case study
Guy’s Hospital
Quintiles is one of the world’s leading
providers of pharmaceutical services,
helping to deliver new drugs and cures
for some of the most challenging
diseases.
To increase their capability to perform
this important work, Quintiles recently
took out a long-term lease for the 13th
floor at Guy’s Hospital London - in order
to create a new unit for clinical trials.
The floor needed a total revamp, and so
started with a strip-out all the way back
to the external walls. With everything
removed, the project could then start
with an empty shell.
CBS were called in to design and install
the plumbing, heating, ventilation and
cooling for the new clinic. An important
condition laid down by the hospital was
that any new climate control equipment
would have to use existing services
-presenting some real challenges.
The services available were hot and
chilled water in the central risers, fed
and controlled from a main boiler house
and chiller plant. These circuits provided
heating or cooling duty that could then
be fed into ductwork to provide the
desired temperature for the floor.
However, CBS’ Project Managers
calculated that these centralised services
would provide insufficient heating and
cooling for the floor.
So in order to supplement them, CBS
installed additional Trane fan coil units
around the perimeter. These fan coil
units were fed with the chilled water
from the central riser but also had high
efficiency electric heaters installed,
enabling them to produce additional
heating and cooling as required.
The next challenge CBS faced was how
to give the Quintiles staff control over
their heating and cooling sytems. This
was made difficult by the conditioned air
from the central plant being controlled by
a different system to the additional fan
coil units.
A solution was quickly found and CBS
installed a BMS (building management
system) which was designed specifically
for the installation. This had the ability to
control the additional Trane units as well
as the fan coils around the central riser.
This unique method of local control
made the best use of the building’s
existing plant and given the constraints
laid down by the landlord, worked
suprisingly well.
This was the first installation in which
Guys hospital have ever given one of
their tenants the ability to manipulate
the services from the main plant. The
system also gave Quintiles the ability, via
a touch screen at the nurses station, to
additionally control the extraction of stale
air and the lighting of the floor.
The entire refurbishment of the floor was
finished on time, on budget and to both
the client and landlords specification.
In fact, Quintiles were so happy with the
finished results of the project, that shortly
after completion they hired a film crew
to capture their new facility for corporate
marketing purposes.
Installation
Complete Refurbishment
Local.
Dependable.
Professional.
Safe & Secure
Push fit fittings were used for
all water pipework throughout
the installation. Not only did
this make the installation safer,
as no soldering was required,
but the fittings are also
incredibly strong - Rated for
up to 16 bar of pressure.
ENSURING COMFORT
It was calculated that the
services coming from the
central plant would be
insufficient. So Trane fan coil
units where installed around
the perimeter of the floor
to provide supplementary
heating and cooling.
PEACE OF MIND
Due to the nature of the
building, an advanced water
leak detection system
was fitted underneath the
raised floor. This would
automatically alert the nurses
station and the floor below if
ever there was a problem.
Comfort Building Services are based in Basingstoke
and operate within a radius of approximately 100
miles. CBS employ a crew of engineers who’s
combined skills cover all areas of building services.
Investors in People
Active participants of the Investors in People
programme and with the policy of developing their
own engineers CBS operate an apprentice-training
programme in conjunction with the local colleges.
Gas Safe, HVCA, NICEIC
In accordance with the requirements of their trades
CBS engineers hold the relevant professional
qualifications.
Comfort Building Services Ltd Sterling House
Stroudley Road, Basingstoke, Hampshire, RG24 8UG
T: 01256 842500 F: 01256 814661,
ww.cbsuk.com, enquiries@cbsuk.com
Project Data
Category	 Installation
Description	 Complete Refurbishment
Timescale	 5 Months
Value	 ÂŁ300,000
Services
Hot and cold water, drainage,heating, air conditioning,
leak detection, project management and the
implementation of a BCM system.
CBS have once
again exceeded our
expectations. This job
had more than its fair
share of challenges
which CBS have come
up with innovative
solutions for. This has
resulted in a first class
job which was finished
on time and to a high
standard.
Steve Coull
Sales Director
Astra Office Interiors -
Main Contractor
4593

Guys Hospital[1]

  • 1.
    case study Guy’s Hospital Quintilesis one of the world’s leading providers of pharmaceutical services, helping to deliver new drugs and cures for some of the most challenging diseases. To increase their capability to perform this important work, Quintiles recently took out a long-term lease for the 13th floor at Guy’s Hospital London - in order to create a new unit for clinical trials. The floor needed a total revamp, and so started with a strip-out all the way back to the external walls. With everything removed, the project could then start with an empty shell. CBS were called in to design and install the plumbing, heating, ventilation and cooling for the new clinic. An important condition laid down by the hospital was that any new climate control equipment would have to use existing services -presenting some real challenges. The services available were hot and chilled water in the central risers, fed and controlled from a main boiler house and chiller plant. These circuits provided heating or cooling duty that could then be fed into ductwork to provide the desired temperature for the floor. However, CBS’ Project Managers calculated that these centralised services would provide insufficient heating and cooling for the floor. So in order to supplement them, CBS installed additional Trane fan coil units around the perimeter. These fan coil units were fed with the chilled water from the central riser but also had high efficiency electric heaters installed, enabling them to produce additional heating and cooling as required. The next challenge CBS faced was how to give the Quintiles staff control over their heating and cooling sytems. This was made difficult by the conditioned air from the central plant being controlled by a different system to the additional fan coil units. A solution was quickly found and CBS installed a BMS (building management system) which was designed specifically for the installation. This had the ability to control the additional Trane units as well as the fan coils around the central riser. This unique method of local control made the best use of the building’s existing plant and given the constraints laid down by the landlord, worked suprisingly well. This was the first installation in which Guys hospital have ever given one of their tenants the ability to manipulate the services from the main plant. The system also gave Quintiles the ability, via a touch screen at the nurses station, to additionally control the extraction of stale air and the lighting of the floor. The entire refurbishment of the floor was finished on time, on budget and to both the client and landlords specification. In fact, Quintiles were so happy with the finished results of the project, that shortly after completion they hired a film crew to capture their new facility for corporate marketing purposes. Installation Complete Refurbishment
  • 2.
    Local. Dependable. Professional. Safe & Secure Pushfit fittings were used for all water pipework throughout the installation. Not only did this make the installation safer, as no soldering was required, but the fittings are also incredibly strong - Rated for up to 16 bar of pressure. ENSURING COMFORT It was calculated that the services coming from the central plant would be insufficient. So Trane fan coil units where installed around the perimeter of the floor to provide supplementary heating and cooling. PEACE OF MIND Due to the nature of the building, an advanced water leak detection system was fitted underneath the raised floor. This would automatically alert the nurses station and the floor below if ever there was a problem. Comfort Building Services are based in Basingstoke and operate within a radius of approximately 100 miles. CBS employ a crew of engineers who’s combined skills cover all areas of building services. Investors in People Active participants of the Investors in People programme and with the policy of developing their own engineers CBS operate an apprentice-training programme in conjunction with the local colleges. Gas Safe, HVCA, NICEIC In accordance with the requirements of their trades CBS engineers hold the relevant professional qualifications. Comfort Building Services Ltd Sterling House Stroudley Road, Basingstoke, Hampshire, RG24 8UG T: 01256 842500 F: 01256 814661, ww.cbsuk.com, enquiries@cbsuk.com Project Data Category Installation Description Complete Refurbishment Timescale 5 Months Value £300,000 Services Hot and cold water, drainage,heating, air conditioning, leak detection, project management and the implementation of a BCM system. CBS have once again exceeded our expectations. This job had more than its fair share of challenges which CBS have come up with innovative solutions for. This has resulted in a first class job which was finished on time and to a high standard. Steve Coull Sales Director Astra Office Interiors - Main Contractor 4593