1. Project & Interface Manager/Coordinator J. Bagheri(jaf.bagheri@gmail.com)
1/9 (Nov 2016)
Name Bagheri, Jafar
Tehran, Iran, Work Tel: #98 (0)21 23154376 Cell: #98 (0)912 3751915
Email: Jaf.Bagheri@Gmail.com,
https://ir.linkedin.com/in/jafar-bagheri-8a140228
Date of Birth 1979
Nationality Iranian
COMPETENCIES
EPC Project Manager in field of metro, urban railway and main line E&M with 6 years of
experience, using project management tools and skills and general knowledge of PMBOK
5 years of experience as PMC (consulting company) and simultaneously 8 years' experience
as engineering studies project manager in the field of metro, urban railway and main line's
all disciplines
6 years' experience as station track experts, capacity and operation simulation, rolling stock,
alignment and permanent way
Railway transportation (BSc) and MBA Degree leads to in depth knowledge of railway
transportation, and member of "Iran Railway Think Tank" and "Iran Public Transportation
Integration Council"
Leadership and business management experience as the vice president and board member of
railway consultant Co., able to prioritize, delegate tasks, and make sound decisions quickly
while maintaining a focus on the bottom line, ability to oversee and manage hundreds of
individuals while ensuring timely completion of project deadlines all while remaining on or
under budget.
Problem solving skill, identifying the problems and implement corrective processes
Skilled at presenting technical and abstract concepts in a clear and concise way
Preparing technical, legal, and financial proposal tenders
EDUCATION
B.S of Rail way Transportation Eng., Iran University of Science & Technology, 2002
MBA, University of Tehran, 2016
Preliminary course of ISO 9001-2000, TSQ, 2002
FIDIC advanced seminar of EPC, Iranian Society of Consulting Engineers, 2004
PMBOK course, METRA, 2001
PM course, Sharif University of Iran, 2005
Autodesk Land Desktop, Jahad Daneshgahi Amirkabir University of Iran, 2008
Primavera (Pe6), Microsystem Educational Organization. 2008
LANGUAGES
READING SPEAKING WRITING
PERSIAN Native Native Native
ENGLISH Excellent Good Very Good
ARABIC Preliminary
AZARBAIJANI Preliminary
2. Project & Interface Manager/Coordinator J. Bagheri(jaf.bagheri@gmail.com)
2/9 (Nov 2016)
COMPUTER SKILLS
Microsoft Office Package (added MSP) Excellent
PASCAL PL Excellent
DELPHI WPL Good
Visual Basic Familiar
AutoCAD 2D Very Good
Autodesk Land Desktop Good
PRIMAVERA P6 Good
PROFESSIONAL EXPERIENCE, FULL TIME POSITION
SCIENCE 2014 PM OF TEHRAN-MASHHAD RAILWAY ELECTRIFICATION MAPNA RAIL
PROJECT MANAGER OF ELECTRIFICATION OF TEHRAN-MASHHAD RAILWAY (950KM DOUBLE
TRACK) IN CONSORTIUM OF MAPNA-CMC-SUPOWER
********
SCIENCE 2012 PM OF ESFAHAN METRO L1, E&M EXECUTION MAPNA RAIL
PROJECT MANAGER OF E&M (POWER, SIGNALING, TELECOM) EXECUTION OF LINE 1 OF
ESFAHAN METRO (21 STATIONS, 21KM)
********
2010-2012 VICE PRESIDENT METRA
(220 STAFF, 430 PROJECTS AND 8 MILLION DOLLARS ANNUAL TURNOVER)
►◄
2011-2012 BOARD MEMBER METRA
►◄
2008-2010 HEAD OF DEPARTMENT METRA
(SUPERSTRUCTURE AND PERMANENT WAY) (27 STAFF AND MORE THAN 70 PROJECTS OF
RAILWAY AND METRO STUDIES AND EXECUTION)
►◄
2001-2008 PROJECT MANAGER & SUPERSTRUCTURE EXPERT METRA
(RAILWAY TRACK AND STATIONS)
SUPERSTRUCTURE & STATIONS DEPARTMENT
METRO DEPARTMENT
PROJECT MANAGER:
DETAIL DESIGN OF TEHRAN-QOM-ESFAHAN HIGH-SPEED RAILWAY
(410Km of high-speed railway with speed of 320km/h, study the permanent way, signaling &
telecom, rolling stock, operation, buildings and structure, and preparing EPC tender doc. with
assistance of Systra consultant, France. Included VE process and training courses of Iran
Transportation Ministry personnel)
FEASIBILITY TO DETAIL DESIGN OF ISFAHAN – SHIRAZ RAILWAY STUDIES
(500Km, 24 stations, leads to EPC/Finance project under construction)
ISFAHAN – SHIRAZ INFRASTRUCTURE STUDIES COORDINATING
(Coordination between 6 consulting Co. during 4 years)
FEASIBILITY TO DETAIL DESIGN OF MARAGEH – URUMIEH RAILWAY STUDIES
(180Km, 9 stations, leads to EPC/Finance project under construction)
MARAGEH – URUMIEH RAILWAY STUDIES COORDINATING
(Coordination between 3 consulting Co. during 3 years)
FEASIBILITY TO DETAIL DESIGN OF GAZVIN – RASHT-ANZALI RAILWAY STUDIES
(300Km, 15 stations, leads to EPC/Finance project under construction)
GAZVIN – RASHT-ANZALI INFRASTRUCTURE STUDIES COORDINATING
3. Project & Interface Manager/Coordinator J. Bagheri(jaf.bagheri@gmail.com)
3/9 (Nov 2016)
(Coordination between 6 consulting Co. during 4 years)
PRELIMINARY STUDY OF SOUTH RAILWAY CAPACITY AND OPERATION PROBLEM
SOLVING
(Preliminary studies of electrification, signaling modification, using long rolling stock, study
of more than 1000Km railway, traffic and economic studies)
FEASIBILITY TO DETAIL DESIGN OF KHORASAN STEEL COMPANY RAIL BRANCH
(18Km connection line, 5Km internal network, study of route, alignment, sub/superstructure,
operation, rolling stock …)
FEASIBILITY TO DETAIL DESIGN OF TURBAT CEMENT FACTORY RAIL BRANCH
(20Km connection line, 3 site in Khorasan with accumulative 10 Km internal network, study
of route, alignment, sub/superstructure, operation, rolling stock, loading system, transportation
plan …)
STUDY OF KARAJ METRO LINE 4
(18 km, 20 stations, MRT, Preliminary to detail design of alignment, track works, E&M,
stations, elevator & escalator, architectural works, civil, tunnel, depot & parking, OCS, posts,
etc.)
STUDY OF MASHHAD METRO LINE 2 (ALIGNMENT)
(20 km, 22 stations, LRT, detail design of alignment, track works)
STUDY OF ESFEHAN METRO LINE 2
(23 km, 22 stations, MRT, Preliminary to detail design of alignment, track works, E&M,
stations, elevator & escalator, architectural works, civil, tunnel, depot & parking, OCS, posts,
etc. with Cooperation of Systra consultant, France.)
STUDY OF AHVAZ METRO LINE 2
(22 km, 22 stations, MRT, Preliminary to detail design of alignment, track works, E&M,
stations, elevator & escalator, architectural works, civil, tunnel, depot & parking, OCS, posts,
etc. with Cooperation of Systra consultant, France.)
PMC OF ESFEHAN METRO LINE 1 OF E&M
(21 km, 22 stations, MRT, EPC project of Signaling, Power, and Telecom with Cooperation of
Systra consultant, France.)
►◄
KEY EXPERT OF STATION TRACK DESIGN, TRAIN SIMULATION STUDIES, TRACK GEOMETRY,
OPERATION STUDIES IN THE PROJECTS OF:
PRELIMINARY DESIGN OF HIGH SPEED RAILWAY OF SYRIA ALKHANSA-AKKARY
(Simulation, stations and operation of 45Km of rough mountainous area, improve the existing
track, traffic & economic study, simulation … , under supervision of Italferr Co. Italy)
DETAIL DESIGN OF HIGH SPEED RAILWAY OF SYRIA ALTABIEH- DEIRALZOR
(Modification of a shunting station, connection to the network, under supervision of Italferr
Co. Italy)
DETAIL DESIGN OF HIGH SPEED RAILWAY OF SYRIA DEIRALZOR-ALBOOKAMAL
(Operation, simulation, station design, superstructure study of 250Km, 9 stations, under
supervision of Italferr Co. Italy)
DETAIL DESIGN OF TEHRAN-QOM-ISFAHAN HIGH SPEED RAILWAY
(Key personnel of Operation and superstructure studies, Training manager, …)
FEASIBILITY TO DETAIL DESIGN OF IRAN WEST RAILWAY
(QC of station and operation design and simulation of 350 Km railway connecting Arak-
Kermanshah-Khosravi to the railway network, 15 stations, leads to EPC/Finance project under
construction)
FEASIBILITY TO DETAIL DESIGN MIANEH-BOSTANABAD-TABRIZ RAILWAY
(QC of station and operation design and simulation of 200 Km, 8 stations, leads to EPC/Finance
project under construction)
FEASIBILITY OF TEHRAN-MASHHAD HIGH SPEED RAILWAY
(Key personnel of Operation and superstructure studies, QC of station and operation design
and simulation performed by SYSTRA Co. France of 900 Km, 10 stations)
DETAIL DESIGN OF SHIRAZ URBAN RAILWAY, LINE 1
4. Project & Interface Manager/Coordinator J. Bagheri(jaf.bagheri@gmail.com)
4/9 (Nov 2016)
(Operation, simulation, traffic modification studies and depot track design of 35Km urban
railway under supervision of SYSTRA Co. France)
PRELIMINARY STUDY OF SHIRAZ URBAN RAILWAY, LINE 2
(Operation, simulation, traffic, rolling stock & depot studies of 35Km urban railway under
supervision of CITIC Co. China)
SIMULATION OF TEHRAN URBAN RAILWAY, LINE 4
(QC of rectifier stations simulation study performed by MM Co. Italy)
PRELIMINARY AND DETAIL DESIGN OF KERMANSHAH METRO, LINE1
(Key personnel of Operation and station studies)
PRELIMINARY AND DETAIL DESIGN OF QOM METRO, LINE1
(Key personnel of Operation and station studies)
…
►◄
PREPARING OF TENDER DOCUMENTS (EPC, BOT, …)
ISFAHAN – SHIRAZ RAILWAY (EPC OF SUPERSTRUCTURE)
MARAGEH – URUMIEH RAILWAY (EPC OF SUPERSTRUCTURE)
GAZVIN – RASHT-ANZALI (EPC OF SUPERSTRUCTURE)
IRAN WEST RAILWAY (EPC OF SUPERSTRUCTURE)
MIANEH-BOSTANABAD-TABRIZ RAILWAY (EPC OF SUPERSTRUCTURE)
KHORASAN STEEL COMPANY RAIL BRANCH
TURBAT CEMENT FACTORY RAIL BRANCH
DEIRALZOR-ALBOOKAMAL RAILWAY (SUPERSTRUCTURE)
…
►◄
EVALUATING OF THE CONTRACTORS TENDER PROPOSAL OF EPC PROJECTS OF:
ISFAHAN – SHIRAZ RAILWAY (EPC OF SUPERSTRUCTURE)
MARAGEH – URUMIEH RAILWAY (EPC OF SUPERSTRUCTURE)
GAZVIN – RASHT-ANZALI (EPC OF SUPERSTRUCTURE)
IRAN WEST RAILWAY (EPC OF SUPERSTRUCTURE)
MIANEH-BOSTANABAD-TABRIZ RAILWAY (EPC OF SUPERSTRUCTURE)
SARI-RASHT RAILWAY (EPC WHOLE JOB)
►◄
FINANCIAL & TECHNICAL OFFERS PREPARING FOR CONSULTING TENDERS
STUDY OF 4 RAILWAYS IN SYRIA (INTERNATIONAL TENDER)
STUDY OF A RAILWAY IN INDIA (INTERNATIONAL TENDER)
STUDY OF TRANSPORTATION GENERAL PLAN OF AFGHANISTAN (INTERNATIONAL
TENDER)
MP OF 6 RAILWAYS AND URBAN RAILWAY IN IRAN
STUDY OF 7 METRO, GENERAL PLAN, PRILIMINARY, DETAIL DESIGN (ALIGNMENT,
CIVIL, STRUCTURES, SYSTEMS, BUILDINGS, HVAC, ROLLING STOCK, DEPOT …)
STUDY OF
STUDY OF 17 CONVENTIONAL RAILWAYS, FEASIBILITY, DETAIL DESIGN
(ALIGNMENT, SUB/SUPERSTRUCTURE, STRUCTURES, SYSTEMS, STATIONS, ROLLING
STOCK, DEPOT …)
STUDY OF 2 HIGH SPEED RAILWAYS FEASIBILITY, DETAIL DESIGN (ALIGNMENT,
SUB/SUPERSTRUCTURE, STRUCTURES, SIGNALING, TELECOM, ELECTRIFICATION,
STATIONS, BUILDINGS, ROLLING STOCK, DEPOT …)
STUDY OF 2 MAINTENANCE DEPOT OF RAJA CO. (TEHRAN & MASHHAD STATIONS)
…
*****
2000 EXPERT TEHRAN URBAN & SUBURBAN RAILWAY
(OPERATION CONTROL AND DISPATCHING)
CTC OF E2(TEHRAN) STATION
5. Project & Interface Manager/Coordinator J. Bagheri(jaf.bagheri@gmail.com)
5/9 (Nov 2016)
During this 8 month of work in the CTC center of Tehran urban railway at E2, the general
position and functionality of many parts of railway which added lots of information to
academic knowledge in the fields of general operation, control systems, signaling principles,
power supply, rolling stock and maintenance.
PROFESSIONAL EXPERIENCE PART TIME
SINCE 2012 PROJECT MANAGER & DESIGNER BOOMPAAD CONSULTING
2015 TEHRAN-KARAJ RAILWAY
(Preparation of tender documents for new double track)
2012-2015 (RAILWAY DESIGN, SULFURIC ACID PLANT OF SARCHEMEH COPPER COMPLEX )
(Railway Preliminary to Detail design)
2014 AHVAZ-SARBANDAR RAILWAY PRELIMINARY STUDY
(Feasibility Study)
*****
2013-2014 PROJECT MANAGER NAMAD MOBTAKER CONSULTING
(RAILWAY DESIGN, VENTILATION, ELECTRIFICATION AND SUPERSTRUCTURE OF SOUTH
REGION RAILWAY)
PM OF RAILWAY PRELIMINARY TO DETAIL DESIGN
*****
SINCE 2013 TECHNICAL EXPERT HEXA CONSULTING
(RAILWAY DESIGN, GOLGOHAR INDUSTRIAL SITE)
RAILWAY PRELIMINARY AND DETAIL DESIGN
*****
2012 TECHNICAL COORDINATOR SYSTRA
(QOM URBAN LINE 1 STUDIES)
TECHNICAL COORDINATOR AND ADVISOR OF SYSTRA, QOM URBAN LINE 1 SYSTEM DESIGN,
(OPERATION, SWITCH AND TRACKS LAYOUT, PERMANENT WAY, SIGNALING AND TELECOM,
VENTILATION, ROLLING STOCK AND DEPOT, POWER AND LIGHTING, PRELIMINARY AND
DETAIL DESIGN)
*****
2009-2011 PROJECT MANAGER SAHAND STEEL COMPLEX
(RAILWAY DESIGN SAHAND STEEL COMPLEX)
PM OF RAILWAY DETAIL DESIGN OF SAHAND STEEL COMPLEX (OPERATION, SWITCH AND
TRACKS LAYOUT, SUBSTRUCTURE AND SUPERSTRUCTURE, PRELIMINARY AND DETAIL DESIGN)
*****
2008-2011 PROJECT MANAGER IRAN UNIVERSITY OF SCIENCE & TECHNOLOGY
(RAILWAY DESIGN OF ARAK REFINERY)
RAILWAY ACADEMY
PM OF RAILWAY DETAIL DESIGN OF SULFUR SOLIDIFICATION UNIT, ARAK REFINERY
(OPERATION, SWITCH AND TRACKS LAYOUT, SUBSTRUCTURE AND SUPERSTRUCTURE, SITE
SURVEY, LOADING SYSTEMS, PRELIMINARY AND DETAIL DESIGN) FOR ODCC CO.
*****
2008-2010 PROJECT MANAGER PETROSADIAN CONSULTING CO.
PM AND DESIGNER OF RAILWAY DETAIL DESIGN OF
6. Project & Interface Manager/Coordinator J. Bagheri(jaf.bagheri@gmail.com)
6/9 (Nov 2016)
KERMAN OIL DISTRIBUTION SITE:
TRACK GEOMETRY, STATIONS & YARDS, SOIL WORKS, ALIGNMENT
TEHRAN OIL DISTRIBUTION SITE:
TRACK GEOMETRY, STATIONS & YARDS, SOIL WORKS, ALIGNMENT
MASHHAD OIL DISTRIBUTION SITE REHABILITATION:
TRACK GEOMETRY, STATIONS & YARDS, SOIL WORKS, ALIGNMENT
*****
2009 PROJECT MANAGER HARAZRAH CONSULTING CO.
PM AND DESIGNER OF 4 SUBURBAN RAILWAY LINES (TEHRAN-QOM, TEHRAN-VARAMIN,
TEHRAN-KARAJ, TEHRAN-GARMSAR) PRELIMINARY AND DETAIL STUDIES, (OPERATION,
STATION STUDIES, SIGNALING AND TELECOMMUNICATION, TRACK, EPC TENDER DOCUMENTS
PREPARATION) FOR 550KM OF RAILWAY AND 29 STATIONS
*****
2008 CONTRACTOR FOR PROPOSAL PREPARATION KEYHAN PARS CO.
(TENDER PREPARATION)
CONTRACTOR FOR PREPARING OF TECHNICAL PROPOSAL FOR RAILWAY OF KERMAN
PETROLEUM SITE (EPC CONTRACT)
*****
2008-2012 PROJECT MANAGER RAHYAB BEHINEH CONSULTING CO.
PM OF SHIRAZ-BOUSHEHR-ASALUYEH SUPERSTRUCTURE AND PERMANENT WAY
PRELIMINARY AND DETAIL STUDIES, (OPERATION, STATION STUDIES, SIGNALING AND
TELECOMMUNICATION, ROLLING STOCK AND MAINTENANCE DEPOT, TRACK, EPC TENDER
DOCUMENTS PREPARATION)
*****
2007-2008 PROJECT MANAGER YTP CONSULTING CO.
PM OF RAILWAY DETAIL DESIGN OF TEHRAN RAILWAY STATION RAJA NEW COACH SHED AND
MAINTENANCE DEPOT FOR DMU (OPERATION, SWITCH AND TRACKS LAYOUT, SUBSTRUCTURE
AND SUPERSTRUCTURE, SHOP DWGS, HYDRAULIC AND DRAINAGE SYSTEM, GEOTECHNICAL
STUDIES, QUANTITY ESTIMATION) FOR THE JOINT VENTURE OF IOEC CO.-NEUERO
TECHNOLOGY UNDER SUPERVISION OF PROKONSEPT CONSULTING CO.
2008 PROJECT MANAGER
PM OF RAILWAY DETAIL DESIGN OF NEYSHABUR CEMENT SITE (OPERATION, SWITCH AND
TRACKS LAYOUT, SUBSTRUCTURE AND SUPERSTRUCTURE, QUANTITY ESTIMATION,
PRELIMINARY AND DETAIL DESIGN) FOR RIVAND KHAVARAN CO.
*****
SINCE 2007 TECHNICAL ADVISOR AND VE EXPERT
TECHNICAL ADVISOR AND VE EXPERT OF VALUE ENGINEERING PROCESS OF RAILWAYS AND
METRO LINES SUCH AS: RAILWAYS OF CHABAHAR-FAHRAJ, WEST, QAZVIN-RASHT-ANZALI,
SHIRAZ-BOUSHERHR, ESFAHAN-SHIRAZ, MIANEH-TABRIZ, SHIRAZ METRO LINES, TABRIZ
METRO LINES, MASHAHD METRO LINES
*****
2007 EXPERT IMEN SAZAN CONSULTING CO.
7. Project & Interface Manager/Coordinator J. Bagheri(jaf.bagheri@gmail.com)
7/9 (Nov 2016)
(EXPERT OF OPERATION & STATIONS)
URBAN RAILWAY OFFICE
EXPERT OF OPERATION AND STATION STUDIES, TENDER PREPARATION, QC, AND
COORDINATOR OF THE PROJECTS:
MP OF TABRIZ URBAN RAILWAY, LINE 2
(Consultant selection, QC of studies, Contractor selection)
CONSULTANT FOR EPC CONTRACTOR MASHHAD URBAN RAILWAY, LINE2
(Expert of operation, Station, and rolling stock)
EPC CONSULTANT OF CONTRACTOR OF MASHHAD URBAN RAILWAY, LINE2
(Expert of operation, Station, and rolling stock)
*****
2007 CONTRACTOR FOR PROPOSAL PREPARATION ESTUKY PARS CONSULTING CO.
(TENDER PREPARATION)
CONTRACTOR FOR PREPARING OF TECHNICAL-FINANCIAL PROPOSAL FOR KARAJ METRO
LINE 2 EPC CONTRACTOR (SABIR CO.)
(Civil, Structure, Superstructure, System, Station, Rolling stock & depot,… for 2M€ consultant
project)
IN COOPERATION WITH SYSTRA CONSULTING CO.
*****
2007 CONTRACTOR FOR PROPOSAL PREPARATION FARAMAD DARYA CO.
(TENDER PREPARATION)
TECHNICAL & ENGINEERING OFFICE
CONTRACTOR FOR PREPARING OF EPC TECHNICAL-FINANCIAL PROPOSAL FOR SHAHID
RAJAII PORT RAILWAY
(Substructure & Superstructure for the 10M$ project)
*****
2006 EXPERT RAH SHAHR CONSULTING CO.
(EXPERT OF ROUTE & FEASIBILITY STUDY)
GENERAL PLAN OFFICE
EXPERT OF BASIC DESIGN OF RAILWAY BRANCH OF:
PERSIAN GULF MINERAL & METAL INDUSTRIAL SPECIAL ZONE
(Railway study of a 50Km2
industrial zone)
SALMAS ECONOMIC ESPECIAL ZONE
(Preliminary study of 50 Km railway Branch and yard design)
SOUTHERN PARS GAS ECONOMICAL ZONE
(Feasibility studies of 150 Km railway and branches inside a 240Km2 area)
*****
2006 CONTRACTOR FOR PROPOSAL PREPARATION PANAH SAZ CONSTRUCTION CO.
(TENDER PREPARATION)
TECHNICAL & ENGINEERING OFFICE
CONTRACTOR FOR PREPARING OF EPC TECHNICAL-FINANCIAL PROPOSAL FOR NEW COACH
SHED OF DMUS, TEHRAN RAILWAY:
TRACKS, SERVICE ROADS, CONSTRUCTION, SIGNALING & TELECOM, WORKSHOPS &
EQUIPMENTS, ETC.
(A 60M$ project)
*****
2005-2006 CHIEF SUPERVISOR CHADORMALU INDUSTRIAL & MINERAL CO.
8. Project & Interface Manager/Coordinator J. Bagheri(jaf.bagheri@gmail.com)
8/9 (Nov 2016)
(SUPERVISOR OF SOIL WORKS & TRACK LAYING)
ARDAKAN PELLETIZING PLANT
CHIEF SUPERVISOR OF CONSTRUCTION OF RAILWAY TRACK (SOIL WORK, BRIDGES, TRACK
LAYING, OPERATION DURING 28 MONTHS OF CONSTRUCTION)
*****
2005-2006 DESIGNER NAMAD MOBTAKER CONSULTING CO.
(BASIC DESIGN)
DESIGNER EXPERT OF TRACKS OF COACH SHEDS, MASHHAD STATION:
TRACK GEOMETRY, SWITCH LAYOUT, SUPERSTRUCTURE, PREPARING OF EPC TENDER
DOCUMENTS
*****
2004 DESIGNER BARSOO CONSULTING CO.
(DESIGNER OF SUPERSTRUCTURE & YARD)
DESIGNER EXPERT OF RAILWAY BRANCH OF HORMOZGAN STEEL PLANT:
TRACK GEOMETRY, STATIONS & YARDS, SOLUTION FINDING
*****
2003-2004 DESIGNER BINESH FAN CONSULTING CO.
(DESIGNER OF ROUTE & SUPERSTRUCTURE)
DESIGNER EXPERT OF RAILWAY BRANCH OF SHAHID RAJAII PORT, OIL DISTRIBUTION
ZONING:
TRACK GEOMETRY, STATIONS & YARDS, SUPERSTRUCTURE, UNLOADING
*****
2003 DESIGNER SANO CONSULTING CO.
(DESIGNER OF ROUTE & SUPERSTRUCTURE)
DESIGNER EXPERT OF RAILWAY BRANCH OF HAMA CEMENT FACTORY, SYRIA:
TRACK GEOMETRY, SWITCH LAYOUT, STATIONS & YARDS, SUPERSTRUCTURE
*****
2002 DESIGNER TAZAND CONSULTING CO.
(DESIGNER OF ROUTE & SUPERSTRUCTURE)
DESIGNER EXPERT OF HAFT TAPEH SUGAR FACTORY RAILWAYS:
TRACK GEOMETRY, STATIONS & YARDS, SUPERSTRUCTURE
PROFESSIONAL MEMBERSHIP
SINCE 2013 IRAN RAILWAY THINK TANK
IRAN RAILWAY THINK TANK IS A COMMITTEE INSIDE IRAN RAILWAY ORGANIZATION
CONSISTING OF ALL RAILWAY MANAGERS AND SOME OF MOST EXPERIENCED RAILWAY
EXPERTS STABLISHED TO CONSIDER IRAN RAILWAY PROBLEMS AND PROVIDE THE SOLUTIONS
AND DEFINE THE RAILWAY STRATEGIES
HTTP://TRAI.IR/
*****
2012-2015 IRAN PUBLIC TRANSPORTATION INTEGRATION COUNCIL
HTTP://WWW.TINN.IR/FA/DOC/NEWS/6365/%D8%A7%D8%B9%D8%B6%D8%A7%DB%8C-
%D8%B4%D9%88%D8%B1%D8%A7%DB%8C-%D8%AD%D9%85%D9%84-%D9%86%D9%82%D9%84-
%D9%87%D9%85%DA%AF%D8%A7%D9%86%DB%8C
PUBLICATION
9. Project & Interface Manager/Coordinator J. Bagheri(jaf.bagheri@gmail.com)
9/9 (Nov 2016)
2015 MAHDI ABBAS TAHER, AZADEH ASGARI, JAFAR BAGHERI, KNOWLEDGE MANAGEMENT KEY
SUCCESS FACTORS ON E-BUSINESS, LAP LAMBERT ACADEMIC PUBLISHING, ISBN-13: 978-
3659792885
HTTPS://WWW.LAP-PUBLISHING.COM/CATALOG/DETAILS//STORE/GB/BOOK/978-3-659-79288-5/KNOWLEDGE-
MANAGEMENT-KEY-SUCCESS-FACTORS-ON-E-BUSINESS
*****
2015 JAFAR BAGHERI, DR. MAHDI ABBAS TAHER, DR. AZADEH ASGARI. HOW E-RELATIONSHIP
QUALITY ENHANCE E-LOYALTY IN LODGING WEBSITES. TIJRPS (THE INTERNATIONAL
JOURNAL RESEARCH PUBLICATIONS), VOL 5, ISSN: 2251-1571
HTTP://WWW.THEINTERNATIONALJOURNAL.ORG/OJS/INDEX.PHP?JOURNAL=TIJ&PAGE=ARTICLE&OP=VIEW&PATH%5B%5
D=4390
*****
2015 DR. MAHDI ABBAS TAHER, JAFAR BAGHERI, DR. AZADEH ASGARI. THE COLLABORATION OF
ORGANIZATIONAL INFRASTRUCTURE ON SUPPLY CHAIN PERFORMANCE IN SMES. TIJRPS
(THE INTERNATIONAL JOURNAL RESEARCH PUBLICATIONS), VOL 5, ISSN: 2251-1571
HTTP://WWW.THEINTERNATIONALJOURNAL.ORG/OJS/INDEX.PHP?JOURNAL=TIJ&PAGE=ARTICLE&OP=VIEW&PATH%5B%5
D=4391
*****
2015 DR. MAHDI ABBAS TAHER, JAFAR BAGHERI, DR. AZADEH ASGARI. THE RELATIONSHIP
BETWEEN QUALITY MANAGEMENT TECHNIQUES AND FIRM’S PERFORMANCES".TIJRPS (THE
INTERNATIONAL JOURNAL RESEARCH PUBLICATIONS), VOL 5, ISSN: 2251-1571-1571
HTTP://WWW.THEINTERNATIONALJOURNAL.ORG/OJS/INDEX.PHP?JOURNAL=TIJ&PAGE=ARTICLE&OP=VIEW&PATH%5B%5
D=4392
OTHER
DEVELOPING OF TERMINATOR APPLICATION FOR SIMULATION OF TRAIN RUNNING
(Using for Dynamic train running Simulation, traction load and fuel consumption calculation,
deriving speed-time-distance graph…)
TEACHING OPERATION RESEARCH (OR) APPLICATION, RAILWAY CAMPUS, IRAN UNIVERSITY
OF SCIENCE & TECHNOLOGY
(One semester)
LECTURER OF URBAN RAIL TRANSPORTATION TYPES, TEHRAN
(Different type of urban rail transportation mode and characteristics)