This document appears to be a student's practicum report on studying the super structural construction process of a ten-story residential building. It includes sections on the company profile, project details and design specifications, construction materials and equipment used, and descriptions of the construction processes for columns, beams, slabs and stairs. The report is submitted to fulfill degree requirements and acknowledges assistance from supervisors and others involved in the project.
PRACTICUM REPORT ON Monitoring the Construction Process of Superstructure ...Rubel Rana
A Practicum Report Submitted to Practicum & Placement Committee, Department of Civil Engineering, College of Engineering & Technology (CEAT), IUBAT for the Partial Fulfillment of the Requirement for the
Bachelor of Science in Civil Engineering (BSCE) Degree
Report is about the Internship of a Civil Engineer.
This Report is for the students of civil engineering. In this report u can find the format of the Report, Mechanism of the internship report. It is very useful to understand some civil engineering terms.
Analysis and Design of Structural Components of a Ten Storied RCC Residential...Shariful Haque Robin
This report has been prepared as an integral part of the internship program for the Bachelor of Science in Civil Engineering (BSCE) under the Department of Civil Engineering in IUBAT−International University of Business Agriculture and Technology. The Dynamic Design and Development (DDD) Ltd. nominated as the organization for the practicum while honorable Prof. Dr. Md. Monirul Islam, Chair of the Department of Civil Engineering rendered his kind consent to academically supervise the internship program.
Super-Structural Construction Work of a Six Storied Residential BuildingShariful Haque Robin
The internship report in broad-spectrum contains ten chapters in which I try to explain my
three-month experience in my hosting company. The content of all chapters is broadly
explained and it is constructed from the practical basis of the site work ended all months
CIVIL ENGINEERING INTERNSHIP REPORT, DETAILED INTERNSHIP REPORT ON A CIVIL ENGINEERING SITE , USEFUL REPORT FOR FRESHER CIVIL ENGINEERS WITH EXTRA ORDINARY DETAILS WITH IMAGES AND CHECK LIST, FOR CIVIL ENGINEERING STUDENTS FOR HOW TO MAKE INTERNSHIP REPORT
PRACTICUM REPORT ON Monitoring the Construction Process of Superstructure ...Rubel Rana
A Practicum Report Submitted to Practicum & Placement Committee, Department of Civil Engineering, College of Engineering & Technology (CEAT), IUBAT for the Partial Fulfillment of the Requirement for the
Bachelor of Science in Civil Engineering (BSCE) Degree
Report is about the Internship of a Civil Engineer.
This Report is for the students of civil engineering. In this report u can find the format of the Report, Mechanism of the internship report. It is very useful to understand some civil engineering terms.
Analysis and Design of Structural Components of a Ten Storied RCC Residential...Shariful Haque Robin
This report has been prepared as an integral part of the internship program for the Bachelor of Science in Civil Engineering (BSCE) under the Department of Civil Engineering in IUBAT−International University of Business Agriculture and Technology. The Dynamic Design and Development (DDD) Ltd. nominated as the organization for the practicum while honorable Prof. Dr. Md. Monirul Islam, Chair of the Department of Civil Engineering rendered his kind consent to academically supervise the internship program.
Super-Structural Construction Work of a Six Storied Residential BuildingShariful Haque Robin
The internship report in broad-spectrum contains ten chapters in which I try to explain my
three-month experience in my hosting company. The content of all chapters is broadly
explained and it is constructed from the practical basis of the site work ended all months
CIVIL ENGINEERING INTERNSHIP REPORT, DETAILED INTERNSHIP REPORT ON A CIVIL ENGINEERING SITE , USEFUL REPORT FOR FRESHER CIVIL ENGINEERS WITH EXTRA ORDINARY DETAILS WITH IMAGES AND CHECK LIST, FOR CIVIL ENGINEERING STUDENTS FOR HOW TO MAKE INTERNSHIP REPORT
Design of G+8 RCC Training Institute & Hostel Blockjeyanthi4
The building is located in seismic zone V and the basic wind speed in this location is 55m/s. The preliminary gravity and lateral load analysis are carried out manually for a typical 2D frame and compared with software results. The member sizes for beams and columns were found out from the preliminary manual analysis and design. 3D finite element modeling was carried out in ETABS for the building. Based on the analytical results (moment, shear force), the member sizes are finalized and design was carried out as per the codes IS 456, SP16, IS 13920. Ductile design and detailing is carried out as per IS 13920 & SP34.
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARERakeshDas161
REPORT ON G+4 RCC HOSTEL BUILDING IN ( SEISMIC ZONE 5 ) ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
PREPARED BY RAKESH DAS AND HIS GROUP
DEPARTMENT OF CIVIL ENGINEERING
GIRIJANANDA CHOWDHURY INSTITUTE OF MANAGEMENT AND TECHNOLOGY GUWAHATI ASSAM
This Report is about civil engineering project done by L&T.This report will be very helpful if u need it for reference for preparing internship report.
Design of G+8 RCC Training Institute & Hostel Blockjeyanthi4
The building is located in seismic zone V and the basic wind speed in this location is 55m/s. The preliminary gravity and lateral load analysis are carried out manually for a typical 2D frame and compared with software results. The member sizes for beams and columns were found out from the preliminary manual analysis and design. 3D finite element modeling was carried out in ETABS for the building. Based on the analytical results (moment, shear force), the member sizes are finalized and design was carried out as per the codes IS 456, SP16, IS 13920. Ductile design and detailing is carried out as per IS 13920 & SP34.
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARERakeshDas161
REPORT ON G+4 RCC HOSTEL BUILDING IN ( SEISMIC ZONE 5 ) ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
PREPARED BY RAKESH DAS AND HIS GROUP
DEPARTMENT OF CIVIL ENGINEERING
GIRIJANANDA CHOWDHURY INSTITUTE OF MANAGEMENT AND TECHNOLOGY GUWAHATI ASSAM
This Report is about civil engineering project done by L&T.This report will be very helpful if u need it for reference for preparing internship report.
A STUDY ON OPERATION AND MAINTENANCE OF UTILITY, FABRIC DYEING, FINISHING, CU...Md. Jaber Ahmed Patwary
This Practicum Report is the result of guidance and support from many respected and honorable
persons. I would like to express my sincere gratitude to these persons as mentioned below.
Firstly, I sincerely would like to pay my gratitude to my supervisor, Dr KMN Sarwar Iqbal,
Professor, Department of Mechanical Engineering for preparing this report.
Also, I would like to pay my gratitude to Engr. Hasan Md. Jubayer, Mechanical Engineer, at
Esquire Knit Composite Limited for his guidance and teaching me the practical aspects of my
internship work.
Secondly, I would like to express my heartfelt thanks to the honorable Prof. Dr. Md. Monirul
Islam, Professor and Chair, Department of Civil Engineering Dean, CEAT of IUBAT.
Thirdly, I sincerely acknowledge the contributions of the honorable Chair of the Department of
Mechanical Engineering Prof. Dr. Engr. A.Z.A. Saifullah.
Finally, I gratefully remember the visionary leadership and contributions of our departed
honorable founder and first Vice Chancellor of IUBAT Late Prof. Dr. M. Alimullah Miyan. I
would like to express my heartfelt thanks to the honorable Vice Chancellor, Prof. Dr. Abdur
Rab of IUBAT for his guidance and leadership.
I also acknowledge the contributions of my faculties at IUBAT, and the staffs and employees of
Esquire Knit Composite Limited for enabling me to complete my practicum report.
ELECTRICITY GENERATION USING STAIRCASE- HARVESTING RENEWABLE ENERGYShubham Patel
The world as we know is continuously exploiting resources in one form or the another. The idea of exploitation and saving has been showcased by many authors. Here, I present this example of harvesting a form of energy which gets exhausted while we do the very needful thing of her everyday life, "We Walk". Yes, when we do walk we are exerting a force on the pavement or the road or the stairs; in short our considerable part of energy gets exhausted. But, if this energy be utilized, saved and harvested for some other cause which in case helps to decrease the level of natural resource exploitation then this can be a boon to the present day world. The report showcases a similar type of an engineering material and its use in some mechanical means to help earth become a better place to live in.
At present scenario, productivity and economics of machining work pieces in large
quantity is greatly affected by use of work holding devices like fixture. To achieve
require accuracy with reduced rework and easy handling, fixtures are provided. This
project is about designing the fixture for pressing bearing inside the crank case. For
this purpose of designing and analysing the modelling software known as solid works is
to be used. The fixture is design mainly to get multiple bearing pressed on crank case
while keeping it stable and to get the accuracy of press within tolerance limit.
This report describes about steam boiler,classification of boiler ,boiler mounting,
boiler accessories, operation & maintenance of boiler, boiler starting & shut downing
systems, and safety operation of boiler. some common problems that occurred during
boiler operation have been also presented in the report along with solutions . Finally
some recommendations are being suggested.
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...ssuser7dcef0
Power plants release a large amount of water vapor into the
atmosphere through the stack. The flue gas can be a potential
source for obtaining much needed cooling water for a power
plant. If a power plant could recover and reuse a portion of this
moisture, it could reduce its total cooling water intake
requirement. One of the most practical way to recover water
from flue gas is to use a condensing heat exchanger. The power
plant could also recover latent heat due to condensation as well
as sensible heat due to lowering the flue gas exit temperature.
Additionally, harmful acids released from the stack can be
reduced in a condensing heat exchanger by acid condensation. reduced in a condensing heat exchanger by acid condensation.
Condensation of vapors in flue gas is a complicated
phenomenon since heat and mass transfer of water vapor and
various acids simultaneously occur in the presence of noncondensable
gases such as nitrogen and oxygen. Design of a
condenser depends on the knowledge and understanding of the
heat and mass transfer processes. A computer program for
numerical simulations of water (H2O) and sulfuric acid (H2SO4)
condensation in a flue gas condensing heat exchanger was
developed using MATLAB. Governing equations based on
mass and energy balances for the system were derived to
predict variables such as flue gas exit temperature, cooling
water outlet temperature, mole fraction and condensation rates
of water and sulfuric acid vapors. The equations were solved
using an iterative solution technique with calculations of heat
and mass transfer coefficients and physical properties.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Forklift Classes Overview by Intella PartsIntella Parts
Discover the different forklift classes and their specific applications. Learn how to choose the right forklift for your needs to ensure safety, efficiency, and compliance in your operations.
For more technical information, visit our website https://intellaparts.com
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
HEAP SORT ILLUSTRATED WITH HEAPIFY, BUILD HEAP FOR DYNAMIC ARRAYS.
Heap sort is a comparison-based sorting technique based on Binary Heap data structure. It is similar to the selection sort where we first find the minimum element and place the minimum element at the beginning. Repeat the same process for the remaining elements.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
Civil Engineering Practicum Report
1. i
Study on Super Structural Construction Work Process of a
Ten Storied Residential Building
Practicum Report
By
Md. Abdullah Al Baki
ID# 15106040
Program: BSCE
IUBAT— International University of Business Agriculture and Technology
4 Embankment Drive Road, Sector-10 Uttara Model Town, Dhaka-1230
20th
December, 2018
2. ii
Study on Super Structural Construction Work Process of a
Ten Storied Residential Building
Practicum Report
by
Md. Abdullah Al Baki
ID No # 15106040
Program: BSCE
Examination Committee
Position Name Signature
Chair, Dept. of Civil Eng. Professor Dr. Md. Monirul Islam
Supervisor Asif Ahmed
Department of Civil Engineering
College of Engineering & Technology (CEAT)
IUBAT—International University of Business Agriculture and Technology
This practicum report is done for the partial fulfillment of requirements for the Bachelor of
Science degree at the IUBAT ̶ International University of Business Agriculture and
Technology Dhaka, Bangladesh
20th
December, 2018
3. iii
Letter of Transmittal
20th
December 2018
Prof. Dr. Md. Monirul Islam
Chair, Department of Civil Engineering
IUBAT- International University of Business Agriculture and Technology
4 Embankment Drive Road, Sector 10, Uttara Model Town, Dhaka-1230
Subject: Submission of practicum report.
Dear Sir,
With due respect, I would like to approach you that it is a great opportunity as well as great
pleasure for me to submit this practicum report titled “Study on Super Structural
Construction Work Process of a Ten Storied Residential Building” for the partial
fulfillment of the requirement of Bachelor of Science & Civil Engineering degree. I have
tried at my level of best to prepare this report according to the required standard. It was certainly
a great opportunity for me to work on this report to actualize my theoretical knowledge in the
practical field.
I express my heart full gratitude to you to go through this report and make your valuable
comments. It would be very kind of you, if you please evaluate my performance regarding this
report.
Thanking you
Yours Faithfully,
_________________
Md. Abdullah Al Baki
ID# 15106040
Department of Civil Engineering
IUBAT- International University of Business Agriculture and Technology
5. v
Student’s Declaration
I am Md. Abdullah Al Baki, a student of IUBAT - International University of Business
Agriculture and Technology, ID# 15106040 declaring that this internship report on “Study on
Super Structural Construction Work Process of a Ten Storied Residential Building” has
only been prepared for the partial fulfilment of the degree Bachelor of Science in Civil
Engineering (BSCE) but not for any other purposes. Rather, it will not be used with the interest
of any other competitors without the proper acclamation of the writer.
_________________
Md. Abdullah Al Baki
ID# 15106040
Department of Civil Engineering
IUBAT- International University of Business Agriculture and Techno
6. vi
Acknowledgements
All Praise and thanks to Almighty Allah who helped me to complete the research work and the
practicum report, leading to Bachelor of Science in Civil Engineering. In the process of
completion of my practicum and preparing this practicum report. I would like to pay my
gratitude to some person for their immense help and enormous cooperation.
First of all, I would like to pay my gratitude to the University authority to permit me for doing
my practicum. In this respect, I would like to mention the name of our respected Chair,
Department of Civil Engineering, Prof. Dr. Md. Monirul Islam for his supervision, helpful
guidance and continuous encouragement to take the necessary activities throughout the period of
this report.
Then I would like to thank to Basic Builders Ltd for giving the opportunity of doing practicum
and generous gratitude to Project Engineer Md. Hasanuzzaman, Assistant Manager Md.
Abdullah Al Mamun and Senior Manager Md. Humayon Kabir at Basic Builders Ltd for
their continuous support at the project site.
Especially, I would like to thank to our honorable teacher Asif Ahmed, Faculty, Department of
Civil Engineering, IUBAT, for his valuable and patient advice, sympathetic assistance,
cooperation, and contribution of new idea which helped me a lot to prepare this report
successfully.
In fine, I am, indeed, grateful to all those from whom I got sincere co-operation and help for the
preparation of this report.
_________________
Md. Abdullah Al Baki
ID# 15106040
Department of Civil Engineering
IUBAT- International University of Business Agriculture and Technology
7. vii
Executive Summary
This report named “Study on Super Structural Construction Work Process of a Ten Storied
Residential Building” is made based on my three months practicum at the ongoing project
named ‘Basic Korobi’ under ‘Basic Builders ltd’. It is a ten storied residential building and
located at Mirpur, Dhaka. I have split this report into some chapters and described them
sequentially. The first chapter of this report is introductory part where I have discussed about the
main objectives of this report. In the second chapter I have discussed about the Company profile
and its mission, vision and Company Organogram. In chapter three I have described about my
project details and the design specifications. In the chapter four I have discussed about the
materials and equipments that used in my project. In chapter five, six, seven I have described
about the construction process of column, beam, slab and stair. I have fully described about the
shuttering works, shuttering estimation, reinforcement estimation, reinforcement placement
works, casting and curing works of those components. Chapter eight is the last chapter of this
report. In this chapter I have discussed about conclusion of report. Things I have learned from
three months of my internship I also discussed about it in chapter eight.
8. viii
Table of Contents
CHAPTER ONE: Introduction..................................................................................... 1
1.1 General..............................................................................................................................1
1.2 Scope of the Study.............................................................................................................1
1.3 Objectives of the Study......................................................................................................2
1.4 Responsibilities..................................................................................................................2
1.5 Limitation of the Study ......................................................................................................2
CHAPTER TWO: Company Profile ............................................................................ 3
2.1 Company Name and Address.............................................................................................3
2.2 Background .......................................................................................................................3
2.3 Company Mission & Vision...............................................................................................4
2.3.1 Mission .......................................................................................................................4
2.3.2 Vision .........................................................................................................................4
2.3.3 Values .........................................................................................................................4
2.3.4 Think...........................................................................................................................4
2.4 Company Organogram.......................................................................................................5
2.5 Requisition Slip .................................................................................................................6
CHAPTER THREE: Project Details & Design Specification ..................................... 7
3.1 Project Details ...................................................................................................................7
3.2 Location of the Project.......................................................................................................8
3.3 Ground Floor Plan of my Project .......................................................................................9
3.4 Typical Floor Plan of my Project .....................................................................................10
3.5 Design Specification........................................................................................................11
3.6 Clear Cover .....................................................................................................................11
3.7 Lap Location....................................................................................................................12
3.8 Required lap Length.........................................................................................................12
3.9 Details about Beam and Columns Tie Bar & Stirrups.......................................................13
CHAPTER FOUR: Construction Materials & Equipments ..................................... 14
4.1 General............................................................................................................................14
4.2 Cement ............................................................................................................................14
4.2.1 Ingredients of Cement ...............................................................................................15
4.2.2 Checking Manufacture Date ......................................................................................15
4.3 Field Test of Cement........................................................................................................16
4.3.1 Color Test .................................................................................................................16
4.3.2 Floating Test .............................................................................................................16
4.3.3 Temperature Test.......................................................................................................17
4.3.4 Adulteration Test.......................................................................................................17
4.4 Comparison between Standard Tests with Field Tests ......................................................18
9. ix
4.5 Bricks ..............................................................................................................................18
4.5.1 Bricks Dimension Check ...........................................................................................19
4.6 Field Test of Brick ...........................................................................................................19
4.6.1 T-Test .......................................................................................................................20
4.6.2 Hardness Test............................................................................................................20
4.6.3 Sound Test ................................................................................................................21
4.7 Comparison between Standard Tests with Field Tests ......................................................21
4.8 Fine Aggregates...............................................................................................................22
4.9 Field Test of Fine Aggregate............................................................................................22
4.9.1 Clay Test...................................................................................................................23
4.9.2 Silt Test.....................................................................................................................23
4.10 Comparison between Standard Tests with Field Tests ....................................................24
4.11 Laboratory Test of Fine Aggregate.................................................................................24
4.11.1 Sieve Analysis of Sylhet Sand .................................................................................24
4.11.2 Sieve Analysis of Local Sand ..................................................................................26
4.12 Comparison between Required value with Test Value....................................................28
4.13 Coarse Aggregate...........................................................................................................28
4.13.1 Stone Chips .............................................................................................................29
4.13.2 Brick Chips .............................................................................................................29
4.14 Laboratory Test of Coarse Aggregate.............................................................................30
4.14.1 Sieve Analysis of Stone Chips .................................................................................30
4.14.2 Sieve Analysis of Brick Chips .................................................................................32
4.15 Comparison between Required value with Test Value....................................................34
4.16 Concrete ........................................................................................................................35
4.17 Concrete Compressive Strength Test..............................................................................35
4.17.1 Concrete Cylinder Crushing (Beam, Slab & Stair) ...................................................36
4.17.2 Concrete Cylinder Crushing (Column).....................................................................38
4.18 Reinforcement Bars .......................................................................................................40
4.19 Field Test of Reinforcement Bars...................................................................................40
4.19.1 Surface checking .....................................................................................................40
4.19.2 Bending Test ...........................................................................................................41
4.19.3 Color Checking .......................................................................................................41
4.20 Comparison between Standard Tests with Field Tests ....................................................42
4.21 Water.............................................................................................................................42
4.22 Block Making ................................................................................................................43
4.23 Formwork Materials.......................................................................................................44
4.23.1 Wooden Planks........................................................................................................44
4.23.2 Wooden Runner ......................................................................................................45
4.23.3 Bamboo Props.........................................................................................................46
4.23.4 Steel Forms .............................................................................................................48
10. x
4.23.5 Nut Bolt & Turn Bolt ..............................................................................................48
4.23.6 Plain Sheet ..............................................................................................................49
4.24 Construction Equipments ...............................................................................................50
4.24.1 Mixture Machine.....................................................................................................50
4.24.2 Vibrator Machine ....................................................................................................50
4.24.3 Roof Hoist...............................................................................................................51
4.24.4 Reinforcement Bar Cutter........................................................................................51
CHAPTER FIVE: Construction of Column............................................................... 52
5.1 General............................................................................................................................52
5.2 About Column .................................................................................................................52
5.3 Column Layout Plan ........................................................................................................52
5.4 Column Schedule.............................................................................................................53
5.5 Construction Work of Column .........................................................................................54
5.6 Column Kicker Work.......................................................................................................54
5.7 Column reinforcement Placing.........................................................................................57
5.7.1 Estimation of Column Reinforcement........................................................................60
5.7.2 Comparison for Column Reinforcement Bars ............................................................63
5.8 Column Shuttering...........................................................................................................64
5.9 Column Casting ...............................................................................................................65
5.9.1 Estimation of Column Casting...................................................................................66
5.10 Column Curing ..............................................................................................................68
5.11 Work Schedule for Column............................................................................................68
CHAPTER SIX: Construction of Beam & Slab......................................................... 69
6.1 General............................................................................................................................69
6.2 About Beam & Slab.........................................................................................................69
6.3 Beam Layout plan............................................................................................................69
6.4 Beam Schedule ................................................................................................................70
6.5 Reinforcement Details for Slab ........................................................................................72
6.6 Construction Work of Beam & Slab.................................................................................73
6.7 Beam and slab shuttering work ........................................................................................73
6.8 Estimation of Shuttering ..................................................................................................75
6.8.1 Estimation of Wooden Planks for Beam ....................................................................75
6.8.2 Estimation of Wooden Runners for Beam..................................................................77
6.8.3 Estimation of Bamboos for Beam..............................................................................79
6.8.4 Estimation of Wooden Planks for Slab ......................................................................80
6.8.5 Estimation of Wooden Runners for Slab....................................................................80
6.8.6 Estimation of Bamboos for Slab ................................................................................81
6.8.7 Estimation of Plain Sheet for Slab .............................................................................82
6.9 Beam & Slab Reinforcement Placing ...............................................................................83
6.9.1 Reinforcement placing of Beam.................................................................................83
11. xi
6.9.2 Estimation of Beam Reinforcement ...........................................................................86
6.9.3 Comparison for Beam Reinforcement Bars................................................................92
6.9.4 Reinforcement placing of Slab...................................................................................93
6.9.5 Estimation of Slab Reinforcement .............................................................................95
6.9.6 Comparison for Slab Reinforcement Bars..................................................................99
6.10 Beam & Slab Casting...................................................................................................100
6.10.1 Estimation of Beam & Slab Casting.......................................................................102
6.11 Slab Curing Work........................................................................................................105
6.12 Beam & Slab De-Shuttering.........................................................................................105
6.13 Work Schedule for Beam & Slab .................................................................................106
CHAPTER SEVEN: Construction of Stair .............................................................. 107
7.1 General..........................................................................................................................107
7.2 About Stair ....................................................................................................................107
7.3 Stair Layout Plan ...........................................................................................................107
7.4 Stair Reinforcement Details ...........................................................................................108
7.5 Construction Work of Stair ............................................................................................109
7.6 Stair shuttering work......................................................................................................109
7.7 Estimation of Shuttering ................................................................................................110
7.7.1 Estimation of Wooden Planks for Stair ....................................................................110
7.7.2 Estimation of Wooden Runners for Stair .................................................................111
7.7.3 Estimation of Bamboos for Stair..............................................................................112
7.8 Stair Reinforcement Placing...........................................................................................112
7.9 Tread & Riser Placing....................................................................................................114
7.10 Stair Casting ................................................................................................................115
7.10.1 Estimation of Stair Casting ....................................................................................116
7.11 Stair Curing Work........................................................................................................119
7.12 Work Schedule for Stair...............................................................................................119
CHAPTER EIGHT: Conclusion............................................................................... 120
8.1 General..........................................................................................................................120
8.2 Knowledge Development...............................................................................................120
8.3 Conclusion.....................................................................................................................120
8.4 References .....................................................................................................................121
12. xii
List of Figures
Figure 2.1: Company Logo..........................................................................................................3
Figure 2.2: Company Organogram ..............................................................................................5
Figure 2.3: Requisition Slip.........................................................................................................6
Figure 3.1: 3D View of the Building ...........................................................................................7
Figure 3.2: Project Location ........................................................................................................8
Figure 3.3: Map...........................................................................................................................8
Figure 3.4: Ground Floor Plan.....................................................................................................9
Figure 3.5: Typical Floor Plan...................................................................................................10
Figure 3.6: Tie & Stirrup of Beam & Column ...........................................................................13
Figure 4.1: Shah Cement...........................................................................................................14
Figure 4.2: Percentage of Cement..............................................................................................15
Figure 4.3: Manufacture Date of Cement...................................................................................15
Figure 4.4: Color Test of Cement ..............................................................................................16
Figure 4.5: Floating Test of Cement ..........................................................................................16
Figure 4.6: Temperature Test of Cement ...................................................................................17
Figure 4.7: Adulteration Test of Cement....................................................................................17
Figure 4.8: Brick .......................................................................................................................18
Figure 4.9: Measuring Brick size...............................................................................................19
Figure 4.10: T-Test of Brick......................................................................................................20
Figure 4.11: Hardness Test of Brick ..........................................................................................20
Figure 4.12: Sound Test of Brick...............................................................................................21
Figure 4.13: Sylhet Sand ...........................................................................................................22
Figure 4.14: Local Sand ............................................................................................................22
Figure 4.15: Clay Test of Cement..............................................................................................23
Figure 4.16: Silt Test of Cement................................................................................................23
Figure 4.17: Sieve Analysis of Sylhet Sand ...............................................................................24
Figure 4.18: Sieve Analysis graph of Sylhet Sand .....................................................................25
Figure 4.19: Sieve Analysis of Local Sand ................................................................................26
Figure 4.20: Sieve Analysis graph of Local Sand ......................................................................27
Figure 4 21: Stone Chips...........................................................................................................29
Figure 4.22: Brick Chips ...........................................................................................................29
Figure 4.23: Sieve Analysis of Stone Chips...............................................................................30
Figure 4.24: Sieve Analysis graph of Stone Chips .....................................................................32
Figure 4.25: Sieve Analysis of Brick Chips ...............................................................................32
Figure 4.26: Sieve Analysis graph of Brick Chips .....................................................................34
Figure 4.27: Making Cylinder Block .........................................................................................35
Figure 4.29: Concrete Compressive Test (Beam, Slab & Stair)..................................................36
13. xiii
Figure 4.30: Concrete Compressive Test Result (Beam, Slab & Stair) .......................................36
Figure 4.31: Comparison Between Actual & Design Concrete Compressive Strength................37
Figure 4.32: Concrete Compressive Test (Column) ...................................................................38
Figure 4.33: Concrete Compressive Test Result (Column).........................................................38
Figure 4.34: Comparison Between Actual & Design Concrete Compressive Strength................39
Figure 4.35: Reinforcement Bars...............................................................................................40
Figure 4.36: Surface of the Bar..................................................................................................40
Figure 4.37: Bending a Bar .......................................................................................................41
Figure 4.38: Checking Fragment of Bar.....................................................................................41
Figure 4.39: Bar Color Checking...............................................................................................41
Figure 4.40: Water ....................................................................................................................42
Figure 4.41: Block Casting........................................................................................................43
Figure 4.42: The Blocks ............................................................................................................43
Figure 4.43: Measuring Blocks..................................................................................................43
Figure 4.44: Wooden Planks .....................................................................................................44
Figure 4.45: Wooden Planks Width...........................................................................................44
Figure 4.46: Wooden Planks Thickness.....................................................................................44
Figure 4.47: Wooden Runners...................................................................................................45
Figure 4.48: Wooden Runner Width..........................................................................................45
Figure 4.49: Wooden Runner Thickness....................................................................................45
Figure 4.50: Bamboo Props.......................................................................................................46
Figure 4.51: Measuring Bamboo Props......................................................................................46
Figure 4.52: Steel Forms ...........................................................................................................48
Figure 4.53: Nut Bolt ................................................................................................................48
Figure 4.54: Turn Bolt...............................................................................................................48
Figure 4.55: Plain Sheet ............................................................................................................49
Figure 4.56: Measuring Plain Sheet...........................................................................................49
Figure 4.57: Mixture Machine...................................................................................................50
Figure 4.58: Vibrator Machine ..................................................................................................50
Figure 4.59: Roof Hoist.............................................................................................................51
Figure 4.60: Reinforcement Cutter ............................................................................................51
Figure 5.1: Layout of Column ...................................................................................................52
Figure 5.2: Column Schedule ....................................................................................................53
Figure 5.3: Making Shuttering for Column Kicker ....................................................................54
Figure 5.4: Measuring Column Kicker ......................................................................................55
Figure 5.5: Column Kicker Casting ...........................................................................................56
Figure 5.6: Checking Kicker Height ..........................................................................................56
Figure 5.7: Reinforcement Bars Placing ....................................................................................57
Figure 5.8: Binding Tie with Main Bar......................................................................................57
Figure 5.9: Checking Clear Cover of Column...........................................................................58
14. xiv
Figure 5.10: Checking Reinforcement Bar of Column ...............................................................58
Figure 5.11: Checking Spacing of tie Bars in Middle.................................................................59
Figure 5.12: Checking Spacing of tie Bars in bottom of Column ...............................................59
Figure 5.13: Comparison of Reinforcement Bars (kg) Used in Column .....................................63
Figure 5.14: Making column Shuttering ....................................................................................64
Figure 5.15: Column Casting.....................................................................................................65
Figure 5.16: Comparison of Casting Materials for Column........................................................67
Figure 5.17: Column Curing......................................................................................................68
Figure 5.18: Column Work Schedule.........................................................................................68
Figure 6.1: Layout of Beam.......................................................................................................69
Figure 6.2: Beam Schedule........................................................................................................71
Figure 6.3: Slab Reinforcement Details .....................................................................................72
Figure 6.4: Making Beam Shuttering.........................................................................................73
Figure 6.5: Beam Shuttering......................................................................................................74
Figure 6.6: Bamboo Props.........................................................................................................74
Figure 6.7: Slab Shuttering........................................................................................................74
Figure 6.8: Measuring Beams Size & Depth..............................................................................74
Figure 6.9: Comparison between Actual and estimated number of Bamboo for Beam ...............79
Figure 6.10: Comparison between Actual and estimated number of Bamboo for Slab................81
Figure 6.11: Reinforcement Bars of the Beam...........................................................................83
Figure 6.12: Workers are Placing Reinforcement of Beam ........................................................84
Figure 6.13: Measuring Lapping length of Beam.......................................................................84
Figure 6.14: Location of the Lapping Length.............................................................................84
Figure 6.15: Measuring Extra Top Bar of Beam ........................................................................85
Figure 6.16: Measuring Development Length & Stirrup Hook Length.......................................85
Figure 6.17: Measuring Stirrup Spacing in the middle & side of the Beam ................................85
Figure 6.18: Comparison of Reinforcement Bars (kg) Used in Column .....................................92
Figure 6.19: Placing Reinforcement of Slab ..............................................................................93
Figure 6.20: Reinforcement of Slab Placing Complete ..............................................................93
Figure 6.21: Measuring Crank Length.......................................................................................94
Figure 6.22: Measuring Spacing of Top Bars.............................................................................94
Figure 6.23: Measuring Spacing of Bottom Bars .......................................................................94
Figure 6.24: Number of Panel in Slab........................................................................................96
Figure 6.25: Comparison of Reinforcement Bars (kg) for Slab in Long Direction......................99
Figure 6.26: Comparison of Reinforcement Bars (kg) for Slab in Short Direction......................99
Figure 6.27: Slab & Beam Casting ..........................................................................................100
Figure 6.28: Mixer Machine Used for Mixing Concrete ..........................................................100
Figure 6.29: Using Vibrator for Compaction of Concrete ........................................................101
Figure 6.30: Concrete Leveling Process of Slab Surface..........................................................101
Figure 6.31: Using Roof Hoist.................................................................................................101
15. xv
Figure 6.32: Comparison of Casting Materials for Beam & Slab .............................................104
Figure 6.33: Curing Work of Slab ...........................................................................................105
Figure 6.34: De-Shuttering of Beam & Slab ............................................................................105
Figure 6.35: Beam & Slab Work Schedule ..............................................................................106
Figure 7.1: Stair Plan...............................................................................................................107
Figure 7.2: Stair Plan with Reinforcement Details ...................................................................108
Figure 7.3: Workers were Making Shuttering ..........................................................................109
Figure 7.4: Shuttering of Waist Slab........................................................................................109
Figure 7.5: Waist Slab Sides Wood .........................................................................................110
Figure 7.6: Bamboo Props Supporting Runners.......................................................................110
Figure 7.7: Placing reinforcement Bar of Stair.........................................................................112
Figure 7.8: Bar Details of Stair (Landing) ...............................................................................113
Figure 7.9: Bar Details of Stair (Waist Slab)............................................................................113
Figure 7.10: Steps of Stair.......................................................................................................114
Figure 7.11: Measuring Vertical & Horizontal Adjustment......................................................114
Figure 7.12: Checking Tread Height........................................................................................115
Figure 7.13: Checking Riser Width .........................................................................................115
Figure 7.14: Stair Casting........................................................................................................115
Figure 7.15: Comparison of Casting Materials for Stair...........................................................118
Figure 7.16: Curing Work of Stair...........................................................................................119
Figure 7.17: Stair Work Schedule............................................................................................119
16. xvi
List of Table
Table 3.1: My project Details ......................................................................................................7
Table 3.2: Lapping Length of Bars ............................................................................................12
Table 4.1: Percentage of Ingredients in Cement.........................................................................15
Table 4.2: Comparison between Standard Tests with Field Tests...............................................18
Table 4.3: Dimension of Bricks.................................................................................................19
Table 4.4: Comparison between Standard Tests with Field Tests...............................................21
Table 4.5: Materials Mixing Amount.........................................................................................22
Table 4.6: Comparison between Standard Tests with Field Tests...............................................24
Table 4.7: Sieve Analysis of Sylhet Sand ..................................................................................25
Table 4.8: Sieve Analysis of Local Sand ...................................................................................26
Table 4.9: Comparison between Required Values with Test Value ............................................28
Table 4.10: Materials Mixing Amount.......................................................................................28
Table 4.11: Sieve Analysis of Stone Chips ................................................................................31
Table 4.12: Sieve Analysis of Brick Chips ................................................................................33
Table 4.13: Comparison between Required Values with Test Value ..........................................34
Table 4.14: Data of Actual and Design Concrete Compressive Strength ....................................37
Table 4.15: Data of Actual and Design Concrete Compressive Strength ....................................39
Table 4.16: Comparison between Standard Tests with Field Tests.............................................42
Table 4.17: Bamboos Diameter .................................................................................................47
Table 5.1: Column Design Specifications..................................................................................53
Table 5.2: Shuttering of Column Kicker....................................................................................55
Table 5.3: Estimation of Column Reinforcement According to the Drawing..............................61
Table 5.4: Estimation of Column Reinforcement that Used in the Field.....................................62
Table 5.5: Comparison of Column Reinforcement.....................................................................63
Table 5.6: Estimation of Steel Shuttering of Column.................................................................64
Table 5.7: Estimation of the Casting Materials of Column.........................................................66
Table 5.8: Comparison of Casting Materials for Column...........................................................67
Table 6.1: Estimation of Beams Bottom Wooden Plank ............................................................75
Table 6.2: Estimation of Beams sides Wooden Plank ................................................................76
Table 6.3: Estimation of Beams sides Wooden Runners ............................................................77
Table 6.4: Estimation of Beams Bottom Wooden Runners ........................................................78
Table 6.5: Estimation of Bamboos for Beams............................................................................79
Table 6.6: Estimation of Slab Wooden Planks ...........................................................................80
Table 6.7: Estimation of Slab Wooden Runners.........................................................................80
Table 6.8: Estimation of Bamboos for Slab ...............................................................................81
Table 6.9: Adding Lap length with Beams Main Bar .................................................................86
Table 6.10: Estimation of Beam Reinforcement According to the Drawing ...............................89
17. xvii
Table 6.11: Estimation of Beam that Used in the Field ..............................................................91
Table 6.12: Comparison of Beam Reinforcement ......................................................................92
Table 6.13: Estimation of Beam Reinforcement in Short Direction............................................97
Table 6.14: Estimation of Beam Reinforcement in Long Direction............................................98
Table 6.15: Estimation of the Casting Materials of Slab ..........................................................102
Table 6.16: Estimation of the Casting Materials of Beam ........................................................103
Table 6.17: Comparison of Casting Materials for Beam & Slab...............................................104
Table 7.1: Estimation of Stair Flight sides Wooden Planks......................................................110
Table 7.2: Estimation of Stair Flight Bottoms (Waist Slab) Wooden Planks ............................110
Table 7.3: Estimation of Stair Landing Wooden Planks...........................................................111
Table 7.4: Estimation of Stair Flight sides Wooden Runners ...................................................111
Table 7.5: Estimation of Stair Flight Bottoms & Landing Wooden Planks...............................111
Table 7.6: Estimation of Stairs Bamboo Props.........................................................................112
Table 7.7: Estimation of Reinforcement of Waist Slab for Stair...............................................113
Table 7.8: Estimation of the Casting Materials of Stair............................................................117
Table 7.9: Comparison of Casting Materials for Stair ..............................................................118
18. 1
CHAPTER ONE:
Introduction
1.1 General
Each and every students need to learn practical knowledge about his expert department. It is also
required to know theoretical knowledge about his expert fields. The internship is the bridge
between the theoretical knowledge and the practical knowledge at the field of civil engineering
work. And a practicum report is the storage of information which one did during of his training
period at the particular project. In my practicum period I got the chance to observe a super
structural construction project which is a 10th storied residential building under the Basic
Builders Ltd. As a civil engineering student it was a great opportunity for me to work in a
construction project. As a trainee engineer, I joined there. In that time I learned about
construction process and structural components of a residential building. I worked there around
three months. In that period I learned about many things. Such as, there I learned about
construction components like beam, column, slab and stair etc. I also learned about construction
process of those components also I got know about construction materials and their properties. I
also learned about design speciation, estimation of materials and detailed drawing in the field. I
am going to describe about all of those things in this report.
1.2 Scope of the Study
For me it is a great opportunity that I was doing my internship in a leading developer company
like Basic Builders Ltd. As a trainee engineer, I joined there. In the practical field I got the
chance to monitor a super structural construction work process. On my practicum time I tried to
apply my theoretical knowledge in practical field which I have acquired from my University. I
have got lots of knowledge about construction materials and equipments from there which before
I did not know. In my project I worked with the engineer, contractor, labors and collect
information on building construction which will be effective for my future career.
19. 2
1.3 Objectives of the Study
The main objective of my internship was to understand the construction work which was done in
practical field. Some specifics objectives are follows:
– To understand the structural drawing and its application
– To learn about structural elements and its construction process
– To know about project engineer’s task
– To compare the actual data with practical data according to the drawing
– To learn how to deal with supervisor, engineer, contractor and labours
– To learn how to manage the construction work
– To collect practical knowledge of construction work
1.4 Responsibilities
As a trainee engineer, I have some responsibilities. The responsibilities are as follow:
– Monitoring the construction work at the site
– Ensuring the safety matters for labours
– Monitoring the casting and curing work
– Catching the instant mistakes of workers
– Oversee the whole construction work
– Gaining proper knowledge to solve problem
– Ensuring the mixture ratio according to the design
– Checking the spacing, clear cover of beam, column
1.5 Limitation of the Study
In my site I got only the super structural work. I did not get the work of sub structural work like
as soil taste, pile cap, mat, retaining wall and grade beam. That’s why I could not include those
parts in my report. There was also no work schedule or bar chat in the construction site. In my
internship I only got three months and it is not possible to gather all things about building
construction in three month months.
20. 3
CHAPTER TWO:
Company Profile
2.1 Company Name and Address
Figure 2.1: Company Logo
Name of the Firm : Basic Builders Ltd.
Address : House- 06, Road-16/A, Gulshan-1, Dhaka
Phone : +880-8833249, 9859218, Ext-108
Fax : +880-9849246, Ext-107
E-mail : sales@basicbuildersltd.com
Industry : Real Estate/Developers
Website : http://www.basicbuildersltd.com
2.2 Background
Basic Builders Limited started its journey 2005,vits date of inception 28.12.2005, Founder
Managing Director Engr. Abdul Latif B.Sc.Engg. (Civil) & Chairman Farhana Yasmin and its
maiden company Best Builders & Designer. Basic Builders Limited is a fast growing
organization in the Real Estate development sector. It has vast and excellent working experience
in exclusive apartment projects at prime location of Dhaka City. Their main view is to construct
and develop high quality residential buildings.
They have 36 nos ongoing project, 60 nos completed project & 12 nos upcoming Project in
different prime location of Dhaka city. Also the 100 plus professional human resources in their
different working team for maintaining their quality and customer satisfaction which is the core
strength in their organization.
21. 4
2.3 Company Mission & Vision
2.3.1 Mission
Best Product
Best commitment
Best Service
Best Friendship
Best partnership
2.3.2 Vision
To have the reputation to be the contractor of choice committed to achieving the highest level of
quality and performance through dedication and become the most successful and respected
construction company in Bangladesh through hard work, ethical business Practices and
philanthropic endeavors. Client's need and our design and the relationship between them are
fundamental and the establishment of a professional and trusting relationship between the two is
the bedrock of every successful projects. The commercial sector demands buildings that are rapid
to construct, of high quality, flexible and adaptable in application, and energy efficient in use.
2.3.3 Values
They are working in Real Estate Development sector more than 10 years successfully and
gathered customer confidence by our sound ethics in our professional work of business.
2.3.4 Think
They are always committed to update their policy to fulfill customer needs, demand and
satisfaction by our activities in the future Real Estate Market of Bangladesh.
22. 5
2.4 Company Organogram
Figure 2.2: Company Organogram
Chairman
Managing
Director
Director
Marketing
Manager
Marketing
Marketing
Executive
Manager
Procurement
Procurement
Executive
Director Finanace
& Administration
Manager
Accounts
Executive
Accounts
Administrative
Officer
Office
Executive
Director
Technical
Chief
Engineer
Project
Coordinator
Project
Engineer
Deputy
Project
Engineer
Junior
Project
Engineer
Trainee
EngineerMy Position
24. 7
CHAPTER THREE:
Project Details & Design Specification
3.1 Project Details
Project
Name:
Basic Korobi 3D View
Address: Plot #02, Block #A, Avenue-
2, Section #11, Pallabi,
Mirpur, Dhaka
Building
Storied:
(G+9) = 10 Storied
Apartment
Size:
1250 sft
Building
Facings:
North facing
Apartment
Details:
Each floor of the building
will be two flats and each
flat have 3 bad, living,
dining kitchen, 3 bathroom,
and varandahs.
Ground
Floor
Details:
Guard room, drivers waiting
room, power room, generator
room, wash room, 14 nos car
parking etc
Engineer: Md. Ali Ahmed Mondol
B.Sc. Engg. (Civil) MIEB
Handover
Date
May 2020
Table 3.1: My project Details
Figure 3.1: 3D View of the Building
25. 8
3.2 Location of the Project
Figure 3.2: Project Location
Figure 3.3: Map
Project location
28. 11
3.5 Design Specification
1. Foundation has been design ass per soil test report.
2. M.S deformed bar (BILLET) with yield strength fy = 72,500 psi (500 grade) should be
used & should be confirmed by laboratory test.
3. Concrete mix ratio should be 1:1.25:2.5 for column (ground floor) only.
4. Concrete mix ratio should be 1:1.5:3 to get concrete crushing strength (cylinder test) f’y
= 3500 psi beside it should be confirmed by mix design method in testing laboratory for
column (1st
to 9th
floor) only
5. Concrete mix ratio should be 1:2:4 to get concrete crushing strength (cylinder test) f’y =
3000 psi beside it should be confirmed by mix design method in testing laboratory for
footing / pile cap only.
6. Concrete mix ratio should be 1:2:4 to get concrete crushing strength (cylinder test) f’y =
2800 psi beside it should be confirmed by mix design method in testing laboratory for
other R.C.C works, where not mentioned.
7. Concrete mix ratio should be 1:2:3.5 to get concrete crushing strength (cylinder test) for
U.G.W.R & O.H.W.R only.
8. Stone chips should be used in column and footing / pile cap, best quality picked jhama
brick chips should be used in other R.C.C works including basement floor slab &
retaining wall.
9. Water / cement ratio should be 0.5 by weight of cement and slump value 2-3.
10. Coarse sand (Sylhet) & fine sand (Local) ratio should be 2:1.
11. Best quality local cement should be used.
12. No change of drawing should be made without concerned design Engineer & Architect.
3.6 Clear Cover
A. In Foundation
(1) Top & Bottom - 3″
(2) Side - 3″
B. In Grade Beam
(1) Top, Bottom & Side - 3″
C. In Column
(2) Above G.B – 1.5″
(3) Up to G.B – 3″
D. In Beams
(1) Top, Bottom & Side - 1.5″
E. In Slab, Stair & Sunshade
(2) Top – 0.75″
(3) Bottom - 1″
29. 12
3.7 Lap Location
a) For beam bottom bar, lap not to be provided at middle third zone of the span.
b) For beam top bar, lap may be provided at middle third zone of the span.
c) Not more than 50%of the bars shall be spliced at one placed.
d) Lap splices are to be confined by hoops with maximum spacing or pitch of d/4 or 4″
where d is the effective depth of the beam.
3.8 Required lap Length
Unless otherwise mentioned in the drawing, lap length of bars shall be:
Bar Dia (mm)
Tension (in)
(beam, all types of slab, stair,
retaining wall etc bars)
Compression (in)
(column & shear wall bars)
10 ϕ 12 12
12 ϕ 16 14
16 ϕ 21 17
20 ϕ 25 22
22 ϕ 28 25
25 ϕ 32 27
Table 3.2: Lapping Length of Bars
30. 13
3.9 Details about Beam and Columns Tie Bar & Stirrups
Figure 3.6: Tie & Stirrup of Beam & Column
31. 14
CHAPTER FOUR:
Construction Materials & Equipments
4.1 General
In this project, I have observed different types of materials and equipments that used in
construction work. In this chapter I have discussed about those materials that used in
construction and field test and laboratory test of those materials. I have also discussed about
equipments that used in the construction.
4.2 Cement
Cement is commonly used as a binder that sets and hardens independently and can bind other
materials together. In my site Portland composite cement was used. The name of the cement that
used in my site is ‘Shah Cement’.
Figure 4.1: Shah Cement
32. 15
4.2.1 Ingredients of Cement
Percentage of Ingredients in cement is given below by table:
SL Ingredients Percent of Ingredients
01 Clinker 65-79%
02 Slag, Fly Ash, Lime Stone 21-35%
03 Gypsum 0-5%
Table 4.1: Percentage of Ingredients in Cement
Figure 4.2: Percentage of Cement
4.2.2 Checking Manufacture Date
The manufacture date of the cement was October, 2018
Figure 4.3: Manufacture Date of Cement
October, 2018
33. 16
4.3 Field Test of Cement
It is necessary to check the physical components of cement in every project. On my project I
checked the color test, floating test, temperature test and adulteration test.
4.3.1 Color Test
The color of cement should be uniform and grey color with a light greenish shade. I took some
amount of cement from the cement bag for checking the color it was uniform and grey. So we
can say that the cement was suitable for use.
Figure 4.4: Color Test of Cement
4.3.2 Floating Test
I took a bucket and filled water into it. Then I took some cement in my hand and thrown it into
the water. When I threw some amount of cement into the water it had taken some time to sink.
So we can say that the cement was good.
Figure 4.5: Floating Test of Cement
34. 17
4.3.3 Temperature Test
For testing temperature of the cement I thrust my hand into the cement bag. I felt that the
temperature was cool. So the cement’s quality was good.
Figure 4.6: Temperature Test of Cement
4.3.4 Adulteration Test
For the adulteration test I took some amount of cement in between my figure and rubbed it. The
cement was smooth. So we can say that the cement was good.
Figure 4.7: Adulteration Test of Cement
35. 18
4.4 Comparison between Standard Tests with Field Tests
Comparisons between standard tests with field tests of cement are given below:
SL Standard Result Field Test Result Remarks
01 Cement color should be grey with
a light greenish shade
The color was grey with a light
greenish shade
Good
02 Temperature should be cool Temperature was cool
03 Cement should be sinks into the
water for a while
It sank into the water for a while
04 Cement should be smooth Cement was smooth
Table 4.2: Comparison between Standard Tests with Field Tests
4.5 Bricks
In my site bricks were brought for making chips out of it by crushing. It was done by the
machine. Those bricks were irregular in shape. Bricks chips were used in beam, slab and stair
case casting as a material. In my site bricks were also used for partition wall which was regular
in shape and uniform in size.
Figure 4.8: Brick
36. 19
4.5.1 Bricks Dimension Check
The standard size for bricks is 9.5" x 4.5" x 2.75". From my site I have collected 10 bricks for
checking its dimension.
Figure 4.9: Measuring Brick size
Those 10 bricks that I have measured in my site are given below:
SL Standard Size Actual Size Average Size Remarks
01.
9.5"×4.5"×2.75"
9.47"×4.5"×2.76"
9.49"×4.48"×2.74" OK
02. 9.5"×4.45"×2.7"
03. 9.48"×4.4"×2.72"
04. 9.5"×4.5"×2.76"
05. 9.5"×4.5"×2.75"
06. 9.5"×4.46"×2.75"
07. 9.5"×4.5"×2.75"
08. 9.45"×4.5"×2.76"
09. 9.5"×4.45"×2.73"
10. 9.45"×4.5"×2.73"
Table 4.3: Dimension of Bricks
4.6 Field Test of Brick
In my site I have done some field tests of bricks for checking its quality. I have done T-test,
hardness test and sound test of bricks. Descriptions are given below:
37. 20
4.6.1 T-Test
Firstly I took two bricks from my site and formed those two bricks into T-shape. Then I dropped
that T-shape bricks into surface from 6 ft height. The brick was broke. So the bricks failed this
test.
Figure 4.10: T-Test of Brick
4.6.2 Hardness Test
I took a brick from my site and try to scratch on the surface of that brick by my nail. I have tried
many times but couldn’t do it. So it proved that the brick was good.
Figure 4.11: Hardness Test of Brick
38. 21
4.6.3 Sound Test
From my site I took two bricks on my hand. Then I hit one brick with another and got metallic
sound. I also done this test with hammer and got metallic sound. This sound proved that the
bricks were good.
Figure 4.12: Sound Test of Brick
4.7 Comparison between Standard Tests with Field Tests
Comparisons between standard tests with field tests of bricks are given below:
SL Standard Result Field Test Result Remarks
01 Brick sound be metallic It produced metallic sound
Pass
02 Scratch should not be done on its
surface.
Couldn’t scratch on its surface
03 Brick should not be break Brick was broke Fail
Table 4.4: Comparison between Standard Tests with Field Tests
39. 22
4.8 Fine Aggregates
In our country most of the construction projects were used local and sylhet sand as a fine
aggregate. Find aggregates that used in my site are also sylhet sand and local sand.
Figure 4.13: Sylhet Sand Figure 4.14: Local Sand
During different RCC works, mixing amount of aggregates that used in my site are given below:
Item Fine Aggregate
Beam 66.6% Sylhet sand used 33.3% Local sand used
Slab 66.6% Sylhet sand used 33.3% Local sand used
Stair Case 66.6% Sylhet sand used 33.3% Local sand used
Column 100% Sylhet sand used Local sand not used
Shear Wall 100% Sylhet sand used Local sand not used
Table 4.5: Materials Mixing Amount
4.9 Field Test of Fine Aggregate
Sand is the fine aggregate which define that it will pass through a 4 no sieve. In my site I have
done mainly two test of sand and that were clay and silt test of sand. Field test was doing on
project which ensures the quality of sand.
40. 23
4.9.1 Clay Test
I took some amount of sand from my site. Then I found a bucket with fresh water. I threw that
amount of sand into that bucket of water. Then I mixed the water with my hand. After some
while I did not get any color that represents clay. So we can say that the sand was good.
Figure 4.15: Clay Test of Cement
4.9.2 Silt Test
I took some sand on my hand and rubbed it and observed for some times to find silt in that sand.
I couldn’t see any silt. So we can say that the sand was suitable to use for any constructions.
Figure 4.16: Silt Test of Cement
41. 24
4.10 Comparison between Standard Tests with Field Tests
Comparisons between standard tests with field tests of sand are given below:
SL Standard Result Field Test Result Remarks
01 Sand should be clay free It was clay free
Good
02 Sand should be silt free It was silt free
Table 4.6: Comparison between Standard Tests with Field Tests
4.11 Laboratory Test of Fine Aggregate
The Fineness Modulus of the aggregates is found out by the sieve analysis. By doing sieve
analysis we can found the actual quality of fine aggregate. That’s why laboratory test is
important. I have collected the materials of fine aggregate both sylhet sand and Local sand from
my site and done sieve analysis test in our University Lab.
4.11.1 Sieve Analysis of Sylhet Sand
I took 1000 gm of dry Sylhet sand and measuring it by digital scale for doing the sieve analysis.
Then I organized the US standard sieve plate in ascending order. I kept the sample into the upper
sieve plate and shook it properly for few minutes. Then I took the measurements of the retained
sample. Lastly I calculated the fineness modulus of that sample.
Figure 4.17: Sieve Analysis of Sylhet Sand
42. 25
Total Weight = 1000 gm Lose = 1 gm
Sieve No. Sieve Size
(mm)
Retained
Weight (gm)
% Retained Cumulative
% Retained
% Finer
#4 4.75 0 0 0 100
#8 2.38 41 4.1 4.1 95.9
#16 1.19 170 17.02 21.12 78.88
#30 0.595 366 36.64 57.35 42.65
#50 0.297 342 34.25 91.58 8.42
#100 0.149 56 5.61 97.19 2.81
Pan - 24 2.4 99.89 0.11
Total=999 gm
Table 4.7: Sieve Analysis of Sylhet Sand
FM = (∑Cumulative percent retained) / 100
FM = (0+4.1+21.12+57.35+91.58+97.19)/100
FM = 271.34/100
FM = 2.71
Comment:
After sieve analysis I got the value 2.71 and according to the design specification, F.M value of
fine aggregates must be minimum 2.5. So, it was ok.
Figure 4.18: Sieve Analysis graph of Sylhet Sand
100
95.9
78.88
42.65
8.422.81
0
10
20
30
40
50
60
70
80
90
100
Sieve Size (mm)
%Finer
particle size distribution Curve
43. 26
4.11.2 Sieve Analysis of Local Sand
For doing sieve analysis of local sand I follow same procedure. First I took 1000 gm of dry local
sand and measured it by digital scale. Then I organized the US standard sieve plate in ascending
order. I kept the sample into upper sieve and shook it properly for few minutes. Then I took the
measurements of the retained sample. Lastly I calculated the fineness modulus of that sample.
Figure 4.19: Sieve Analysis of Local Sand
Total Weight = 1000 gm Lose = 3 gm
Sieve No. Sieve Size
(mm)
Retained
Weight (gm)
% Retained Cumulative
% Retained
% Finer
#4 4.75 0 0 0 100
#8 2.38 0 0 0 100
#16 1.19 0 0 0 100
#30 0.595 28 2.80 2.80 97.2
#50 0.297 784 78.63 81.43 18.57
#100 0.149 132 13.24 94.67 5.33
Pan - 53 5.33 100 0
Total=997 gm
Table 4.8: Sieve Analysis of Local Sand
44. 27
FM = (∑Cumulative percent retained) / 100
FM = (0+0+0+2.80+81.43+94.67)/100
FM = 178.9/100
FM = 1.79
Comment:
After sieve analysis I got the value 1.79 and according to the design specification, F.M value of
fine aggregates must be minimum 2.5. But in my site, the project engineer told me that they used
67% of the sylhet sand and 33% of the local sand. That’s why we have to find combined FM of
both sands.
Figure 4.20: Sieve Analysis graph of Local Sand
Combined F.M calculation:
Fcom = ((1000 x 2.71) + (1000 x 1.79)) / (1000+1000)
= 2.25
Comment:
F.M values of fine aggregates must be minimum 2.5 in the design specification. But after the
combined FM calculation I got the result 2.36. So it is under the deign value.
100100100
97.2
18.57
5.33
0
10
20
30
40
50
60
70
80
90
100
Sieve Size (mm)
%Finer
particle size distribution Curve
45. 28
4.12 Comparison between Required value with Test Value
Comparison between required values with test value of fine aggregate is given below:
SL Fine Aggregate Test Value Required Value
1. FM of sylhet sand I got the value 2.71
FM value must be
minimum 2.52. Combined FM calculation I got the value 2.36
Table 4.9: Comparison between Required Values with Test Value
4.13 Coarse Aggregate
Coarse aggregates materials that used in my site are also stone chips and brick chips.
During different RCC works, mixing amount of aggregates that used in my site are given below:
Item Coarse Aggregate
Beam Stone Chips not used Brick Chips not used
Slab Stone Chips not used Brick Chips used
Stair Case Stone Chips not used Brick Chips used
Column Stone Chips used Brick Chips not used
Shear Wall Stone Chips used Brick Chips not used
Table 4.10: Materials Mixing Amount
46. 29
4.13.1 Stone Chips
Stone chips are commonly formed by the breaking of large stones into small particles. In my site
stone chips used for column, lift Shear wall, foundation and grade beam casting.
Figure 4 21: Stone Chips
4.13.2 Brick Chips
Brick chips were formed by breaking of bricks into smaller particles. In my site brick chips used
for beam, slab and stair casting.
Figure 4.22: Brick Chips
47. 30
4.14 Laboratory Test of Coarse Aggregate
The fineness modulus test of coarse aggregate is as important as the fineness modulus test of fine
aggregate. To find the actual quality of coarse aggregate we have done sieve analysis test. I have
collected the materials of coarse aggregate both stone chips and brick chips from my site and
done sieve analysis test in our University Lab.
4.14.1 Sieve Analysis of Stone Chips
I took 2000 gm of stone chips sand and measuring it by digital scale. Then I organized the US
standard sieve plate in ascending order. I kept the sample into the upper sieve plate and shook it
properly for few minutes. Then I took the measurements and calculated fineness modulus.
Figure 4.23: Sieve Analysis of Stone Chips
48. 31
Total Weight = 2000 gm
Sieve No. Sieve Size
(mm)
Retained
Weight (gm)
% Retained Cumulative
% Retained
% Finer
1″ 25 129 6.45 6.45 93.55
3/4″ 19 647 32.35 38.8 61.2
1/2″ 12.5 866 43.3 82.1 17.9
3/8″ 10 179 8.95 91.05 8.95
#4 4.75 170 8.5 99.55 0.45
#8 2.38 0 0 99.55 0.45
#16 1.19 0 0 99.55 0.45
#30 0.595 0 0 99.55 0.45
#50 0.297 0 0 99.55 0.45
#100 0.149 0 0 99.55 0.45
pan - 9 0.45 100 0
Total=2000gm
Table 4.11: Sieve Analysis of Stone Chips
FM = (∑Cumulative percent retained) / 100
FM = (38.8+91.05+99.55+99.55+99.55+99.55+99.55+99.55)/100
FM = 727.15/100
FM = 7.27
Comment:
I got the value 7.27 and the FM value of coarse aggregate must be minimum 25 mm downgrade
in the design specification. So it was ok to use in the construction.
49. 32
Figure 4.24: Sieve Analysis graph of Stone Chips
4.14.2 Sieve Analysis of Brick Chips
Again I follow the same procedure. I took 2000 gm of brick chips sand and measuring it by
digital scale. Then I organized the US standard sieve plate in ascending order. I kept the sample
into the upper sieve plate and shook it properly for few minutes. Then I took the measurements
of the retained sample and calculated the fineness modulus of that sample.
Figure 4.25: Sieve Analysis of Brick Chips
93.55
61.2
17.9
8.950.450.45
0
10
20
30
40
50
60
70
80
90
100
Sieve Size (mm)
%Finer
particle size distribution Curve
50. 33
Total Weight = 2000 gm
Sieve No. Sieve Size
(mm)
Retained
Weight (gm)
% Retained Cumulative
% Retained
% Finer
1″ 25 397 19.85 19.85 80.15
3/4″ 19 836 41.8 61.65 38.35
1/2″ 12.5 635 31.75 93.4 6.60
3/8″ 10 65 3.25 96.65 3.35
#4 4.75 53 2.65 99.3 0.7
#8 2.38 0 0 99.3 0.7
#16 1.19 0 0 99.3 0.7
#30 0.595 0 0 99.3 0.7
#50 0.297 0 0 99.3 0.7
#100 0.149 0 0 99.3 0.7
Pan - 14 0.7 100 0
Total=2000gm
Table 4.12: Sieve Analysis of Brick Chips
FM = (∑Cumulative percent retained) / 100
FM = (61.65+96.65+99.3+99.3+99.3+99.3+99.3+99.3)/100
FM = 754.1/100
FM = 7.54
Comment:
The FM value of coarse aggregate must be minimum 25 mm downgrade in the design
specification. And I got the value 7.54 so it was ok to use in the construction.
51. 34
Figure 4.26: Sieve Analysis graph of Brick Chips
4.15 Comparison between Required value with Test Value
Comparison between required values with test value of coarse aggregate is given below:
SL Coarse Aggregate Test Value Required Value
1. FM of stone chips I got the value 7.27
FM value must be minimum
20 mm downgrade2. FM of brick chips I got the value 7.54
Table 4.13: Comparison between Required Values with Test Value
80.15
38.35
6.6
3.35
0.70.7
0
10
20
30
40
50
60
70
80
90
100
Sieve Size (mm)
%Finer
particle size distribution Curve
52. 35
4.16 Concrete
In my project for casting the beam, slab and stair they used brick chips as coarse aggregate,
sylhet sand and local sand as fine aggregate. The concrete mix ratio was 1:2:4. For casting the
column they used stone chips as coarse aggregate and sylhet sand as fine aggregate and the
concrete mix ratio was 1:1.5:3.
4.17 Concrete Compressive Strength Test
I have done cylinder test to get the actual compressive strength of concrete. In my project the
materials that used in the casting for beam, slab and stair was different with the materials that
used in the casting for column. The mixing ratio was also different for both casting. That’s why I
have done two cylinder tests- one for beam, slab and stair and another for column.
Procedure
I collected a cylinder for doing cylinder test from my varsity laboratory the day before slab
casting. During the slab casting I took some concrete from the site and inserted it into the
cylinder. Then I tamped 25 times into the cylinder with a 16 mm metal rod to filling all void
inside the cylinder. I kept the cylinder into cold weather for 24 hours. Then for curing I kept the
block in water tank for 28 days. I followed the same procedure for making second block during
column casting.
Figure 4.27: Making Cylinder Block
53. 36
4.17.1 Concrete Cylinder Crushing (Beam, Slab & Stair)
From the crushing I got the value for this concrete 149.27 KN. So I converted this value into psi
for comparing with the design book. According to the design book the concrete crushing strength
for beam, slab and stair is 2800 psi.
Figure 4.28: Concrete Compressive Test (Beam, Slab & Stair)
Figure 4.29: Concrete Compressive Test Result (Beam, Slab & Stair)
54. 37
Result:
Crushing value = 149.27 KN
= (149.27 x 1000) N
= 149270 N
= (149270 x 0.224) lb
= 33436.48 lb
= (33436.48/12.56) psi
= 2662.14 psi
So the compressive strength value is 2662.14 psi but in the design book the required value was
2800 psi. The failure that occurred in the cylinder block was combined failure. It means failure
will occurred both in mortar and aggregate.
Data of Actual and Design Concrete Compressive Strength values are given below:
Date of
Casting
Date of
Crushing
Time
Takes
Crushing
Value
(KN)
Actual
Reading
(psi)
Design
Reading
(psi)
Failure
18.10.2018 15.11.2018 28 days 149.27 2662.14 2800 Combined
Table 4.14: Data of Actual and Design Concrete Compressive Strength
Figure 4.30: Comparison Between Actual & Design Concrete Compressive Strength
Design Reading Actual Reading
psi 2800 2662.14
2550
2600
2650
2700
2750
2800
2850
Comparison between actual & design of
compressive strength
55. 38
4.17.2 Concrete Cylinder Crushing (Column)
From the crushing I got the value for this concrete 157.90 KN. Now I converted this value into
psi for comparing with the design book. According to the design book the column concrete
crushing strength is 3500 psi.
Figure 4.31: Concrete Compressive Test (Column)
Figure 4.32: Concrete Compressive Test Result (Column)
56. 39
Result:
Crushing value = 157.90 KN
= (157.90 x 1000) N
= 157900 N
= (157900 x 0.224) lb
= 35369.60 lb
= (35369.60/12.56) psi
= 2816.05 psi
So the compressive strength value is 2816.05 psi but in the design book the required value was
3500 psi. The failure that occurred in the cylinder block was mortar failure. It means failure will
occurred only in mortar.
Data of Actual and Design Concrete Compressive Strength values are given below:
Date of
Casting
Date of
Crushing
Time
Takes
Crushing
Value
(KN)
Actual
Reading
(psi)
Design
Reading
(psi)
Failure
31.10.2018 29.11.2018 29 days 157.90 2816.05 3500 Mortar
Table 4.15: Data of Actual and Design Concrete Compressive Strength
Figure 4.33: Comparison Between Actual & Design Concrete Compressive Strength
Design Reading Actual Reading
psi 3500 2816.05
0
500
1000
1500
2000
2500
3000
3500
4000
Comparison between actual & design of
compressive strength
57. 40
4.18 Reinforcement Bars
The main purpose of the reinforcement bars is to provide tensile strength to the concrete
structure. The different diameter of reinforcement bars such as- 10mm ϕ, 12mm ϕ, 16mm ϕ,
20mm ϕ & 25mm ϕ was used in my site. 10mm and 12mm diameter of bars was used in Slab and
stair. 16mm, 20mm and 25mm diameter of bars was use in beam and column. Only 10mm
diameter of bar used for making tie and stirrups. In my site they used M.S deformed bar with
yield strength fy = 72500 psi (500 grade).
Figure 4.34: Reinforcement Bars
4.19 Field Test of Reinforcement Bars
I have done some field tests for checking the quality of reinforcement bars in my site.
Descriptions are given below:
4.19.1 Surface checking
I checked the cross section surface of the bar. It was smooth and free of paint.
Figure 4.35: Surface of the Bar
58. 41
4.19.2 Bending Test
When a worker was bending a bar, I checked its surface to know it was cracked or not. But I
didn’t found any crack on that bending fragment.
Figure 4.36: Bending a Bar Figure 4.37: Checking Fragment of Bar
4.19.3 Color Checking
When they first bought the reinforcement bars it should be in blackish gray color. And the bars at
my site are also in blackish gray color.
Figure 4.38: Bar Color Checking
59. 42
4.20 Comparison between Standard Tests with Field Tests
Comparisons between standard tests with field tests of sand are given below:
SL Standard Result Field Test Result
1. Bar cross section should be smooth and paint free It was smooth and paint free
2. After bending it should not cracked It did not crack
3. Color should be blackish gray It was blackish gray
Table 4.16: Comparison between Standard Tests with Field Tests
4.21 Water
In my site clean potable water is used in concrete mixing and curing work.
Figure 4.39: Water
60. 43
4.22 Block Making
For maintaining the clear cover of reinforcement the block are made. It was made by cement and
sand. The size of the blocks that used in my site was 1 inch, 1.5 inch and 3 inch. 1.5 inch blocks
were used in beam. 1 inch blocks used in slab and stair to maintain the clear cover of its bottom
reinforcement and 3 inch blocks used to maintain the clear cover of top reinforcement.
Figure 4.40: Block Casting
Figure 4.41: The Blocks
Figure 4.42: Measuring Blocks
61. 44
4.23 Formwork Materials
4.23.1 Wooden Planks
Wood is very common and available materials that use in the construction work. In my site
wooden planks was use for making shuttering of beam, slab and stairs. The width of the wooden
planks is 6 in and the thickness is 1 in.
Figure 4.43: Wooden Planks
Figure 4.44: Wooden Planks Width Figure 4.45: Wooden Planks Thickness
1 inch
6 inch
62. 45
4.23.2 Wooden Runner
Wooden runners are very similar to wooden planks. It is use to hold the wooden plank. It is use
on top of bamboo. Its width is 3 in and thickness is 2 in.
Figure 4.46: Wooden Runners
Figure 4.47: Wooden Runner Width Figure 4.48: Wooden Runner Thickness
Wooden runner
2 inch
3 inch
63. 46
4.23.3 Bamboo Props
Bamboo is also common and easily available materials in construction works. Bamboo was use
to support the runners of beam and slab.
Figure 4.49: Bamboo Props
Figure 4.50: Measuring Bamboo Props
First, took bamboo perimeter.
Then divided by π (3.1416). we
will found diameter of bamboo
w
64. 47
My supervisor told me to records some bamboos diameters at the site. I selected 30 bamboos
randomly and found out their diameters. Descriptions are given below:
SL NO Perimeter
(in)
D=P/π (in) SL NO Perimeter
(in)
D=P/π (in)
Average
Diameter
(in)
01 9 2.86 16 7.5 2.38
2.60
02 9.8 3.12 17 6 1.90
03 8.5 2.71 18 6.5 2.06
04 9.1 2.89 19 9 2.86
05 8.8 2.80 20 10 3.18
06 9 2.86 21 10.5 3.34
07 10.3 3.27 22 11 3.50
08 8 2.55 23 10 3.18
09 9.5 3.02 24 9.5 3.02
10 8.5 2.70 25 8.5 2.70
11 9 2.55 26 10 3.18
12 9.5 3.02 27 9.5 3.02
13 8.5 2.70 28 10.5 3.34
14 10 3.18 29 9 2.86
15 9.5 3.02 30 8 2.55
Table 4.17: Bamboos Diameter
65. 48
4.23.4 Steel Forms
In my site steel forms are used to make column shuttering. Steel forms make beams and columns
surface smooth. But it is more costly then shuttering that made of wood.
Figure 4.51: Steel Forms
4.23.5 Nut Bolt & Turn Bolt
Nut bolt used to hold one steel form to another and turn bolt use to keep column vertical
adjustment.
Figure 4.52: Nut Bolt Figure 4.53: Turn Bolt
Turn
bolt
66. 49
4.23.6 Plain Sheet
Plain sheet are used for slab and stair shuttering. It was placed over the wooden plank of slab and
stair. The length of the plain sheet was 6 ft and width was 3 ft.
Figure 4.54: Plain Sheet
Figure 4.55: Measuring Plain Sheet
6 ft
3 ft
67. 50
4.24 Construction Equipments
4.24.1 Mixture Machine
The mixture machine was used to mix the concrete. The machine runs by diesel engine.
Figure 4.56: Mixture Machine
4.24.2 Vibrator Machine
It was used to compact the mixed concrete into the beam, slab and column and so that the voids
can remove.
Figure 4.57: Vibrator Machine
Vibrator Machine
68. 51
4.24.3 Roof Hoist
It was used to lift up the concrete mixture from the ground to the roof.
Figure 4.58: Roof Hoist
4.24.4 Reinforcement Bar Cutter
Reinforcement cutter is usually used for cutting the reinforcement. In my site there are two type
of reinforcement cutters used. The big one was used for cutting wide diameter reinforcements.
Figure 4.59: Reinforcement Cutter
69. 52
CHAPTER FIVE:
Construction of Column
5.1 General
In this chapter I am going to narrate the construction work of column and its whole procedure
including column kicker, reinforcement, shuttering, casting and curing.
5.2 About Column
A column is a compression member that carries load. Column is very important element of the
building. So, everyone should be attentive to do proper construction works of column.
5.3 Column Layout Plan
By looking at the column layout plan we can easily found the column position and the total
number of columns. There are total 14 columns in my project.
Figure 5.1: Layout of Column
70. 53
5.4 Column Schedule
Just like column layout plan, we can easily found the size and the details of the reinforcement
bars of column by looking at the column schedule. In my project there are six types of column
such as- C1, C2, C3, C3A, C4 and C5.
Figure 5.2: Column Schedule
The design specifications of those six types of column for 4th
, 5th and 6th
floor are given below:
Type of
column
No. of
Column
Column Size
(in)
Dia of Bar
(mm)
No. of Bar Clear Cover
(in)
Spacing
(in)
C1 2
(12″x20″)
16mm ϕ 8
1.5″ 10mm ϕ @
5-9-5
C2 4 20mm ϕ 8
C3 2 (12″x30″)
16mm ϕ 4
20mm ϕ 6
C3A 2 (10″x40″) 16mm ϕ 14
C4 2 (12″x30″)
25mm ϕ
12
C5 2 (15″x30″) 12
Table 5.1: Column Design Specifications
71. 54
5.5 Construction Work of Column
The whole construction process of column can be done by these following steps. The steps
are given below:
1. Column kicker work
2. Column reinforcement Placing
3. Column shuttering
4. Column casting
5. Column curing work
5.6 Column Kicker Work
The column kicker was made before the start of the column constructions work. It was made for
finding the correct location of column. For making the shuttering of column kicker they used the
wooden planks. According to the column cross section they made kicker shuttering. When
workers finished the shuttering works, I have checked the cross section of the column and height
of the kicker. I have also checked the cleat cover of the reinforcement bars. After that they
prepared mix concrete for casting of the column kicker. The mixing ratio of the concrete was
1:1.5:3. The materials that used on the concrete were cement, sand and stone chips. The height of
the kicker casting was 6 inch.
Figure 5.3: Making Shuttering for Column Kicker
72. 55
Total wooden planks used in the making of column kickers are given below:
Table 5.2: Shuttering of Column Kicker
Figure 5.4: Measuring Column Kicker
ColumnType
ColumnSize
No.ofColumn
Column Length Column Width
Volume(cft)
Wood
length
(ft)
Wood
width
(ft)
Wood
thickn
ess
(ft)
No.
of
side
Wood
length
(ft)
Wood
width
(ft)
Wood
thickn
ess
(ft)
No.
of
side
C1 (12″x20″)
2 1.17 0.5 0.08 2 1 0.5 0.08 2 0.348
C2 (12″x20″)
4 1.17 0.5 0.08 2 1 0.5 0.08 2 0.348
C3 (12″x30″)
2 3 0.5 0.08 2 1 0.5 0.08 2 0.64
C3A
(10″x40″)
2 3.83 0.5 0.08 2 0.83 0.5 0.08 2 0.744
C4 (12″x30″)
2 3 0.5 0.08 2 1 0.5 0.08 2 0.64
C5 (15″x30″)
2 3 0.5 0.08 2 1.25 0.5 0.08 2 0.68
Total= 3.40 cft
40 inch
Column– C3A
10 inch
74. 57
5.7 Column reinforcement Placing
The workers started working on the reinforcement bars of column after finishing the column
kicker work. Some are making tie bars and ring for column and some are placing those bars
in the column and some are binding tie bars with main bars. I have observed the entire work
process of the workers. I have checked whether the tie spacing is ok or not according to the
drawing book. I have also checked whether the clear cover from tie bar to column is 1.5
inches or not. I have also calculated total number of main bars and tie bars of each column in
the field. In my project every column was rectangular. The diameter of the main bar of
column was 16mm ϕ, 20mm ϕ and 25mm ϕ respectively. The diameter of tie bar and ring of
column was 10mm ϕ and tie bar spacing was 5″-9″-5″ @ C/C
Figure 5.7: Reinforcement Bars Placing
Figure 5.8: Binding Tie with Main Bar
75. 58
Figure 5.10: Checking Clear Cover of Column
Main bar: 14-16mm ϕ
Tie bar: 10mm ϕ
Column type – C3A
Ring: 10mm ϕ
Ring: 10mm ϕ
Figure 5.9: Checking Reinforcement
Bar of Column
Clear cover 1.5 inch
76. 59
Figure 5.11: Checking Spacing of tie Bars in Middle
Figure 5.12: Checking Spacing of tie Bars in bottom of Column
9″+9″= 18″
18/2= 9″
Average 9″c/c
4.5″+ 5.1″=9.6″
9.6/2=4.8″
Average 4.8 c/c
4.8″+ 5.0″+5.1″=14.9″
14.9/3=4.96″
Average 4.96″ c/c
77. 60
5.7.1 Estimation of Column Reinforcement
Calculation of reinforcement for column-3A
Tie bars
Length = 2× (A+B) +4″
= 2× (37+7) +4″
= 92″ = 7ʹ7″
= 7.58ʹ
20 -10mm ϕ = 20×0.19×7.58
= 28.80 kg
Ring-1
Length = 2× (A+B) +4″
= 2× (24.67+7) +4″
= 67.34″
= 5.61ʹ
20 -10mm ϕ = 20×0.19×5.61
= 21.31 kg
Ring-2
Length = 2× (A+B) +4″
= 2× (12.32+7) +4″
= 42.64″
= 3.55ʹ
20 -10mm ϕ = 20×0.19×3.55
= 13.49 kg
Total weight = (87.36+28.80+21.31+13.49)
= 150.96 kg
Here,
16 mm ϕ = 0.48 kg/ft
Number of bar = 14
Bar length = 13 ft
(Including lapping length)
A= 40″-(1.5″+1.5″) = 37″
B= 10″-(1.5″+1.5″) = 7″
Here,
10mm ϕ = 0.19 kg/ft
Number of tie bar = 20
A= 40″-(1.5″+1.5″) = 37″
= 37/6=6.16
= 6.16×4
= 24.67″
B= 10″-(1.5″+1.5″) = 7″
Number of ring = 20
A= 40″-(1.5″+1.5″) = 37″
= 37/6=6.16
= 6.16×2
= 12.32″
B= 10″-(1.5″+1.5″) = 7″
Number of ring = 20
Main Bar
14 -16mm ϕ = 14×0.48×13
= 87.36 kg
78. 61
Estimation of column reinforcement according to the design book is given below:Columntype
ColumnSize(in)
NO.ofcolumn
Bartype
Bardia.(mm)
UnitWeight
(kg/ft)
No.ofbar
Barlength(ft)
Weight(kg)
C1
(12″x20″)
2
Main bar 16 0.48 8 13 99.84
Tie bar 10 0.19 20 4.58 34.81
Ring 10 0.19 20 2.92 20.90
C2
(12″x20″)
4
Main bar 20 0.75 8 13 312
Tie bar 10 0.19 20 4.58 69.62
Ring 10 0.19 20 2.92 41.80
C3
(12″x30″)
2
Main bar
20 0.75 6 13 117
16 0.48 4 13 49.92
Tie bar 10 0.19 20 6.25 47.5
Ring 10 0.19 20 2.25 20.90
C3A
(10″x40″)
2
Main bar 16 0.48 14 13 174.7
Tie bar 10 0.19 20 7.58 57.61
Ring
10 0.19 20 5.61 42.63
10 0.19 20 3.55 26.98
C4
(12″x30″)
2
Main bar 25 1.17 12 13 365.1
Tie bar 10 0.19 20 6.25 47.5
Ring 10 0.19 20 3.25 24.7
C5
(15″x30″)
2
Main bar 25 1.17 12 13 365.1
Tie bar 10 0.19 20 6.75 51.3
Ring 10 0.19 20 3.58 27.21
Total = 1976.89 kg
Table 5.3: Estimation of Column Reinforcement According to the Drawing
79. 62
Estimation of column reinforcement that actually use in the field is given below:Columntype
ColumnSize(in)
NO.ofcolumn
Bartype
Bardia.(mm)
UnitWeight
(kg/ft)
No.ofbar
Barlength(ft)
Weight(kg)
C1
(12″x20″)
2
Main bar 16 0.48 8 13 99.84
Tie bar 10 0.19 19 4.58 33.07
Ring 10 0.19 19 2.75 19.86
C2
(12″x20″)
4
Main bar 20 0.75 8 13 312
Tie bar 10 0.19 19 4.58 66.14
Ring 10 0.19 19 2.75 39.71
C3
(12″x30″)
2
Main bar
20 0.75 6 13 117
16 0.48 4 13 49.92
Tie bar 10 0.19 19 6.25 45.13
Ring 10 0.19 19 2.25 16.25
C3A
(10″x40″)
2
Main bar 16 0.48 14 13 174.7
Tie bar 10 0.19 18 7.58 51.85
Ring
10 0.19 18 5.61 38.37
10 0.19 18 3.55 24.28
C4
(12″x30″)
2
Main bar 25 1.17 12 13 365.1
Tie bar 10 0.19 19 6.25 45.13
Ring 10 0.19 19 3.25 23.47
C5
(15″x30″)
2
Main bar 25 1.17 12 13 365.1
Tie bar 10 0.19 19 6.75 48.74
Ring 10 0.19 19 3.58 25.85
Total = 1943.29 kg
Table 5.4: Estimation of Column Reinforcement that Used in the Field
80. 63
5.7.2 Comparison for Column Reinforcement Bars
There was some slightly difference in reinforcement of column that used in practical field with
design book. Descriptions are given below:
Column Types Total Required (kg) Use in Field (kg) Difference (+/-)
C1 155.55 152.77 -2.78
C2 423.42 417.85 -5.57
C3 235.32 228.30 -7.02
C3A 301.92 291.21 -10.71
C4 457.30 453.70 -3.60
C5 443.61 439.69 -3.92
Table 5.5: Comparison of Column Reinforcement
Figure 5.13: Comparison of Reinforcement Bars (kg) Used in Column
C1 C2 C3 C3A C4 C5
DESIGN 155.55 423.42 235.32 301.92 457.3 443.61
ACTUAL 152.77 417.85 228.3 291.21 453.7 439.69
0
50
100
150
200
250
300
350
400
450
500
Comparison of Reinforcement Bars Used in Column
81. 64
5.8 Column Shuttering
The workers started working on the column shuttering after finishing the reinforcement placing
of the column. Only steel form plate was used in column shuttering at my project. The shuttering
was hold by using nut bolt and rivet. Bamboo props were also used. It was used to keep
shuttering straight. Using plumb bob they checked whether the vertical alignment of column was
straight or not. They also checked the clear cover of column. It was kept according to the design.
The clear cover of the column is 1.5 inch.
Figure 5.14: Making column Shuttering
The table of estimation for column steel shuttering is given below:
Type of
column
No. of
Column
Column
Size (in)
Column
Height (ft)
Required Amount
(sft)
Total Amount
(sft)
C1 2 (12″x20″)
8.33'
44.48 88.96
C2 4 (12″x20″) 44.48 177.92
C3 2 (12″x30″) 58.31 116.62
C3A 2 (10″x40″) 69.31 138.62
C4 2 (12″x30″) 58.31 116.62
C5 2 (15″x30″) 62.48 124.95
Total = 763.69 sft
Table 5.6: Estimation of Steel Shuttering of Column
82. 65
5.9 Column Casting
After finishing the shuttering work, the workers were ready to casting of column. They used
mixer machine for mixing the concrete. The materials that used in the concrete mixture were
cement, sand and stone chips. The mixing ratio of the concrete was1:1.5:3. During the casting of
column they used vibrator to fill the void.
Figure 5.15: Column Casting
83. 66
5.9.1 Estimation of Column Casting
In my site there are six types of column such as- C1, C2, C3, C3A, C4 and C5. The estimation of
the materials that used on those columns is given below:
Column Type- C3A
Number of column = 2
Column height = 8.33'
Column size = (10"×40") = (0.83'×3.33')
Volume of column = (0.83'×3.33'×8.33') = 23.02 cft
Total volume = (23.02×2) = 46.04 cft [no. of column= 2]
Dry volume = (46.04×1.5) = 69.03 cft
Mixing ratio = 1:1.5:3
Summation of the ratio = (1+1.5+3) = 5.5
Cement = (69.03/5.5) ×1 = 12.55 cft
= 10.05 bags [1.25 cft = 1 bag]
Sand = (69.03/5.5) ×1.5 = 18.84 cft
Stone Chips = (69.03/5.5) ×3 = 37.67 cft
Estimation of the casting materials for column is given in table:
Column
Types
Column
Size
Column
Length
(ft)
No of
Column
Volume
(cft)
Dry
Volume
(cft)
Cement
(bag)
Sand
(cft)
Stone
Chips
(cft)
C1 (12″x20″) 8.33' 2 30.48 45.72 6.65 12.47 24.94
C2 (12″x20″) 8.33' 4 60.64 91.44 16.62 24.94 49.88
C3 (12″x30″) 8.33' 2 41.65 62.48 9.09 17.04 34.08
C3A (10″x40″) 8.33' 2 46.05 69.07 10.05 18.84 37.67
C4 (12″x30″) 8.33' 2 41.65 62.48 9.09 17.04 34.08
C5 (15″x30″) 8.33' 2 52.06 78.09 11.35 21.29 42.59
Total= 62.85 117.62 235.24
Table 5.7: Estimation of the Casting Materials of Column
84. 67
But in the field total cement used = 60 bags [1 bag =1.25 cft]
= 75 cft
Dry volume = (75×5.5)/1 = 412.50 cft [mixing ratio =5.5]
Actual used of sand = (412.50/5.5) ×1.5 = 112.50 cft
Actual used of stone chips = (412.50/5.5) ×3 = 225 cft
Comparison of casting materials between estimation and actual used in the field is given below:
Materials Estimation Actual Used Difference (+/-)
Cement 62.85 bags 60 bags -2.85
Sand 117.62 cft 112.50 cft -5.12
Brick Chips 235.24 cft 225 cft -10.24
Table 5.8: Comparison of Casting Materials for Column
Figure 5.16: Comparison of Casting Materials for Column
Cement (bag) Sand (cft) Stone Chips (cft)
Estimated 62.85 117.62 235.24
Actual used 60 112.5 225
Difference 2.85 5.12 10.24
0
50
100
150
200
250
Comparison of Casting Materials
85. 68
5.10 Column Curing
After two days the column shuttering was removed. Then the column curing was started. The
column was wrapped by jute fabric and sprinkling water by hose pipe constantly. They spread
water by pipe 3 times in a day. They did it nearly 15 days.
Figure 5.17: Column Curing
5.11 Work Schedule for Column
Figure 5.18: Column Work Schedule
86. 69
CHAPTER SIX:
Construction of Beam & Slab
6.1 General
In this chapter I am going to describe the construction works of beam and slab and its whole
process including beam and slab shuttering work, reinforcement work, casting and curing.
6.2 About Beam & Slab
A beam is a horizontal member of a structure that carries transverse loads and a slab is a flat
horizontal surface which supported by beam and column, it transfers load to the beam.
The layout of beam and slab of my project are given below:
6.3 Beam Layout plan
There are 10 types of beam in my project. Such as FB-1, FB-2, FB-3, FB-4, FB-5, FB-6A, FB-7,
FB-8, FB-9, FB-10.
Figure 6.1: Layout of Beam
89. 72
6.5 Reinforcement Details for Slab
By looking at the drawing we can identified the position of the slab reinforcement bars.
Figure 6.3: Slab Reinforcement Details
BOTTOM BAR
1) 10 mm ϕ 6″ C/C ALT. CKD
2) 10 mm ϕ 7″ C/C ALT. CKD
3) 10 mm ϕ 8.5″ C/C ALT. CKD
4) 10 mm ϕ Binder 10″ C/C where necessary
TOP BAR
a) 1-10 mm ϕ ext.betn ckd
b) 2-10 mm ϕ ext.betn ckd
c) 2-12 mm ϕ ext.betn ckd
SLAB THICKNESS = 6″ where not shown
90. 73
6.6 Construction Work of Beam & Slab
The whole construction process of beam and slab can be done by these following steps. The
steps are given below:
1. Beam and slab shuttering work
2. Beam and slab reinforcement placing
3. Beam and slab Casting
4. Slab curing work
5. Beam and slab de-shuttering
6.7 Beam and slab shuttering work
After finishing the column construction work they started making shuttering of the beam and
slab. In my project beam and slab shuttering were made using only wood. At first they made
beams bottom, then the sides of the beam. They provided bamboo props to support the beams
bottom. The distance between one bamboo to another was 2 feet. After that they started placing
wooden runners for slab shuttering. The distance between one wooden runner to another was
also 2 feet. They placed wooden runners in short direction of the panel. After placing wooden
runners, they provided bamboos to hold the runners. Then they placed wooden planks above the
runners for slab. They used 70% of total area of the slab. The beams sides were connected with
the wooden planks of the slab. After that they provided plain sheet over the wooden planks. I
also measured beams width and depth.
Figure 6.4: Making Beam Shuttering