SlideShare a Scribd company logo
Concurrent
Engineering –
Breaking down
the silos
Gilad Langer and EJ Alston
Agenda
Introduction
• What is Concurrent or Integrated Engineering?
• What are the benefits
Engineering in Pharma – the traditional approach
• Examples
Concurrent Engineering Best Practice
• Examples
Concurrent Engineering In Practice
• Examples
• Advantages
• Value
Concurrent Engineering / Integrated Engineering
• The process of Designs “tossed over the wall”
are inherently wasteful and risky
• Concurrent Engineering - simultaneous
engineering activities leading to a higher quality
design and a more effective engineering process.
What are the benefits?
• Effectively Achieve Design Goals
• Reduction in time to market
• Right first time
• Cost of quality
• Enhanced Productivity
• Earlier discoveries of design problems
• More efficient C&Q
• Decrease Design and Development Time
• Products & process that match customer’s
needs, in less time and at a reduced cost
A bit of historical perspective…
Concurrent Engineering
• 1988
• Aero & Defence
…
QbD by FDA
• 2006
QbD
• 1992
• Automotive
CIM
• 1993
• Auto, A&D, Ship
…
Integrated Engineering
• 2017
• Pharma
THE TRADITIONAL APPROACH
6
Disadvantages of the traditional approach
7
• The process vendor sends the completed process design to the automation vendor – this makes
integration difficult
• Automation system design becomes a matter of “this is possible – this is not possible”
• Small changes in the process design can have huge consequences for the automation system –
leads to scope changes/change orders and ultimately delays
• You miss any chances of identifying process steps which may prove to be redundant
• Discussions focus on scope changes rather than on functionality
• Things get lost in translation between the process people and the automation people
• No one takes ownership of solving the problem – both the process vendor and automation vendor
are doing their jobs
Example Brownfield Fill Finish Facility
• $120 mill. Fill Finish Facility under a consent decree with GMP fill and finish suites and packaging
• Equipment and facility designed by one company with installation, electrical, and automation
managed by other companies.
• Design delivered on time but automation programing 3 months delayed
• Document review cycles executed 6 times due to changes
• Executed multiple change orders increase project cost
Melted Instrumentation and Tubing
• Instrumentation installed and positioned
after design, FAT acceptance, and skid
installation
• Several valve operational failures due to
melted pneumatic control tubing during SIP
• Damaged instrumentation due to close
proximity to piping during SIP
• Damaged electrical conduit due to close
proximity to piping during SIP
Design and Automation Interface Issues
• Automation programing reworked due to
misalignment between process description, valve
matrix, automation scope, and process
development
• Automation scope did not match user
requirement specifications and required additional
work
• Skid design not aligned with automation and
instrumentation requirements for program
functionality causing additional work
• Functional specifications and valve matrix
required several updates to align process design
and automation requirements
Example: Greenfield Fill Finish Facility
• $500 mill. Fill Finish Facility with GMP fill and finish suites, utility plant, central warehouse
• Different companies for Process Design, Architect, Automation Design & Integration, and G.C.
• 1+ year delay
• Design review cycle from 2 to 5+ (still not enough)
• 30% new scope in automation due to “unfinished” process and HVAC design
No room to mount actuator
• Process specified instruments
• Automation design purchased instruments
• Installed by G.C.
WFI Loop Sanitization Cycle – all or nothing
Best practice example
Novo Nordisk DAPI US
14
Facility design + operating model
• Overall aspiration
• Operating principles
• Manufacturing processes
• Business processes
• Organisational structure
• Roles and responsibilities
• Competence/capacity requirements
• Quality system setup
• IT system alignment
• SOP development programme
• Recruitment programme
• Training programme
• Communication programme
Client contact: Morten Nielsen, head of DAPI-US
Elements of Pharma Facility Design – The key
Design framework should focus on the product attributes and the process
• unit operations required for manufacturing the product and the risks
• introduced by implementing the right technology
PROCESS
• Product produced
– Logical operating
units (LOUs)
• Equipment
– Steel and Single-use
• Input materials
INFRASTRUCTURE
• Control system
– Procedures/SOP’
– Computer systems
– Operating and
maintenance systems
– Documentation
• People
– Personal discipline
– Qualification/training
FACILITY
• Layout - flow
• Environment
• Utility systems
PROCESS
INFRASTRUCTUREFACILITY
Process and automation designed concurrently
to support each other
16
PROCESS AND AUTOMATION
• Complete understanding of process, equipment,
regulatory requirements, and support activities
(e.g., sampling)
• Complete understanding of software and
hardware requirements to support the defined
process
• Utilize pharmaceutical heritage to deliver a
comprehensive solution (Just works vs. works
even when there is human error)
PROCESS
INFRASTRUCTUREFACILITY
Our Front-End/CD Roadmap (OurModel)
17
What are the real business objectives?
18
Agile manufacturing Effective documentation Process capability Supply chain reliability Operational excellence
Flexibility Compliance Quality Volumes Competitiveness
New product intro Stable production volumes Patent expiry
Time
Recipe/
workflow
execution
Batch
reporting and
verification
AutomationandITcapabilities
Business
objectives
Enterprise
resource
planning
Scheduling
Unit control
Product and
process
definition
Electronic log
books
Batch control
Transport
control
Review by
exception
Manufacturing
intelligence
Quality
monitoring
Data collection
Laboratory
data
management
Quality test
workflow
execution
Calibration
management
Maintenance
management
19
Advantages
20
• Ensures risk free design and implementation of automation and IT
• Leads to better and more robust design – the system is more effective and meets design objectives
• Facilitates a leaner process as it enables parallel design of process and automation system, which
optimises the project and the time schedule
• Enables optimisation of the process during the design phase
• Allows for automation input to process design, which creates room for optimisation and control
strategy – “have you thought about …”
• Allows for process input to automation design (what can we do to achieve seamless manufacturing?)
• Supports flexibility, agility and GMP readiness – all documentation is more homogenous – test
documentation for process and automation is the same
• Facilitates concurrent engineering – flexible manufacturing systems (FMS)
Value to the customer
21
• Transform automation solution from “just automating the process” to a complete system solution that
enables flexibility, agility and is “future proof”
• Design driven by business objectives
• Eliminate isolated and subjective technology decision
• Clear cost/benefit for solution elements
• Roadmap for solution elements not in initial scope
• Enable “informed” decisions during design and implementation phases using enterprise architecture
• Organisational alignment around common architecture
• Enterprise system touchpoints and integration
• Third party automation solution and equipment suppliers
Thank you
For further information please contact
EJ Alston
Director, Engineering
edal@nne.com
919-338-3160
Gilad Langer
Director, Automation & MIS
gidl@nne.com
415-405-6743

More Related Content

What's hot

Product Design & Process Selection-Manufacturing
Product Design & Process Selection-Manufacturing Product Design & Process Selection-Manufacturing
Product Design & Process Selection-Manufacturing
Joshua Miranda
 
Social write ups 01
Social write ups 01Social write ups 01
Social write ups 01Adam Tarr
 
Chapter 7 process strategy production and operation and management
Chapter 7  process strategy production and operation and management Chapter 7  process strategy production and operation and management
Chapter 7 process strategy production and operation and management Christine Aguirre Cayanan
 
Lean Manufacturing in Pharmaceutical Industry
Lean Manufacturing in Pharmaceutical IndustryLean Manufacturing in Pharmaceutical Industry
Lean Manufacturing in Pharmaceutical Industry
Aniket Joshi
 
5a session 5a_jit systems cfvg 2012
5a session 5a_jit systems cfvg 20125a session 5a_jit systems cfvg 2012
5a session 5a_jit systems cfvg 2012kimsach
 
Mba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aMba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection a
Rai University
 
LeanSigma for IW 2005
LeanSigma for IW 2005LeanSigma for IW 2005
LeanSigma for IW 2005
Randall Cooper
 
IMPROVEMENT OF MANUFACTURING OPERATIONS THROUGH A LEAN MANAGEMENT APPROACH A...
IMPROVEMENT OF MANUFACTURING OPERATIONS  THROUGH A LEAN MANAGEMENT APPROACH A...IMPROVEMENT OF MANUFACTURING OPERATIONS  THROUGH A LEAN MANAGEMENT APPROACH A...
IMPROVEMENT OF MANUFACTURING OPERATIONS THROUGH A LEAN MANAGEMENT APPROACH A...
sanobar77
 
(Student assignment) riordan manufacturing process improvement final
(Student assignment) riordan manufacturing process improvement final(Student assignment) riordan manufacturing process improvement final
(Student assignment) riordan manufacturing process improvement final
Charles James
 
Ops management lecture 4 process design & strategy
Ops management lecture 4 process design & strategyOps management lecture 4 process design & strategy
Ops management lecture 4 process design & strategy
jillmitchell8778
 
Cb12e basic ppt ch11
Cb12e basic ppt ch11Cb12e basic ppt ch11
Cb12e basic ppt ch11Eric
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & Sustainability
IRJET Journal
 
Workshop trondheim working without waste qrm
Workshop trondheim working without waste qrmWorkshop trondheim working without waste qrm
Workshop trondheim working without waste qrm
Vincent Wiegel
 
Rod Cornell ResumeA2
Rod Cornell ResumeA2Rod Cornell ResumeA2
Rod Cornell ResumeA2Rod Cornell
 
Process strategy ppt @ bec doms
Process strategy ppt @ bec domsProcess strategy ppt @ bec doms
Process strategy ppt @ bec doms
Babasab Patil
 
Literature review - Data mining and Business Intelligence in Manufacturing
Literature review - Data mining and Business Intelligence in ManufacturingLiterature review - Data mining and Business Intelligence in Manufacturing
Literature review - Data mining and Business Intelligence in Manufacturing
Abhishek Nandgaonkar
 
Landon mertz cerion nanomaterials
Landon mertz   cerion nanomaterialsLandon mertz   cerion nanomaterials
Landon mertz cerion nanomaterials
The Advanced Materials Show
 
Product and process planning
Product and process planningProduct and process planning
Product and process planning
zimbar
 
Agile manufacturing
Agile manufacturingAgile manufacturing
Agile manufacturingHammaduddin
 

What's hot (20)

Product Design & Process Selection-Manufacturing
Product Design & Process Selection-Manufacturing Product Design & Process Selection-Manufacturing
Product Design & Process Selection-Manufacturing
 
Social write ups 01
Social write ups 01Social write ups 01
Social write ups 01
 
Chapter 7 process strategy production and operation and management
Chapter 7  process strategy production and operation and management Chapter 7  process strategy production and operation and management
Chapter 7 process strategy production and operation and management
 
Lean Manufacturing in Pharmaceutical Industry
Lean Manufacturing in Pharmaceutical IndustryLean Manufacturing in Pharmaceutical Industry
Lean Manufacturing in Pharmaceutical Industry
 
5a session 5a_jit systems cfvg 2012
5a session 5a_jit systems cfvg 20125a session 5a_jit systems cfvg 2012
5a session 5a_jit systems cfvg 2012
 
Mba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aMba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection a
 
LeanSigma for IW 2005
LeanSigma for IW 2005LeanSigma for IW 2005
LeanSigma for IW 2005
 
GLH resume 2016
GLH resume 2016GLH resume 2016
GLH resume 2016
 
IMPROVEMENT OF MANUFACTURING OPERATIONS THROUGH A LEAN MANAGEMENT APPROACH A...
IMPROVEMENT OF MANUFACTURING OPERATIONS  THROUGH A LEAN MANAGEMENT APPROACH A...IMPROVEMENT OF MANUFACTURING OPERATIONS  THROUGH A LEAN MANAGEMENT APPROACH A...
IMPROVEMENT OF MANUFACTURING OPERATIONS THROUGH A LEAN MANAGEMENT APPROACH A...
 
(Student assignment) riordan manufacturing process improvement final
(Student assignment) riordan manufacturing process improvement final(Student assignment) riordan manufacturing process improvement final
(Student assignment) riordan manufacturing process improvement final
 
Ops management lecture 4 process design & strategy
Ops management lecture 4 process design & strategyOps management lecture 4 process design & strategy
Ops management lecture 4 process design & strategy
 
Cb12e basic ppt ch11
Cb12e basic ppt ch11Cb12e basic ppt ch11
Cb12e basic ppt ch11
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & Sustainability
 
Workshop trondheim working without waste qrm
Workshop trondheim working without waste qrmWorkshop trondheim working without waste qrm
Workshop trondheim working without waste qrm
 
Rod Cornell ResumeA2
Rod Cornell ResumeA2Rod Cornell ResumeA2
Rod Cornell ResumeA2
 
Process strategy ppt @ bec doms
Process strategy ppt @ bec domsProcess strategy ppt @ bec doms
Process strategy ppt @ bec doms
 
Literature review - Data mining and Business Intelligence in Manufacturing
Literature review - Data mining and Business Intelligence in ManufacturingLiterature review - Data mining and Business Intelligence in Manufacturing
Literature review - Data mining and Business Intelligence in Manufacturing
 
Landon mertz cerion nanomaterials
Landon mertz   cerion nanomaterialsLandon mertz   cerion nanomaterials
Landon mertz cerion nanomaterials
 
Product and process planning
Product and process planningProduct and process planning
Product and process planning
 
Agile manufacturing
Agile manufacturingAgile manufacturing
Agile manufacturing
 

Similar to Concurrent Engineering – Breaking down the silos

Spm lecture-3
Spm lecture-3Spm lecture-3
Spm lecture-3
Sulman Ahmed
 
Lect3
Lect3Lect3
POM .ppt
POM .pptPOM .ppt
POM .ppt
kcsekar77
 
Engineering solutions
Engineering solutionsEngineering solutions
Engineering solutions
Genpact Ltd
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Chris Baichoo
 
Systems Engineering
Systems EngineeringSystems Engineering
Systems Engineering
SergeyDolgorukov
 
Product innovation & process innovation
Product innovation & process innovationProduct innovation & process innovation
Product innovation & process innovation
VijayKrKhurana
 
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
Synergis Engineering Design Solutions
 
Discovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
Discovering New Product Introduction (NPI) using Autodesk Fusion LifecycleDiscovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
Discovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
Razorleaf Corporation
 
Product Design.pptx
Product Design.pptxProduct Design.pptx
Product Design.pptx
RiadHasan25
 
3.2 Managing Engineering Design.ppt
3.2 Managing Engineering Design.ppt3.2 Managing Engineering Design.ppt
3.2 Managing Engineering Design.ppt
KrishnaGupta191
 
Sonoco products smart manufacturing initiative boosts uptime 30 percent
Sonoco products smart manufacturing initiative boosts uptime 30 percentSonoco products smart manufacturing initiative boosts uptime 30 percent
Sonoco products smart manufacturing initiative boosts uptime 30 percent
IntelligentManufacturingInstitute
 
lean manufacturing
 lean manufacturing lean manufacturing
lean manufacturing
Tonny Danny
 
Mme Group 2 2011
Mme Group 2 2011Mme Group 2 2011
Mme Group 2 2011
barchambault
 
Mg6088 spm unit-2
Mg6088 spm unit-2Mg6088 spm unit-2
Mg6088 spm unit-2
SIMONTHOMAS S
 
D_David_ Thompson_resume_15_1
D_David_ Thompson_resume_15_1D_David_ Thompson_resume_15_1
D_David_ Thompson_resume_15_1Dave Thompson
 
Production & opeartions management
Production & opeartions managementProduction & opeartions management
Production & opeartions managementShimelis Mutera
 
Software Project Management (lecture 3)
Software Project Management (lecture 3)Software Project Management (lecture 3)
Software Project Management (lecture 3)Syed Muhammad Hammad
 
PDSA Results Flexsteel
PDSA Results FlexsteelPDSA Results Flexsteel
PDSA Results Flexsteel
Sophia Hudson
 
APQP
APQP APQP

Similar to Concurrent Engineering – Breaking down the silos (20)

Spm lecture-3
Spm lecture-3Spm lecture-3
Spm lecture-3
 
Lect3
Lect3Lect3
Lect3
 
POM .ppt
POM .pptPOM .ppt
POM .ppt
 
Engineering solutions
Engineering solutionsEngineering solutions
Engineering solutions
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 
Systems Engineering
Systems EngineeringSystems Engineering
Systems Engineering
 
Product innovation & process innovation
Product innovation & process innovationProduct innovation & process innovation
Product innovation & process innovation
 
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
 
Discovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
Discovering New Product Introduction (NPI) using Autodesk Fusion LifecycleDiscovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
Discovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
 
Product Design.pptx
Product Design.pptxProduct Design.pptx
Product Design.pptx
 
3.2 Managing Engineering Design.ppt
3.2 Managing Engineering Design.ppt3.2 Managing Engineering Design.ppt
3.2 Managing Engineering Design.ppt
 
Sonoco products smart manufacturing initiative boosts uptime 30 percent
Sonoco products smart manufacturing initiative boosts uptime 30 percentSonoco products smart manufacturing initiative boosts uptime 30 percent
Sonoco products smart manufacturing initiative boosts uptime 30 percent
 
lean manufacturing
 lean manufacturing lean manufacturing
lean manufacturing
 
Mme Group 2 2011
Mme Group 2 2011Mme Group 2 2011
Mme Group 2 2011
 
Mg6088 spm unit-2
Mg6088 spm unit-2Mg6088 spm unit-2
Mg6088 spm unit-2
 
D_David_ Thompson_resume_15_1
D_David_ Thompson_resume_15_1D_David_ Thompson_resume_15_1
D_David_ Thompson_resume_15_1
 
Production & opeartions management
Production & opeartions managementProduction & opeartions management
Production & opeartions management
 
Software Project Management (lecture 3)
Software Project Management (lecture 3)Software Project Management (lecture 3)
Software Project Management (lecture 3)
 
PDSA Results Flexsteel
PDSA Results FlexsteelPDSA Results Flexsteel
PDSA Results Flexsteel
 
APQP
APQP APQP
APQP
 

Recently uploaded

Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 

Recently uploaded (20)

Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 

Concurrent Engineering – Breaking down the silos

  • 1. Concurrent Engineering – Breaking down the silos Gilad Langer and EJ Alston
  • 2. Agenda Introduction • What is Concurrent or Integrated Engineering? • What are the benefits Engineering in Pharma – the traditional approach • Examples Concurrent Engineering Best Practice • Examples Concurrent Engineering In Practice • Examples • Advantages • Value
  • 3. Concurrent Engineering / Integrated Engineering • The process of Designs “tossed over the wall” are inherently wasteful and risky • Concurrent Engineering - simultaneous engineering activities leading to a higher quality design and a more effective engineering process.
  • 4. What are the benefits? • Effectively Achieve Design Goals • Reduction in time to market • Right first time • Cost of quality • Enhanced Productivity • Earlier discoveries of design problems • More efficient C&Q • Decrease Design and Development Time • Products & process that match customer’s needs, in less time and at a reduced cost
  • 5. A bit of historical perspective… Concurrent Engineering • 1988 • Aero & Defence … QbD by FDA • 2006 QbD • 1992 • Automotive CIM • 1993 • Auto, A&D, Ship … Integrated Engineering • 2017 • Pharma
  • 7. Disadvantages of the traditional approach 7 • The process vendor sends the completed process design to the automation vendor – this makes integration difficult • Automation system design becomes a matter of “this is possible – this is not possible” • Small changes in the process design can have huge consequences for the automation system – leads to scope changes/change orders and ultimately delays • You miss any chances of identifying process steps which may prove to be redundant • Discussions focus on scope changes rather than on functionality • Things get lost in translation between the process people and the automation people • No one takes ownership of solving the problem – both the process vendor and automation vendor are doing their jobs
  • 8. Example Brownfield Fill Finish Facility • $120 mill. Fill Finish Facility under a consent decree with GMP fill and finish suites and packaging • Equipment and facility designed by one company with installation, electrical, and automation managed by other companies. • Design delivered on time but automation programing 3 months delayed • Document review cycles executed 6 times due to changes • Executed multiple change orders increase project cost
  • 9. Melted Instrumentation and Tubing • Instrumentation installed and positioned after design, FAT acceptance, and skid installation • Several valve operational failures due to melted pneumatic control tubing during SIP • Damaged instrumentation due to close proximity to piping during SIP • Damaged electrical conduit due to close proximity to piping during SIP
  • 10. Design and Automation Interface Issues • Automation programing reworked due to misalignment between process description, valve matrix, automation scope, and process development • Automation scope did not match user requirement specifications and required additional work • Skid design not aligned with automation and instrumentation requirements for program functionality causing additional work • Functional specifications and valve matrix required several updates to align process design and automation requirements
  • 11. Example: Greenfield Fill Finish Facility • $500 mill. Fill Finish Facility with GMP fill and finish suites, utility plant, central warehouse • Different companies for Process Design, Architect, Automation Design & Integration, and G.C. • 1+ year delay • Design review cycle from 2 to 5+ (still not enough) • 30% new scope in automation due to “unfinished” process and HVAC design
  • 12. No room to mount actuator • Process specified instruments • Automation design purchased instruments • Installed by G.C.
  • 13. WFI Loop Sanitization Cycle – all or nothing
  • 14. Best practice example Novo Nordisk DAPI US 14 Facility design + operating model • Overall aspiration • Operating principles • Manufacturing processes • Business processes • Organisational structure • Roles and responsibilities • Competence/capacity requirements • Quality system setup • IT system alignment • SOP development programme • Recruitment programme • Training programme • Communication programme Client contact: Morten Nielsen, head of DAPI-US
  • 15. Elements of Pharma Facility Design – The key Design framework should focus on the product attributes and the process • unit operations required for manufacturing the product and the risks • introduced by implementing the right technology PROCESS • Product produced – Logical operating units (LOUs) • Equipment – Steel and Single-use • Input materials INFRASTRUCTURE • Control system – Procedures/SOP’ – Computer systems – Operating and maintenance systems – Documentation • People – Personal discipline – Qualification/training FACILITY • Layout - flow • Environment • Utility systems PROCESS INFRASTRUCTUREFACILITY
  • 16. Process and automation designed concurrently to support each other 16 PROCESS AND AUTOMATION • Complete understanding of process, equipment, regulatory requirements, and support activities (e.g., sampling) • Complete understanding of software and hardware requirements to support the defined process • Utilize pharmaceutical heritage to deliver a comprehensive solution (Just works vs. works even when there is human error) PROCESS INFRASTRUCTUREFACILITY
  • 17. Our Front-End/CD Roadmap (OurModel) 17
  • 18. What are the real business objectives? 18 Agile manufacturing Effective documentation Process capability Supply chain reliability Operational excellence Flexibility Compliance Quality Volumes Competitiveness New product intro Stable production volumes Patent expiry Time Recipe/ workflow execution Batch reporting and verification AutomationandITcapabilities Business objectives Enterprise resource planning Scheduling Unit control Product and process definition Electronic log books Batch control Transport control Review by exception Manufacturing intelligence Quality monitoring Data collection Laboratory data management Quality test workflow execution Calibration management Maintenance management
  • 19. 19
  • 20. Advantages 20 • Ensures risk free design and implementation of automation and IT • Leads to better and more robust design – the system is more effective and meets design objectives • Facilitates a leaner process as it enables parallel design of process and automation system, which optimises the project and the time schedule • Enables optimisation of the process during the design phase • Allows for automation input to process design, which creates room for optimisation and control strategy – “have you thought about …” • Allows for process input to automation design (what can we do to achieve seamless manufacturing?) • Supports flexibility, agility and GMP readiness – all documentation is more homogenous – test documentation for process and automation is the same • Facilitates concurrent engineering – flexible manufacturing systems (FMS)
  • 21. Value to the customer 21 • Transform automation solution from “just automating the process” to a complete system solution that enables flexibility, agility and is “future proof” • Design driven by business objectives • Eliminate isolated and subjective technology decision • Clear cost/benefit for solution elements • Roadmap for solution elements not in initial scope • Enable “informed” decisions during design and implementation phases using enterprise architecture • Organisational alignment around common architecture • Enterprise system touchpoints and integration • Third party automation solution and equipment suppliers
  • 22. Thank you For further information please contact EJ Alston Director, Engineering edal@nne.com 919-338-3160 Gilad Langer Director, Automation & MIS gidl@nne.com 415-405-6743