WLCO2T

Calculating whole life cost and whole life carbon
footprint of pavement projects
June 01, 2012
Contents

• Context
• What does the app do?
• How does the app work?
• How to use the app
  • Case study 1: Determine the optimum maintenance strategy
  • Case study 2: Determine the optimum year for intervention
• Summary
• Limitations
• Future developments




       WLCO2T
                                                                2
Context

• Current legislation
    • Carbon Reduction Commitment Energy Efficiency Scheme
    • Climate Change Levy
    • Climate Change Agreements
    • Building Regulations
    • EU Energy Performance in Buildings Directive
    • EU Energy Trading Scheme
• Future legislation
• Market mechanism
    • Emissions trading
    • Clean Development Mechanism
    • Joint implementation


       WLCO2T
                                                             3
Context

 “Less carbon does not mean less construction. It means constructing different
  forms of infrastructure, by different methods, using different materials. And to do
  that we need to develop new skills and new tools.
 We need new tools for project appraisal. Today this is about whole-life costs and
 net present value in monetary terms. We refer to 'Capex' and 'Opex'. We now
 need to add the carbon factor. We need to know how much carbon will be
 embodied in the proposed infrastructure, and how much will be used during
 construction and operation.
 We need to know the 'CapCarb' and 'OpCarb' - new terms for most of us. And
 importantly we need to understand the relationship and trade-off between these
 two measures.”
  Peter Hansford, ICE President




      WLCO2T
                                                                                        4
Context

  “While there are noticeable highs and lows in year to year data, over longer
  periods of time there is a discernable warming trend across the globe. Natural
  causes can explain only a small part of this warming. The overwhelming
  majority of scientists agree that this is due to rising concentrations of heat-
  trapping greenhouse gases in the atmosphere caused by human activities”.
  To avoid these problems, we will have to significantly reduce our energy
  needs and generate more power from non-carbon sources. The transition to a
  low carbon economy presents major global opportunities for business. The
  demand for low carbon and environmental goods and services is already
  worth £3.2 trillion per year, and is predicted to increase as the move to a low
  carbon economy occurs.”
  www.metoffice.gov.uk/climate-change




     WLCO2T
                                                         COMPANY CONFIDENTIAL: Use this space for disclaimer if needed.
                                                                                                                          5
Context

 “Global warming could shrink the global economy by 20% while taking action
 now would cost just 1% of global gross domestic product.”
 The Economics of Climate Change, Sir Nicholas Stern




     WLCO2T
                                                                              6
What does the app do?

• Calculates costs and emissions associated with pavement maintenance based
  on quantities of resources required during a 60 year analysis period
• The app allows decision makers to understand the balance between cost and
  carbon by calculating the following parameters for a range of alternative
  maintenance strategies:
   • Capital cost (Capex): discounted costs in Years 1 - 5
   • Operational cost (Opex): discounted costs in Years 6 - 60
   • Whole life cost (WLC): discounted costs in Years 1 - 60
   • Capital carbon footprint (CapCarb): carbon in Years 1 - 5
   • Operational carbon footprint (OpCarb): carbon in Years 6 - 60
   • Whole life carbon footprint (WLCO2): carbon in Years 1 - 60




      WLCO2T
                                                                              7
How does the app work?

• Built on standard approach to whole life cost analysis
    • Considers initial maintenance and future maintenance
    • Database contains unit costs for a range of treatments
• Follows basic HM Treasury rules for project appraisal
    • 60 year analysis period
    • 3.5% discount for first 30 years
    • 3.0% discount rate thereafter
    • Residual value is taken into account
• Carbon emissions factors included in treatments database
   (ICE CESMM3 Carbon and Price Book 2011)




       WLCO2T
                                                               8
How does the app work?




    WLCO2T
                         9
Treatments database
    Flexible pavements                      Structural Patch: 100mm depth
    Retexture: Limestone                    Structural Patch: 150mm depth
    Retexture: Flint                        Structural Patch: 200mm depth
    Emulsion tack coat                      Recycled Thin Surf.: 20mm
    Thin Surfacing: 20mm                    Recycled Thin Surf.: 25mm
    Thin Surfacing: 25mm                    Recycled Thin Surf.: 30mm
    Thin Surfacing: 30mm                    Recycled Resurface (to same level)
    High Friction Surfacing (new)           Recycled Resurface (Por. Asphalt)
    High Friction Surfacing (replacement)   Recycled Inlay: 100mm
    Resurface (to same level)               Recycled P/O + Overlay: 50mm (Net)
    Resurface (Porous Asphalt)              Recycled P/O + Overlay:100mm (Net)
    Inlay: 100mm                            Recycled P/O + Overlay: 150mm (Net)
    Plane off + Overlay: 50mm (Net)         Recycled P/O + Overlay: 200mm (Net)
    Plane off + Overlay:100mm (Net)         Recycled P/O + Overlay: 250mm (Net)
    Plane off + Overlay:150mm (Net)         Recycled Reconst.: 150mm Full flex.
    Plane off + Overlay:200mm (Net)         Recycled Reconst.: 200mm Full Flex..
    Plane off + Overlay:250mm (Net)         Recycled Reconst.: 200mm Flex. Comp.
    Reconstruction: 150mm Full flex.        Recycled Reconst.: 250mm Full Flex.
    Reconstruction: 200mm Full Flex.        Recycled Reconst.: 250mm Flex. Comp.
    Reconstruction: 200mm Flex. Comp.       Recycled Reconst.: 300mm Full Flex.
    Reconstruction: 250mm Full Flex.        Recycled Reconst.: 300mm Flex. Comp.
    Reconstruction: 250mm Flex. Comp.       Recycled Reconst.: 350mm Full Flex.
    Reconstruction: 300mm Full Flex.        Recycled Reconst.: 350mm Flex. Comp.
    Reconstruction: 300mm Flex. Comp.       Recycled Reconst.: 400mm Full Flex.
    Reconstruction: 350mm Full Flex.        Recycled Reconst.: 400mm Flex. Comp.
    Reconstruction: 350mm Flex. Comp.       Recycled Structural Patch: 50mm depth
    Reconstruction: 400mm Full Flex.        Recycled Structural Patch: 100mm depth
    Reconstruction: 400mm Flex. Comp.       Recycled Structural Patch: 150mm depth
    Structural Patch: 50mm depth            Recycled Structural Patch: 200mm depth


     WLCO2T
                                                                                     10
Treatments database

  Concrete pavements                          Overlay: 150mm
  Thin Surf.: 30mm                            Overlay: 180mm
  Thin Bonded Repairs                         Overlay: 300mm
  Full Depth Repairs: JRC                     Overlay: 200mm of CRCP
  Full Depth Repairs: URC                     Crack & Seat with 150mm Overlay
  Retexture: Limestone                        Crack & Seat with 180mm Overlay
  Retexture: Flint                            Crack & Seat with 300mm Overlay
  Joint seal JRC: longitudinal(*)
                                              Reconstruction: CRCR with 100mm Bit
  Joint seal URC: longitudinal(*)
                                              Reconstruction: CRCR with 150mm Bit
  Joint seal JRC: transverse(*)
                                              Reconstruction: CRCR with 200mm Bit
  Joint seal URC: transverse(*)
  Joint saw-cut & seal JRC: longitudinal(*)   Reconstruction: 200mm JRC
  Joint saw-cut & seal URC: longitudinal(*)   Reconstruction: 200mm URC
  Joint saw-cut & seal JRC: transverse(*)     Reconstruction: 200mm CRCP
  Joint saw-cut & seal URC: transverse (*)    Reconstruction: 250mm JRC
  Joint Repairs                               Reconstruction: 250mm URC
  Punch Out Repairs                           Reconstruction: 250mm CRCP
  Vacuum Grout: Bay                           Reconstruction: 300mm JRC
  Vacuum Grout: Joint                         Reconstruction: 300mm URC




     WLCO2T
                                                                                    11
Input screen




    WLCO2T
               12
Input screen




    WLCO2T
               13
Build scenarios




    WLCO2T
                  14
Results


                                                                                                            Whole
                                                                                                              Life
                                             Capital Cost Operational    Whole Life    CapCarb   OpCarb
 Option             Description                                                                            Carbon
                                                 (£)       Cost (£)       Cost (£)      (tCO2)   (tCO2)
                                                                                                          Footprint
                                                                                                            (tCO2)
   A         20 year fully flexible design   £207,174.00   £249,323.30   £456,497.30    172.18   618.66     790.84
   B         40 year fully flexible design   £259,208.40   £158,394.23   £417,602.63    464.81   620.83    1,085.65
   C             40 year rigid design        £324,733.20   £175,523.23   £500,256.43     0.00    156.02     156.02
   D                 do minimum               £11,087.39   £355,117.83   £366,205.23     5.76    501.66     507.43




          WLCO2T
                                                                                                                      15
Case study 1: strategy selection

• Three-lane dual carriageway in London
• Significant structural deterioration
    • Client needs to select the treatment that optimises cost and carbon to
      progress to detailed design
• Maintenance strategies
    • 20 year fully flexible design
    • 20 year flexible composite design
    • 40 year fully flexible design
    • 40 year rigid design




       WLCO2T
                                                                               16
Case study 1: strategy selection



     Year                Option A                                  Option B                        Option C                            Option D
                   20 year flexible design            20 year flexible composite design      40 year flexible design              40 year rigid design
2011: Year 01   Reconstruction: 250mm Full Flex.   Reconstruction: 250mm Flex Comp.       Reconstruction: 350mm Full Flex.   Reconstruction: 200mm CRCP
       -                         -                                         -                               -                                  -
2020: Year 10   Resurface (to same level)          Resurface (to same level)              Resurface (to same level)          Resurface (to same level)
       -                         -                                         -                               -                                  -
2030: Year 20   Reconstruction: 250mm Full Flex.   Reconstruction: 250mm Flex Comp.       Resurface (to same level)          Resurface (to same level)
       -                         -                                         -                               -                                  -
2040: Year 30   Resurface (to same level)          Resurface (to same level)              Resurface (to same level)          Resurface (to same level)
       -                         -                                         -                               -                                  -
2050: Year 40   Reconstruction: 250mm Full Flex.   Reconstruction: 250mm Flex Comp.       Reconstruction: 350mm Full Flex.   Reconstruction: 200mm CRCP
       -                         -                                         -                               -                                  -
2060: Year 50   Resurface (to same level)          Resurface (to same level)              Resurface (to same level)          Resurface (to same level)
       -                         -                                         -                               -                                  -
2070: Year 60   Reconstruction: 250mm Full Flex.   Reconstruction: 250mm Flex Comp.       Resurface (to same level)          Resurface (to same level)




                WLCO2T
                                                                                                                                                          17
Case study 1: strategy selection


                                                                                                                Whole Life
                                                Capital Cost Operational    Whole Life    CapCarb    OpCarb      Carbon
 Option               Description
                                                    (£)       Cost (£)       Cost (£)      (tCO2)    (tCO2)     Footprint
                                                                                                                 (tCO2)

   A             20 year flexible design        £207,174.00   £249,323.30   £456,497.30    172.18     618.66      790.84
   B        20 year flexible composite design   £246,199.80   £284,951.71   £531,151.51    453.86    1,285.45    1,739.30
   C             40 year flexible design        £259,208.40   £158,394.23   £417,602.63    464.81     620.83     1,085.65
   D              40 year rigid design          £300,161.40   £169,099.85   £469,261.25   8,063.89   8,219.90   16,283.79




          WLCO2T
                                                                                                                             18
Case study 1: strategy selection

                                                    Whole Life Cost


                      £600,000.00



                      £500,000.00



                      £400,000.00
 Cumulative NPV (£)




                                                                                       Option A
                                                                                       Option B
                      £300,000.00
                                                                                       Option C
                                                                                       Option D
                      £200,000.00



                      £100,000.00



                            £0.00
                                    0   10   20           30            40   50   60
                                                        Years




                                              Whole Life Carbon Footprint

                           WLCO2T
                      18000.00                                                                    19
£0.00

Case study 1: strategy selection                       0        10    20              30
                                                                                    Years
                                                                                                    40   50   60




                                                                          Whole Life Carbon Footprint


                                        18000.00


                                        16000.00
   Cumulative Carbon Footprint (tCO2)




                                        14000.00


                                        12000.00
                                                                                                                   Option A
                                        10000.00
                                                                                                                   Option B
                                                                                                                   Option C
                                         8000.00
                                                                                                                   Option D
                                         6000.00


                                         4000.00


                                         2000.00


                                            0.00
                                                   0       10        20              30            40    50   60
                                                                                   Years




                                        WLCO2T
                                                                                                                              20
Case study 2: time for intervention
                                                                                                                Whole Life
                                                Capital Cost Operational    Whole Life    CapCarb    OpCarb      Carbon
Option                Description
                                                    (£)       Cost (£)       Cost (£)      (tCO2)    (tCO2)     Footprint
                                                                                                                 (tCO2)

  A              20 year flexible design        £207,174.00   £249,323.30   £456,497.30    172.18     618.66      790.84
  B         20 year flexible composite design   £246,199.80   £284,951.71   £531,151.51    453.86    1,285.45    1,739.30
  C              40 year flexible design        £259,208.40   £158,394.23   £417,602.63    464.81     620.83     1,085.65
  D               40 year rigid design          £300,161.40   £169,099.85   £469,261.25   8,063.89   8,219.90   16,283.79


 • Option A selected from Case Study 1
         • Now study the impact of continuing with routine maintenance to defer the
           major capital expenditure
 • Maintenance strategies
         • Construct option A in Year 1
         • Routine maintenance in Year 1, construct option A in Year 2
         • Routine maintenance in Years 1 and 2, construct option A in Year 3
         • Routine maintenance in Years 1, 2 and 3, construct option A in Year 4

           WLCO2T
                                                                                                                             21
Case study 2: time for intervention
            Year                Option A                           Option B                         Option C                             Option D
                          20 year flexible design            20 year flexible design          20 year flexible design              20 year flexible design
                                                               deferred by 1 year              deferred by 2 years                  deferred by 3 years
       2011: Year 01   Reconstruction: 250mm Full Flex.   Structural Patch: 50mm depth       Structural Patch: 50mm depth       Structural Patch: 50mm depth
       2012: Year 02                    -                 Reconstruction: 250mm Full Flex.   Structural Patch: 50mm depth       Structural Patch: 50mm depth
       2013: Year 03                    -                                  -                 Reconstruction: 250mm Full Flex. Structural Patch: 50mm depth
       2014: Year 04                    -                                  -                                -                   Reconstruction: 250mm Full Flex.
              -                         -                                  -                                -                                    -
       2020: Year 10   Resurface (to same level)                           -                                -                                    -
       2021: Year 11                    -                 Resurface (to same level)                         -                                    -
       2022: Year 12                    -                                  -                 Resurface (to same level)                           -
       2023: Year 13                    -                                  -                                -                   Resurface (to same level)
              -                         -                                  -                                -                                    -
       2030: Year 20   Reconstruction: 250mm Full Flex.                    -                                -                                    -
       2031: Year 21                    -                 Reconstruction: 250mm Full Flex.                  -                                    -
       2032: Year 22                    -                                  -                 Reconstruction: 250mm Full Flex.                    -
       2033: Year 23                    -                                  -                                -                   Reconstruction: 250mm Full Flex.
              -                         -                                  -                                -                                    -
       2040: Year 30   Resurface (to same level)                           -                                -                                    -
       2041: Year 31                    -                 Resurface (to same level)                         -                                    -
       2042: Year 32                    -                                  -                 Resurface (to same level)                           -
       2043: Year 33                    -                                  -                                -                   Resurface (to same level)
              -                         -                                  -                                -                                    -
       2050: Year 40   Reconstruction: 250mm Full Flex.                    -                                -                                    -
       2051: Year 41                    -                 Reconstruction: 250mm Full Flex.                  -                                    -
       2052: Year 42                    -                                  -                 Reconstruction: 250mm Full Flex.                    -
       2053: Year 43                    -                                  -                                -                   Reconstruction: 250mm Full Flex.
              -                         -                                  -                                -                                    -
       2060: Year 50   Resurface (to same level)                           -                                -                                    -
       2061: Year 51                    -                 Resurface (to same level)                         -                                    -
       2062: Year 52                    -                                  -                 Resurface (to same level)                           -
       2063: Year 53                    -                                  -                                -                   Resurface (to same level)
              -                         -                                  -                                -                                    -
       2070: Year 60   Reconstruction: 250mm Full Flex.                    -                                -                                    -


     WLCO2T
                                                                                                                                                                   22
Case study 2: time for intervention


                                                                                                             Whole Life
                                                Capital Cost Operational    Whole Life    CapCarb   OpCarb    Carbon
 Option               Description
                                                    (£)       Cost (£)       Cost (£)      (tCO2)   (tCO2)   Footprint
                                                                                                              (tCO2)

   A         20 year flexible design (year 1)   £207,174.00   £249,323.30   £456,497.30    172.18   618.66     790.84
   B         20 year flexible design (year 2)   £204,215.24   £214,594.59   £418,809.82    137.94   365.64     503.58
   C         20 year flexible design (year 3)   £201,356.53   £207,337.77   £408,694.29    139.86   365.64     505.50
   D         20 year flexible design (year4)    £198,594.49   £200,326.34   £398,920.83    141.78   365.64     507.43




          WLCO2T
                                                                                                                          23
Case study 2: time for intervention

                                                         Whole Life Cost


                        £500,000.00

                        £450,000.00

                        £400,000.00

                        £350,000.00
   Cumulative NPV (£)




                        £300,000.00                                                         Option A
                                                                                            Option B
                        £250,000.00
                                                                                            Option C
                        £200,000.00                                                         Option D

                        £150,000.00

                        £100,000.00

                         £50,000.00

                                 £0.00
                                         0   10   20           30            40   50   60
                                                             Years




                                                   Whole Life Carbon Footprint


                        900.00
                        WLCO2T
                                                                                                       24
                        800.00
£50,000.00

                                                  £0.00

Case study 2: time for intervention                       0        10        20              30
                                                                                         Years
                                                                                                        40   50   60




                                                                              Whole Life Carbon Footprint


                                         900.00


                                         800.00
    Cumulative Carbon Footprint (tCO2)




                                         700.00


                                         600.00

                                                                                                                       Option A
                                         500.00
                                                                                                                       Option B
                                                                                                                       Option C
                                         400.00
                                                                                                                       Option D
                                         300.00


                                         200.00


                                         100.00


                                           0.00
                                                  0           10        20              30            40     50   60
                                                                                       Years




                                         WLCO2T
                                                                                                                                  25
Summary

• Allows decision makers to understand the trade off between cost and carbon for
  a range of options, can be used to:
   • Select options for further design development
   • Demonstrate the optimum time to invest to obtain maximum value for money
• Relatively quick and easy to use
• Enables appraisal of various options under a single system architecture
• Database can be populated with project-specific cost and carbon data
• Cost and carbon data are mutually exclusive items in the database so, the app
  can be used to study both parameters together or one parameter individually




       WLCO2T
                                                                                   26
Limitations

• Can analyse four alternative maintenance strategies
• Inputs cannot be saved for future editing
• Costs do not include:
    • Preliminaries
    • Traffic Management
    • User delay costs
    • Non pavement items
    • Optimism bias
• Carbon emissions factors for some treatments are not available
    • Particularly rigid pavement maintenance treatments




       WLCO2T
                                                                   27
Future development

• Improve user friendliness
• Include new-build construction activities
• Include Traffic Management costs
• Link to other highway asset types
    • Earthworks
    • Street lighting
• Adopt system architecture for other linear assets
    • Rail
    • Drainage




       WLCO2T
                                                      28
steve.finnie@urs.com




                       29

More Related Content

Viewers also liked

Viewers also liked (20)

Effect of discrete_fiber_reinforcement_on_soil_ten
Effect of discrete_fiber_reinforcement_on_soil_tenEffect of discrete_fiber_reinforcement_on_soil_ten
Effect of discrete_fiber_reinforcement_on_soil_ten
 
Flyash in geotechnical engineering
Flyash in geotechnical engineeringFlyash in geotechnical engineering
Flyash in geotechnical engineering
 
Lightweight and heavyweight concrete
Lightweight and heavyweight concrete Lightweight and heavyweight concrete
Lightweight and heavyweight concrete
 
CCSVI -Hector Ferral - enero2012
CCSVI -Hector Ferral - enero2012CCSVI -Hector Ferral - enero2012
CCSVI -Hector Ferral - enero2012
 
Analysis Of Opening Film Techniques Employed
Analysis Of Opening Film Techniques EmployedAnalysis Of Opening Film Techniques Employed
Analysis Of Opening Film Techniques Employed
 
Creativecommons i skolan
Creativecommons i skolanCreativecommons i skolan
Creativecommons i skolan
 
minaochandrasbilder
minaochandrasbilderminaochandrasbilder
minaochandrasbilder
 
Foro Internacional
Foro Internacional Foro Internacional
Foro Internacional
 
Wikipedia i skolan Medioteket 100429
Wikipedia i skolan Medioteket 100429Wikipedia i skolan Medioteket 100429
Wikipedia i skolan Medioteket 100429
 
Child Abuse
Child AbuseChild Abuse
Child Abuse
 
Question 1
Question 1Question 1
Question 1
 
Intensivdagarna
IntensivdagarnaIntensivdagarna
Intensivdagarna
 
Powerpoint version of question two
Powerpoint version of question twoPowerpoint version of question two
Powerpoint version of question two
 
Bartus Wackowski
Bartus WackowskiBartus Wackowski
Bartus Wackowski
 
Database Fuckery
Database FuckeryDatabase Fuckery
Database Fuckery
 
Cckth
CckthCckth
Cckth
 
Källkritik-lektionsexempel (20/1-10)
Källkritik-lektionsexempel (20/1-10)Källkritik-lektionsexempel (20/1-10)
Källkritik-lektionsexempel (20/1-10)
 
About vanessa-levin
About vanessa-levinAbout vanessa-levin
About vanessa-levin
 
The new way of outsourcing
The new way of outsourcingThe new way of outsourcing
The new way of outsourcing
 
Bb 103 micro economics chitwan
Bb 103 micro economics chitwanBb 103 micro economics chitwan
Bb 103 micro economics chitwan
 

Similar to WLCO2T URS

Stream D_David Riley
Stream D_David RileyStream D_David Riley
Stream D_David RileyBecarAsset
 
moej Toward Zero Carbon Emission Thermal Power Plants
moej Toward Zero Carbon Emission Thermal Power Plantsmoej Toward Zero Carbon Emission Thermal Power Plants
moej Toward Zero Carbon Emission Thermal Power PlantsGlobal CCS Institute
 
Advance Net Zero Carbon (18 Aug 2021).pdf
Advance Net Zero Carbon (18 Aug 2021).pdfAdvance Net Zero Carbon (18 Aug 2021).pdf
Advance Net Zero Carbon (18 Aug 2021).pdfCalvinWong58696
 
Paul Ciniglio presentation for South Coast green breakfast - 22 May
Paul Ciniglio presentation for South Coast green breakfast - 22 MayPaul Ciniglio presentation for South Coast green breakfast - 22 May
Paul Ciniglio presentation for South Coast green breakfast - 22 MayBlake Morgan
 
Zero carbon projects
Zero carbon projectsZero carbon projects
Zero carbon projectsPeter Mumford
 
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...IRJET Journal
 
USING CARBBROD TO ESTIMATE THE COST OF PHYTOPHTHORAS
USING CARBBROD TO ESTIMATE THE COST OF PHYTOPHTHORASUSING CARBBROD TO ESTIMATE THE COST OF PHYTOPHTHORAS
USING CARBBROD TO ESTIMATE THE COST OF PHYTOPHTHORASForest Research
 
Costs for CO2 capture in cement manufacture - Duncan Barker, Mott MacDonald
Costs for CO2 capture in cement manufacture - Duncan Barker, Mott MacDonaldCosts for CO2 capture in cement manufacture - Duncan Barker, Mott MacDonald
Costs for CO2 capture in cement manufacture - Duncan Barker, Mott MacDonaldGlobal CCS Institute
 
IRJET- Analytical Study of Solid Slab with Different Types of Cavity
IRJET- Analytical Study of Solid Slab with Different Types of CavityIRJET- Analytical Study of Solid Slab with Different Types of Cavity
IRJET- Analytical Study of Solid Slab with Different Types of CavityIRJET Journal
 
The Uses Of Ecocem GGBS In Concrete 2009
The Uses Of Ecocem GGBS In Concrete 2009The Uses Of Ecocem GGBS In Concrete 2009
The Uses Of Ecocem GGBS In Concrete 2009DavidOFlynn
 
Michel Sacotte - Schneider Electric
Michel Sacotte - Schneider ElectricMichel Sacotte - Schneider Electric
Michel Sacotte - Schneider Electriccwiemeexpo
 
Renewable Energy From Municipal Solid Waste And Automobile Shredder Residues
Renewable Energy From Municipal Solid Waste And Automobile Shredder ResiduesRenewable Energy From Municipal Solid Waste And Automobile Shredder Residues
Renewable Energy From Municipal Solid Waste And Automobile Shredder ResiduesJaapaz
 
B&i2013 donderdag 15.45_zaal_b_low-carbon concretes using novel mineral binde...
B&i2013 donderdag 15.45_zaal_b_low-carbon concretes using novel mineral binde...B&i2013 donderdag 15.45_zaal_b_low-carbon concretes using novel mineral binde...
B&i2013 donderdag 15.45_zaal_b_low-carbon concretes using novel mineral binde...Bouwmaterialen_Innovatie
 
Introduction to CO2GEO software
Introduction to CO2GEO softwareIntroduction to CO2GEO software
Introduction to CO2GEO softwareGeoconsult Ltda
 
Steel & CCS - Jean-Pierre Birat, ESTEP
Steel & CCS - Jean-Pierre Birat, ESTEPSteel & CCS - Jean-Pierre Birat, ESTEP
Steel & CCS - Jean-Pierre Birat, ESTEPGlobal CCS Institute
 
The role of Direct Air Capture and Carbon Dioxide Removal in well below 2C sc...
The role of Direct Air Capture and Carbon Dioxide Removal in well below 2C sc...The role of Direct Air Capture and Carbon Dioxide Removal in well below 2C sc...
The role of Direct Air Capture and Carbon Dioxide Removal in well below 2C sc...IEA-ETSAP
 
Sea NG - Small Market Gas Project Development
Sea NG - Small Market Gas Project DevelopmentSea NG - Small Market Gas Project Development
Sea NG - Small Market Gas Project DevelopmentLyndon Ward
 

Similar to WLCO2T URS (20)

Stream D_David Riley
Stream D_David RileyStream D_David Riley
Stream D_David Riley
 
moej Toward Zero Carbon Emission Thermal Power Plants
moej Toward Zero Carbon Emission Thermal Power Plantsmoej Toward Zero Carbon Emission Thermal Power Plants
moej Toward Zero Carbon Emission Thermal Power Plants
 
Advance Net Zero Carbon (18 Aug 2021).pdf
Advance Net Zero Carbon (18 Aug 2021).pdfAdvance Net Zero Carbon (18 Aug 2021).pdf
Advance Net Zero Carbon (18 Aug 2021).pdf
 
Session 27 Björn Birgisson
Session 27 Björn BirgissonSession 27 Björn Birgisson
Session 27 Björn Birgisson
 
CO2 - EOR and its role in CCS
CO2 - EOR and its role in CCSCO2 - EOR and its role in CCS
CO2 - EOR and its role in CCS
 
Paul Ciniglio presentation for South Coast green breakfast - 22 May
Paul Ciniglio presentation for South Coast green breakfast - 22 MayPaul Ciniglio presentation for South Coast green breakfast - 22 May
Paul Ciniglio presentation for South Coast green breakfast - 22 May
 
Zero carbon projects
Zero carbon projectsZero carbon projects
Zero carbon projects
 
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
 
USING CARBBROD TO ESTIMATE THE COST OF PHYTOPHTHORAS
USING CARBBROD TO ESTIMATE THE COST OF PHYTOPHTHORASUSING CARBBROD TO ESTIMATE THE COST OF PHYTOPHTHORAS
USING CARBBROD TO ESTIMATE THE COST OF PHYTOPHTHORAS
 
Costs for CO2 capture in cement manufacture - Duncan Barker, Mott MacDonald
Costs for CO2 capture in cement manufacture - Duncan Barker, Mott MacDonaldCosts for CO2 capture in cement manufacture - Duncan Barker, Mott MacDonald
Costs for CO2 capture in cement manufacture - Duncan Barker, Mott MacDonald
 
IRJET- Analytical Study of Solid Slab with Different Types of Cavity
IRJET- Analytical Study of Solid Slab with Different Types of CavityIRJET- Analytical Study of Solid Slab with Different Types of Cavity
IRJET- Analytical Study of Solid Slab with Different Types of Cavity
 
CO2 standard for new aircraft
CO2 standard for new aircraftCO2 standard for new aircraft
CO2 standard for new aircraft
 
The Uses Of Ecocem GGBS In Concrete 2009
The Uses Of Ecocem GGBS In Concrete 2009The Uses Of Ecocem GGBS In Concrete 2009
The Uses Of Ecocem GGBS In Concrete 2009
 
Michel Sacotte - Schneider Electric
Michel Sacotte - Schneider ElectricMichel Sacotte - Schneider Electric
Michel Sacotte - Schneider Electric
 
Renewable Energy From Municipal Solid Waste And Automobile Shredder Residues
Renewable Energy From Municipal Solid Waste And Automobile Shredder ResiduesRenewable Energy From Municipal Solid Waste And Automobile Shredder Residues
Renewable Energy From Municipal Solid Waste And Automobile Shredder Residues
 
B&i2013 donderdag 15.45_zaal_b_low-carbon concretes using novel mineral binde...
B&i2013 donderdag 15.45_zaal_b_low-carbon concretes using novel mineral binde...B&i2013 donderdag 15.45_zaal_b_low-carbon concretes using novel mineral binde...
B&i2013 donderdag 15.45_zaal_b_low-carbon concretes using novel mineral binde...
 
Introduction to CO2GEO software
Introduction to CO2GEO softwareIntroduction to CO2GEO software
Introduction to CO2GEO software
 
Steel & CCS - Jean-Pierre Birat, ESTEP
Steel & CCS - Jean-Pierre Birat, ESTEPSteel & CCS - Jean-Pierre Birat, ESTEP
Steel & CCS - Jean-Pierre Birat, ESTEP
 
The role of Direct Air Capture and Carbon Dioxide Removal in well below 2C sc...
The role of Direct Air Capture and Carbon Dioxide Removal in well below 2C sc...The role of Direct Air Capture and Carbon Dioxide Removal in well below 2C sc...
The role of Direct Air Capture and Carbon Dioxide Removal in well below 2C sc...
 
Sea NG - Small Market Gas Project Development
Sea NG - Small Market Gas Project DevelopmentSea NG - Small Market Gas Project Development
Sea NG - Small Market Gas Project Development
 

WLCO2T URS

  • 1. WLCO2T Calculating whole life cost and whole life carbon footprint of pavement projects June 01, 2012
  • 2. Contents • Context • What does the app do? • How does the app work? • How to use the app • Case study 1: Determine the optimum maintenance strategy • Case study 2: Determine the optimum year for intervention • Summary • Limitations • Future developments WLCO2T 2
  • 3. Context • Current legislation • Carbon Reduction Commitment Energy Efficiency Scheme • Climate Change Levy • Climate Change Agreements • Building Regulations • EU Energy Performance in Buildings Directive • EU Energy Trading Scheme • Future legislation • Market mechanism • Emissions trading • Clean Development Mechanism • Joint implementation WLCO2T 3
  • 4. Context “Less carbon does not mean less construction. It means constructing different forms of infrastructure, by different methods, using different materials. And to do that we need to develop new skills and new tools. We need new tools for project appraisal. Today this is about whole-life costs and net present value in monetary terms. We refer to 'Capex' and 'Opex'. We now need to add the carbon factor. We need to know how much carbon will be embodied in the proposed infrastructure, and how much will be used during construction and operation. We need to know the 'CapCarb' and 'OpCarb' - new terms for most of us. And importantly we need to understand the relationship and trade-off between these two measures.” Peter Hansford, ICE President WLCO2T 4
  • 5. Context “While there are noticeable highs and lows in year to year data, over longer periods of time there is a discernable warming trend across the globe. Natural causes can explain only a small part of this warming. The overwhelming majority of scientists agree that this is due to rising concentrations of heat- trapping greenhouse gases in the atmosphere caused by human activities”. To avoid these problems, we will have to significantly reduce our energy needs and generate more power from non-carbon sources. The transition to a low carbon economy presents major global opportunities for business. The demand for low carbon and environmental goods and services is already worth £3.2 trillion per year, and is predicted to increase as the move to a low carbon economy occurs.” www.metoffice.gov.uk/climate-change WLCO2T COMPANY CONFIDENTIAL: Use this space for disclaimer if needed. 5
  • 6. Context “Global warming could shrink the global economy by 20% while taking action now would cost just 1% of global gross domestic product.” The Economics of Climate Change, Sir Nicholas Stern WLCO2T 6
  • 7. What does the app do? • Calculates costs and emissions associated with pavement maintenance based on quantities of resources required during a 60 year analysis period • The app allows decision makers to understand the balance between cost and carbon by calculating the following parameters for a range of alternative maintenance strategies: • Capital cost (Capex): discounted costs in Years 1 - 5 • Operational cost (Opex): discounted costs in Years 6 - 60 • Whole life cost (WLC): discounted costs in Years 1 - 60 • Capital carbon footprint (CapCarb): carbon in Years 1 - 5 • Operational carbon footprint (OpCarb): carbon in Years 6 - 60 • Whole life carbon footprint (WLCO2): carbon in Years 1 - 60 WLCO2T 7
  • 8. How does the app work? • Built on standard approach to whole life cost analysis • Considers initial maintenance and future maintenance • Database contains unit costs for a range of treatments • Follows basic HM Treasury rules for project appraisal • 60 year analysis period • 3.5% discount for first 30 years • 3.0% discount rate thereafter • Residual value is taken into account • Carbon emissions factors included in treatments database (ICE CESMM3 Carbon and Price Book 2011) WLCO2T 8
  • 9. How does the app work? WLCO2T 9
  • 10. Treatments database Flexible pavements Structural Patch: 100mm depth Retexture: Limestone Structural Patch: 150mm depth Retexture: Flint Structural Patch: 200mm depth Emulsion tack coat Recycled Thin Surf.: 20mm Thin Surfacing: 20mm Recycled Thin Surf.: 25mm Thin Surfacing: 25mm Recycled Thin Surf.: 30mm Thin Surfacing: 30mm Recycled Resurface (to same level) High Friction Surfacing (new) Recycled Resurface (Por. Asphalt) High Friction Surfacing (replacement) Recycled Inlay: 100mm Resurface (to same level) Recycled P/O + Overlay: 50mm (Net) Resurface (Porous Asphalt) Recycled P/O + Overlay:100mm (Net) Inlay: 100mm Recycled P/O + Overlay: 150mm (Net) Plane off + Overlay: 50mm (Net) Recycled P/O + Overlay: 200mm (Net) Plane off + Overlay:100mm (Net) Recycled P/O + Overlay: 250mm (Net) Plane off + Overlay:150mm (Net) Recycled Reconst.: 150mm Full flex. Plane off + Overlay:200mm (Net) Recycled Reconst.: 200mm Full Flex.. Plane off + Overlay:250mm (Net) Recycled Reconst.: 200mm Flex. Comp. Reconstruction: 150mm Full flex. Recycled Reconst.: 250mm Full Flex. Reconstruction: 200mm Full Flex. Recycled Reconst.: 250mm Flex. Comp. Reconstruction: 200mm Flex. Comp. Recycled Reconst.: 300mm Full Flex. Reconstruction: 250mm Full Flex. Recycled Reconst.: 300mm Flex. Comp. Reconstruction: 250mm Flex. Comp. Recycled Reconst.: 350mm Full Flex. Reconstruction: 300mm Full Flex. Recycled Reconst.: 350mm Flex. Comp. Reconstruction: 300mm Flex. Comp. Recycled Reconst.: 400mm Full Flex. Reconstruction: 350mm Full Flex. Recycled Reconst.: 400mm Flex. Comp. Reconstruction: 350mm Flex. Comp. Recycled Structural Patch: 50mm depth Reconstruction: 400mm Full Flex. Recycled Structural Patch: 100mm depth Reconstruction: 400mm Flex. Comp. Recycled Structural Patch: 150mm depth Structural Patch: 50mm depth Recycled Structural Patch: 200mm depth WLCO2T 10
  • 11. Treatments database Concrete pavements Overlay: 150mm Thin Surf.: 30mm Overlay: 180mm Thin Bonded Repairs Overlay: 300mm Full Depth Repairs: JRC Overlay: 200mm of CRCP Full Depth Repairs: URC Crack & Seat with 150mm Overlay Retexture: Limestone Crack & Seat with 180mm Overlay Retexture: Flint Crack & Seat with 300mm Overlay Joint seal JRC: longitudinal(*) Reconstruction: CRCR with 100mm Bit Joint seal URC: longitudinal(*) Reconstruction: CRCR with 150mm Bit Joint seal JRC: transverse(*) Reconstruction: CRCR with 200mm Bit Joint seal URC: transverse(*) Joint saw-cut & seal JRC: longitudinal(*) Reconstruction: 200mm JRC Joint saw-cut & seal URC: longitudinal(*) Reconstruction: 200mm URC Joint saw-cut & seal JRC: transverse(*) Reconstruction: 200mm CRCP Joint saw-cut & seal URC: transverse (*) Reconstruction: 250mm JRC Joint Repairs Reconstruction: 250mm URC Punch Out Repairs Reconstruction: 250mm CRCP Vacuum Grout: Bay Reconstruction: 300mm JRC Vacuum Grout: Joint Reconstruction: 300mm URC WLCO2T 11
  • 12. Input screen WLCO2T 12
  • 13. Input screen WLCO2T 13
  • 14. Build scenarios WLCO2T 14
  • 15. Results Whole Life Capital Cost Operational Whole Life CapCarb OpCarb Option Description Carbon (£) Cost (£) Cost (£) (tCO2) (tCO2) Footprint (tCO2) A 20 year fully flexible design £207,174.00 £249,323.30 £456,497.30 172.18 618.66 790.84 B 40 year fully flexible design £259,208.40 £158,394.23 £417,602.63 464.81 620.83 1,085.65 C 40 year rigid design £324,733.20 £175,523.23 £500,256.43 0.00 156.02 156.02 D do minimum £11,087.39 £355,117.83 £366,205.23 5.76 501.66 507.43 WLCO2T 15
  • 16. Case study 1: strategy selection • Three-lane dual carriageway in London • Significant structural deterioration • Client needs to select the treatment that optimises cost and carbon to progress to detailed design • Maintenance strategies • 20 year fully flexible design • 20 year flexible composite design • 40 year fully flexible design • 40 year rigid design WLCO2T 16
  • 17. Case study 1: strategy selection Year Option A Option B Option C Option D 20 year flexible design 20 year flexible composite design 40 year flexible design 40 year rigid design 2011: Year 01 Reconstruction: 250mm Full Flex. Reconstruction: 250mm Flex Comp. Reconstruction: 350mm Full Flex. Reconstruction: 200mm CRCP - - - - - 2020: Year 10 Resurface (to same level) Resurface (to same level) Resurface (to same level) Resurface (to same level) - - - - - 2030: Year 20 Reconstruction: 250mm Full Flex. Reconstruction: 250mm Flex Comp. Resurface (to same level) Resurface (to same level) - - - - - 2040: Year 30 Resurface (to same level) Resurface (to same level) Resurface (to same level) Resurface (to same level) - - - - - 2050: Year 40 Reconstruction: 250mm Full Flex. Reconstruction: 250mm Flex Comp. Reconstruction: 350mm Full Flex. Reconstruction: 200mm CRCP - - - - - 2060: Year 50 Resurface (to same level) Resurface (to same level) Resurface (to same level) Resurface (to same level) - - - - - 2070: Year 60 Reconstruction: 250mm Full Flex. Reconstruction: 250mm Flex Comp. Resurface (to same level) Resurface (to same level) WLCO2T 17
  • 18. Case study 1: strategy selection Whole Life Capital Cost Operational Whole Life CapCarb OpCarb Carbon Option Description (£) Cost (£) Cost (£) (tCO2) (tCO2) Footprint (tCO2) A 20 year flexible design £207,174.00 £249,323.30 £456,497.30 172.18 618.66 790.84 B 20 year flexible composite design £246,199.80 £284,951.71 £531,151.51 453.86 1,285.45 1,739.30 C 40 year flexible design £259,208.40 £158,394.23 £417,602.63 464.81 620.83 1,085.65 D 40 year rigid design £300,161.40 £169,099.85 £469,261.25 8,063.89 8,219.90 16,283.79 WLCO2T 18
  • 19. Case study 1: strategy selection Whole Life Cost £600,000.00 £500,000.00 £400,000.00 Cumulative NPV (£) Option A Option B £300,000.00 Option C Option D £200,000.00 £100,000.00 £0.00 0 10 20 30 40 50 60 Years Whole Life Carbon Footprint WLCO2T 18000.00 19
  • 20. £0.00 Case study 1: strategy selection 0 10 20 30 Years 40 50 60 Whole Life Carbon Footprint 18000.00 16000.00 Cumulative Carbon Footprint (tCO2) 14000.00 12000.00 Option A 10000.00 Option B Option C 8000.00 Option D 6000.00 4000.00 2000.00 0.00 0 10 20 30 40 50 60 Years WLCO2T 20
  • 21. Case study 2: time for intervention Whole Life Capital Cost Operational Whole Life CapCarb OpCarb Carbon Option Description (£) Cost (£) Cost (£) (tCO2) (tCO2) Footprint (tCO2) A 20 year flexible design £207,174.00 £249,323.30 £456,497.30 172.18 618.66 790.84 B 20 year flexible composite design £246,199.80 £284,951.71 £531,151.51 453.86 1,285.45 1,739.30 C 40 year flexible design £259,208.40 £158,394.23 £417,602.63 464.81 620.83 1,085.65 D 40 year rigid design £300,161.40 £169,099.85 £469,261.25 8,063.89 8,219.90 16,283.79 • Option A selected from Case Study 1 • Now study the impact of continuing with routine maintenance to defer the major capital expenditure • Maintenance strategies • Construct option A in Year 1 • Routine maintenance in Year 1, construct option A in Year 2 • Routine maintenance in Years 1 and 2, construct option A in Year 3 • Routine maintenance in Years 1, 2 and 3, construct option A in Year 4 WLCO2T 21
  • 22. Case study 2: time for intervention Year Option A Option B Option C Option D 20 year flexible design 20 year flexible design 20 year flexible design 20 year flexible design deferred by 1 year deferred by 2 years deferred by 3 years 2011: Year 01 Reconstruction: 250mm Full Flex. Structural Patch: 50mm depth Structural Patch: 50mm depth Structural Patch: 50mm depth 2012: Year 02 - Reconstruction: 250mm Full Flex. Structural Patch: 50mm depth Structural Patch: 50mm depth 2013: Year 03 - - Reconstruction: 250mm Full Flex. Structural Patch: 50mm depth 2014: Year 04 - - - Reconstruction: 250mm Full Flex. - - - - - 2020: Year 10 Resurface (to same level) - - - 2021: Year 11 - Resurface (to same level) - - 2022: Year 12 - - Resurface (to same level) - 2023: Year 13 - - - Resurface (to same level) - - - - - 2030: Year 20 Reconstruction: 250mm Full Flex. - - - 2031: Year 21 - Reconstruction: 250mm Full Flex. - - 2032: Year 22 - - Reconstruction: 250mm Full Flex. - 2033: Year 23 - - - Reconstruction: 250mm Full Flex. - - - - - 2040: Year 30 Resurface (to same level) - - - 2041: Year 31 - Resurface (to same level) - - 2042: Year 32 - - Resurface (to same level) - 2043: Year 33 - - - Resurface (to same level) - - - - - 2050: Year 40 Reconstruction: 250mm Full Flex. - - - 2051: Year 41 - Reconstruction: 250mm Full Flex. - - 2052: Year 42 - - Reconstruction: 250mm Full Flex. - 2053: Year 43 - - - Reconstruction: 250mm Full Flex. - - - - - 2060: Year 50 Resurface (to same level) - - - 2061: Year 51 - Resurface (to same level) - - 2062: Year 52 - - Resurface (to same level) - 2063: Year 53 - - - Resurface (to same level) - - - - - 2070: Year 60 Reconstruction: 250mm Full Flex. - - - WLCO2T 22
  • 23. Case study 2: time for intervention Whole Life Capital Cost Operational Whole Life CapCarb OpCarb Carbon Option Description (£) Cost (£) Cost (£) (tCO2) (tCO2) Footprint (tCO2) A 20 year flexible design (year 1) £207,174.00 £249,323.30 £456,497.30 172.18 618.66 790.84 B 20 year flexible design (year 2) £204,215.24 £214,594.59 £418,809.82 137.94 365.64 503.58 C 20 year flexible design (year 3) £201,356.53 £207,337.77 £408,694.29 139.86 365.64 505.50 D 20 year flexible design (year4) £198,594.49 £200,326.34 £398,920.83 141.78 365.64 507.43 WLCO2T 23
  • 24. Case study 2: time for intervention Whole Life Cost £500,000.00 £450,000.00 £400,000.00 £350,000.00 Cumulative NPV (£) £300,000.00 Option A Option B £250,000.00 Option C £200,000.00 Option D £150,000.00 £100,000.00 £50,000.00 £0.00 0 10 20 30 40 50 60 Years Whole Life Carbon Footprint 900.00 WLCO2T 24 800.00
  • 25. £50,000.00 £0.00 Case study 2: time for intervention 0 10 20 30 Years 40 50 60 Whole Life Carbon Footprint 900.00 800.00 Cumulative Carbon Footprint (tCO2) 700.00 600.00 Option A 500.00 Option B Option C 400.00 Option D 300.00 200.00 100.00 0.00 0 10 20 30 40 50 60 Years WLCO2T 25
  • 26. Summary • Allows decision makers to understand the trade off between cost and carbon for a range of options, can be used to: • Select options for further design development • Demonstrate the optimum time to invest to obtain maximum value for money • Relatively quick and easy to use • Enables appraisal of various options under a single system architecture • Database can be populated with project-specific cost and carbon data • Cost and carbon data are mutually exclusive items in the database so, the app can be used to study both parameters together or one parameter individually WLCO2T 26
  • 27. Limitations • Can analyse four alternative maintenance strategies • Inputs cannot be saved for future editing • Costs do not include: • Preliminaries • Traffic Management • User delay costs • Non pavement items • Optimism bias • Carbon emissions factors for some treatments are not available • Particularly rigid pavement maintenance treatments WLCO2T 27
  • 28. Future development • Improve user friendliness • Include new-build construction activities • Include Traffic Management costs • Link to other highway asset types • Earthworks • Street lighting • Adopt system architecture for other linear assets • Rail • Drainage WLCO2T 28