects
 
Solution of numerical problem on boiler performance (Part 1)
Solution of numerical problem on boiler performance (Part 1)Solution of numerical problem on boiler performance (Part 1)
Solution of numerical problem on boiler performance (Part 1)
AVDHESH TYAGI
 
BIOCNG PLANT.pdf
BIOCNG PLANT.pdfBIOCNG PLANT.pdf
BIOCNG PLANT.pdf
DILIP RAJA KOLLI
 
Novomykolayivskyi Dairy Plant
Novomykolayivskyi Dairy PlantNovomykolayivskyi Dairy Plant
Novomykolayivskyi Dairy Plant
EnergyEfficiencyplat
 
Presentación de Jørgen Abildgaard en la Jornada "Barcelona hacia la transició...
Presentación de Jørgen Abildgaard en la Jornada "Barcelona hacia la transició...Presentación de Jørgen Abildgaard en la Jornada "Barcelona hacia la transició...
Presentación de Jørgen Abildgaard en la Jornada "Barcelona hacia la transició...
Fundación Renovables
 
On demand boiler system fujifilm hunt chemicals
On demand boiler system   fujifilm hunt chemicalsOn demand boiler system   fujifilm hunt chemicals
On demand boiler system fujifilm hunt chemicalsTNenergy
 
Supply Chain Opportunities in the Bioenergy Sector Workshop - Hilary Kinney
Supply Chain Opportunities in the Bioenergy Sector Workshop  - Hilary KinneySupply Chain Opportunities in the Bioenergy Sector Workshop  - Hilary Kinney
Supply Chain Opportunities in the Bioenergy Sector Workshop - Hilary Kinney
Invest Northern Ireland
 
Beautiful beijing esco report summary 9 nov 2015
Beautiful beijing esco report summary 9 nov 2015Beautiful beijing esco report summary 9 nov 2015
Beautiful beijing esco report summary 9 nov 2015
Business Finland
 
Lanzatech: le pari technologique d'ArcelorMittal
Lanzatech: le pari technologique d'ArcelorMittalLanzatech: le pari technologique d'ArcelorMittal
Lanzatech: le pari technologique d'ArcelorMittal
Luxemburger Wort
 
Khorolska Mechanised Bakery
Khorolska Mechanised BakeryKhorolska Mechanised Bakery
Khorolska Mechanised Bakery
EnergyEfficiencyplat
 

What's hot (19)

GSC meeting PM - Final
GSC meeting  PM - FinalGSC meeting  PM - Final
GSC meeting PM - Final
 
Deep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building StandardsDeep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building Standards
 
NZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean ArmstrongNZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean Armstrong
 
Health Business Services, HSE NZEB approach by Brendan Reddington
Health Business Services, HSE NZEB approach by Brendan ReddingtonHealth Business Services, HSE NZEB approach by Brendan Reddington
Health Business Services, HSE NZEB approach by Brendan Reddington
 
DURBAN PORT COMMITTEE - 20 April
 DURBAN PORT COMMITTEE - 20 April DURBAN PORT COMMITTEE - 20 April
DURBAN PORT COMMITTEE - 20 April
 
Itm Hannover Presentation
Itm Hannover PresentationItm Hannover Presentation
Itm Hannover Presentation
 
3. Brochure Trilogy Swindon
3. Brochure Trilogy Swindon3. Brochure Trilogy Swindon
3. Brochure Trilogy Swindon
 
Greenergy Facility Presentation
Greenergy Facility PresentationGreenergy Facility Presentation
Greenergy Facility Presentation
 
NZEB Office Building including renewable energy ratio calculation orla coyle
NZEB Office Building including renewable energy ratio calculation  orla coyleNZEB Office Building including renewable energy ratio calculation  orla coyle
NZEB Office Building including renewable energy ratio calculation orla coyle
 
Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...
Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...
Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...
 
Solution of numerical problem on boiler performance (Part 1)
Solution of numerical problem on boiler performance (Part 1)Solution of numerical problem on boiler performance (Part 1)
Solution of numerical problem on boiler performance (Part 1)
 
BIOCNG PLANT.pdf
BIOCNG PLANT.pdfBIOCNG PLANT.pdf
BIOCNG PLANT.pdf
 
Novomykolayivskyi Dairy Plant
Novomykolayivskyi Dairy PlantNovomykolayivskyi Dairy Plant
Novomykolayivskyi Dairy Plant
 
Presentación de Jørgen Abildgaard en la Jornada "Barcelona hacia la transició...
Presentación de Jørgen Abildgaard en la Jornada "Barcelona hacia la transició...Presentación de Jørgen Abildgaard en la Jornada "Barcelona hacia la transició...
Presentación de Jørgen Abildgaard en la Jornada "Barcelona hacia la transició...
 
On demand boiler system fujifilm hunt chemicals
On demand boiler system   fujifilm hunt chemicalsOn demand boiler system   fujifilm hunt chemicals
On demand boiler system fujifilm hunt chemicals
 
Supply Chain Opportunities in the Bioenergy Sector Workshop - Hilary Kinney
Supply Chain Opportunities in the Bioenergy Sector Workshop  - Hilary KinneySupply Chain Opportunities in the Bioenergy Sector Workshop  - Hilary Kinney
Supply Chain Opportunities in the Bioenergy Sector Workshop - Hilary Kinney
 
Beautiful beijing esco report summary 9 nov 2015
Beautiful beijing esco report summary 9 nov 2015Beautiful beijing esco report summary 9 nov 2015
Beautiful beijing esco report summary 9 nov 2015
 
Lanzatech: le pari technologique d'ArcelorMittal
Lanzatech: le pari technologique d'ArcelorMittalLanzatech: le pari technologique d'ArcelorMittal
Lanzatech: le pari technologique d'ArcelorMittal
 
Khorolska Mechanised Bakery
Khorolska Mechanised BakeryKhorolska Mechanised Bakery
Khorolska Mechanised Bakery
 

Similar to Coventry university CASE STUDY

Schiedel Commercial Brochure
Schiedel Commercial BrochureSchiedel Commercial Brochure
Schiedel Commercial Brochure
Schiedel UK
 
China CSP Demonstration Projects
China CSP Demonstration ProjectsChina CSP Demonstration Projects
China CSP Demonstration Projects
Klaus Pottler
 
“Towards net zero: extracting energy from flooded coal mines for heating and ...
“Towards net zero: extracting energy from flooded coal mines for heating and ...“Towards net zero: extracting energy from flooded coal mines for heating and ...
“Towards net zero: extracting energy from flooded coal mines for heating and ...
Kyungeun Sung
 
Moore_S_25.10.13
Moore_S_25.10.13Moore_S_25.10.13
Moore_S_25.10.13Moore Sarah
 
Polymer Processing Cost Saving Workshop - 06 Ceramicx
Polymer Processing Cost Saving Workshop - 06 CeramicxPolymer Processing Cost Saving Workshop - 06 Ceramicx
Polymer Processing Cost Saving Workshop - 06 CeramicxInvest Northern Ireland
 
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
Global CCS Institute
 
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Global CCS Institute
 
CIBSEoct10 pp57-60 Hydrogen
CIBSEoct10 pp57-60 HydrogenCIBSEoct10 pp57-60 Hydrogen
CIBSEoct10 pp57-60 HydrogenKevin Stanley
 
Chalcroft construction for the warehouse and logistics industries
Chalcroft construction for the warehouse and logistics industriesChalcroft construction for the warehouse and logistics industries
Chalcroft construction for the warehouse and logistics industries
Chalcroft Ltd
 
Practical Implementation Of Renewable Hydrogen & Fuel Cell Installations in t...
Practical Implementation Of Renewable Hydrogen & Fuel Cell Installations in t...Practical Implementation Of Renewable Hydrogen & Fuel Cell Installations in t...
Practical Implementation Of Renewable Hydrogen & Fuel Cell Installations in t...
guest083950
 
Introduction to Cofely and Southampton
Introduction to Cofely and SouthamptonIntroduction to Cofely and Southampton
Introduction to Cofely and Southampton
New Engineering Foundation
 
Tony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdfTony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdfTony Greenfield
 
REMOURBAN Information package n2 - Energiesprong 2050 project
REMOURBAN Information package n2 - Energiesprong 2050 project REMOURBAN Information package n2 - Energiesprong 2050 project
REMOURBAN Information package n2 - Energiesprong 2050 project
REMOURBAN
 
Chalcroft Special Projects
Chalcroft Special ProjectsChalcroft Special Projects
Chalcroft Special Projects
Chalcroft Ltd
 
Show and Tell - Heat.pdf
Show and Tell - Heat.pdfShow and Tell - Heat.pdf
Show and Tell - Heat.pdf
SIFOfgem
 

Similar to Coventry university CASE STUDY (20)

Schiedel Commercial Brochure
Schiedel Commercial BrochureSchiedel Commercial Brochure
Schiedel Commercial Brochure
 
China CSP Demonstration Projects
China CSP Demonstration ProjectsChina CSP Demonstration Projects
China CSP Demonstration Projects
 
“Towards net zero: extracting energy from flooded coal mines for heating and ...
“Towards net zero: extracting energy from flooded coal mines for heating and ...“Towards net zero: extracting energy from flooded coal mines for heating and ...
“Towards net zero: extracting energy from flooded coal mines for heating and ...
 
Moore_S_25.10.13
Moore_S_25.10.13Moore_S_25.10.13
Moore_S_25.10.13
 
Khursaniyah Project Brochure
Khursaniyah Project BrochureKhursaniyah Project Brochure
Khursaniyah Project Brochure
 
Polymer Processing Cost Saving Workshop - 06 Ceramicx
Polymer Processing Cost Saving Workshop - 06 CeramicxPolymer Processing Cost Saving Workshop - 06 Ceramicx
Polymer Processing Cost Saving Workshop - 06 Ceramicx
 
Guys Hospital[1]
Guys Hospital[1]Guys Hospital[1]
Guys Hospital[1]
 
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
 
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
 
william-first-revision
william-first-revisionwilliam-first-revision
william-first-revision
 
CIBSEoct10 pp57-60 Hydrogen
CIBSEoct10 pp57-60 HydrogenCIBSEoct10 pp57-60 Hydrogen
CIBSEoct10 pp57-60 Hydrogen
 
Chalcroft construction for the warehouse and logistics industries
Chalcroft construction for the warehouse and logistics industriesChalcroft construction for the warehouse and logistics industries
Chalcroft construction for the warehouse and logistics industries
 
Practical Implementation Of Renewable Hydrogen & Fuel Cell Installations in t...
Practical Implementation Of Renewable Hydrogen & Fuel Cell Installations in t...Practical Implementation Of Renewable Hydrogen & Fuel Cell Installations in t...
Practical Implementation Of Renewable Hydrogen & Fuel Cell Installations in t...
 
Introduction to Cofely and Southampton
Introduction to Cofely and SouthamptonIntroduction to Cofely and Southampton
Introduction to Cofely and Southampton
 
TB Clinic Project Report
TB Clinic Project ReportTB Clinic Project Report
TB Clinic Project Report
 
Tony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdfTony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdf
 
REMOURBAN Information package n2 - Energiesprong 2050 project
REMOURBAN Information package n2 - Energiesprong 2050 project REMOURBAN Information package n2 - Energiesprong 2050 project
REMOURBAN Information package n2 - Energiesprong 2050 project
 
GC - Alder Hey
GC - Alder HeyGC - Alder Hey
GC - Alder Hey
 
Chalcroft Special Projects
Chalcroft Special ProjectsChalcroft Special Projects
Chalcroft Special Projects
 
Show and Tell - Heat.pdf
Show and Tell - Heat.pdfShow and Tell - Heat.pdf
Show and Tell - Heat.pdf
 

Coventry university CASE STUDY

  • 1. INDUSTRIAL CASE STUDY Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571 www.envirotechltd.co.uk info@envirotechltd.co.uk COVENTRY UNIVERSITY Project: Charles Ward Energy Centre Date of Project: June 2014 - September 2014 Project Value: £2.2million
  • 2. INDUSTRIAL CASE STUDY Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571 www.envirotechltd.co.uk info@envirotechltd.co.uk Project Description:- Charles ward energy centre Work Elements:- New 6.5mw energy centre Period of Works:- June 2014 - September 2014 Total time span:- 12 weeks including 5 week asbestos strip out Project value:- £2.2m Overview:- 6.5mw of Heating load Thermal store 34,000 litre BIM model NEW CHP Revitt Modelling Saving of 489 tonnes of carbon off site fabrication Temporary boiler plant for hot water 5 new 1200kw boilers New flue system Siemens Bons control 350kw air cooled chiller "spill & fill" pressurisation units Ongoing water Carbon Reduction Measures
  • 3. INDUSTRIAL CASE STUDY Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571 www.envirotechltd.co.uk info@envirotechltd.co.uk
  • 4. INDUSTRIAL CASE STUDY Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571 www.envirotechltd.co.uk info@envirotechltd.co.uk What did the project involve? The project comprised the replacement of 5 boilers, 1 new chiller and 1 CHP unit that previously fed a district heating circuit, and adding a further district heating branch to a local student accommodation facility. Existing boilers were approximately 40 years old, one boiler had failed its annual insurance inspection and the remaining four were well beyond their expected lifespan. The existing CHP unit was 12 years old, oversized, and replacement parts were hard to source. Total plantroom heating load is approximately 6.5MW. In addition to this, a large thermal store was installed to maximise CHP run hours and minimise dumping. The systems pumping strategy was drastically rationalised from individual pumped circuits on every branch (24 pumps in total) to main packaged pump arrangements, inverter driven, pressure controlled and automatic zone control valves. The plantroom 10 years overdue a refurbishment and had always been avoided due to the expectation that this was a project that could not be undertakenduring a single summer break. A lengthy asbestos strip was required before any refurbishment could begin and this required allboilers being switched off reducing programme evenfurther. Stand out achievement Programme was the main constraint of the project. With a maximum period of ‘heat off’ of 12 weeks and a 5 week asbestos strip reducing this to an actual plant room access time of 7 weeks, the decision was made that the project required almost complete off site fabrication. The plantroom was BIM modelled and the offsite fabrication produced from the BIM model when plant room access was unavailable. Once available, only small stool pieces were required on site to account for level changes within the existing floorslab. Without off site fabrication and the BIM model, this project could not have been completed within the heat off timeframe. The University are committed to a programme of carbon reduction and as one of its largest campus boiler rooms saw this project as key to their ongoing commitment to energy efficiency. Previously the CHP installation was oversized and as such dumped a lot of its heat. This system was linked to a nearby accommodation block to allow additional run hours to be utilised and also involved the installation of a 34,000L thermal store to recover heat outside of this and re-use if the following day.
  • 5. INDUSTRIAL CASE STUDY Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571 www.envirotechltd.co.uk info@envirotechltd.co.uk BIM MODEL ACTUAL INSTALL Used as our presentation for the 2015 HVAC Awards in March Coventry University Charles Ward Boiler House (BIM model and Actual Build)
  • 6. INDUSTRIAL CASE STUDY Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571 www.envirotechltd.co.uk info@envirotechltd.co.uk Environmental concerns. The existing CHP system dumped a significant proportion of its heat. Calculations determined that the improvements in boiler efficiency and the addition of a thermal store should save 240 tonnes of carbon and the addition of the student accommodation block would save a further 249 tonnes resulting in a total saving of 489 tonnes Carbon. Improvements in pumping strategy and moving over to zone control and inverter driven pressure controlled pumps will result in further energy savings. These are difficult to calculate, however we have installed a significant energy metering system which over the next 12 months will monitor and report on energy consumption against predictedusages. Capitalizing on the projectsuccess Due to the complexity and timescales involved with project, we took the decision to enter this project for the 2015 H&V award for the “Building Services Project for theyear”. To date ewe have been shortlisted from hundreds of entries and have reached the finals which take place in April 2015 In addition to this we are able, through our relationship with the university to disseminate information regarding this project through the Association of University Engineers (AUE). The AUE have over 200 members from nationwide universities, over 50 of these universities have existing CHP units that are nearing the end of their lives and they would benefit from the knowledge gained from thisproject. FINALIST
  • 7. INDUSTRIAL CASE STUDY Unit 2, The Courtyard, Roman Way, Coleshill, B46 1HQ Tel: 0845 671 8271 Fax: 01675 466 571 www.envirotechltd.co.uk info@envirotechltd.co.uk What differentiates us from our competitors? We believe what differentiates us from our competitors is our overall approach to the project from the start. From initial interview (pre-contract award) we devised a very detailed plan and programme to achieve the vital heat on date. Post contract start, we had a dedicated team not only on the installation but on the project management side with a full time on site manager along with a site based procurement team. This ensured that the tight time frame became easier to manage and achieve. In addition, by collaborating in detail with the specialist sub-contractors, i.e. controls and electrical engineers, we were able to ensure all necessary milestones and key dates were achieved. In addition, the use of the BIM modelling and off site fabrication meant that we could confidently demonstrate to the client that we could deliver what we said we would.