rned
            L ea        from …..
    so ns
L es
Site characteristics
Described by site topography and
site climate change.

To calculate the effects of site
topography on the wind power, it
is necessary to describe the nature
of the site topography i.e.
roughness, Obstacles, and
orography, to understand the
effects of each parameter on the
wind power.

Climate change

B= ρRT

P1 =0.5 X ρ1 X U3
Zafarana Wind Farm is located 120km south of Suez on the Red Sea.
   Zafarana site
   Flat area 20 km along sea     cost,
   Average wind speed 8.5 m/s
   Turbulence intensity lower than 7%,
   Summer windy - prevailing wind direction bounded in Narrow zone
Machine technology
   Utility-scale wind turbines for land-based wind farms come in
    various sizes, with rotor diameters ranging from about 50 meters to
    about 90 meters, and with towers of roughly the same size. A 90-
    meter machine. with a 90-meter tower would have a total height
    from the tower base to the tip of the rotor of approximately 135
    meters.

   Offshore turbine designs now under development will have larger
    rotors—at the moment, the largest has a 110-meter rotor
    diameter—because it is easier to transport large rotor blades by ship
    than by land.

   Small wind turbines intended for residential or small business use
    are much smaller. Most have rotor diameters of 8 meters or less
    and would be mounted on towers of 40 meters in height or less.
Machine technology
Wind Farm
    Arrangement of arrays inside wind farm is called
    (micro-siting) and it is one of the main factors that
    improve the wind farm performance because of the
    following:
   Reduce wake interaction between turbines each other to
    avoid:
    - fatigue damage.
    - Reduce stress on movement parts ( yaw system, and
    blades of turbines)
   Minimize required area maximize energy production of
    wind farm.
Operation & Maintenance
Zafarana
              ‫ﺻﯿﺎﻧﺔ دورﯾﺔ‬TIME BASED MAINTENANCE
                                                          H.R.OF
                TIME BASED MAINTENANCE                   FAULTS&
  MANF. PLAN                             NO FEED BACK    FAILURE




                 • ‫ﺻﯿﺎﻧﺔ اﻻﻧﮭﯿﺎرات‬          BREAKDOWN
                                         MAINTENANCE

                                                          M.DEP.
                                                          MAJOR
FAULTS - FAILURE BREAKDOWN MAINTENANCE   NO CORRECTION   FAULTS&
                                                         FAILURE
Total Productive Maintenance




TPM is often presented as a series of pillars supporting Lean
Manufacturing and resting on a foundation of education and
training. Below this is the attitude of environmental responsibility
and safety.
Total Productive Maintenance
   Supporting Lean
    Maintenance enables and supports Lean efforts in at least three major
    ways: Quality, Setup Reduction (SMED) and predictability. In turn,
    other Lean elements support TPM through Workcells, Teamwork and Problem-
                                                                          Problem-
    solving.

   The Foundations
    Education & Training-- Education, training and investments in people characterize
                    Training--
    all aspects of Lean. In the maintenance area, they are even more important because
    of the specialized knowledge required on typical manufacturing equipment. This is
                                                                     equipment.
    one of the foundation stones of TPM. Without it, the pillars of TPM will have limited
    impact.
    Safety/Environment-- Underlying even the training and education piece are the
    Safety/Environment--
    more fundamental values of responsibility to the environment and safety for
    employees. One important reason is simple: it is the right thing to do.
    A more pragmatic reason involves motivation. Most people want to be a part
    of something larger than themselves; appeals to higher motivation bring involvement
                                                             motivation
    and commitment. It is difficult to argue against safety and a common commitment to
                                                                   common
    safety can be a bond that brings people together on other issues.
                                                                issues.
Zafarana
              ‫ﺻﯿﺎﻧﺔ دورﯾﺔ‬TIME BASED MAINTENANCE
                                                          H.R.OF
                TIME BASED MAINTENANCE                   FAULTS&
  MANF. PLAN                             NO FEED BACK    FAILURE




                 • ‫ﺻﯿﺎﻧﺔ اﻻﻧﮭﯿﺎرات‬          BREAKDOWN
                                         MAINTENANCE

                                                          M.DEP.
                                                          MAJOR
FAULTS - FAILURE BREAKDOWN MAINTENANCE   NO CORRECTION   FAULTS&
                                                         FAILURE
Autonomous Maintenance
   Autonomous maintenance is the concept that the people who
    operate a machine should maintain the machine. The degree
    of autonomous maintenance depends on the level of training and
    the abilities of operators. It often starts with basic lubrication,
    cleaning and inspection and then graduates to minor or even major
    repairs.
   For example, in the foundry where this author worked, machinists
    repaired and overhauled their own machine tools. A trained and
    competent machinist is certainly capable of overhauling a gearbox.
    And, as the users, they tended to know the equipment
    intimately. In the military, everyone cleans their own
    weapon. When their life depends on proper functioning,
    people take more care.
   Autonomous maintenance frees resources in the
    maintenance department for the other activities such as
    equipment improvement or major overhauls. It amplifies the
    maintenance efforts and involves the operators who then take
    better care of the equipment.
To apply Autonomous
             Maintenance
   Reward policy.
   Plan for revamping people in operation not
    less than 3 years.
   Interaction between maintenance team
    and operation team and highlighting the
    problems.
   Information transparency
           ‫ﺻﯿﺎﻧﺔ دورﯾﺔ‬AUTONOMUS M.+TIME BASED MAINTENANCE


                                                                                 R.R.OF
 SHORT TERM PLAN                    T B M + A.M                                 FAULTS&
                                                                    FEED BACK   FAILURE



                                      P.CHECK
                           (PRES.,TEMP.,AMP.,…VIB. CHECK))
                           (PRES.,TEMP.,AMP.,…




      •            ‫ﺻﯿﺎﻧﺔ اﻟﺘﺼﺤﯿﺢ‬                             CORRECTIVE MAINTENANCE


                                                                                 MINOR
                                                                                FAULTS&
FAULTS - FAILURE            CORRECTIVE MAINTENANCE                  FEED BACK   FAILURE




                                      P.CHECK
                           (PRES.,TEMP.,AMP.,…VIB. CHECK))
                           (PRES.,TEMP.,AMP.,…
Planned Maintenance
   Planned maintenance is the deliberate planning and scheduling of
    maintenance activities as opposed to reacting to breakdowns and
    emergencies. A maintenance department that uses TPM effectively
    generally devotes less than 10% of its labor hours to such unplanned
    activities.

   Without TPM it is not unusual for 80%-90% of the labor to be unplanned.
    Unplanned maintenance is a strong indicator that prevention and
    improvement programs are non-existent or ineffective.

   In addition, high percentages of unplanned maintenance creates
    problems. For example:

   Huge inefficiencies in maintenance labor.
   Confusion and disturbance in scheduling, production and other
    areas.
   Morale problems.
How to plan all activities

   Activate Reporting
   Build CMMS system
   Activate manufacturer recommendation
   Predictive maintenance
   Check plans
PLAN




                                                                        DO


                                                    PLAN
          ACTION                                     DO                CHECK
       CORRECTION & MODFICATION
                                               REG. M. + OVERHAULING
                                                EG.      OVERHAULING


                                                                       ACTION




                             CHECK
                                  P.CHECK
                       (PRES.,TEMP.,AMP.,…VIB. CHECK)
                       (PRES.,TEMP.,AMP.,…


        CMS
       Aut. M                CT T
                           RE AC
                         DI NT
                         CO

DATA
New Equipment
          Management

New equipment management is related
somewhat to equipment improvement. It refers
to the careful design, selection and testing of
equipment. The purpose is to ensure a smooth
commissioning process with minimal design
defects and problems. New equipment
management includes vendor selection,
evaluating options for maintainability, training
personnel in advance and other common-sense
techniques.
Maintenance management
      organization
Maintenance management
      organization
Zafarana is a location with extreme conditions the wind turbines that have
been installed have been specially prepared to cope with Egypt’s hot desert
climate, sand storms and salty air. Special seals had to be created to prevent
sand from getting in to the units and rotor-blade cleaning have been planned
for several times per year.
To utilize wind power

 Meteorological  conditions.
 Location (site topography).
 Machine technology (turbine design).
 Grid connection
 O&M management
Capacity building 2010 day 3 lessons
Capacity building 2010 day 3 lessons
Capacity building 2010 day 3 lessons
Capacity building 2010 day 3 lessons

Capacity building 2010 day 3 lessons

  • 1.
    rned L ea from ….. so ns L es
  • 6.
    Site characteristics Described bysite topography and site climate change. To calculate the effects of site topography on the wind power, it is necessary to describe the nature of the site topography i.e. roughness, Obstacles, and orography, to understand the effects of each parameter on the wind power. Climate change B= ρRT P1 =0.5 X ρ1 X U3
  • 7.
    Zafarana Wind Farmis located 120km south of Suez on the Red Sea.
  • 8.
    Zafarana site  Flat area 20 km along sea cost,  Average wind speed 8.5 m/s  Turbulence intensity lower than 7%,  Summer windy - prevailing wind direction bounded in Narrow zone
  • 9.
    Machine technology  Utility-scale wind turbines for land-based wind farms come in various sizes, with rotor diameters ranging from about 50 meters to about 90 meters, and with towers of roughly the same size. A 90- meter machine. with a 90-meter tower would have a total height from the tower base to the tip of the rotor of approximately 135 meters.  Offshore turbine designs now under development will have larger rotors—at the moment, the largest has a 110-meter rotor diameter—because it is easier to transport large rotor blades by ship than by land.  Small wind turbines intended for residential or small business use are much smaller. Most have rotor diameters of 8 meters or less and would be mounted on towers of 40 meters in height or less.
  • 10.
  • 11.
    Wind Farm Arrangement of arrays inside wind farm is called (micro-siting) and it is one of the main factors that improve the wind farm performance because of the following:  Reduce wake interaction between turbines each other to avoid: - fatigue damage. - Reduce stress on movement parts ( yaw system, and blades of turbines)  Minimize required area maximize energy production of wind farm.
  • 14.
  • 15.
    Zafarana  ‫ﺻﯿﺎﻧﺔ دورﯾﺔ‬TIME BASED MAINTENANCE H.R.OF TIME BASED MAINTENANCE FAULTS& MANF. PLAN NO FEED BACK FAILURE • ‫ﺻﯿﺎﻧﺔ اﻻﻧﮭﯿﺎرات‬ BREAKDOWN MAINTENANCE M.DEP. MAJOR FAULTS - FAILURE BREAKDOWN MAINTENANCE NO CORRECTION FAULTS& FAILURE
  • 16.
    Total Productive Maintenance TPMis often presented as a series of pillars supporting Lean Manufacturing and resting on a foundation of education and training. Below this is the attitude of environmental responsibility and safety.
  • 17.
    Total Productive Maintenance  Supporting Lean Maintenance enables and supports Lean efforts in at least three major ways: Quality, Setup Reduction (SMED) and predictability. In turn, other Lean elements support TPM through Workcells, Teamwork and Problem- Problem- solving.  The Foundations Education & Training-- Education, training and investments in people characterize Training-- all aspects of Lean. In the maintenance area, they are even more important because of the specialized knowledge required on typical manufacturing equipment. This is equipment. one of the foundation stones of TPM. Without it, the pillars of TPM will have limited impact. Safety/Environment-- Underlying even the training and education piece are the Safety/Environment-- more fundamental values of responsibility to the environment and safety for employees. One important reason is simple: it is the right thing to do. A more pragmatic reason involves motivation. Most people want to be a part of something larger than themselves; appeals to higher motivation bring involvement motivation and commitment. It is difficult to argue against safety and a common commitment to common safety can be a bond that brings people together on other issues. issues.
  • 18.
    Zafarana  ‫ﺻﯿﺎﻧﺔ دورﯾﺔ‬TIME BASED MAINTENANCE H.R.OF TIME BASED MAINTENANCE FAULTS& MANF. PLAN NO FEED BACK FAILURE • ‫ﺻﯿﺎﻧﺔ اﻻﻧﮭﯿﺎرات‬ BREAKDOWN MAINTENANCE M.DEP. MAJOR FAULTS - FAILURE BREAKDOWN MAINTENANCE NO CORRECTION FAULTS& FAILURE
  • 19.
    Autonomous Maintenance  Autonomous maintenance is the concept that the people who operate a machine should maintain the machine. The degree of autonomous maintenance depends on the level of training and the abilities of operators. It often starts with basic lubrication, cleaning and inspection and then graduates to minor or even major repairs.  For example, in the foundry where this author worked, machinists repaired and overhauled their own machine tools. A trained and competent machinist is certainly capable of overhauling a gearbox. And, as the users, they tended to know the equipment intimately. In the military, everyone cleans their own weapon. When their life depends on proper functioning, people take more care.  Autonomous maintenance frees resources in the maintenance department for the other activities such as equipment improvement or major overhauls. It amplifies the maintenance efforts and involves the operators who then take better care of the equipment.
  • 20.
    To apply Autonomous Maintenance  Reward policy.  Plan for revamping people in operation not less than 3 years.  Interaction between maintenance team and operation team and highlighting the problems.  Information transparency
  • 21.
    ‫ﺻﯿﺎﻧﺔ دورﯾﺔ‬AUTONOMUS M.+TIME BASED MAINTENANCE R.R.OF SHORT TERM PLAN T B M + A.M FAULTS& FEED BACK FAILURE P.CHECK (PRES.,TEMP.,AMP.,…VIB. CHECK)) (PRES.,TEMP.,AMP.,… • ‫ﺻﯿﺎﻧﺔ اﻟﺘﺼﺤﯿﺢ‬ CORRECTIVE MAINTENANCE MINOR FAULTS& FAULTS - FAILURE CORRECTIVE MAINTENANCE FEED BACK FAILURE P.CHECK (PRES.,TEMP.,AMP.,…VIB. CHECK)) (PRES.,TEMP.,AMP.,…
  • 22.
    Planned Maintenance  Planned maintenance is the deliberate planning and scheduling of maintenance activities as opposed to reacting to breakdowns and emergencies. A maintenance department that uses TPM effectively generally devotes less than 10% of its labor hours to such unplanned activities.  Without TPM it is not unusual for 80%-90% of the labor to be unplanned. Unplanned maintenance is a strong indicator that prevention and improvement programs are non-existent or ineffective.  In addition, high percentages of unplanned maintenance creates problems. For example:  Huge inefficiencies in maintenance labor.  Confusion and disturbance in scheduling, production and other areas.  Morale problems.
  • 23.
    How to planall activities  Activate Reporting  Build CMMS system  Activate manufacturer recommendation  Predictive maintenance  Check plans
  • 24.
    PLAN DO PLAN ACTION DO CHECK CORRECTION & MODFICATION REG. M. + OVERHAULING EG. OVERHAULING ACTION CHECK P.CHECK (PRES.,TEMP.,AMP.,…VIB. CHECK) (PRES.,TEMP.,AMP.,… CMS Aut. M CT T RE AC DI NT CO DATA
  • 25.
    New Equipment Management New equipment management is related somewhat to equipment improvement. It refers to the careful design, selection and testing of equipment. The purpose is to ensure a smooth commissioning process with minimal design defects and problems. New equipment management includes vendor selection, evaluating options for maintainability, training personnel in advance and other common-sense techniques.
  • 26.
  • 27.
  • 28.
    Zafarana is alocation with extreme conditions the wind turbines that have been installed have been specially prepared to cope with Egypt’s hot desert climate, sand storms and salty air. Special seals had to be created to prevent sand from getting in to the units and rotor-blade cleaning have been planned for several times per year.
  • 29.
    To utilize windpower  Meteorological conditions.  Location (site topography).  Machine technology (turbine design).  Grid connection  O&M management