SlideShare a Scribd company logo
Universiti
                                               Malaysia
                                               PAHANG       . C.riciviil,




                    UNIVERSITI MALAYSIA PAHANG
           FACULTY OF CIVI ENGINEERING & EARTH RESOURCES

                                 FINAL EXAMINATION

COIIRSE                               CONSTRUCTION ENGINEERING

COURSE CODE                           BAA1322

LECTURER                              DR. KHAIRUNISA BINTI ABDULLAH

                                      ENGR. ROSLINA BINTI OMAR

DATE                                  ll   JANUARY 2012

DURATION                              2 HOURS

SESSION/SEMESTER                      SESSION ZOII/20I2 SEMESTER            I
PROGRAMME CODE                        BAA/BAE


 TNSTRUCTIONS TO CANDIDATE:

   1.        This question paper consists of FIVE (5) questions.
   2.        Answer ALL questions.
   3.        All answers to a new question should start on new page.
   4.        All calculations must be clearly shown.
   5.        Candidates are not allowed to bring any material other than those requested by
             the course coordinator into the examination room.

 EXAMINATION         RE   OUIREMENTS       :




           DO NOT TURN THIS PAGE UNTIL YOU ARE TOLD TO DO SO

        This examination paper consists of SIX (6) printed pages including front page.
CONF'IDENTIAL                                                                                                             BAA /BAE/1IIZVBAAI322



          QUESTION                          1                                        d*
                                                                          {_    st +                                             {:).v
                                                                        /,/
          a) Miss Lina has hired Arkj.dk Indah to prepare arc{ectwal drawings for her house.
                 Consequerrry,S.Ig                                                        appont"/o                 prepare the structural drawings.
                                                                   ""(rultanfas
                 Through tendering process, (Syarikat Bina Sdn Bhd) was awarded a contract to
                 construct the house.(En.Amin')fro* sYutll<ul F!q? Sq B    s appointed as the
                 project manager for the project. He                                   assigne{t1Ot*un tp Perform the task                                     as a.site

                 engineq:r in that Project.



             ,{ - -                                                                 to prepare the     arclritgg1lg{igryilgs?                                  (1 marks)
           //.'/ ,/Wnois the person in charge
          "/ 1y{ Stut"three (3) tasks of the person who is responsible to prepare the structural
            /     drawings.                                                               (3 marks)

                 ,yf       Ot       a project manager,                 En.Amin needs to "Plan the Construction Project". Explain
                '/             the particular               task.                                                                                              (4 marks)

                 iv)       State three (3) tasks of                     En. Azman.                                                                             (3 marks)



           b),Site investigation is an important stage in the planning and construction of a project to
      /
                 proride information about the proposed site. Explain tft"Qes5;ga)',                                                                 fi!" ylsigund soil
                 investigation which is conducted during !-he stage.                                                                                           (6 marks)



               c)€xp       lai(ne               protective equ ipmentlh at needs to be used by a worker who performs
           '    /weldins workbt                         a construction site.                                                                                   (3 Marks)
                'e--_--r"


                                                                                                                                         .,.
                                                                                                                                        -i. /t
                                                                                                                                                 1

i4.
v L.L(/,/ lrv
    t
                     t
                                            _--/
                                                q.:l''                        r'.{',
                                                                                    rL                                    
                                                                                                                           
                                                                                                           li                                                   Qauvrt
                                                                                                           l.             . r'
                                                  t^h                                                               {
                                                                                                                    t,i
                                                                                                                          ,                                   t;t'tv'a
                               L/                                     i-,1^
                         (/,
                                                                                                                                i,
               rnv                                                                                                              | "r'                     -'   lntz   1



                                                                               tl                 .,*t -
                                                                                              ct't"
                           '            , "j,
                                       r,V'r
                         t*    fl'

                                                      fr!
                                                            {"tr
                                                                                                     (tatt'
                                                                                                       t
                                                                                                             t--


                                                                                                                           t"t'c
                                                                                                                                            t. *^$
                                                                                                                           1)
                                                U
                                                  
                                                                    .4+                      2

                                                             t
I   CONFIDENTIAL                                                              BAA /BAE/1II2ABAA'I322



    QUESTTON 2


    a) Scaffolding, formwork and shoring        are among the temporary work structures that are

           usually used in construction work.



     /'
           x{ ./ Explain |putlog scaffolding
                   '          -9!-
                                                                                      (3 marks)

          .nd Stut" four (4) safety precautions that need to be taken when handling scaffolding.
                                 -"                                                       (4 marks)

                     four (4) advantages of using permanent formwork compared to conventional
          'YState
                formwork.                                                                 (4 Marks)

                                                    Lu"o {cu*,,,f<
    b) Heavy machineries        and small powered plants are usually used at a construction site to

           facilitate the work achieve faster completion time of a project.


                        vibrator used in construction work.                               (3 marks)
      .*t'nxplain
                State three (3) benefits that can be obtained when using machineries at
          ,yl
                construction site.                                                         (3 marks)

                     three (3) safety precautions that need to be taken when handling
          -ffitxe                                                                          (3 marks)
                machineries.
I        CONFIDENTIAL


         QUESTION 3
                                                                           BAA/BAE/11I2WAAI322




         gff oundation is one of the important structural elements of a building.
     J


                         shallow foundation and its advantages compared to deep foundation.
         ( ),-Explain                                                                 (5 marks)
               ,..
           ,d9xptain     precast concrete   pile.                                     (5 marks)



             xplain one type of roof which is widely used in Malaysia.                (4 marks)



                                                                                      (3 marks)



                     a shear   wall.                                                  (3 marks)
    /Af6*plain




                                                      4
CONTIDENTIAL                                                          BAA IBAE/ 1 II2TTB AAI322



     QUESTTON 4


               escribe what is prestressed concrete and explain two (2) methods of prestressing.
                                                                                          (6 marks)

         .a'
    76   Witnthe aid of diagrams, explain the differences between.quyity retaining wall and
/        cantilever retaining wall. Explain three (3) differences between both walls and draw
         the diagrams.                                                                    (8 marks)


         ./                                 tvc&
    Vffne        use of precast concrete frames is common in the Industrialized Building System
'        (IBS). Give three (3) advantages and disadvantages of using IBS      frames.     (6 marks)


                                     k
                        t7 e,vo'
                         r


                                                         gtvect"^5
BAA/BAE/1II2I/B.AAI322



       QTTESTTON s


       aththe       aid of a diagram, explain rigid pavement.                             (5 marks)



       b)rfiate four (4) types ofjoint that are used in the construction of a rigid pavement.
       ,/                                                                                  (4 marks)



                        one form of transportation system that usually connects two adjacent
                                                                                             sites
       c)
            )hridgeis
      ,/    or"ra valley or a river to provide   a smooth   flow between them.
n-/

            t'Stur"five    (5) types of bridge according to its structural   form.         (5 marks)
            '1   firrand explain the function of three (3) components of the suspension bridge.
                                                                                           (6 marks)

More Related Content

What's hot

Earthwork
EarthworkEarthwork
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
Sumaiya Jabin
 
Ms.jkr.20800.2005
Ms.jkr.20800.2005Ms.jkr.20800.2005
Ms.jkr.20800.2005
Syifaa Abu Seman
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Shanmugasundaram N
 
Bq preamble
Bq preambleBq preamble
Bq preamble
aizat76
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
Dayat Mohamad
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
AshwiniChaudhari13
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sum
Est
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickwork
AshwiniChaudhari13
 
Construction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdfConstruction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdf
EyobMiteku
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
politeknik malaysia
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
Kheng Hoe Advocates
 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a Building
ARAVINDBORRA1
 
Construction contract
Construction contract Construction contract
Construction contract
Rakshith Reddy
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering Measurment
Sultan M Muzahir
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
Anep Botak
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
PachyCarmona1
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
Dr K M SONI
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
lizwi nyandu
 
Probe machintosh
Probe machintoshProbe machintosh
Probe machintosh
Kartina Sazali
 

What's hot (20)

Earthwork
EarthworkEarthwork
Earthwork
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Ms.jkr.20800.2005
Ms.jkr.20800.2005Ms.jkr.20800.2005
Ms.jkr.20800.2005
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
 
Bq preamble
Bq preambleBq preamble
Bq preamble
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sum
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickwork
 
Construction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdfConstruction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdf
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a Building
 
Construction contract
Construction contract Construction contract
Construction contract
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering Measurment
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Probe machintosh
Probe machintoshProbe machintosh
Probe machintosh
 

Viewers also liked

Marine
MarineMarine
Model Qes 2
Model Qes 2Model Qes 2
Model Qes 2
shojan84
 
Significant Guidance for Design and Construction of Marine and Offshore Struc...
Significant Guidance for Design and Construction of Marine and Offshore Struc...Significant Guidance for Design and Construction of Marine and Offshore Struc...
Significant Guidance for Design and Construction of Marine and Offshore Struc...
Professor Kabir Sadeghi
 
Engineering design and construction of marine structures in Arctic
Engineering design and construction of marine structures in ArcticEngineering design and construction of marine structures in Arctic
Engineering design and construction of marine structures in Arctic
Александр Головизнин
 
Dept NA-ME
Dept NA-MEDept NA-ME
Dept NA-ME
ewanbaird
 
Top 10 marine engineer interview questions and answers
Top 10 marine engineer interview questions and answersTop 10 marine engineer interview questions and answers
Top 10 marine engineer interview questions and answers
kitejonh
 
Careers in Marine Engineering
Careers  in Marine EngineeringCareers  in Marine Engineering
Careers in Marine Engineering
Shravan Shetty
 

Viewers also liked (7)

Marine
MarineMarine
Marine
 
Model Qes 2
Model Qes 2Model Qes 2
Model Qes 2
 
Significant Guidance for Design and Construction of Marine and Offshore Struc...
Significant Guidance for Design and Construction of Marine and Offshore Struc...Significant Guidance for Design and Construction of Marine and Offshore Struc...
Significant Guidance for Design and Construction of Marine and Offshore Struc...
 
Engineering design and construction of marine structures in Arctic
Engineering design and construction of marine structures in ArcticEngineering design and construction of marine structures in Arctic
Engineering design and construction of marine structures in Arctic
 
Dept NA-ME
Dept NA-MEDept NA-ME
Dept NA-ME
 
Top 10 marine engineer interview questions and answers
Top 10 marine engineer interview questions and answersTop 10 marine engineer interview questions and answers
Top 10 marine engineer interview questions and answers
 
Careers in Marine Engineering
Careers  in Marine EngineeringCareers  in Marine Engineering
Careers in Marine Engineering
 

Recently uploaded

Community pharmacy- Social and preventive pharmacy UNIT 5
Community pharmacy- Social and preventive pharmacy UNIT 5Community pharmacy- Social and preventive pharmacy UNIT 5
Community pharmacy- Social and preventive pharmacy UNIT 5
sayalidalavi006
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
David Douglas School District
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
Nicholas Montgomery
 
How to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRMHow to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRM
Celine George
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Excellence Foundation for South Sudan
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
RAHUL
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
BBR 2024 Summer Sessions Interview Training
BBR  2024 Summer Sessions Interview TrainingBBR  2024 Summer Sessions Interview Training
BBR 2024 Summer Sessions Interview Training
Katrina Pritchard
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
taiba qazi
 
Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
NgcHiNguyn25
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
TechSoup
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
Celine George
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
AyyanKhan40
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
IreneSebastianRueco1
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
simonomuemu
 

Recently uploaded (20)

Community pharmacy- Social and preventive pharmacy UNIT 5
Community pharmacy- Social and preventive pharmacy UNIT 5Community pharmacy- Social and preventive pharmacy UNIT 5
Community pharmacy- Social and preventive pharmacy UNIT 5
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
 
How to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRMHow to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRM
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
BBR 2024 Summer Sessions Interview Training
BBR  2024 Summer Sessions Interview TrainingBBR  2024 Summer Sessions Interview Training
BBR 2024 Summer Sessions Interview Training
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
 
Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
 

BAA 1322 CONSTRUCTION ENGINEERING FINAL EXAM PAPER

  • 1. Universiti Malaysia PAHANG . C.riciviil, UNIVERSITI MALAYSIA PAHANG FACULTY OF CIVI ENGINEERING & EARTH RESOURCES FINAL EXAMINATION COIIRSE CONSTRUCTION ENGINEERING COURSE CODE BAA1322 LECTURER DR. KHAIRUNISA BINTI ABDULLAH ENGR. ROSLINA BINTI OMAR DATE ll JANUARY 2012 DURATION 2 HOURS SESSION/SEMESTER SESSION ZOII/20I2 SEMESTER I PROGRAMME CODE BAA/BAE TNSTRUCTIONS TO CANDIDATE: 1. This question paper consists of FIVE (5) questions. 2. Answer ALL questions. 3. All answers to a new question should start on new page. 4. All calculations must be clearly shown. 5. Candidates are not allowed to bring any material other than those requested by the course coordinator into the examination room. EXAMINATION RE OUIREMENTS : DO NOT TURN THIS PAGE UNTIL YOU ARE TOLD TO DO SO This examination paper consists of SIX (6) printed pages including front page.
  • 2. CONF'IDENTIAL BAA /BAE/1IIZVBAAI322 QUESTION 1 d* {_ st + {:).v /,/ a) Miss Lina has hired Arkj.dk Indah to prepare arc{ectwal drawings for her house. Consequerrry,S.Ig appont"/o prepare the structural drawings. ""(rultanfas Through tendering process, (Syarikat Bina Sdn Bhd) was awarded a contract to construct the house.(En.Amin')fro* sYutll<ul F!q? Sq B s appointed as the project manager for the project. He assigne{t1Ot*un tp Perform the task as a.site engineq:r in that Project. ,{ - - to prepare the arclritgg1lg{igryilgs? (1 marks) //.'/ ,/Wnois the person in charge "/ 1y{ Stut"three (3) tasks of the person who is responsible to prepare the structural / drawings. (3 marks) ,yf Ot a project manager, En.Amin needs to "Plan the Construction Project". Explain '/ the particular task. (4 marks) iv) State three (3) tasks of En. Azman. (3 marks) b),Site investigation is an important stage in the planning and construction of a project to / proride information about the proposed site. Explain tft"Qes5;ga)', fi!" ylsigund soil investigation which is conducted during !-he stage. (6 marks) c)€xp lai(ne protective equ ipmentlh at needs to be used by a worker who performs ' /weldins workbt a construction site. (3 Marks) 'e--_--r" .,. -i. /t 1 i4. v L.L(/,/ lrv t t _--/ q.:l'' r'.{', rL li Qauvrt l. . r' t^h { t,i , t;t'tv'a L/ i-,1^ (/, i, rnv | "r' -' lntz 1 tl .,*t - ct't" ' , "j, r,V'r t* fl' fr! {"tr (tatt' t t-- t"t'c t. *^$ 1) U .4+ 2 t
  • 3. I CONFIDENTIAL BAA /BAE/1II2ABAA'I322 QUESTTON 2 a) Scaffolding, formwork and shoring are among the temporary work structures that are usually used in construction work. /' x{ ./ Explain |putlog scaffolding ' -9!- (3 marks) .nd Stut" four (4) safety precautions that need to be taken when handling scaffolding. -" (4 marks) four (4) advantages of using permanent formwork compared to conventional 'YState formwork. (4 Marks) Lu"o {cu*,,,f< b) Heavy machineries and small powered plants are usually used at a construction site to facilitate the work achieve faster completion time of a project. vibrator used in construction work. (3 marks) .*t'nxplain State three (3) benefits that can be obtained when using machineries at ,yl construction site. (3 marks) three (3) safety precautions that need to be taken when handling -ffitxe (3 marks) machineries.
  • 4. I CONFIDENTIAL QUESTION 3 BAA/BAE/11I2WAAI322 gff oundation is one of the important structural elements of a building. J shallow foundation and its advantages compared to deep foundation. ( ),-Explain (5 marks) ,.. ,d9xptain precast concrete pile. (5 marks) xplain one type of roof which is widely used in Malaysia. (4 marks) (3 marks) a shear wall. (3 marks) /Af6*plain 4
  • 5. CONTIDENTIAL BAA IBAE/ 1 II2TTB AAI322 QUESTTON 4 escribe what is prestressed concrete and explain two (2) methods of prestressing. (6 marks) .a' 76 Witnthe aid of diagrams, explain the differences between.quyity retaining wall and / cantilever retaining wall. Explain three (3) differences between both walls and draw the diagrams. (8 marks) ./ tvc& Vffne use of precast concrete frames is common in the Industrialized Building System ' (IBS). Give three (3) advantages and disadvantages of using IBS frames. (6 marks) k t7 e,vo' r gtvect"^5
  • 6. BAA/BAE/1II2I/B.AAI322 QTTESTTON s aththe aid of a diagram, explain rigid pavement. (5 marks) b)rfiate four (4) types ofjoint that are used in the construction of a rigid pavement. ,/ (4 marks) one form of transportation system that usually connects two adjacent sites c) )hridgeis ,/ or"ra valley or a river to provide a smooth flow between them. n-/ t'Stur"five (5) types of bridge according to its structural form. (5 marks) '1 firrand explain the function of three (3) components of the suspension bridge. (6 marks)