SlideShare a Scribd company logo
2. ADVERTISEMENT/POSTING OF THE INVITATION TO
BID OR REQUEST FOR EXPRESSION OF INTEREST
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
 Purpose: To signal the start of the bidding process and invite interested
bidders to participate in the procurement activity, through the following:
 Bid opportunity, including complete Bidding Documents is uploaded for
at least seven (7) calendar days at the websites of the agency and the
Philippine Government Electronic Procurement System (PhilGEPS);
 Bid opportunity is posted at conspicuous places; and
 Recently Repealed: Advertisement in at least one (1) newspaper of
general nationwide circulation for procurement projects with ABC
>PhP10,000,000.00 for Goods, >PhP 15,000,000.00 for Infrastructure
Projects, and >PhP5,000,00.00 for Consulting Services
2. ADVERTISEMENT/POSTING
 Procuring entity may charge fees for the acquisition of Bidding Documents
based on the following rates:
APPROVED BUDGET FOR THE
CONTRACT
MAXIMUM COST OF BIDDING
DOCUMENTS IN PHP
500, 000 and below 500.00
More than 500, 000 up to 1 Million 1,000.00
More than 1 Million up to 5 Million 5,000.00
More than 5 Million up to 10 Million 10,000.00
More than 10 Million up to 50 Million 25,000.00
More than 50 Million to 500 Million 50,000.00
More than 500 Million 75,000.00
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
3. PRE-BID CONFERENCE
 Purpose: To discuss, clarify and explain the different aspects of the
project of the procuring entity with the prospective bidders
 When is it conducted: Held at least 12 calendar days before the
deadline for bid submission but not earlier than seven (7) calendar
days from the advertisement/posting of bid opportunity
 Required for procurement projects with ABC of equal to or more than
1,000,000.00
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
3. PRE-BID CONFERENCE
 May be conducted in person or face-to-face through
videoconferencing, webcasting, or similar technology, or a
combination thereof
 Answers to requests for clarifications or interpretation, as well as any
changes in the Bidding Documents shall be issued by the BAC through
the Supplemental/Bid Bulletins which is posted at the websites of
PhilGEPS and the agency, and at conspicuous places at least seven (7)
calendar days before the deadline for the submission of bids
 Modification or withdrawal of bids is allowed prior to the deadline for
the submission of bids
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
4. RECEIPT AND OPENING OF BIDS
 Bids submitted should be on the date, time, and place specified in
the advertisement through a Two-Envelope System:
 1st Envelope - Eligibility Requirements (except for Consulting
Services) and Technical Component
 2nd Envelope – Financial Component
 Only the 2nd envelope of eligible bidders whose 1st envelope have
been rated “passed” shall be opened
 Bids submitted after the deadline shall not be accepted
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
In the case of foreign bidders, appropriate equivalent documents issued
by the country of the foreign bidder under Class “A” Documents shall be
submitted, provided that:
 The documents are in English, or
 If the documents submitted are in a foreign language other than
English, it must be accompanied by a translation of documents in
English by any of the following:
 relevant foreign government agency;
 the foreign government agency authorized to translate
documents, or
 a registered translator in the foreign bidder’s country.
 Submitted documents of foreign bidder shall be authenticated by the
appropriate Philippine foreign service establishment/post or the
equivalent office having jurisdiction over the foreign bidder’s affairs
in the Philippines.
 Only upon actual determination and confirmation of this equivalence
through post qualification by the BAC may it be categorically
resolved that the foreign documents submitted are acceptable
substitutes of the required eligibility documents pursuant to Section
23.2 of the IRR. (NPM 42-2013)
 Only 1 form of Bid Security among the following allowed forms
is required to be submitted by the participating bidders
Form of Bid Security
Amount
Bid Security (% = ABC)
a) Cash or cashier’s/manager’s check
2%
b) Bank guarantee/draft or Irrevocable LC
c) Surety bond callable upon demand 5%
e) Bid Securing Declaration No percentage required
4. RECEIPT AND OPENING OF BIDS
 To ensure transparency and accurate representation of the bid
submission, the BAC Secretariat shall notify in writing all bidders
whose bids it has received within seven (7) calendar days from the
date of the bid opening.
 Original copy of bid form shall be typed or written in ink and shall be
signed by the bidder or its duly authorized representative
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
5. BID EVALUATION
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
 Purpose: To determine the Lowest Calculated Bid/LCB (for Goods and
Infrastructure Projects) or Highest Rated Bid/HRB (for Consulting
Services) by:
 Establishing correct calculated prices of bids; and
 Ranking calculated total bid prices from lowest to highest
 A non-discretionary criterion shall be used, which shall include
consideration of:
 Completeness of bids; and
 Minor arithmetical corrections
5. BID EVALUATION FOR CONSULTING SERVICES
 Two Methods of Evaluation:
 Quality-Based Evaluation (QBE) which considers only the
Technical Proposals in the ranking of consultants
 Quality-Cost-Based Evaluation (QCBE) which considers both the
Technical and Financial Proposals in the ranking of consultants
 Evaluation may be per individual or collegial
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
5. BID EVALUATION
 The No Contact Rule which prohibits communication between bidders and the
BAC shall apply only to those whose bids are being evaluated by the BAC after
passing the preliminary examination until the issuance of Notice of Award.
 No communication should be made by bidders until a decision to award a
contract is made by the BAC
 Domestics Preference shall only apply to Goods where the lowest bid has a
foreign component (foreign bid/entity) and the next lowest bid has a
domestic component (domestic bidder/entity)
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
NEGOTIATION FOR CONSULTING SERVICES
 Negotiations shall cover the following:
a) Discussion and clarification of the TOR and Scope of Services;
b) Discussion and finalization of the Procedural Requirements and work
program;
c) Consideration of appropriateness of qualifications and pertinent
compensation, number of man-months and the personnel;
d) Discussion on the services, facilities and data, if any, to be provided by
PE
concerned
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
NEGOTIATION FOR CONSULTING SERVICES
 Negotiations shall cover the following:
e) Discussion on the financial proposal submitted by the
consultant for QBE; and
f) Provisions of the contract.
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
 Except for meritorious reasons, negotiations with any one
consultant shall be completed within ten (10) calendar days
6. POST - QUALIFICATION
 Purpose: To determine whether the bidder/consultant with the LCB/HRB
complies with and is responsive to all requirements and conditions of
eligibility and the bidding of the contract – to be declared the Lowest
Calculated and Responsive Bid (LCRB)/Highest Rated Responsive Bid
(HRRB)
 A non-discretionary pass/fail criterion shall be used to “Verify, Validate
and Ascertain” all statements and documents (licenses, certificates, etc.)
submitted by the LCB/HRB
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
7. AWARD OF CONTRACT
 Additional documents are also required to be submitted by the
LCRB/HRRB
 Contract shall be awarded to the bidder with the LCRB/HRRB at its
submitted price or total calculated bid price, whichever is lower
 The BAC shall notify all other bidders, in writing, of its
recommendation to HOPE of award of contract to LCRB/HRRB within
three (3) calendar days from the issuance of the resolution
recommending award
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
7. AWARD OF CONTRACT
 The Notice of Award (NOA) and Notice to Proceed (NTP) are issued
by the Head of the Procuring Entity (HoPE)
 The NOA, and NTP along with the contract are required to be
posted at the websites of PhilGEPS and the agency, and at any
conspicuous place within three (3) calendar days and 15 calendar
days from the respective date of issuance
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
7. AWARD OF CONTRACT
 The contract effectivity date should be provided in the Notice to
Proceed, which should not be later than seven (7) calendar days
from its issuance.
 The BAC Secretariat shall post the NOA in the PhilGEPS, PE’s
websites and in any conspicuous place within 3 calendar days
from its issuance.
Pre-Procurement
Conference
Advertisement
and Posting
Pre-Bid
Conference
Receipt and
Opening of Bids
Bid Evaluation
Post-
Qualification
Award of
Contract
FAILURE OF BIDDING
 A failure of bidding is declared by the BAC when:
a) No bids are received;
b) Bids were received but no one was eligible;
c) All bids failed to post qualify; or
d) Someone post qualified but refused without justifiable cause
to
accept the award.
RESERVATION CLAUSE
 The HoPE reserves the right to:
a) Reject any and all bids;
b) Declare a failure of bidding; or
c) Not award the contract.
 Grounds:
a) Prima facie evidence of collusion;
b) BAC is found to have failed in following the prescribed bidding
procedures;
c) For justifiable reasons, the award of contract will not redound to
the
benefit of the Government
RECOMMENDED POSSIBLE PERIOD TO
COMPLETE THE PROCUREMENT ACTIVITY
Type
Earliest Period
(calendar days)
Maximum
Period
(calendar
days)
Goods and Services 26 136
Infrastructure
Projects
26 142 or 156
Consulting Services 36 180
PARTICIPATION OF OBSERVERS
 Observers represent the public, the taxpayers who are interested
in seeing to it that procurement laws are observed and
irregularities are averted
 At least three (3) Observers shall be invited by the BAC coming
from the following:
a) Commission on Audit (COA);
b) Duly recognized private group in the sector or discipline of
the particular type of procurement involved; and
c) Non-Government Organization (NGO)
PARTICIPATION OF OBSERVERS
 Observes must be invited in writing at least five (5) calendar days
before the date of the following procurement stage/activity:
a) Eligibility checking;
b) Shortlisting;
c) Pre-bid Conference;
d) Preliminary examination of bids;
e) Bid evaluation; and
f) Post qualification
 The GPPB has issued Standard Bidding Documents to be adopted
by all procuring entities, downloadable at the GPPB website:
a) Philippine Bidding Documents for Goods and Services, 5th
Edition
b) Philippine Bidding Documents for Infrastructure Projects, 5th
Edition
c) Philippine Bidding Documents for Consulting Services, 5th
Edition
25
RA 8182 as amended by RA 8555
Procurement funded from Foreign Grants
An Act Excluding Official Development Assistance (ODA)
from the Foreign Debt Limit in order to Facilitate the
Absorption and Optimize the Utilization of ODA Resources
Acquisition of Real Property
RA 8974 as amended by RA 10752
“An Act to Facilitate the Acquisition of Right-of-Way Site
or Location for National Government Infrastructure
Projects and for Other Purposes,”
Public-Private Sector Projects
RA 6957 as amended by RA 7718 (BOT Law)
“An Act Authorizing the Financing, Construction,
Operation and Maintenance of Infrastructure Projects by
the Private Sector, and for Other Purposes,”
Direct financial or material assistant to beneficiaries
If the direct financial or material assistance takes the form of goods, supplies or items that are
to be procured (e.g., relief goods), the same do not fall within the coverage of the cited
provision, but is subject to procurement rules and regulations embodied in RA 9184 and its IRR.
- (GPPB Circular 01-2017)
Participation to scholarships, training programs, continuing education,
etc.
Lease of government property for private use
Job order workers
Joint Venture Agreements between Private Entities and GOCCs or LGUs
Disposal of property and assets
Issue/s Revision Impact
Lack of
members to
constitute
BAC
Allows designation of an officer of the
next lower rank, in case of
unavailability of 5th ranking
permanent official (except for BAC
Chairperson) (Sec. 11.2.2)
In case of procurement outsourcing, a
representative from the Procuring Entity
may be designated as a provisional
member
The Chairperson and Vice-chairperson
shall be designated by the local chief
executive (Sec.11.2.2, 11.2.3(a),
11.2.3(b)(iii))
Increases the
pool from which
HOPE select its
BAC members
32
Issue/s Revision Impact
Lack of full-
time BAC
Sec
members to
support the
BAC in every
procurement
activity
Allows designation of an officer of the
next lower rank, in case of
unavailability of 5th ranking permanent
official
In case of ad hoc BAC Secretariat,
the HOPE shall assign full-time
support staff in its BAC Secretariat
(Sec. 14.2)
Fast-track
procurement
34
Issue/s Revision Impact
Lack of
training of
HOPE, BAC,
Secretariat
and TWG
The HoPE shall ensure that the BAC,
its Secretariat and TWG members,
including other relevant procurement
personnel are sent to attend capacity
development program.
Within six (6) months upon
designation, the BAC, its Secretariat
and TWG members should have
satisfactorily completed such training
or program conducted, authorized
or accredited by the GPPB through
its Technical Support Office.
Procurement
Professionali-
zation
36
Issue/s Revision Impact
Poor
specifications
a. Bid documents shall reflect the
necessary specifications required
to meet the needs of the PE
b. For mixed procurement, PE shall
specify all relevant requirements
for each procurement type (Sec.
17.2)
Quality of
Goods for the
lowest prices
Non-
Refundable
Fee
For bid docs
Provide instances when bid doc fees
may be refunded to the bidder, i.e.
declaration of failure of bidding
under Section 41 (Sec. 17.5)
Fairness in
procurement
38
Issue/s Revision Impact
Difficulty in
preparing
technical
specifications
Reference to
Brand Names
Prohibition on brand names likewise
apply to the goods component of
Infrastructure Projects and
Consulting Services. (Sec. 18)
However, PEs may indicate brand
names for items or parts that are
compatible with the existing fleet or
equipment of the same make and
brand and will maintain the
performance, functionality and useful
life of the equipment.
Ensure
compatibility,
interoperability,
performance,
functionality
and useful life
of the
equipment.
40
Issue/s Revision Impact
Newspaper
advertisement
a. Increase thresholds for
advertisement requirement
b. 2 years sunset clause on
advertisement requirement (Sec.
21.2.1)
Reduce
government cost
for newspaper
advertisements
Low
participation of
bidders in pre-
bid
a. Allow conduct of pre-bid via video-
conferencing, webcasting
b. Allow all prospective bidders
(even those who did not buy bid
docs) to raise queries (Sec. 22)
Clarifies
procurement
requirements;
Reduce
disqualification;
Increase
competition
42
Issue/s Revision Impact
Disqualificati
on of
Bidders/
Failure of
Biddings due
to
documentary
requirements
Low turn-out
of bidders
a. Mandatory registration under
Platinum Membership (Sec. 8.5.2,
25.2)
Per GPPB Circular No. 07-2017 which
took effect on 3 September 2017, the
mandatory requirement under Sec.
8.5.2 on the submission of PhilGEPS
Certificate of Registration and
Membership under Platinum
category for Competitive Bidding,
Limited Source Bidding and Two-
Failed Bidding has been deferred
until revoked by the GPPB.
Easier
eligibility check
Reduce
disqualification
of bidders/
failure of
biddings
Increase
competition
43
Issue/s Revision Impact
Disqualification
of Bidders/
Failure of
Biddings due to
documentary
requirements
Low turn-out of
bidders
b. Mayor’s permit:
- Allows submission of recently
expired mayor’s permit with
official receipt of application
for renewal of permit
- Allows equivalent document
for economic zones (Sec.
23.1(a)(ii), 24.1(a)(ii))
c. For goods procurement,
submission of a Credit Line, as
an alternative to NFCC (Sec.
23.1(a)(viii))
Easier
eligibility check
Reduce
disqualification
of bidders/
failure of
biddings
Increase
competition
44
Issue/s Revision Impact
Disqualificatio
n of Bidders/
Failure of
Biddings due
to
documentary
requirements
Low turn-out
of bidders
b. Mayor’s permit:
- Allows submission of recently
expired mayor’s permit with official
receipt of application for renewal of
permit
- Allows equivalent document for
economic zones (Sec. 23.1(a)(ii),
24.1(a)(ii))
c. For goods procurement, submission
of a Credit Line, as an alternative to
NFCC (Sec. 23.1(a)(viii))
Easier eligibility
check
Reduce
disqualification
of bidders/
failure of
biddings
Increase
competition
46
Issue/s Revision Impact
Disqualification
of
Bidders/Failure
of Biddings
due to
documentary
requirements
Low turn-out of
bidders
d. For goods and infrastructure projects,
fixing the NFCC’s K factor at 15,
regardless of contract duration (Sec.
23.4.1.4, 23.4.2.7)
e. For individual consultants not
registered as sole proprietors,
they can submit BIR Certificate of
Registration instead of DTI and
Mayor’s Permit (Sec. 24.1(a)(ii))
f. In consulting services, submission of
foreign bidders’ SEC Certificate of
Registration and/or PRC permit is
moved from eligibility to contract
award (Sec. 37.1.4(a)(iv))
Easier
eligibility check
Reduce
disqualification
of bidders/
failure of
biddings
Increase
competition
48
Issue/s Revision Impact
Strict rules on
marking/
sealing of
bids
Bid envelopes that are not properly
sealed and marked, as required in the
bidding documents, shall be
accepted, provided that the bidder or
its duly authorized representative shall
acknowledge such condition of the
bid as submitted. The BAC shall
assume no responsibility for the
misplacement of the contents of the
improperly sealed or marked bid, or for
its premature opening(Sec. 25.9)
Reduce
disqualification
of bidders
50
Issue/s Revision Impact
Bid Rigging/
Simulation of
bids;
a. BAC Secretariat shall notify in
writing all bidders whose bids it
has received through its PhilGEPS-
registered physical address or
official e-mail address (Sec. 25.7)
b. The BAC shall notify all other
bidders, in writing, of its
recommendation to HOPE of
award of contract to LCRB/HRRB
within 3 calendar days. (Sec.
37.1.1)
Ensure
transparency
and accurate
representation
of the bid
submission
52
Issue/s Revision Impact
Procurement
by Foreign
Service Posts
a. Exempts foreign bidders from the
mandatory PhilGEPS Certificate of
Registration (Sec. 25.2)
b. Winning bidder shall be required
to register (Registration Number
only) prior to contract signing.
(Section 37.1.4(a)(ii)
Encourage
participation of
foreign bidders
in the
procurement
by FSPs
Bid and
Performance
Securities
a. Allows the bidder to choose their
preferred form of bid security (Sec.
27.2)
b. Clarifies the required amount for Bid
Security and Performance
Security(Secs. 27.2 and 39.2)
Avoid undue
disqualification
of bidders who
posted more
than the
required
amount.
54
Issue/s Revision Impact
Bid and
Performance
Securities
a. Allows the bidder to choose their
preferred form of bid security
(Sec. 27.2)
b. Clarifies the required amount for Bid
Security and Performance
Security(Secs. 27.2 and 39.2)
Avoid undue
disqualification
of bidders who
posted more
than the
required
amount.
58
Issue/s Revision Impact
Difficulty in
procuring the
following:
-Media
services;
-Scientific,
academic
references,
works
- life-saving
equipment
-Legal services
-Artistic works
- Infra projects
with exclusive
technology
New Alternative Modality:
Section 53.6 Scientific, Scholarly or
Artistic Work, Exclusive Technology
and Media Services.
Efficiency in
procurement
considering
that only 1
supplier/contra
ctor could
provide the
needs of the
PE
60
Issue/s Revision Impact
Delay in
procurement
process due to
declaration of
holidays
Specific procurement activities
may be held on a Saturday, Sunday,
nonworking day or holiday: provided,
that the BAC, secretariat and TWG
members shall be available on such
date, and the appropriate
supplemental/bid bulletin is
issued and posted pursuant to the
posting requirements embodied in
section 22.5.3 of
this IRR.
(GPPB Resolution No. 21-2017)
Fast-track
procurement
activities
62
Issue/s Revision
The number
of quotation
that the BAC
has to obtain,
in order to
proceed with
the
negotiation
a. Shopping 52.1(a) and Emergency Procurement–
send at least 1 RFQ
b. Shopping 52.1(b) – send at least 3 RFQs, receive
at least 3 quotations
c. Two Failed Biddings, Small Value Procurement,
Lease of Real Property/Venue - send at least 3
RFQs, receive at least 1 quotation will suffice
Streamline Bidding Process
Use of pump prices for the procurement of non-bulk petroleum, oil and lubricant
products
Use of Digital Signature on all procurement documents
Use of Videoconferencing, Webcasting and Similar Technology in the Conduct
of Meetings and Determination of Quorum by the BAC
Responsive Bidding Rules
Rules for Sangguniang Kabataan Procurement
Removal on the ceiling of maximum percentage of liquidated damage
BIDDING PROCEDURES AND UPDATES.pptx

More Related Content

What's hot

Supply and property management
Supply and property managementSupply and property management
Supply and property management
JosephCarreon6
 
Ra 9184
Ra 9184Ra 9184
Philippine procurement system
Philippine procurement systemPhilippine procurement system
Philippine procurement system
eddiethehead1968
 
Philippine government procurement
Philippine government procurementPhilippine government procurement
Philippine government procurement
haragascon
 
Procurement
ProcurementProcurement
Procurement
Howard Untalan
 
RA9184 GPPB Presentation
RA9184 GPPB PresentationRA9184 GPPB Presentation
RA9184 GPPB PresentationAlain Pinsotes
 
Ra9184 rules
Ra9184 rulesRa9184 rules
Ra9184 rules
jbonvier
 
Salient Features_RA 9184.pptx
Salient Features_RA 9184.pptxSalient Features_RA 9184.pptx
Salient Features_RA 9184.pptx
DanteRevamonte
 
Got Problems with Government Procurement? Here's how to do it right.
Got Problems with Government Procurement?  Here's how to do it right.Got Problems with Government Procurement?  Here's how to do it right.
Got Problems with Government Procurement? Here's how to do it right.
Ninfa Geloryao
 
Ge 122 lecture 3 (CADASTRAL AND PUBLIC LAND SUBDIVISION SURVEY) by: Broddett ...
Ge 122 lecture 3 (CADASTRAL AND PUBLIC LAND SUBDIVISION SURVEY) by: Broddett ...Ge 122 lecture 3 (CADASTRAL AND PUBLIC LAND SUBDIVISION SURVEY) by: Broddett ...
Ge 122 lecture 3 (CADASTRAL AND PUBLIC LAND SUBDIVISION SURVEY) by: Broddett ...
BPA ABATAYO Land Surveying Services
 
Construction disputes
Construction disputesConstruction disputes
Construction disputes
gayathrysatheesan1
 
Topic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxTopic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptx
VanJasperCastillo
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
VISHNU VIJAYAN
 
Republic Act No. 9184
Republic Act No. 9184Republic Act No. 9184
Republic Act No. 9184
esviege
 
Powerpoint Presentation on Public Procurement.pdf
Powerpoint Presentation on Public Procurement.pdfPowerpoint Presentation on Public Procurement.pdf
Powerpoint Presentation on Public Procurement.pdf
kayerencaole1
 
Sglg 2021 lds
Sglg 2021 ldsSglg 2021 lds
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Juan Paolo Somorostro - Aranas, MPA, BSOSM
 
01 RA9184 SEMINAR.pptx
01 RA9184 SEMINAR.pptx01 RA9184 SEMINAR.pptx
01 RA9184 SEMINAR.pptx
MichaelVMagallano
 
Real Estate Service Act Philippines
Real Estate Service Act PhilippinesReal Estate Service Act Philippines
Real Estate Service Act Philippines
Gus Agosto
 

What's hot (20)

Supply and property management
Supply and property managementSupply and property management
Supply and property management
 
Ra 9184
Ra 9184Ra 9184
Ra 9184
 
Philippine procurement system
Philippine procurement systemPhilippine procurement system
Philippine procurement system
 
Philippine government procurement
Philippine government procurementPhilippine government procurement
Philippine government procurement
 
Procurement
ProcurementProcurement
Procurement
 
RA9184 GPPB Presentation
RA9184 GPPB PresentationRA9184 GPPB Presentation
RA9184 GPPB Presentation
 
Ra9184 rules
Ra9184 rulesRa9184 rules
Ra9184 rules
 
Salient Features_RA 9184.pptx
Salient Features_RA 9184.pptxSalient Features_RA 9184.pptx
Salient Features_RA 9184.pptx
 
Got Problems with Government Procurement? Here's how to do it right.
Got Problems with Government Procurement?  Here's how to do it right.Got Problems with Government Procurement?  Here's how to do it right.
Got Problems with Government Procurement? Here's how to do it right.
 
Ge 122 lecture 3 (CADASTRAL AND PUBLIC LAND SUBDIVISION SURVEY) by: Broddett ...
Ge 122 lecture 3 (CADASTRAL AND PUBLIC LAND SUBDIVISION SURVEY) by: Broddett ...Ge 122 lecture 3 (CADASTRAL AND PUBLIC LAND SUBDIVISION SURVEY) by: Broddett ...
Ge 122 lecture 3 (CADASTRAL AND PUBLIC LAND SUBDIVISION SURVEY) by: Broddett ...
 
Procurement process
Procurement processProcurement process
Procurement process
 
Construction disputes
Construction disputesConstruction disputes
Construction disputes
 
Topic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxTopic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptx
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Republic Act No. 9184
Republic Act No. 9184Republic Act No. 9184
Republic Act No. 9184
 
Powerpoint Presentation on Public Procurement.pdf
Powerpoint Presentation on Public Procurement.pdfPowerpoint Presentation on Public Procurement.pdf
Powerpoint Presentation on Public Procurement.pdf
 
Sglg 2021 lds
Sglg 2021 ldsSglg 2021 lds
Sglg 2021 lds
 
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
 
01 RA9184 SEMINAR.pptx
01 RA9184 SEMINAR.pptx01 RA9184 SEMINAR.pptx
01 RA9184 SEMINAR.pptx
 
Real Estate Service Act Philippines
Real Estate Service Act PhilippinesReal Estate Service Act Philippines
Real Estate Service Act Philippines
 

Similar to BIDDING PROCEDURES AND UPDATES.pptx

Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
Ritesh Kumar Baranwal
 
1658466483_Supply_of_Stationery_Items_English.pdf
1658466483_Supply_of_Stationery_Items_English.pdf1658466483_Supply_of_Stationery_Items_English.pdf
1658466483_Supply_of_Stationery_Items_English.pdf
AMITTRIPATHI182
 
Tpt's tendering process at a glance
Tpt's tendering process at a glanceTpt's tendering process at a glance
Tpt's tendering process at a glance
Transnet Port Terminals
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Joy Irman
 
Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...
Mauricio Portugal Ribeiro
 
Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”
RCREEE
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
umes manandhar
 
Mscm 3 c-conduct procurement-advertising
Mscm 3 c-conduct procurement-advertisingMscm 3 c-conduct procurement-advertising
Mscm 3 c-conduct procurement-advertising
AlexieMarinelaRamos
 
SBD - 3 - ICTAD
SBD - 3 - ICTADSBD - 3 - ICTAD
SBD - 3 - ICTAD
Vj NiroSh
 
Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation services
abenyeung1
 
Procurement of works
Procurement of worksProcurement of works
Procurement of works
Ayush Joshi
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptx
DoctorOkelloBen
 
DC030-202009 DOJ BAC Internal Rules for the Efficient Conduct of Procurement ...
DC030-202009 DOJ BAC Internal Rules for the Efficient Conduct of Procurement ...DC030-202009 DOJ BAC Internal Rules for the Efficient Conduct of Procurement ...
DC030-202009 DOJ BAC Internal Rules for the Efficient Conduct of Procurement ...
ssuser2a3833
 
Terms of reference CLPE auction Nº3 - 2021
Terms of reference CLPE auction Nº3 - 2021Terms of reference CLPE auction Nº3 - 2021
Terms of reference CLPE auction Nº3 - 2021
ProColombia
 
StandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdfStandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdf
PSENTHILMURUGAN2
 
Procurement of infrastructure projects
Procurement of infrastructure projectsProcurement of infrastructure projects
Procurement of infrastructure projects
wil_mia
 
Instructions to bidders
Instructions to biddersInstructions to bidders
Instructions to biddersRISHARD FAIS
 
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Gensol Engineering Limited
 

Similar to BIDDING PROCEDURES AND UPDATES.pptx (20)

Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
1658466483_Supply_of_Stationery_Items_English.pdf
1658466483_Supply_of_Stationery_Items_English.pdf1658466483_Supply_of_Stationery_Items_English.pdf
1658466483_Supply_of_Stationery_Items_English.pdf
 
Tpt's tendering process at a glance
Tpt's tendering process at a glanceTpt's tendering process at a glance
Tpt's tendering process at a glance
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...
 
Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Mscm 3 c-conduct procurement-advertising
Mscm 3 c-conduct procurement-advertisingMscm 3 c-conduct procurement-advertising
Mscm 3 c-conduct procurement-advertising
 
Document samples
Document samplesDocument samples
Document samples
 
SBD - 3 - ICTAD
SBD - 3 - ICTADSBD - 3 - ICTAD
SBD - 3 - ICTAD
 
CIDA SBD 03.pdf
CIDA SBD 03.pdfCIDA SBD 03.pdf
CIDA SBD 03.pdf
 
Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation services
 
Procurement of works
Procurement of worksProcurement of works
Procurement of works
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptx
 
DC030-202009 DOJ BAC Internal Rules for the Efficient Conduct of Procurement ...
DC030-202009 DOJ BAC Internal Rules for the Efficient Conduct of Procurement ...DC030-202009 DOJ BAC Internal Rules for the Efficient Conduct of Procurement ...
DC030-202009 DOJ BAC Internal Rules for the Efficient Conduct of Procurement ...
 
Terms of reference CLPE auction Nº3 - 2021
Terms of reference CLPE auction Nº3 - 2021Terms of reference CLPE auction Nº3 - 2021
Terms of reference CLPE auction Nº3 - 2021
 
StandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdfStandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdf
 
Procurement of infrastructure projects
Procurement of infrastructure projectsProcurement of infrastructure projects
Procurement of infrastructure projects
 
Instructions to bidders
Instructions to biddersInstructions to bidders
Instructions to bidders
 
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
 

Recently uploaded

Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
ILC- UK
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
JSchaus & Associates
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
ehbuaw
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
evkovas
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
850fcj96
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
ahcitycouncil
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
ukyewh
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
AjayVejendla3
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
ahcitycouncil
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ahcitycouncil
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
RIDPRO11
 

Recently uploaded (20)

Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
 

BIDDING PROCEDURES AND UPDATES.pptx

  • 1. 2. ADVERTISEMENT/POSTING OF THE INVITATION TO BID OR REQUEST FOR EXPRESSION OF INTEREST Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract  Purpose: To signal the start of the bidding process and invite interested bidders to participate in the procurement activity, through the following:  Bid opportunity, including complete Bidding Documents is uploaded for at least seven (7) calendar days at the websites of the agency and the Philippine Government Electronic Procurement System (PhilGEPS);  Bid opportunity is posted at conspicuous places; and  Recently Repealed: Advertisement in at least one (1) newspaper of general nationwide circulation for procurement projects with ABC >PhP10,000,000.00 for Goods, >PhP 15,000,000.00 for Infrastructure Projects, and >PhP5,000,00.00 for Consulting Services
  • 2. 2. ADVERTISEMENT/POSTING  Procuring entity may charge fees for the acquisition of Bidding Documents based on the following rates: APPROVED BUDGET FOR THE CONTRACT MAXIMUM COST OF BIDDING DOCUMENTS IN PHP 500, 000 and below 500.00 More than 500, 000 up to 1 Million 1,000.00 More than 1 Million up to 5 Million 5,000.00 More than 5 Million up to 10 Million 10,000.00 More than 10 Million up to 50 Million 25,000.00 More than 50 Million to 500 Million 50,000.00 More than 500 Million 75,000.00 Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 3. 3. PRE-BID CONFERENCE  Purpose: To discuss, clarify and explain the different aspects of the project of the procuring entity with the prospective bidders  When is it conducted: Held at least 12 calendar days before the deadline for bid submission but not earlier than seven (7) calendar days from the advertisement/posting of bid opportunity  Required for procurement projects with ABC of equal to or more than 1,000,000.00 Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 4. 3. PRE-BID CONFERENCE  May be conducted in person or face-to-face through videoconferencing, webcasting, or similar technology, or a combination thereof  Answers to requests for clarifications or interpretation, as well as any changes in the Bidding Documents shall be issued by the BAC through the Supplemental/Bid Bulletins which is posted at the websites of PhilGEPS and the agency, and at conspicuous places at least seven (7) calendar days before the deadline for the submission of bids  Modification or withdrawal of bids is allowed prior to the deadline for the submission of bids Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 5. 4. RECEIPT AND OPENING OF BIDS  Bids submitted should be on the date, time, and place specified in the advertisement through a Two-Envelope System:  1st Envelope - Eligibility Requirements (except for Consulting Services) and Technical Component  2nd Envelope – Financial Component  Only the 2nd envelope of eligible bidders whose 1st envelope have been rated “passed” shall be opened  Bids submitted after the deadline shall not be accepted Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 6. In the case of foreign bidders, appropriate equivalent documents issued by the country of the foreign bidder under Class “A” Documents shall be submitted, provided that:  The documents are in English, or  If the documents submitted are in a foreign language other than English, it must be accompanied by a translation of documents in English by any of the following:  relevant foreign government agency;  the foreign government agency authorized to translate documents, or  a registered translator in the foreign bidder’s country.
  • 7.  Submitted documents of foreign bidder shall be authenticated by the appropriate Philippine foreign service establishment/post or the equivalent office having jurisdiction over the foreign bidder’s affairs in the Philippines.  Only upon actual determination and confirmation of this equivalence through post qualification by the BAC may it be categorically resolved that the foreign documents submitted are acceptable substitutes of the required eligibility documents pursuant to Section 23.2 of the IRR. (NPM 42-2013)
  • 8.  Only 1 form of Bid Security among the following allowed forms is required to be submitted by the participating bidders Form of Bid Security Amount Bid Security (% = ABC) a) Cash or cashier’s/manager’s check 2% b) Bank guarantee/draft or Irrevocable LC c) Surety bond callable upon demand 5% e) Bid Securing Declaration No percentage required
  • 9. 4. RECEIPT AND OPENING OF BIDS  To ensure transparency and accurate representation of the bid submission, the BAC Secretariat shall notify in writing all bidders whose bids it has received within seven (7) calendar days from the date of the bid opening.  Original copy of bid form shall be typed or written in ink and shall be signed by the bidder or its duly authorized representative Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 10. 5. BID EVALUATION Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract  Purpose: To determine the Lowest Calculated Bid/LCB (for Goods and Infrastructure Projects) or Highest Rated Bid/HRB (for Consulting Services) by:  Establishing correct calculated prices of bids; and  Ranking calculated total bid prices from lowest to highest  A non-discretionary criterion shall be used, which shall include consideration of:  Completeness of bids; and  Minor arithmetical corrections
  • 11. 5. BID EVALUATION FOR CONSULTING SERVICES  Two Methods of Evaluation:  Quality-Based Evaluation (QBE) which considers only the Technical Proposals in the ranking of consultants  Quality-Cost-Based Evaluation (QCBE) which considers both the Technical and Financial Proposals in the ranking of consultants  Evaluation may be per individual or collegial Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 12. 5. BID EVALUATION  The No Contact Rule which prohibits communication between bidders and the BAC shall apply only to those whose bids are being evaluated by the BAC after passing the preliminary examination until the issuance of Notice of Award.  No communication should be made by bidders until a decision to award a contract is made by the BAC  Domestics Preference shall only apply to Goods where the lowest bid has a foreign component (foreign bid/entity) and the next lowest bid has a domestic component (domestic bidder/entity) Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 13. NEGOTIATION FOR CONSULTING SERVICES  Negotiations shall cover the following: a) Discussion and clarification of the TOR and Scope of Services; b) Discussion and finalization of the Procedural Requirements and work program; c) Consideration of appropriateness of qualifications and pertinent compensation, number of man-months and the personnel; d) Discussion on the services, facilities and data, if any, to be provided by PE concerned Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 14. NEGOTIATION FOR CONSULTING SERVICES  Negotiations shall cover the following: e) Discussion on the financial proposal submitted by the consultant for QBE; and f) Provisions of the contract. Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract  Except for meritorious reasons, negotiations with any one consultant shall be completed within ten (10) calendar days
  • 15. 6. POST - QUALIFICATION  Purpose: To determine whether the bidder/consultant with the LCB/HRB complies with and is responsive to all requirements and conditions of eligibility and the bidding of the contract – to be declared the Lowest Calculated and Responsive Bid (LCRB)/Highest Rated Responsive Bid (HRRB)  A non-discretionary pass/fail criterion shall be used to “Verify, Validate and Ascertain” all statements and documents (licenses, certificates, etc.) submitted by the LCB/HRB Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 16. 7. AWARD OF CONTRACT  Additional documents are also required to be submitted by the LCRB/HRRB  Contract shall be awarded to the bidder with the LCRB/HRRB at its submitted price or total calculated bid price, whichever is lower  The BAC shall notify all other bidders, in writing, of its recommendation to HOPE of award of contract to LCRB/HRRB within three (3) calendar days from the issuance of the resolution recommending award Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 17. 7. AWARD OF CONTRACT  The Notice of Award (NOA) and Notice to Proceed (NTP) are issued by the Head of the Procuring Entity (HoPE)  The NOA, and NTP along with the contract are required to be posted at the websites of PhilGEPS and the agency, and at any conspicuous place within three (3) calendar days and 15 calendar days from the respective date of issuance Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 18. 7. AWARD OF CONTRACT  The contract effectivity date should be provided in the Notice to Proceed, which should not be later than seven (7) calendar days from its issuance.  The BAC Secretariat shall post the NOA in the PhilGEPS, PE’s websites and in any conspicuous place within 3 calendar days from its issuance. Pre-Procurement Conference Advertisement and Posting Pre-Bid Conference Receipt and Opening of Bids Bid Evaluation Post- Qualification Award of Contract
  • 19. FAILURE OF BIDDING  A failure of bidding is declared by the BAC when: a) No bids are received; b) Bids were received but no one was eligible; c) All bids failed to post qualify; or d) Someone post qualified but refused without justifiable cause to accept the award.
  • 20. RESERVATION CLAUSE  The HoPE reserves the right to: a) Reject any and all bids; b) Declare a failure of bidding; or c) Not award the contract.  Grounds: a) Prima facie evidence of collusion; b) BAC is found to have failed in following the prescribed bidding procedures; c) For justifiable reasons, the award of contract will not redound to the benefit of the Government
  • 21. RECOMMENDED POSSIBLE PERIOD TO COMPLETE THE PROCUREMENT ACTIVITY Type Earliest Period (calendar days) Maximum Period (calendar days) Goods and Services 26 136 Infrastructure Projects 26 142 or 156 Consulting Services 36 180
  • 22. PARTICIPATION OF OBSERVERS  Observers represent the public, the taxpayers who are interested in seeing to it that procurement laws are observed and irregularities are averted  At least three (3) Observers shall be invited by the BAC coming from the following: a) Commission on Audit (COA); b) Duly recognized private group in the sector or discipline of the particular type of procurement involved; and c) Non-Government Organization (NGO)
  • 23. PARTICIPATION OF OBSERVERS  Observes must be invited in writing at least five (5) calendar days before the date of the following procurement stage/activity: a) Eligibility checking; b) Shortlisting; c) Pre-bid Conference; d) Preliminary examination of bids; e) Bid evaluation; and f) Post qualification
  • 24.  The GPPB has issued Standard Bidding Documents to be adopted by all procuring entities, downloadable at the GPPB website: a) Philippine Bidding Documents for Goods and Services, 5th Edition b) Philippine Bidding Documents for Infrastructure Projects, 5th Edition c) Philippine Bidding Documents for Consulting Services, 5th Edition
  • 25. 25
  • 26.
  • 27. RA 8182 as amended by RA 8555 Procurement funded from Foreign Grants An Act Excluding Official Development Assistance (ODA) from the Foreign Debt Limit in order to Facilitate the Absorption and Optimize the Utilization of ODA Resources Acquisition of Real Property RA 8974 as amended by RA 10752 “An Act to Facilitate the Acquisition of Right-of-Way Site or Location for National Government Infrastructure Projects and for Other Purposes,” Public-Private Sector Projects RA 6957 as amended by RA 7718 (BOT Law) “An Act Authorizing the Financing, Construction, Operation and Maintenance of Infrastructure Projects by the Private Sector, and for Other Purposes,”
  • 28. Direct financial or material assistant to beneficiaries If the direct financial or material assistance takes the form of goods, supplies or items that are to be procured (e.g., relief goods), the same do not fall within the coverage of the cited provision, but is subject to procurement rules and regulations embodied in RA 9184 and its IRR. - (GPPB Circular 01-2017) Participation to scholarships, training programs, continuing education, etc. Lease of government property for private use Job order workers Joint Venture Agreements between Private Entities and GOCCs or LGUs Disposal of property and assets
  • 29.
  • 30. Issue/s Revision Impact Lack of members to constitute BAC Allows designation of an officer of the next lower rank, in case of unavailability of 5th ranking permanent official (except for BAC Chairperson) (Sec. 11.2.2) In case of procurement outsourcing, a representative from the Procuring Entity may be designated as a provisional member The Chairperson and Vice-chairperson shall be designated by the local chief executive (Sec.11.2.2, 11.2.3(a), 11.2.3(b)(iii)) Increases the pool from which HOPE select its BAC members
  • 31.
  • 32. 32 Issue/s Revision Impact Lack of full- time BAC Sec members to support the BAC in every procurement activity Allows designation of an officer of the next lower rank, in case of unavailability of 5th ranking permanent official In case of ad hoc BAC Secretariat, the HOPE shall assign full-time support staff in its BAC Secretariat (Sec. 14.2) Fast-track procurement
  • 33.
  • 34. 34 Issue/s Revision Impact Lack of training of HOPE, BAC, Secretariat and TWG The HoPE shall ensure that the BAC, its Secretariat and TWG members, including other relevant procurement personnel are sent to attend capacity development program. Within six (6) months upon designation, the BAC, its Secretariat and TWG members should have satisfactorily completed such training or program conducted, authorized or accredited by the GPPB through its Technical Support Office. Procurement Professionali- zation
  • 35.
  • 36. 36 Issue/s Revision Impact Poor specifications a. Bid documents shall reflect the necessary specifications required to meet the needs of the PE b. For mixed procurement, PE shall specify all relevant requirements for each procurement type (Sec. 17.2) Quality of Goods for the lowest prices Non- Refundable Fee For bid docs Provide instances when bid doc fees may be refunded to the bidder, i.e. declaration of failure of bidding under Section 41 (Sec. 17.5) Fairness in procurement
  • 37.
  • 38. 38 Issue/s Revision Impact Difficulty in preparing technical specifications Reference to Brand Names Prohibition on brand names likewise apply to the goods component of Infrastructure Projects and Consulting Services. (Sec. 18) However, PEs may indicate brand names for items or parts that are compatible with the existing fleet or equipment of the same make and brand and will maintain the performance, functionality and useful life of the equipment. Ensure compatibility, interoperability, performance, functionality and useful life of the equipment.
  • 39.
  • 40. 40 Issue/s Revision Impact Newspaper advertisement a. Increase thresholds for advertisement requirement b. 2 years sunset clause on advertisement requirement (Sec. 21.2.1) Reduce government cost for newspaper advertisements Low participation of bidders in pre- bid a. Allow conduct of pre-bid via video- conferencing, webcasting b. Allow all prospective bidders (even those who did not buy bid docs) to raise queries (Sec. 22) Clarifies procurement requirements; Reduce disqualification; Increase competition
  • 41.
  • 42. 42 Issue/s Revision Impact Disqualificati on of Bidders/ Failure of Biddings due to documentary requirements Low turn-out of bidders a. Mandatory registration under Platinum Membership (Sec. 8.5.2, 25.2) Per GPPB Circular No. 07-2017 which took effect on 3 September 2017, the mandatory requirement under Sec. 8.5.2 on the submission of PhilGEPS Certificate of Registration and Membership under Platinum category for Competitive Bidding, Limited Source Bidding and Two- Failed Bidding has been deferred until revoked by the GPPB. Easier eligibility check Reduce disqualification of bidders/ failure of biddings Increase competition
  • 43. 43 Issue/s Revision Impact Disqualification of Bidders/ Failure of Biddings due to documentary requirements Low turn-out of bidders b. Mayor’s permit: - Allows submission of recently expired mayor’s permit with official receipt of application for renewal of permit - Allows equivalent document for economic zones (Sec. 23.1(a)(ii), 24.1(a)(ii)) c. For goods procurement, submission of a Credit Line, as an alternative to NFCC (Sec. 23.1(a)(viii)) Easier eligibility check Reduce disqualification of bidders/ failure of biddings Increase competition
  • 44. 44 Issue/s Revision Impact Disqualificatio n of Bidders/ Failure of Biddings due to documentary requirements Low turn-out of bidders b. Mayor’s permit: - Allows submission of recently expired mayor’s permit with official receipt of application for renewal of permit - Allows equivalent document for economic zones (Sec. 23.1(a)(ii), 24.1(a)(ii)) c. For goods procurement, submission of a Credit Line, as an alternative to NFCC (Sec. 23.1(a)(viii)) Easier eligibility check Reduce disqualification of bidders/ failure of biddings Increase competition
  • 45.
  • 46. 46 Issue/s Revision Impact Disqualification of Bidders/Failure of Biddings due to documentary requirements Low turn-out of bidders d. For goods and infrastructure projects, fixing the NFCC’s K factor at 15, regardless of contract duration (Sec. 23.4.1.4, 23.4.2.7) e. For individual consultants not registered as sole proprietors, they can submit BIR Certificate of Registration instead of DTI and Mayor’s Permit (Sec. 24.1(a)(ii)) f. In consulting services, submission of foreign bidders’ SEC Certificate of Registration and/or PRC permit is moved from eligibility to contract award (Sec. 37.1.4(a)(iv)) Easier eligibility check Reduce disqualification of bidders/ failure of biddings Increase competition
  • 47.
  • 48. 48 Issue/s Revision Impact Strict rules on marking/ sealing of bids Bid envelopes that are not properly sealed and marked, as required in the bidding documents, shall be accepted, provided that the bidder or its duly authorized representative shall acknowledge such condition of the bid as submitted. The BAC shall assume no responsibility for the misplacement of the contents of the improperly sealed or marked bid, or for its premature opening(Sec. 25.9) Reduce disqualification of bidders
  • 49.
  • 50. 50 Issue/s Revision Impact Bid Rigging/ Simulation of bids; a. BAC Secretariat shall notify in writing all bidders whose bids it has received through its PhilGEPS- registered physical address or official e-mail address (Sec. 25.7) b. The BAC shall notify all other bidders, in writing, of its recommendation to HOPE of award of contract to LCRB/HRRB within 3 calendar days. (Sec. 37.1.1) Ensure transparency and accurate representation of the bid submission
  • 51.
  • 52. 52 Issue/s Revision Impact Procurement by Foreign Service Posts a. Exempts foreign bidders from the mandatory PhilGEPS Certificate of Registration (Sec. 25.2) b. Winning bidder shall be required to register (Registration Number only) prior to contract signing. (Section 37.1.4(a)(ii) Encourage participation of foreign bidders in the procurement by FSPs Bid and Performance Securities a. Allows the bidder to choose their preferred form of bid security (Sec. 27.2) b. Clarifies the required amount for Bid Security and Performance Security(Secs. 27.2 and 39.2) Avoid undue disqualification of bidders who posted more than the required amount.
  • 53.
  • 54. 54 Issue/s Revision Impact Bid and Performance Securities a. Allows the bidder to choose their preferred form of bid security (Sec. 27.2) b. Clarifies the required amount for Bid Security and Performance Security(Secs. 27.2 and 39.2) Avoid undue disqualification of bidders who posted more than the required amount.
  • 55.
  • 56.
  • 57.
  • 58. 58 Issue/s Revision Impact Difficulty in procuring the following: -Media services; -Scientific, academic references, works - life-saving equipment -Legal services -Artistic works - Infra projects with exclusive technology New Alternative Modality: Section 53.6 Scientific, Scholarly or Artistic Work, Exclusive Technology and Media Services. Efficiency in procurement considering that only 1 supplier/contra ctor could provide the needs of the PE
  • 59.
  • 60. 60 Issue/s Revision Impact Delay in procurement process due to declaration of holidays Specific procurement activities may be held on a Saturday, Sunday, nonworking day or holiday: provided, that the BAC, secretariat and TWG members shall be available on such date, and the appropriate supplemental/bid bulletin is issued and posted pursuant to the posting requirements embodied in section 22.5.3 of this IRR. (GPPB Resolution No. 21-2017) Fast-track procurement activities
  • 61.
  • 62. 62 Issue/s Revision The number of quotation that the BAC has to obtain, in order to proceed with the negotiation a. Shopping 52.1(a) and Emergency Procurement– send at least 1 RFQ b. Shopping 52.1(b) – send at least 3 RFQs, receive at least 3 quotations c. Two Failed Biddings, Small Value Procurement, Lease of Real Property/Venue - send at least 3 RFQs, receive at least 1 quotation will suffice
  • 63.
  • 64. Streamline Bidding Process Use of pump prices for the procurement of non-bulk petroleum, oil and lubricant products Use of Digital Signature on all procurement documents Use of Videoconferencing, Webcasting and Similar Technology in the Conduct of Meetings and Determination of Quorum by the BAC
  • 65. Responsive Bidding Rules Rules for Sangguniang Kabataan Procurement Removal on the ceiling of maximum percentage of liquidated damage

Editor's Notes

  1. Upon submission of signed waiver that they will not file RR, bid security may be returned.
  2. 2016 Revised IRR Section 11.2.2 The BAC for NGAs, departments, bureaus, offices, or instrumentalities of the GoP, including the judicial and legislative branches, constitutional commissions, SUCs, GOCCs, and GFIs shall be composed of the following:   Regular Members: Chairperson, who is at least a third (3rd) ranking permanent official of the Procuring Entity; An officer, who is at least a fifth (5th) ranking permanent official, or if not available, an officer of the next lower rank with knowledge, experience and/or expertise in procurement who, to the extent possible, represents the legal or administrative area of the Procuring Entity: Provided, that in the case of bureaus, regional offices and sub-regional/district offices, BAC members shall be at least a third (3rd) ranking permanent personnel or if not available, an officer of the next lower rank; An officer, who is at least a fifth (5th) ranking permanent official, or if not available, an officer of the next lower rank with knowledge, experience and/or expertise in procurement who, to the extent possible, represents the finance area of the Procuring Entity: Provided, that in the case of bureaus, regional offices and sub-regional/district offices, BAC members shall be at least a third (3rd) ranking permanent personnel or if not available, an officer of the next lower rank;   Provisional Members: d) An officer who has technical expertise relevant to the procurement at hand, and, to the extent possible, has knowledge, experience and/or expertise in procurement; and e) A representative from the end-user or implementing unit who has knowledge of procurement laws and procedures. When procurement tasks are outsourced to another GoP agency as a procurement agent pursuant to Section 7.3.3, a representative from the Procuring Entity may be designated as a provisional member to the BAC. For this purpose, the procuring entity shall recommend the provisional member to be designated.   The Chairperson and the Vice-Chairperson shall also be designated by the HoPE. Moreover, the Vice-Chairperson shall be a regular member of the BAC. For purposes of this IRR, the term “permanent” shall refer to a plantilla position within the Procuring Entity concerned. (a) 11.2.3 The BAC for Local Government Units shall be composed of the following: a) For Provinces, Cities, and Municipalities   i. One representative each from the regular offices under the Office of the Local Chief Executive such as, but not limited to, the following: Office of the Administrator, Budget Office, Legal Office, Engineering Office, General Services Offices; and   ii. A representative from the end user unit.   The Chairperson and Vice-Chairperson shall be designated by the Local Chief Executive. The Chairperson of the BAC shall be at least a third ranking permanent official of the Procuring Entity. The members of the BAC shall be personnel occupying plantilla positions of the Procuring Entity concerned.   b) For Barangays:   i. The BAC shall be composed of at least five (5), but not more than seven (7) regular members of the Sangguniang Barangay, except the Punong Barangay.   ii. The Punong Barangay, being the Local Chief Executive, shall designate the Chairperson, Vice-Chairperson, and members of the BAC.(a)    11.2.4 The HoPE may designate alternate BAC members, who shall have the same qualifications as that of the members originally designated under Section 11.2.2 of this IRR. The alternate members shall attend meetings of the BAC and receive the proportionate honoraria, whenever the original members are absent. The alternate members shall have the same term as the original members. (a).
  3. 2016 Revised IRR Section 14.2 In case of an existing ad hoc secretariat, the HoPE shall assign full-time support staff to their BAC Secretariat. The head of the Secretariat in central offices shall be at least a fifth (5th) ranking permanent employee or, if not available, a permanent employee of lower rank; or shall be at least a third (3rd) ranking permanent employee in bureaus, regional offices and sub-regional/ district offices, or if not available, a permanent employee of lower rank. In addition to integrity, Heads of Procuring Entities shall consider procurement proficiency as a factor in designating the head of the Secretariat and Procurement Unit.(a)
  4. 2016 IRR Section 16. Professionalization of BAC, TWG Members and Procurement Units   The GPPB shall establish a sustained training program to develop the capability of the BACs, BAC Secretariats, TWGs, and the Procurement Units of Procuring Entities, and professionalize the same.   The HoPE shall ensure that the BAC, its Secretariat and TWG members, including other relevant procurement personnel are sent to attend procurement training or capacity development program. Within six (6) months upon designation, the BAC, its Secretariat and TWG members should have satisfactorily completed such training or program conducted, authorized or accredited by the GPPB through its Technical Support Office.   The HoPE is encouraged to attend similar procurement training and capacity development activities.(a)
  5. 2016 Revised IRR Section 17.2 The specifications and other terms in the Bidding Documents shall reflect the necessary specifications required to meet the needs of the Procuring Entity in clear and unambiguous terms. In mixed procurements, the Procuring Entity shall specify in the Bidding Documents the requirements, criteria and other conditions of the bidding procedures and of the ensuing contract as applicable to each component of the project. In the preparation of Bidding Documents, the Procuring Entity shall ensure compliance with existing laws, rules and regulations especially those concerning licenses and permits required for the project, in accordance with Section 34.2 of this IRR. Sec. 17.4 Bidders may be asked to pay a fee to recover the cost for the preparation and development of the Bidding Documents pursuant to the Guidelines on the Sale of Bidding Documents. The Procuring Entity shall post the complete Bidding Documents at its website and the PhilGEPS website from the time the Invitation to Bid/Request for Expression of Interest is advertised. Bidding Documents may be downloaded from any of the said websites: Provided, That upon submission of their bids, the bidders shall pay the applicable fee, if required. The Bidding Documents may also be secured from the BAC Secretariat upon payment of the corresponding fee, if required.(a)   Sec. 17.5 Bidding Documents Fee may be refunded in accordance with the aforementioned Guidelines based on the grounds provided for under Section 41 of the Act and this IRR.(n)
  6. 2016 Revised IRR Section 18 Specifications for the procurement of Goods shall be based on relevant characteristics, functionality and/or performance requirements. Reference to brand names shall not be allowed except for items or parts that are compatible with the existing fleet or equipment of the same make and brand, and to maintain the performance, functionality and useful life of the equipment.   This Section shall also apply to the goods component of Infrastructure Projects and Consulting Services.(a)
  7. 2016 Revised IRR Section 17.6 Detailed Engineering for the Procurement of Infrastructure Projects   No bidding and award of contract for Infrastructure Projects shall be made unless the detailed engineering investigations, surveys and designs, for the project have been sufficiently carried out and duly approved in accordance with the standards and specifications prescribed by the HoPE concerned or his duly authorized representative, pursuant to the recommendation of the end-user or implementing unit and in accordance with the provisions of Annex “A” of this IRR. In case of projects with pending acquisition of right-of-way site or location, the procurement process may commence, but no award of contract shall be made until an authority or permit to enter is issued by the property owner; or a notarized deed of sale or deed of donation is executed in favor of the government; or a writ of possession is issued by a court of competent jurisdiction, as the case may be.   The exception is in case of design and build scheme, wherein the bidders shall be allowed to submit its preliminary engineering designs as part of its bid. The procedures for the procurement and contract implementation of Infrastructure Projects using a design and build scheme shall be in accordance with the provisions of Annex “G” of this IRR.(a) . Section 21.1. Contents of the Invitation to Bid/Request for Expression of Interest   The Invitation to Bid/Request for Expression of Interest shall provide prospective bidders the following information, among others: … (b) The name of the project, identification and number of lots or items specific to the bidding, as well as the basis of evaluation of the project, lots, or items, where applicable;
  8. 2016 Revised IRR Sec. 8.5.2 All bidders shall upload and maintain in PhilGEPS a current and updated file of the following Class “A” eligibility documents under Sections 23.1(a) and 24.1(a):   a) Registration Certificate; b) Mayor’s/Business Permit; c) Tax Clearance; d) Philippine Contractors Accreditation Board (PCAB) license and registration; and e) Audited Financial Statements.   For Foreign Bidders, the foregoing documents may be substituted by the appropriate equivalent documents in English, if any, issued by the country of the bidder concerned. Otherwise, it must be accompanied by a translation of the documents in English issued by the relevant foreign government agency, the foreign government agency authorized to translate documents, or a registered translator in the foreign bidder’s country; and shall be authenticated by the appropriate Philippine foreign service establishment/post or the equivalent office having jurisdiction over the foreign bidder’s affairs in the Philippines.   These documents shall be accompanied by a Sworn Statement in a form prescribed by the GPPB stating that the documents submitted are complete and authentic copies of the original, and all statements and information provided therein are true and correct. Upon receipt of the said documents, the PhilGEPS shall process the same in accordance with the guidelines on the Government of the Philippines – Official Merchants Registry (GoP-OMR).(a) Sec. 23.1(a)(ii) and 24.1(a)(ii) In cases of recently expired Mayor’s/Business permits, it shall be accepted together with the official receipt as proof that the bidder has applied for renewal within the period prescribed by the concerned local government unit, provided that the renewed permit shall be submitted as a post-qualification requirement in accordance with Section 34.2 of this IRR. Section 23.1(a)(viii) Financial documents … (viii) The prospective bidder’s computation of Net Financial Contracting Capacity (NFCC). However, in the case of procurement of Goods, a bidder may submit a committed Line of Credit from a universal or commercial bank, in lieu of its NFCC computation.
  9. 2016 Revised IRR Sec. 8.5.2 All bidders shall upload and maintain in PhilGEPS a current and updated file of the following Class “A” eligibility documents under Sections 23.1(a) and 24.1(a):   a) Registration Certificate; b) Mayor’s/Business Permit; c) Tax Clearance; d) Philippine Contractors Accreditation Board (PCAB) license and registration; and e) Audited Financial Statements.   For Foreign Bidders, the foregoing documents may be substituted by the appropriate equivalent documents in English, if any, issued by the country of the bidder concerned. Otherwise, it must be accompanied by a translation of the documents in English issued by the relevant foreign government agency, the foreign government agency authorized to translate documents, or a registered translator in the foreign bidder’s country; and shall be authenticated by the appropriate Philippine foreign service establishment/post or the equivalent office having jurisdiction over the foreign bidder’s affairs in the Philippines.   These documents shall be accompanied by a Sworn Statement in a form prescribed by the GPPB stating that the documents submitted are complete and authentic copies of the original, and all statements and information provided therein are true and correct. Upon receipt of the said documents, the PhilGEPS shall process the same in accordance with the guidelines on the Government of the Philippines – Official Merchants Registry (GoP-OMR).(a) Sec. 23.1(a)(ii) and 24.1(a)(ii) In cases of recently expired Mayor’s/Business permits, it shall be accepted together with the official receipt as proof that the bidder has applied for renewal within the period prescribed by the concerned local government unit, provided that the renewed permit shall be submitted as a post-qualification requirement in accordance with Section 34.2 of this IRR. Section 23.1(a)(viii) Financial documents … (viii) The prospective bidder’s computation of Net Financial Contracting Capacity (NFCC). However, in the case of procurement of Goods, a bidder may submit a committed Line of Credit from a universal or commercial bank, in lieu of its NFCC computation.
  10. 2016 Revised IRR Sec. 8.5.2 All bidders shall upload and maintain in PhilGEPS a current and updated file of the following Class “A” eligibility documents under Sections 23.1(a) and 24.1(a):   a) Registration Certificate; b) Mayor’s/Business Permit; c) Tax Clearance; d) Philippine Contractors Accreditation Board (PCAB) license and registration; and e) Audited Financial Statements.   For Foreign Bidders, the foregoing documents may be substituted by the appropriate equivalent documents in English, if any, issued by the country of the bidder concerned. Otherwise, it must be accompanied by a translation of the documents in English issued by the relevant foreign government agency, the foreign government agency authorized to translate documents, or a registered translator in the foreign bidder’s country; and shall be authenticated by the appropriate Philippine foreign service establishment/post or the equivalent office having jurisdiction over the foreign bidder’s affairs in the Philippines.   These documents shall be accompanied by a Sworn Statement in a form prescribed by the GPPB stating that the documents submitted are complete and authentic copies of the original, and all statements and information provided therein are true and correct. Upon receipt of the said documents, the PhilGEPS shall process the same in accordance with the guidelines on the Government of the Philippines – Official Merchants Registry (GoP-OMR).(a) Sec. 23.1(a)(ii) and 24.1(a)(ii) In cases of recently expired Mayor’s/Business permits, it shall be accepted together with the official receipt as proof that the bidder has applied for renewal within the period prescribed by the concerned local government unit, provided that the renewed permit shall be submitted as a post-qualification requirement in accordance with Section 34.2 of this IRR. Section 23.1(a)(viii) Financial documents … (viii) The prospective bidder’s computation of Net Financial Contracting Capacity (NFCC). However, in the case of procurement of Goods, a bidder may submit a committed Line of Credit from a universal or commercial bank, in lieu of its NFCC computation.
  11. 2016 Revised IRR Sections 23.4.1.4 and 23.4.2.7 The computation of a prospective bidder’s NFCC must be at least equal to the ABC to be bid, calculated as follows:   NFCC = [(Current assets minus current liabilities) (15 )] minus the value of all outstanding or uncompleted portions of the projects under ongoing contracts, including awarded contracts yet to be started, coinciding with the contract to be bid. The values of the domestic bidder’s current assets and current liabilities shall be based on the latest Audited Financial Statements submitted to the BIR . For purposes of computing the foreign bidders' NFCC, the value of the current assets and current liabilities shall be based on their Audited Financial Statements prepared in accordance with international financial reporting standards. Sec. 24.(a)(ii) …For individual consultants not registered under a sole proprietorship, a BIR Certificate of Registration shall be submitted, in lieu of DTI registration and Mayor’s/Business permit Sec. 37.1.4(iv) 37.1.4 Notwithstanding the issuance of the Notice of Award, award of contract shall be subject to the following conditions: (a) Submission of the following documents within ten (10) calendar days from Notice of Award: … iv. In the case of Consulting Services, the SEC Certificate of Registration of the foreign consulting firm, and/or the authorization or license issued by the appropriate GoP professional regulatory body of the foreign professionals engaging in the practice of regulated professions and allied professions, where applicable.
  12. 2016 Revised IRR
  13. 2016 Revised IRR
  14. 2016 Revised IRR Sec. 25.2 The first envelope shall contain the following technical information/documents, at the least:   ….  PhilGEPS Certificate of Registration and membership in accordance with Section 8.5.2 of this IRR, except for foreign bidders participating in the procurement by a Philippine Foreign Service Office or Post, which shall submit their eligibility documents under Section 23.1 of this IRR: Provided, That the winning bidder shall register with the PhilGEPS in accordance with Section 37.1.4 of this IRR; 37.1.4 Notwithstanding the issuance of the Notice of Award, award of contract shall be subject to the following conditions: a. Submission of the following documents within ten (10) calendar days from Notice of Award:   …  ii. In the case of procurement by a Philippine Foreign Office or Post, the PhilGEPS Registration Number of the winning foreign bidder; Sec. 27.2 The bidder shall submit a Bid Securing Declaration, or any form of Bid Security, in an amount not less than the percentage of the ABC ... 39.2 The performance security shall be in an amount not less than a percentage of the total contract price …
  15. 2016 Revised IRR Sec. 25.2 The first envelope shall contain the following technical information/documents, at the least:   ….  PhilGEPS Certificate of Registration and membership in accordance with Section 8.5.2 of this IRR, except for foreign bidders participating in the procurement by a Philippine Foreign Service Office or Post, which shall submit their eligibility documents under Section 23.1 of this IRR: Provided, That the winning bidder shall register with the PhilGEPS in accordance with Section 37.1.4 of this IRR; 37.1.4 Notwithstanding the issuance of the Notice of Award, award of contract shall be subject to the following conditions: a. Submission of the following documents within ten (10) calendar days from Notice of Award:   …  ii. In the case of procurement by a Philippine Foreign Office or Post, the PhilGEPS Registration Number of the winning foreign bidder; Sec. 27.2 The bidder shall submit a Bid Securing Declaration, or any form of Bid Security, in an amount not less than the percentage of the ABC ... 39.2 The performance security shall be in an amount not less than a percentage of the total contract price …
  16. 2016 Revised IRR 53.6 Scientific, Scholarly or Artistic Work, Exclusive Technology and Media Services. Where Goods, Infrastructure Projects and Consulting Services can be contracted to a particular supplier, contractor or consultant and as determined by the HoPE, for any of the following:   1. The requirement is for:   a. Work of art; commissioned work or services of an artist for a specific artist skills (e.g., Singer, poet, writer, painter, sculptor, etc.);   b. Scientific, academic, scholarly work or research, or legal services;   c. Highly-specialized life-saving medical equipment, as certified by the Department of Health (DOH);   d. Scientific, technical, economic, business, trade or legal journal, magazine, paper, subscription, or other exclusive statistical publications and references; or   e. Media documentation, advertisement, or announcement through television, radio, newspaper, internet, and other communication media. Due to the nature of the information to be disseminated, alongside principles of transparency, efficiency and economy, award to more than one (1) supplier may be made by the Procuring Entity.   2. The construction or installation of an infrastructure facility where the material, equipment, or technology under a proprietary right can only be obtained from the same contractor.
  17. 2016 Revised IRR Section 54.6 Manufacturers, suppliers, distributors, contractors, and/or consultants are mandated to register with PhilGEPS and provide a PhilGEPS Registration Number in the following alternative methods of procurement as a condition for award of the contract:   a. Section 50 - Direct Contracting b. Section 52.1 (b) - Shopping for Ordinary Office Supplies and Equipment not available in DBM-PS c. Section 53.3 - Take Over of Contracts (Only for New Bidders, if any.) d. Section 53.6 - Scientific, Scholarly, or Artistic Work, Exclusive Technology and Media Services e. Section 53.7 - Highly Technical Consultants f. Section 53.9 - Small Value Procurement g. Section 53.10 - Lease of Real Property and Venue h. Section 53.11 - NGO Participation   For purposes of Limited Source Bidding under Section 49 and Two Failed Biddings under Section 53.1, the BAC shall require the submission of a certificate of PhilGEPS registration in accordance with Section 8.5.2 of this IRR.