Big Data Public Private Forum




BIG DATA PUBLIC PRIVATE FORUM
  (BIG) GENERAL PRESENTATION


        Project co-funded by the European
        Commission within the 7th Framework
        Program (Grant Agreement No. 257943)
Key facts about BIG-project                                                               BIG
                                                                     Big Data Public Private Forum




▶   Type of project: CSA
▶   Project start date: September 2012
▶   Duration: 26 months
▶   Call: FP7-ICT-2011-8
▶   Effort: 552,5 PM
▶   Budget: 3,038 M€
▶   Max EC contribution: 2,499 M€
▶   Consortium: 11 partners




                                   Overall objective
               Work at technical, business and policy levels, shaping the
            future through the positioning of IIM and Big Data specifically
            in H2020 and bringing the necessary stakeholders into a self-
            sustainable industrially-led initiative will greatly contribute to
             enhance the EU competitiveness taking full advantage of Big
                                         Data.

BIG project general presentation October 2012                                         2     BIG 318062
Why BIG project at his moment?                                                                    BIG
                                                                              Big Data Public Private Forum




 • The strategic importance that Big Data technology. From Intelligent
   Information Management in general and Big Data in particular. We are aligned
   with the new unit called G3 Data Value Chain.

 • Push European Big Data research but also the innovation above to
   contribute in increasing the European competitiveness and materializing
   opportunities in the Big Data domains.

 • Therefore BIG will promote a well-developed EU industrial landscape in Big
   Data.
   – Providing a clear picture of existing technology trends and their maturity.

   – Acquiring a sharp understanding of how big data can be applied to concrete environments.

   – Pushing European Big Data research as well as the innovation to contribute in increasing
      European competitiveness.
   – Building a self-sustainable, industry-led intitiative.




Kick Off meeting 10-11/09/2012                                                                 3     BIG 318062
The BIG Idea                                                                              BIG
                                                                      Big Data Public Private Forum




 The approach of BIG to contribute to high quality research can be summarized as
 follows:


 •Not only technology, but also business, policy and regulation;

 •Not only generic plans for research and adoption, but specific plans for those
 sectors that are positioned for greater gains from the use of Big Data;
 •Not only theoretical activities including roadmaps, coordination and dissemination
 aiming at future actions, but also actions in the course of the project to foster
 understanding and adoption of current technology solutions;
 •Not only development activities in the a limited timeframe (the duration of the
 project), but the creation of an operational framework (including stakeholder
 engagement and leadership, organizational structures and technical infrastructure)
 as a starting point for future work that will go beyond the project duration.


Kick Off meeting 10-11/09/2012                                                         4     BIG 318062
Concrete Objectives of BIG project                                                        BIG
                                                                      Big Data Public Private Forum




 • Concretion of Stakeholder’s and players in the value chain.

 • Note and explain a clear picture of existing technological trends and its maturity.

 • Acquire a sharp understanding of how big data can be applied to concrete
   environments/sectors.
 • Approach dissemination actions targeting different stakeholders.

 • Define priorities based on expected impact.

 • Contribute to EU competitiveness and position it in Horizon 2020.


      The main objective is to establish a platform for EU data bound
      industries and data researchers to develop a common vision of
        where Europe should be heading in the 5-10 year future and
       what the supporting role of the European Commission might
                                    be.

Kick Off meeting 10-11/09/2012                                                         5     BIG 318062
From an existing need… for a better result                                             BIG
                                                                  Big Data Public Private Forum




                BIG project goes                And what Big Data is for


        From technology to adoption             Large-scale data processing


                                                 Unveiling new data-driven
           Seeking business impact                services to citizens and
                                                         customers

        Anticipating future R&D and             Tracking social information
              industrial needs,                    and customers needs

          Providing technical and               Fulfilling current needs and
        domain-specific sound advice             further unknown analysis




BIG project general presentation October 2012                                      6     BIG 318062
Project Structure (Work Packages)                                                                  BIG
                                                                              Big Data Public Private Forum




• WP1. Management, dealing with scientific, administrative and financial
  management of the project.
• WP2. Strategy & Operations, include all the technical and sectorial activity.
  – We structure our work along a matrix in which technical specialists and sectorial experts
    collaborate, in order to foster crossfertilisation during the project run-time and beyond.

• WP3. Dissemination and Stakeholder Engagement
  – This WP will cover a wide spectrum of activities, including and not restricted to:
    community extension and management, web site development, BIG conferences
    organization, etc.

• WP4. Big Data Public-Private Forum. This WP will provide:
  – relevant input to H2020.

  – the basis for a sustainable initiative that goes beyond the project duration.

  – links between the Big Data Public-Private Forum and other relevant initiatives in the
    European area.
BIG project general presentation October 2012                                                  7     BIG 318062
Setting up BIG-project Sector’s roadmap                                                               BIG
                                                                                 Big Data Public Private Forum




                                                ▶ Gather requirements and objectives from
                 Identification of
                                                  all Sectors identified (industry driven
                Sector’s requisites
                                                  working groups)


                 Applicability of
                                                ▶ Introduce technologies and trends to the
                Big Data technical
                                                  organizations to better understand Big
                 white papers in
                                                  Data technologies and its capabilities
                   each Sector


                                                ▶ Sectorial roadmap (elaborate a roadmap
                   Elaboration of                 per sector).
                  Sector Roadmap                ▶ Contributions towards integrated roadmap
                                                  (cross-sectorial)




BIG project general presentation October 2012                                                     8     BIG 318062
Sectorial forums and technical working groups                        BIG
                                                Big Data Public Private Forum




BIG project general presentation October 2012                    9     BIG 318062
Project Structure (Gantt)                                                                                        BIG
                                                                                            Big Data Public Private Forum




                                           Period 1                                  Period 2

                       1   2   3   4   5   6    7   8   9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

                       Operational management
                       Operational management
      WP1              Project administrative coordination
                        Project administrative coordination
                       Quality assessment
                        Quality assessment
                       Coord.& Collab. Structure and Processes
                       Coord.& Collab. Structure and Processes
      WP2                   Technological surveys and analysis
                             Technological surveys and analysis
                                                      Sectors' Roadmap
                                                       Sectors' Roadmap
                                                      consolidation
                                                       consolidation
                       Dissemination strategy
                        Dissemination strategy
      WP3              Collaboration spaces
                        Collaboration spaces
                              Stakeholder identification and engagement
                               Stakeholder identification and engagement
                       Sustainability
                        Sustainability
      WP4                                  Towards Horizon 2020
                                            Towards Horizon 2020
                       Governance structure
                       Governance structure

BIG project general presentation October 2012                                                              10      BIG 318062
Timeline of the most important deliverables                                                                            BIG
                                                                                                  Big Data Public Private Forum




04/2013                                                                                                                      04/2013
D2.2.1-1º version of Technical                    D2.2.1             D2.3.1            D2.3.1-1º version of Sector’s requisites
white papers

                                                                                                                             06/2013
                                                            D4.2.1                   D4.2.1-1ºversion of IPR, Standardization
                                                                                                          •recommendations
10/2013
D4.3.1-First draft of the
Big Data Public-Private Forum                     D4.3.1             D2.4.1                                                  09/2013
                                                                                                              D2.4.1 1ª version of
01/2014                                                                                                        Sector´s Roadmap
D2.2.2-Final version of                                    D2.2.2
Technical white paper
                                                                                                                             04/2014
                                                                                                          D2.3.2-Final version of
04/2014                                         D4.2.2               D2.3.2
                                                                                                              Sectors requisites
D4.2.2-Final version of IPR,
Standardization recommendations
                                                                                                                             10/2014
                                                                              D2.5              D2.5-Cross-sectorial roadmap
                                                                                                               consolidation




BIG project general presentation October 2012                                                                    11      BIG 318062
Big Data Public Private Forum




THANK YOU
General contact
info@big-project.eu

Project Coordinator
Jose Maria Cavanillas de San Segundo
Research & Innovation Director

Big Data Public-Private Forum_General Presentation

  • 1.
    Big Data PublicPrivate Forum BIG DATA PUBLIC PRIVATE FORUM (BIG) GENERAL PRESENTATION Project co-funded by the European Commission within the 7th Framework Program (Grant Agreement No. 257943)
  • 2.
    Key facts aboutBIG-project BIG Big Data Public Private Forum ▶ Type of project: CSA ▶ Project start date: September 2012 ▶ Duration: 26 months ▶ Call: FP7-ICT-2011-8 ▶ Effort: 552,5 PM ▶ Budget: 3,038 M€ ▶ Max EC contribution: 2,499 M€ ▶ Consortium: 11 partners Overall objective Work at technical, business and policy levels, shaping the future through the positioning of IIM and Big Data specifically in H2020 and bringing the necessary stakeholders into a self- sustainable industrially-led initiative will greatly contribute to enhance the EU competitiveness taking full advantage of Big Data. BIG project general presentation October 2012 2 BIG 318062
  • 3.
    Why BIG projectat his moment? BIG Big Data Public Private Forum • The strategic importance that Big Data technology. From Intelligent Information Management in general and Big Data in particular. We are aligned with the new unit called G3 Data Value Chain. • Push European Big Data research but also the innovation above to contribute in increasing the European competitiveness and materializing opportunities in the Big Data domains. • Therefore BIG will promote a well-developed EU industrial landscape in Big Data. – Providing a clear picture of existing technology trends and their maturity. – Acquiring a sharp understanding of how big data can be applied to concrete environments. – Pushing European Big Data research as well as the innovation to contribute in increasing European competitiveness. – Building a self-sustainable, industry-led intitiative. Kick Off meeting 10-11/09/2012 3 BIG 318062
  • 4.
    The BIG Idea BIG Big Data Public Private Forum The approach of BIG to contribute to high quality research can be summarized as follows: •Not only technology, but also business, policy and regulation; •Not only generic plans for research and adoption, but specific plans for those sectors that are positioned for greater gains from the use of Big Data; •Not only theoretical activities including roadmaps, coordination and dissemination aiming at future actions, but also actions in the course of the project to foster understanding and adoption of current technology solutions; •Not only development activities in the a limited timeframe (the duration of the project), but the creation of an operational framework (including stakeholder engagement and leadership, organizational structures and technical infrastructure) as a starting point for future work that will go beyond the project duration. Kick Off meeting 10-11/09/2012 4 BIG 318062
  • 5.
    Concrete Objectives ofBIG project BIG Big Data Public Private Forum • Concretion of Stakeholder’s and players in the value chain. • Note and explain a clear picture of existing technological trends and its maturity. • Acquire a sharp understanding of how big data can be applied to concrete environments/sectors. • Approach dissemination actions targeting different stakeholders. • Define priorities based on expected impact. • Contribute to EU competitiveness and position it in Horizon 2020. The main objective is to establish a platform for EU data bound industries and data researchers to develop a common vision of where Europe should be heading in the 5-10 year future and what the supporting role of the European Commission might be. Kick Off meeting 10-11/09/2012 5 BIG 318062
  • 6.
    From an existingneed… for a better result BIG Big Data Public Private Forum BIG project goes And what Big Data is for From technology to adoption Large-scale data processing Unveiling new data-driven Seeking business impact services to citizens and customers Anticipating future R&D and Tracking social information industrial needs, and customers needs Providing technical and Fulfilling current needs and domain-specific sound advice further unknown analysis BIG project general presentation October 2012 6 BIG 318062
  • 7.
    Project Structure (WorkPackages) BIG Big Data Public Private Forum • WP1. Management, dealing with scientific, administrative and financial management of the project. • WP2. Strategy & Operations, include all the technical and sectorial activity. – We structure our work along a matrix in which technical specialists and sectorial experts collaborate, in order to foster crossfertilisation during the project run-time and beyond. • WP3. Dissemination and Stakeholder Engagement – This WP will cover a wide spectrum of activities, including and not restricted to: community extension and management, web site development, BIG conferences organization, etc. • WP4. Big Data Public-Private Forum. This WP will provide: – relevant input to H2020. – the basis for a sustainable initiative that goes beyond the project duration. – links between the Big Data Public-Private Forum and other relevant initiatives in the European area. BIG project general presentation October 2012 7 BIG 318062
  • 8.
    Setting up BIG-projectSector’s roadmap BIG Big Data Public Private Forum ▶ Gather requirements and objectives from Identification of all Sectors identified (industry driven Sector’s requisites working groups) Applicability of ▶ Introduce technologies and trends to the Big Data technical organizations to better understand Big white papers in Data technologies and its capabilities each Sector ▶ Sectorial roadmap (elaborate a roadmap Elaboration of per sector). Sector Roadmap ▶ Contributions towards integrated roadmap (cross-sectorial) BIG project general presentation October 2012 8 BIG 318062
  • 9.
    Sectorial forums andtechnical working groups BIG Big Data Public Private Forum BIG project general presentation October 2012 9 BIG 318062
  • 10.
    Project Structure (Gantt) BIG Big Data Public Private Forum Period 1 Period 2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Operational management Operational management WP1 Project administrative coordination Project administrative coordination Quality assessment Quality assessment Coord.& Collab. Structure and Processes Coord.& Collab. Structure and Processes WP2 Technological surveys and analysis Technological surveys and analysis Sectors' Roadmap Sectors' Roadmap consolidation consolidation Dissemination strategy Dissemination strategy WP3 Collaboration spaces Collaboration spaces Stakeholder identification and engagement Stakeholder identification and engagement Sustainability Sustainability WP4 Towards Horizon 2020 Towards Horizon 2020 Governance structure Governance structure BIG project general presentation October 2012 10 BIG 318062
  • 11.
    Timeline of themost important deliverables BIG Big Data Public Private Forum 04/2013 04/2013 D2.2.1-1º version of Technical D2.2.1 D2.3.1 D2.3.1-1º version of Sector’s requisites white papers 06/2013 D4.2.1 D4.2.1-1ºversion of IPR, Standardization •recommendations 10/2013 D4.3.1-First draft of the Big Data Public-Private Forum D4.3.1 D2.4.1 09/2013 D2.4.1 1ª version of 01/2014 Sector´s Roadmap D2.2.2-Final version of D2.2.2 Technical white paper 04/2014 D2.3.2-Final version of 04/2014 D4.2.2 D2.3.2 Sectors requisites D4.2.2-Final version of IPR, Standardization recommendations 10/2014 D2.5 D2.5-Cross-sectorial roadmap consolidation BIG project general presentation October 2012 11 BIG 318062
  • 12.
    Big Data PublicPrivate Forum THANK YOU General contact info@big-project.eu Project Coordinator Jose Maria Cavanillas de San Segundo Research & Innovation Director