11. METHOD OF INVESTIGATIVE ANALYSIS
1. Isolate sections for investigation
2. Gather relevant information and data
o GPR Data (2011 and 2015)
o Maintenance history (2011- present)
o Relevant section information
3. Compare:
o maintenance history to past GPR data to determine whether the
sections with high fouling identified were being managed.
o past and present GPR data, identifying changes to track
condition over the four-year period.
4. Investigate rate of contamination
12. PRESENTATION OF GPR DATA
Ballast Fouling (Percentage Void Contamination
- GPR PVC)
PVC
Category
Description PVC range (%)
6 Clean 0 to <10
5 Moderately Clean 10 to <20
4
Moderately
Fouled 20 to <30
3 Fouled 30 to <40
2 Highly Fouled 40 to <60
1
Severely fouled >=60
0 Unavailable n/a
15. COMPARATIVE ANALYSIS – BALLAST AND FOULING VOLUMES
0.000
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000
9.000
0.000 1.000 2.000 3.000 4.000 5.000 6.000
Volume(m^3)
Chainage (km)
2011 Ballast Volume: Total against Fouled, Main Line
total volume per 5m
volume fouling
0
2
4
6
8
10
12
14
16
18
20
0.000000 1.000000 2.000000 3.000000 4.000000 5.000000 6.000000
volume(m^3)
Chainage (km)
2015 Ballast Volume: Total against Fouled, Main Line
total folume per 5m
volume fouled
0.000
2.000
4.000
6.000
8.000
10.000
12.000
14.000
16.000
18.000
20.000
0.000 0.500 1.000 1.500 2.000 2.500 3.000 3.500 4.000
AxisTitle
Chainage
2011 Ballast Volume: Total against Fouled, Suban Line
total volume per 5m
volume fouling
0
2
4
6
8
10
12
14
16
18
20
0.000 0.500 1.000 1.500 2.000 2.500 3.000 3.500 4.000
Volume(m^3)
Chainage
2015 Ballast Volume: Total against Fouled, Suban Line
total volume per 5m
volume fowling
BRIDGE
BRIDGE
BRIDGEBRIDGE PLATFORM LEVEL
CROSSING
16. RATES OF CONTAMINATION
Section Distribution of Data Section Rate
Approximation
Approximate
PVC/1000MGT
3 Linear Mean 0.114%
4 Linear Mean 0.334%
5 Non-Linear Median 2.536%
6 Linear Mean 1.638%
Section Traffic Axel Load
(t)
Top Speed (km/h) Mega Gross Tonnage
2011 – 2015
3. Passenger,
Freight
20 80 85931.2
4. Passenger,
Freight
20 80 136811
5. Passenger 15.75 80 28152.71
6. Passenger 15.75 80 28152.71
18. REFERANCE LIST
Australian rail Corporation Ltd. (2007). Engineering (Track and Civil) Code of Practice , Ballast-Section 4 (27)
Retrieved from https://www.artc.com.au/
Selig, E. T., & Waters, J. M. (1992). Track Geotechnology and Substructure Management. Melbourne, VIC:
Technology Development and Application Committee on behalf of the Railways of Australia.