Early Supplier
Developmental Input
Cortec Precision Sheetmetal and Machining
March 2012
Innovative Solutions for Commodity Specific Manufacturing
Introduction
How valuable is supplier input when it comes to minimizing design cost, cost
effective materials and cost efficient processing for your new product?

Early Supplier Developmental Input (ESDI) is a 2nd set of eyes at the front end
of the NPI process that can lead to major producibility and procurement
advantages.

Cortec has an ESDI Program that will provide critical risk assessment as it
pertains to the manufacturing of your new product. DFX; DFP, DFM & DFT
observations on everything from Raw Material, Outside Services, Procured
Components, Logistics, Packaging and Shipping.

Real-time consultation on the Quality Output of materials when processed
through our manufacturing facility.

By providing input on materials that work best with a specific child prototype or
electromechanical parent design, those contributions prevent potential problems
during manufacturing. By identifying these issues in advance, you're more likely
to experience a smooth product realization process once your new product has
been launched.

                                                      Cortec Precision Sheetmetal 2011
Early Developmental Solutions

   When you send Cortec an RFQ it will be reviewed by our Estimating Team (ET).
   Our E.T. has Sheet Metal & Frame Manufacturing, Machine Shop,
    Mechanical/Engineering, Add Value Assembly, NPI Development and Product
    Transfer experience.
   They possess knowledge of material pricing and services related to your Build To
    Print fabrication and assembly needs.
   Our Drawing Process includes DFX feedback during conceptual design stage.
   We are proficient at expediting and providing real-time solutions.
   Actively propose Integrated solutions.
   Advise on potential processing inefficiencies.
   Make logical progression of design recommendations from NPI thru production life
    cycle and value-added assembly.
   Our Experts provide cost impact analysis when revision changes.
   PFMECA reporting can be conducted.
   Ensure lines of communication are open and maintained daily to interface with
    corresponding personnel.
   Capable of working on special projects from NPI to Production transition.
                                                         Cortec Precision Sheetmetal 2011
ESDI DFP Reporting

            BOM              Metric Material                      QTY
            Item         Description and Imperial              Required
TYPE       Number              Equivalent                  to build 2 Frames
                                                                               DFP - Material Assessment
Metric     1, 2, & 3   200 x 100 x 10MM WALL RECT TUBE             4

Imperial       "
                        8" x 4" x .375 WALL A500B STEEL,
                                     RECT TUBE                     4
                                                                               & Material Budgetary Quote
Metric        4        150 x 100 x 8MM WALL RECT TUBE
                       6" X 4" X .312 WALL A500B STEEL,
                                                                   4                     sample
Imperial       "                   RECT TUBE                       4

Metric      5&7        100 x 50 x 8MM WALL RECT TUBE               5
                       4" X 2" X .312 WALL A500B STEEL,
Imperial       "                   RECT TUBE                       5

Metric        8        32MM THK, PL STRUCTURAL STEEL               1
                        2" X 1-1/4" THK STEEL RECT FLAT
Imperial       "                       BAR                         1
                        2.5MM (MILD CARBON HRS STEEL
Metric        10                    PLATE, A36)                    1
                       12 GA CRS (0.1046) ASTM A1008 CS
Imperial       "                      TYPE B                       1

                       19MM THK PL, STRUCTURAL STEEL
                        SUPPLIER DOES NOT SUPPORT,
Metric        6        NEXT SIZE UP IS 20MM (.7874 THK)            1
                            .750 THK PLT ASTM A36
Imperial       "                   48" x 96"                       1

                       13MM THK, PL STRUCTURAL STEEL
Metric        9                      32" X 60"                     1
                        HOT ROLLED PICKLED & OIL .500
                                   (PLATE A36)
Imperial       "                     32" x 48"                     1
 Metric       11             COPPER SH, 1MM THK                    1
                       .040 THK, (1/4 HARD) OFE COPPER
Imperial       "            C10100 HO1, ASTM B 152                 1


                                                                                 Cortec Precision Sheetmetal 2011
ESDI DFM Reporting

Using a sheet metal cover as an
example, Is it possible that the
fasteners you are using could
be substituted for a less
expensive product or be
integrated in our factory at the
next level of assembly?
Cost savings pass through to
you when suggesting alternative
materials or processing ideas       ESDI:
                                      1. Instead of using CLS-832-1 Cortec suggested using SP-832-1.
that work as effectively but cost   Why?

much less because they are          Pem product technology has advanced and supplier created a new type of
                                    hardware designed specifically for installment into Stainless Steel base

incorporated into your design       material.

                                    This new Pem product eliminates the need to tack weld the old type of
from the very start.                hardware customarily used resulting in cost savings.

                                    15% per part cost savings include elimination of tack weld, grinding and
                                    additional regraining of exterior surfaces to remove weld discoloration in the
                                    manufacturing Sequence of Events (SOE).




                                                    Cortec Precision Sheetmetal 2011
ESDI: Quality Review
Quality of new product is directly related
to how involved your ESDI partner is at                       Metal Filler Missing
the beginning of the NPI process. When           • Workmanship
consulting Cortec during the development         • Failure to Follow OMS
                                                 • Type of failure – major
stage, expect to have a product designed
with the right materials that conform to         • Action: Rework by
drawing specifications.                            stripping paint from
                                                   seam and repeat OMS
                                                   #12 STEPS 1-15
When products are designed without the        Slide - 1

contribution of an ESDI partner, there's a                       Cortec Precision Sheetmetal Confidential
possibility requested materials will not
work well with the final product. Materials
used in the production of your new                             Flat Head Screws
product could be inconsistent, laborious         • Flat Head Screws
and very expensive to incorporate or               supposed to be removed.
                                                 • Cause: Frame
rework.                                            manufacturer failed to
                                                   remove Flat Head Screws
                                                   before painting.
                                                 • Type of failure – Minor,
Cortecs’ ESDI solution is to provide an            weld department did not
                                                   follow customer approved
                                                   OMS.
onsite resource and be an adjunct
member of your Engineering team.                 • Action: Option to Return
                                                   to supplier or PAINT
                                              Slide -frame.
                                                      1


                                                                 Cortec Precision Sheetmetal Confidential




                                                               Cortec Precision Sheetmetal 2011
ESDI Solutions identified during RFQ Process
        & change control

                      RFQ Processing and Identification of ESDI Opportunities, DXF reporting and design challenges



                                • Estimators             • Estimators send       • Customer places     • Customer places
                                Review                   Quote Letter to         order.                order.
                                 RFQ Package             Customer along          • Customer Service    • Customer Service
                                • Prepare Pre-           with Pre-FMEA           sees Popup            sees Popup
                                FMEA statement           statement and           notification and      notification and
       RFQ                      • Create Redline
                                drawing to WI 7.1.3
                                                         Redline drawing
                                                         file.
                                                                                 triggers SPS
                                                                                 Process.
                                                                                                       triggers SPS
                                                                                                       Process.
                                • Adds Comment to        • Adds Popup Note
                                Quote Comment            in History Tab and
                                Field.                   clicks Popup Notify
                                                         Note



   • ME always                  • ME gathers data        • ME Reviews            • ME confirms         • ME confirms
   attaches revised             and updates the          drawing files for       redline created by    need for SPS
   redline to                   redline drawing file     any other               Estimator.            and SPS details.
   FabriTRAK.                   if required.
                                                         omissions that
   • Must attach to
   BOTH Quote and
                                                         will prevent
   Router.                                               product
                                                         realization during
                                                         WIP.



   • ME files SPS /             • ME updates             • ME updates            • ME notifies ALL     • ME saves a
   PR / (other                  router and adds          router and adds         departments           copy of the
   customer                     comments to              comments to             affected by SPS       solution in the
   acronym).                    transaction log.         transaction log.        submittal.            Q:/Drive Part
   • Adds comments                                                               • Estimators          number folder.
   to FabriTRAK                                                                  • Customer            • Adds comments
   quote comment                                                                 Service               in Quote and
   field.                                                                        •FAI Team             Router, attaches
Slide - 1                                                                                              solution to
                                                                                                       FabriTRAK.



                                          Cortec Precision Sheetmetal Confidential

                                                                                         Cortec Precision Sheetmetal 2011
Early Developmental Input Benefit

 Applying our ESDI approach affords the opportunity to reassure optimal
 “design implementation” for manufacturability and other processing risks in a
 timely manner, enabling Research and Development the opportunity to
 respond with minimal impact to your product release schedule.
 This fully-integrated and efficient approach assures that your company
 reduces costs because it allows earlier identification of processing issues,
 and it applies your set tolerance for risk in a consistent manner.
 Enables real-time responsiveness and effective direct design input.
 Allows significant processing alternatives to control risk, cut cost and improve
 quality.
 Provides consistent risk analysis, assessment and reporting.
 Conduct risk control validation .
 Cortec guarantees a fully- integrated and value-added approach towards
 assessing and improving your design implementation.


                                                     Cortec Precision Sheetmetal 2011
ESDI Benefit: Quantitative Results
                                 Cosmetic
                              Class A Finish, Cosmetic time savings
                                  2 sides     Class A Finish Outside Surface
      12nc Description010
                     2           Q3 2011      Class C Finish Inside Surface     Quantitative savings 12-02-2011        TQS
                                               Time savings 1 minute per part
xxxx.000.88882 RS XTIV LO-FRONT PANEL IL LSY2
                 $      44.31 $        35.12                                    $                           1.08   $    34.04
                                               Multiple piece assembly, Time
                                              savings 5 min per side; 10 min.
xxxx.000.88882 RS XT4 INN.COV. LSY2 RH ASSY
                 $     289.78 $       272.33                 total              $                         10.83    $   261.50
                                                Multiple piece assembly,Time
                                              savings 5 min per side; 10 min.
xxxx.000.88882 RS XT4 INN.COV. LSY2 ILL ASSY
                 $     258.23 $       250.17                 total              $                         10.83    $   239.34
                                                Multiple piece assembly,Time
                                              savings 5 min per side; 10 min.
xxxx.000.88882 RS XT4 INN.COV.LSY1/2 MID ASSY
                 $     221.93 $       210.84                 total              $                         10.83    $   200.01
                                                Multiple piece assembly,Time
                                              savings 5 min per side; 10 min.
xxxx.000.88882 RS XT4 INN.COV. LSY1 RH ASSY
                 $     283.17 $       271.86                 total              $                         10.83    $   261.03
                                                Multiple piece assembly,Time
                                              savings 5 min per side; 10 min.
xxxx.000.88882 RS XT4 INN.COV. LSY1 ILL ASSY
                 $     294.37 $       279.65                 total              $                         10.83    $   268.82
                                               Time savings 10 min. per side;
xxxx.000.88882 RS AIR SHOWER COVER PLATE ASSY20 min. total
                 $     453.42 $       417.18                                    $                         21.66    $   395.52
xxxx.000.88882 RS XT4 TOP COVER 526.21 ASSY savings is 10 min.
                 $     551.00 $       ILL LSY2    Time                          $                         10.83    $   515.38
xxxx.000.88882 RS XT4 TOP COVER 526.23
                 $     553.91 $       MID LSY2 ASSY savings is 10 min.
                                                  Time                          $                         10.83    $   515.40
xxxx.000.88882 RS XT4 TOP COVER 570.84 ASSY savings is 10 min.
                 $     596.50 $       RH LSY2     Time                          $                         10.83    $   560.01
xxxx.000.88882 RS XT4 TOP COVER 527.25 ASSY savings is 10 min.
                 $     554.97 $       ILL LSY1    Time                          $                         10.83    $   516.42
xxxx.000.88882 RS XT4 TOP COVER 420.26
                 $     440.00 $       MID LSY1 ASSY savings is 10 min.
                                                  Time                          $                         10.83    $   409.43
xxxx.000.88882 RS XT4 TOP COVER 508.98 ASSY savings is 10 min.
                 $     535.75 $       RH LSY1     Time                          $                         10.83    $   498.15
xxxx.000.88882 RS XT4 FRONT COVER LSY1 ASSY
                 $     421.96 $       400.86      Time savings is 20 min.       $                         21.66    $   379.20
xxxx.000.88882 RS XT4 UP-FRT COVER IL-Y2 ASSY
                 $     326.97 $       311.29       Time savings is 7 min.       $                          7.58    $   303.71
xxxx.000.88882 RS XT4 FRONT COVER RH-Y2 ASSY savings is 5 min.
                 $     424.90 $       390.04       Time                         $                          5.42    $   384.62
xxxx.000.88882 RS XT4 FRONT COVER MID-Y2 ASSY savings is 5 min.
                 $     446.11 $       384.73       Time                         $                          5.42    $   379.31
xxxx.000.88882 RS LOS RH COVER ASSY
                 $     580.46 $       554.52      Time savings is 20 min.       $                         21.66    $   532.86
xxxx.000.88882 RS XT4 COVER MOUNT STRIP SA-AMachined flat bar
                 $      71.37 $        62.10
xxxx.000.88882 RS XT4 COVER MOUNT STRIP SA-BMachined flat bar
                 $      69.07 $        60.39
                 $ 7,418.18 $       6,980.85                                    Total                              $ 6,654.75
                                                                                Percentage Quantitative Savings     -24.67%




                                                                                                                                Cortec Precision Sheetmetal 2011
Early Developmental Input
                             Cost Overruns



  New
                        Mechanical Fit Issue
                     Material Processing Issue


                  Issues &
Product         Opportunities
 Design           Identified



  New               Early Supplier

Product          Developmental Input


 Design
                   Cortec Precision Sheetmetal 2011
Logical Manufacturing Progression

New                  Drawing Review
                     POR/PFMECA/
                                        Sheetmetal
                                        Processing
                                                                  Machine Shop
                                                                  Processing

Pro
                       ESDI/DFX
                                  PCV                PCV                            PCV




duct                   Silk Screen      Paint Shop                 Welding Shop

Desi                   Processing       Processing                 Processing


 gn
                                  PCV                PCV                            PCV




Value-Add            Value-Add          Process Control           Shipping
                                                                                    PCV
                                        Validation (PCV)
Assembly             Assembly
                                                                  Project Lessons
Class 10,000         Class 1000
               PCV                PCV   SPC/FAI      PCV          Learned           PCV
Cleanroom            Cleanroom


                                                     Cortec Precision Sheetmetal 2011
Manufacturing Enhancements
   78,000 Sq Ft Manufacturing Facility
Sheetmetal
 Light out laser capabilities added
 QTY 9, AMADA Press brakes, multiple LASER and Punch Presses
Machine Shop
 Qty 7, 3-AXIS Vertical Mills,
 Qty 1 (Lathe) CNC turning Center
14 weld stations – some dedicated work stations to support 4LPM & 2LPM
projects added
Both Powder and Wet coat paint booths can support up to 16ft tall frames,
Material KAN-BAN inventory
Onsite rework team for real time change control
90 day strategic plan in progress for a fully functional ISO 7 CL 10,000 Value-
Add Cleanroom.

                                                    Cortec Precision Sheetmetal 2011
Enhanced Machine Shop Capabilities

                           More Machines




 Better Process Controls


More Capacity                  Cortec Precision Sheetmetal 2011
Project Success Criteria
Multiple Frames developed in Parallel with Optimum Success Criteria
  Ramp to meet customer demand in less than 30 days.
  Dedicated work stations through entire process to support both projects
  PFMECA conducted and reported.
  Added dedicated project weld stations.
  Daily CFT and project timeline updates.
  JIT raw material and procured materials inventory.
  Tab and Key tubing design and fixturing for better welding controls.
  Incorporated Value-Add materials in ISO 8 cleanroom during production.
  Process Control Validation and OMS documented.
  Multiple ESDI and customer design changes cut-in before and during
  development.
  Onsite rework and ESDI participation with customer Engineering team
  eliminated costly logistics burden.
  Imperial material solution provided during production when European
  metric material supplier failed to deliver attributed to ESDI, CFT’s and PR
  reporting.
  100% Product Yield
  Participated in crate recycling program to reduce logistics burden.
  Lessons Learned and reported.                                                 Cortec Precision Sheetmetal 2011
Project Success Criteria
Multiple Frames developed in Parallel with Optimum Success Criteria
  Ramp to meet customer demand in less than 30 days.
  Dedicated work stations through entire process to support both projects
  PFMECA conducted and reported.
  Added dedicated project weld stations.
  Daily CFT and project timeline updates.
  JIT raw material and procured materials inventory.
  Tab and Key tubing design and fixturing for better welding controls.
  Incorporated Value-Add materials in ISO 8 cleanroom during production.
  Process Control Validation and OMS documented.
  Multiple ESDI and customer design changes cut-in before and during
  development.
  Onsite rework and ESDI participation with customer Engineering team
  eliminated costly logistics burden.
  Imperial material solution provided during production when European
  metric material supplier failed to deliver attributed to ESDI, CFT’s and PR
  reporting.
  100% Product Yield
  Participated in crate recycling program to reduce logistics burden.
  Lessons Learned and reported.                                                 Cortec Precision Sheetmetal 2011
Product Transfer Services to LCR

l            • S. Korea
             • Singapore
             • Malaysia
               • China
              • Canada
          • Mexicali, Mexico
                               Cortec Precision Sheetmetal 2011
Value Add Assembly & Cleanroom
                  Is the Next Logical Step In Manufacturing
Coming soon !!!




                                              Cortec Precision Sheetmetal 2011
Summary
 Cortec considers your company a valued partner and would like the
  opportunity to review your design and provide
 The proposed ESDI solution is for an assigned project or Technical P.M.
  to work as an adjunct member of your Engineering team, Quality team,
  Supply Base Management or other groups as required.
 Machine Shop capacity has increased with better controls and could be
  a stronger strategic resource to an existing partnership.
 Welding and Large Frame Capacity has increased with better controls.
 Multiple Frame projects with value-added assembly with 100% yield
  SPC, FAI process validation, and OMS documented and reported;
  benefits all Cortec customer base.
 Strategic plan in progress to provide a Class 10,000 cleanroom for
  increased Value-Added assembly service in 90 days.
 Streamlined communication to correct personnel at Cortec for better
  responsiveness.
 Product Transfer Services to Low cost Region


                                                   Cortec Precision Sheetmetal 2011

More Related Content

What's hot

Fisher-Barton Materials Lab Brochure
Fisher-Barton Materials Lab BrochureFisher-Barton Materials Lab Brochure
Fisher-Barton Materials Lab Brochurefisherbarton
 
Pcb Cost Drivers
Pcb Cost DriversPcb Cost Drivers
Pcb Cost DriversTony Monaco
 
Mfg 01 a_study_on_solid_and_shell_material_model_valeo
Mfg 01 a_study_on_solid_and_shell_material_model_valeoMfg 01 a_study_on_solid_and_shell_material_model_valeo
Mfg 01 a_study_on_solid_and_shell_material_model_valeoAnand Kumar Chinni
 
PCB Manufacturer, Domestic Circuit Board Production and Prototype
PCB Manufacturer, Domestic Circuit Board Production and PrototypePCB Manufacturer, Domestic Circuit Board Production and Prototype
PCB Manufacturer, Domestic Circuit Board Production and PrototypeDomestic PCB Fabrication
 
Tappex Overview Af2
Tappex Overview Af2Tappex Overview Af2
Tappex Overview Af2MULTISERT
 
Coating Trends Rapid Fire
Coating Trends Rapid Fire Coating Trends Rapid Fire
Coating Trends Rapid Fire April Bright
 
Welcome to lantech solutions
Welcome to lantech solutionsWelcome to lantech solutions
Welcome to lantech solutionsSteven Joss
 
Davies molding overview 2013
Davies molding overview 2013Davies molding overview 2013
Davies molding overview 2013DaviesMolding
 
Pipeline pdf brochure
Pipeline pdf brochurePipeline pdf brochure
Pipeline pdf brochurehydrobolt
 
Hydrobolt pdf Brochure
Hydrobolt pdf BrochureHydrobolt pdf Brochure
Hydrobolt pdf Brochurehydrobolt
 
Ddepl Hpml Profile
Ddepl Hpml ProfileDdepl Hpml Profile
Ddepl Hpml ProfileSatish Rao
 
TECH TIPS Steel Studs: Thru Thick & Thin
TECH TIPS Steel Studs: Thru Thick & ThinTECH TIPS Steel Studs: Thru Thick & Thin
TECH TIPS Steel Studs: Thru Thick & ThinRandal Reifsnider
 
Testing/Manufacture/Equipmetns - FEC Catalouge -www.fecproduct.com
Testing/Manufacture/Equipmetns - FEC Catalouge -www.fecproduct.comTesting/Manufacture/Equipmetns - FEC Catalouge -www.fecproduct.com
Testing/Manufacture/Equipmetns - FEC Catalouge -www.fecproduct.comfec2020
 

What's hot (20)

Fisher-Barton Materials Lab Brochure
Fisher-Barton Materials Lab BrochureFisher-Barton Materials Lab Brochure
Fisher-Barton Materials Lab Brochure
 
Semiconductor IT Management
Semiconductor IT ManagementSemiconductor IT Management
Semiconductor IT Management
 
Cbct rods fdf
Cbct rods fdfCbct rods fdf
Cbct rods fdf
 
Pcb Cost Drivers
Pcb Cost DriversPcb Cost Drivers
Pcb Cost Drivers
 
Mfg 01 a_study_on_solid_and_shell_material_model_valeo
Mfg 01 a_study_on_solid_and_shell_material_model_valeoMfg 01 a_study_on_solid_and_shell_material_model_valeo
Mfg 01 a_study_on_solid_and_shell_material_model_valeo
 
SSUSA Presentation V1.07
SSUSA Presentation V1.07SSUSA Presentation V1.07
SSUSA Presentation V1.07
 
PCB Manufacturer, Domestic Circuit Board Production and Prototype
PCB Manufacturer, Domestic Circuit Board Production and PrototypePCB Manufacturer, Domestic Circuit Board Production and Prototype
PCB Manufacturer, Domestic Circuit Board Production and Prototype
 
Tappex Overview Af2
Tappex Overview Af2Tappex Overview Af2
Tappex Overview Af2
 
Coating Trends Rapid Fire
Coating Trends Rapid Fire Coating Trends Rapid Fire
Coating Trends Rapid Fire
 
Welcome to lantech solutions
Welcome to lantech solutionsWelcome to lantech solutions
Welcome to lantech solutions
 
Davies molding overview 2013
Davies molding overview 2013Davies molding overview 2013
Davies molding overview 2013
 
Colpak
ColpakColpak
Colpak
 
Pipeline pdf brochure
Pipeline pdf brochurePipeline pdf brochure
Pipeline pdf brochure
 
Hydrobolt pdf Brochure
Hydrobolt pdf BrochureHydrobolt pdf Brochure
Hydrobolt pdf Brochure
 
Kurek Tool
Kurek ToolKurek Tool
Kurek Tool
 
REPL PROFILE
REPL PROFILEREPL PROFILE
REPL PROFILE
 
Ddepl Hpml Profile
Ddepl Hpml ProfileDdepl Hpml Profile
Ddepl Hpml Profile
 
TECH TIPS Steel Studs: Thru Thick & Thin
TECH TIPS Steel Studs: Thru Thick & ThinTECH TIPS Steel Studs: Thru Thick & Thin
TECH TIPS Steel Studs: Thru Thick & Thin
 
Logiform catalogue
Logiform catalogueLogiform catalogue
Logiform catalogue
 
Testing/Manufacture/Equipmetns - FEC Catalouge -www.fecproduct.com
Testing/Manufacture/Equipmetns - FEC Catalouge -www.fecproduct.comTesting/Manufacture/Equipmetns - FEC Catalouge -www.fecproduct.com
Testing/Manufacture/Equipmetns - FEC Catalouge -www.fecproduct.com
 

Viewers also liked

AddQ Testautomatiseringserfarenheter
AddQ TestautomatiseringserfarenheterAddQ Testautomatiseringserfarenheter
AddQ TestautomatiseringserfarenheterAddQ Consulting
 
Computers by heistking
Computers by heistkingComputers by heistking
Computers by heistkingheistking
 
Cortec Early Supplier Developemental Input, 3 26 2012
Cortec Early Supplier Developemental Input, 3 26 2012Cortec Early Supplier Developemental Input, 3 26 2012
Cortec Early Supplier Developemental Input, 3 26 2012revjoev
 
Muscle labeling for students
Muscle labeling for studentsMuscle labeling for students
Muscle labeling for studentsmannywoodward
 
The Key to a Successful SEO Sales Strategy (the Long Tail)
The Key to a Successful SEO Sales Strategy (the Long Tail)The Key to a Successful SEO Sales Strategy (the Long Tail)
The Key to a Successful SEO Sales Strategy (the Long Tail)Trusted Translations, Inc.
 
How International Businesses Can Market To the United States using Social Media
How International Businesses Can Market To the United States using Social MediaHow International Businesses Can Market To the United States using Social Media
How International Businesses Can Market To the United States using Social Mediajamespetergrant
 
Impact brochure final
Impact brochure finalImpact brochure final
Impact brochure finalchishn
 
About Nicky Chisholm Marketing
About Nicky Chisholm MarketingAbout Nicky Chisholm Marketing
About Nicky Chisholm Marketingchishn
 

Viewers also liked (10)

AddQ Testautomatiseringserfarenheter
AddQ TestautomatiseringserfarenheterAddQ Testautomatiseringserfarenheter
AddQ Testautomatiseringserfarenheter
 
Party rockers
Party rockersParty rockers
Party rockers
 
Computers by heistking
Computers by heistkingComputers by heistking
Computers by heistking
 
Cortec Early Supplier Developemental Input, 3 26 2012
Cortec Early Supplier Developemental Input, 3 26 2012Cortec Early Supplier Developemental Input, 3 26 2012
Cortec Early Supplier Developemental Input, 3 26 2012
 
Party rockers
Party rockersParty rockers
Party rockers
 
Muscle labeling for students
Muscle labeling for studentsMuscle labeling for students
Muscle labeling for students
 
The Key to a Successful SEO Sales Strategy (the Long Tail)
The Key to a Successful SEO Sales Strategy (the Long Tail)The Key to a Successful SEO Sales Strategy (the Long Tail)
The Key to a Successful SEO Sales Strategy (the Long Tail)
 
How International Businesses Can Market To the United States using Social Media
How International Businesses Can Market To the United States using Social MediaHow International Businesses Can Market To the United States using Social Media
How International Businesses Can Market To the United States using Social Media
 
Impact brochure final
Impact brochure finalImpact brochure final
Impact brochure final
 
About Nicky Chisholm Marketing
About Nicky Chisholm MarketingAbout Nicky Chisholm Marketing
About Nicky Chisholm Marketing
 

Similar to Cortec Early Supplier Developemental Input, 3 26 2012

EE driving the cost out of your design
EE driving the cost out of your designEE driving the cost out of your design
EE driving the cost out of your designbmacforever
 
CSIRO Additive Manufacturing - Aug 14
CSIRO Additive Manufacturing - Aug 14CSIRO Additive Manufacturing - Aug 14
CSIRO Additive Manufacturing - Aug 14SME_Engagement
 
SMT Printing Challenges
SMT Printing ChallengesSMT Printing Challenges
SMT Printing ChallengesFCT Solder
 
PCB Fabrication Manufacturer Corporate Brochure
PCB Fabrication Manufacturer Corporate BrochurePCB Fabrication Manufacturer Corporate Brochure
PCB Fabrication Manufacturer Corporate BrochureDomestic PCB Fabrication
 
Rapid Recap 2016 and AMUG
Rapid Recap 2016 and AMUGRapid Recap 2016 and AMUG
Rapid Recap 2016 and AMUGTriCmarketing
 
Pcp Orientation Presentation
Pcp Orientation PresentationPcp Orientation Presentation
Pcp Orientation PresentationJeremyFerguson
 
3 Dimensional Services Group
3 Dimensional Services Group3 Dimensional Services Group
3 Dimensional Services GroupRminowa
 
3D Circuits-Wireless-Save Cost & Assembly
3D Circuits-Wireless-Save Cost & Assembly 3D Circuits-Wireless-Save Cost & Assembly
3D Circuits-Wireless-Save Cost & Assembly sourcepointassociates
 
Public company presentation rev 4 may16
Public company presentation rev 4 may16Public company presentation rev 4 may16
Public company presentation rev 4 may16Jonathan Schnaider
 
YSX TECH Presentation
YSX TECH PresentationYSX TECH Presentation
YSX TECH PresentationJolin Huang
 
RAPID TOOLING - presentationupdate
RAPID TOOLING - presentationupdateRAPID TOOLING - presentationupdate
RAPID TOOLING - presentationupdateKerrie Noble
 

Similar to Cortec Early Supplier Developemental Input, 3 26 2012 (20)

EE driving the cost out of your design
EE driving the cost out of your designEE driving the cost out of your design
EE driving the cost out of your design
 
CSIRO Additive Manufacturing - Aug 14
CSIRO Additive Manufacturing - Aug 14CSIRO Additive Manufacturing - Aug 14
CSIRO Additive Manufacturing - Aug 14
 
SMT Printing Challenges
SMT Printing ChallengesSMT Printing Challenges
SMT Printing Challenges
 
SMT Printing Challenges
SMT Printing ChallengesSMT Printing Challenges
SMT Printing Challenges
 
PCB Fabrication Manufacturer Corporate Brochure
PCB Fabrication Manufacturer Corporate BrochurePCB Fabrication Manufacturer Corporate Brochure
PCB Fabrication Manufacturer Corporate Brochure
 
AdvInMetallography.pptx
AdvInMetallography.pptxAdvInMetallography.pptx
AdvInMetallography.pptx
 
Rush PCB Inc
Rush PCB IncRush PCB Inc
Rush PCB Inc
 
Investment Casting FAQ
Investment Casting FAQInvestment Casting FAQ
Investment Casting FAQ
 
Nujay Tech: PCB Capability Flyer
Nujay Tech: PCB Capability FlyerNujay Tech: PCB Capability Flyer
Nujay Tech: PCB Capability Flyer
 
Rapid Recap 2016 and AMUG
Rapid Recap 2016 and AMUGRapid Recap 2016 and AMUG
Rapid Recap 2016 and AMUG
 
Pcp Orientation Presentation
Pcp Orientation PresentationPcp Orientation Presentation
Pcp Orientation Presentation
 
3 Dimensional Services Group
3 Dimensional Services Group3 Dimensional Services Group
3 Dimensional Services Group
 
3D Circuits-Wireless-Save Cost & Assembly
3D Circuits-Wireless-Save Cost & Assembly 3D Circuits-Wireless-Save Cost & Assembly
3D Circuits-Wireless-Save Cost & Assembly
 
Ball_Flyer_R2
Ball_Flyer_R2Ball_Flyer_R2
Ball_Flyer_R2
 
Public company presentation rev 4 may16
Public company presentation rev 4 may16Public company presentation rev 4 may16
Public company presentation rev 4 may16
 
ASHFAB
ASHFABASHFAB
ASHFAB
 
YSX TECH Presentation
YSX TECH PresentationYSX TECH Presentation
YSX TECH Presentation
 
ICES-Presentation
ICES-PresentationICES-Presentation
ICES-Presentation
 
CSI Company Profile (1)
CSI Company Profile (1)CSI Company Profile (1)
CSI Company Profile (1)
 
RAPID TOOLING - presentationupdate
RAPID TOOLING - presentationupdateRAPID TOOLING - presentationupdate
RAPID TOOLING - presentationupdate
 

Cortec Early Supplier Developemental Input, 3 26 2012

  • 1. Early Supplier Developmental Input Cortec Precision Sheetmetal and Machining March 2012 Innovative Solutions for Commodity Specific Manufacturing
  • 2. Introduction How valuable is supplier input when it comes to minimizing design cost, cost effective materials and cost efficient processing for your new product? Early Supplier Developmental Input (ESDI) is a 2nd set of eyes at the front end of the NPI process that can lead to major producibility and procurement advantages. Cortec has an ESDI Program that will provide critical risk assessment as it pertains to the manufacturing of your new product. DFX; DFP, DFM & DFT observations on everything from Raw Material, Outside Services, Procured Components, Logistics, Packaging and Shipping. Real-time consultation on the Quality Output of materials when processed through our manufacturing facility. By providing input on materials that work best with a specific child prototype or electromechanical parent design, those contributions prevent potential problems during manufacturing. By identifying these issues in advance, you're more likely to experience a smooth product realization process once your new product has been launched. Cortec Precision Sheetmetal 2011
  • 3. Early Developmental Solutions  When you send Cortec an RFQ it will be reviewed by our Estimating Team (ET).  Our E.T. has Sheet Metal & Frame Manufacturing, Machine Shop, Mechanical/Engineering, Add Value Assembly, NPI Development and Product Transfer experience.  They possess knowledge of material pricing and services related to your Build To Print fabrication and assembly needs.  Our Drawing Process includes DFX feedback during conceptual design stage.  We are proficient at expediting and providing real-time solutions.  Actively propose Integrated solutions.  Advise on potential processing inefficiencies.  Make logical progression of design recommendations from NPI thru production life cycle and value-added assembly.  Our Experts provide cost impact analysis when revision changes.  PFMECA reporting can be conducted.  Ensure lines of communication are open and maintained daily to interface with corresponding personnel.  Capable of working on special projects from NPI to Production transition. Cortec Precision Sheetmetal 2011
  • 4. ESDI DFP Reporting BOM Metric Material QTY Item Description and Imperial Required TYPE Number Equivalent to build 2 Frames DFP - Material Assessment Metric 1, 2, & 3 200 x 100 x 10MM WALL RECT TUBE 4 Imperial " 8" x 4" x .375 WALL A500B STEEL, RECT TUBE 4 & Material Budgetary Quote Metric 4 150 x 100 x 8MM WALL RECT TUBE 6" X 4" X .312 WALL A500B STEEL, 4 sample Imperial " RECT TUBE 4 Metric 5&7 100 x 50 x 8MM WALL RECT TUBE 5 4" X 2" X .312 WALL A500B STEEL, Imperial " RECT TUBE 5 Metric 8 32MM THK, PL STRUCTURAL STEEL 1 2" X 1-1/4" THK STEEL RECT FLAT Imperial " BAR 1 2.5MM (MILD CARBON HRS STEEL Metric 10 PLATE, A36) 1 12 GA CRS (0.1046) ASTM A1008 CS Imperial " TYPE B 1 19MM THK PL, STRUCTURAL STEEL SUPPLIER DOES NOT SUPPORT, Metric 6 NEXT SIZE UP IS 20MM (.7874 THK) 1 .750 THK PLT ASTM A36 Imperial " 48" x 96" 1 13MM THK, PL STRUCTURAL STEEL Metric 9 32" X 60" 1 HOT ROLLED PICKLED & OIL .500 (PLATE A36) Imperial " 32" x 48" 1 Metric 11 COPPER SH, 1MM THK 1 .040 THK, (1/4 HARD) OFE COPPER Imperial " C10100 HO1, ASTM B 152 1 Cortec Precision Sheetmetal 2011
  • 5. ESDI DFM Reporting Using a sheet metal cover as an example, Is it possible that the fasteners you are using could be substituted for a less expensive product or be integrated in our factory at the next level of assembly? Cost savings pass through to you when suggesting alternative materials or processing ideas ESDI: 1. Instead of using CLS-832-1 Cortec suggested using SP-832-1. that work as effectively but cost Why? much less because they are Pem product technology has advanced and supplier created a new type of hardware designed specifically for installment into Stainless Steel base incorporated into your design material. This new Pem product eliminates the need to tack weld the old type of from the very start. hardware customarily used resulting in cost savings. 15% per part cost savings include elimination of tack weld, grinding and additional regraining of exterior surfaces to remove weld discoloration in the manufacturing Sequence of Events (SOE). Cortec Precision Sheetmetal 2011
  • 6. ESDI: Quality Review Quality of new product is directly related to how involved your ESDI partner is at Metal Filler Missing the beginning of the NPI process. When • Workmanship consulting Cortec during the development • Failure to Follow OMS • Type of failure – major stage, expect to have a product designed with the right materials that conform to • Action: Rework by drawing specifications. stripping paint from seam and repeat OMS #12 STEPS 1-15 When products are designed without the Slide - 1 contribution of an ESDI partner, there's a Cortec Precision Sheetmetal Confidential possibility requested materials will not work well with the final product. Materials used in the production of your new Flat Head Screws product could be inconsistent, laborious • Flat Head Screws and very expensive to incorporate or supposed to be removed. • Cause: Frame rework. manufacturer failed to remove Flat Head Screws before painting. • Type of failure – Minor, Cortecs’ ESDI solution is to provide an weld department did not follow customer approved OMS. onsite resource and be an adjunct member of your Engineering team. • Action: Option to Return to supplier or PAINT Slide -frame. 1 Cortec Precision Sheetmetal Confidential Cortec Precision Sheetmetal 2011
  • 7. ESDI Solutions identified during RFQ Process & change control RFQ Processing and Identification of ESDI Opportunities, DXF reporting and design challenges • Estimators • Estimators send • Customer places • Customer places Review Quote Letter to order. order. RFQ Package Customer along • Customer Service • Customer Service • Prepare Pre- with Pre-FMEA sees Popup sees Popup FMEA statement statement and notification and notification and RFQ • Create Redline drawing to WI 7.1.3 Redline drawing file. triggers SPS Process. triggers SPS Process. • Adds Comment to • Adds Popup Note Quote Comment in History Tab and Field. clicks Popup Notify Note • ME always • ME gathers data • ME Reviews • ME confirms • ME confirms attaches revised and updates the drawing files for redline created by need for SPS redline to redline drawing file any other Estimator. and SPS details. FabriTRAK. if required. omissions that • Must attach to BOTH Quote and will prevent Router. product realization during WIP. • ME files SPS / • ME updates • ME updates • ME notifies ALL • ME saves a PR / (other router and adds router and adds departments copy of the customer comments to comments to affected by SPS solution in the acronym). transaction log. transaction log. submittal. Q:/Drive Part • Adds comments • Estimators number folder. to FabriTRAK • Customer • Adds comments quote comment Service in Quote and field. •FAI Team Router, attaches Slide - 1 solution to FabriTRAK. Cortec Precision Sheetmetal Confidential Cortec Precision Sheetmetal 2011
  • 8. Early Developmental Input Benefit Applying our ESDI approach affords the opportunity to reassure optimal “design implementation” for manufacturability and other processing risks in a timely manner, enabling Research and Development the opportunity to respond with minimal impact to your product release schedule. This fully-integrated and efficient approach assures that your company reduces costs because it allows earlier identification of processing issues, and it applies your set tolerance for risk in a consistent manner. Enables real-time responsiveness and effective direct design input. Allows significant processing alternatives to control risk, cut cost and improve quality. Provides consistent risk analysis, assessment and reporting. Conduct risk control validation . Cortec guarantees a fully- integrated and value-added approach towards assessing and improving your design implementation. Cortec Precision Sheetmetal 2011
  • 9. ESDI Benefit: Quantitative Results Cosmetic Class A Finish, Cosmetic time savings 2 sides Class A Finish Outside Surface 12nc Description010 2 Q3 2011 Class C Finish Inside Surface Quantitative savings 12-02-2011 TQS Time savings 1 minute per part xxxx.000.88882 RS XTIV LO-FRONT PANEL IL LSY2 $ 44.31 $ 35.12 $ 1.08 $ 34.04 Multiple piece assembly, Time savings 5 min per side; 10 min. xxxx.000.88882 RS XT4 INN.COV. LSY2 RH ASSY $ 289.78 $ 272.33 total $ 10.83 $ 261.50 Multiple piece assembly,Time savings 5 min per side; 10 min. xxxx.000.88882 RS XT4 INN.COV. LSY2 ILL ASSY $ 258.23 $ 250.17 total $ 10.83 $ 239.34 Multiple piece assembly,Time savings 5 min per side; 10 min. xxxx.000.88882 RS XT4 INN.COV.LSY1/2 MID ASSY $ 221.93 $ 210.84 total $ 10.83 $ 200.01 Multiple piece assembly,Time savings 5 min per side; 10 min. xxxx.000.88882 RS XT4 INN.COV. LSY1 RH ASSY $ 283.17 $ 271.86 total $ 10.83 $ 261.03 Multiple piece assembly,Time savings 5 min per side; 10 min. xxxx.000.88882 RS XT4 INN.COV. LSY1 ILL ASSY $ 294.37 $ 279.65 total $ 10.83 $ 268.82 Time savings 10 min. per side; xxxx.000.88882 RS AIR SHOWER COVER PLATE ASSY20 min. total $ 453.42 $ 417.18 $ 21.66 $ 395.52 xxxx.000.88882 RS XT4 TOP COVER 526.21 ASSY savings is 10 min. $ 551.00 $ ILL LSY2 Time $ 10.83 $ 515.38 xxxx.000.88882 RS XT4 TOP COVER 526.23 $ 553.91 $ MID LSY2 ASSY savings is 10 min. Time $ 10.83 $ 515.40 xxxx.000.88882 RS XT4 TOP COVER 570.84 ASSY savings is 10 min. $ 596.50 $ RH LSY2 Time $ 10.83 $ 560.01 xxxx.000.88882 RS XT4 TOP COVER 527.25 ASSY savings is 10 min. $ 554.97 $ ILL LSY1 Time $ 10.83 $ 516.42 xxxx.000.88882 RS XT4 TOP COVER 420.26 $ 440.00 $ MID LSY1 ASSY savings is 10 min. Time $ 10.83 $ 409.43 xxxx.000.88882 RS XT4 TOP COVER 508.98 ASSY savings is 10 min. $ 535.75 $ RH LSY1 Time $ 10.83 $ 498.15 xxxx.000.88882 RS XT4 FRONT COVER LSY1 ASSY $ 421.96 $ 400.86 Time savings is 20 min. $ 21.66 $ 379.20 xxxx.000.88882 RS XT4 UP-FRT COVER IL-Y2 ASSY $ 326.97 $ 311.29 Time savings is 7 min. $ 7.58 $ 303.71 xxxx.000.88882 RS XT4 FRONT COVER RH-Y2 ASSY savings is 5 min. $ 424.90 $ 390.04 Time $ 5.42 $ 384.62 xxxx.000.88882 RS XT4 FRONT COVER MID-Y2 ASSY savings is 5 min. $ 446.11 $ 384.73 Time $ 5.42 $ 379.31 xxxx.000.88882 RS LOS RH COVER ASSY $ 580.46 $ 554.52 Time savings is 20 min. $ 21.66 $ 532.86 xxxx.000.88882 RS XT4 COVER MOUNT STRIP SA-AMachined flat bar $ 71.37 $ 62.10 xxxx.000.88882 RS XT4 COVER MOUNT STRIP SA-BMachined flat bar $ 69.07 $ 60.39 $ 7,418.18 $ 6,980.85 Total $ 6,654.75 Percentage Quantitative Savings -24.67% Cortec Precision Sheetmetal 2011
  • 10. Early Developmental Input Cost Overruns New Mechanical Fit Issue Material Processing Issue Issues & Product Opportunities Design Identified New Early Supplier Product Developmental Input Design Cortec Precision Sheetmetal 2011
  • 11. Logical Manufacturing Progression New Drawing Review POR/PFMECA/ Sheetmetal Processing Machine Shop Processing Pro ESDI/DFX PCV PCV PCV duct Silk Screen Paint Shop Welding Shop Desi Processing Processing Processing gn PCV PCV PCV Value-Add Value-Add Process Control Shipping PCV Validation (PCV) Assembly Assembly Project Lessons Class 10,000 Class 1000 PCV PCV SPC/FAI PCV Learned PCV Cleanroom Cleanroom Cortec Precision Sheetmetal 2011
  • 12. Manufacturing Enhancements 78,000 Sq Ft Manufacturing Facility Sheetmetal Light out laser capabilities added QTY 9, AMADA Press brakes, multiple LASER and Punch Presses Machine Shop Qty 7, 3-AXIS Vertical Mills, Qty 1 (Lathe) CNC turning Center 14 weld stations – some dedicated work stations to support 4LPM & 2LPM projects added Both Powder and Wet coat paint booths can support up to 16ft tall frames, Material KAN-BAN inventory Onsite rework team for real time change control 90 day strategic plan in progress for a fully functional ISO 7 CL 10,000 Value- Add Cleanroom. Cortec Precision Sheetmetal 2011
  • 13. Enhanced Machine Shop Capabilities More Machines Better Process Controls More Capacity Cortec Precision Sheetmetal 2011
  • 14. Project Success Criteria Multiple Frames developed in Parallel with Optimum Success Criteria Ramp to meet customer demand in less than 30 days. Dedicated work stations through entire process to support both projects PFMECA conducted and reported. Added dedicated project weld stations. Daily CFT and project timeline updates. JIT raw material and procured materials inventory. Tab and Key tubing design and fixturing for better welding controls. Incorporated Value-Add materials in ISO 8 cleanroom during production. Process Control Validation and OMS documented. Multiple ESDI and customer design changes cut-in before and during development. Onsite rework and ESDI participation with customer Engineering team eliminated costly logistics burden. Imperial material solution provided during production when European metric material supplier failed to deliver attributed to ESDI, CFT’s and PR reporting. 100% Product Yield Participated in crate recycling program to reduce logistics burden. Lessons Learned and reported. Cortec Precision Sheetmetal 2011
  • 15. Project Success Criteria Multiple Frames developed in Parallel with Optimum Success Criteria Ramp to meet customer demand in less than 30 days. Dedicated work stations through entire process to support both projects PFMECA conducted and reported. Added dedicated project weld stations. Daily CFT and project timeline updates. JIT raw material and procured materials inventory. Tab and Key tubing design and fixturing for better welding controls. Incorporated Value-Add materials in ISO 8 cleanroom during production. Process Control Validation and OMS documented. Multiple ESDI and customer design changes cut-in before and during development. Onsite rework and ESDI participation with customer Engineering team eliminated costly logistics burden. Imperial material solution provided during production when European metric material supplier failed to deliver attributed to ESDI, CFT’s and PR reporting. 100% Product Yield Participated in crate recycling program to reduce logistics burden. Lessons Learned and reported. Cortec Precision Sheetmetal 2011
  • 16. Product Transfer Services to LCR l • S. Korea • Singapore • Malaysia • China • Canada • Mexicali, Mexico Cortec Precision Sheetmetal 2011
  • 17. Value Add Assembly & Cleanroom Is the Next Logical Step In Manufacturing Coming soon !!! Cortec Precision Sheetmetal 2011
  • 18. Summary  Cortec considers your company a valued partner and would like the opportunity to review your design and provide  The proposed ESDI solution is for an assigned project or Technical P.M. to work as an adjunct member of your Engineering team, Quality team, Supply Base Management or other groups as required.  Machine Shop capacity has increased with better controls and could be a stronger strategic resource to an existing partnership.  Welding and Large Frame Capacity has increased with better controls.  Multiple Frame projects with value-added assembly with 100% yield SPC, FAI process validation, and OMS documented and reported; benefits all Cortec customer base.  Strategic plan in progress to provide a Class 10,000 cleanroom for increased Value-Added assembly service in 90 days.  Streamlined communication to correct personnel at Cortec for better responsiveness.  Product Transfer Services to Low cost Region Cortec Precision Sheetmetal 2011