Portfolio
This portfolio contains most projects managed by Eng. Ahmad Samir in Total solutions;
integrated services Company .
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: HILAS
Client: Procter and Gamble (P&G)
Location: Cornflake building, P&G 6th of October Plant, Giza, Egypt
Scope of Work:
 Replace two steel paddle mixers by two Stainless steel paddle mixers.
 Replace the old pumps by new pumps.
 Replace the old Heat exchangers by new Heat Exchangers.
 Supply, fabricate and install supply and two return pipe lines.
 Supply, fabricate and install air receiver.
Duration: 4 months
Replace two Steel Paddle mixers by two Stainless Steel paddle mixers
one Steel Paddle Mixer before un-installation it weighs about 6 tons
A hole opened in the building structure to pass the steel paddle
mixers from the first floor to the ground floor and vise verse for
the Stainless steel paddle mixers.
A supports added to support the steel structure after
modifications done to pass the paddle mixers.
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Installation of the new stainless steel paddle mixers
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Replace Pumps and Heat Exchangers by new ones
Replaced Pumps Replaced Heat Exchangers
New pumps Heat Exchangers
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
lifting and install the Air Receiver
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: Inter Connecting Piping
Client: Metito
Location: Total Solutions Yard
Scope of Work:
 Phase One: Fabricate 300 inches of Alloy 20 pipe line.
 Phase two: Fabricate 3000 inches of Stainless Steel .
 Phase Three: Fabricate 1500 inches of Carbon Steel.
Duration: 2 months
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Phase One
Alloy 20
Packing for finished pipe lines
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Phase two
Stainless Steel
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Phase Three
Carbon Steel
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: Pipe Line
Client: AL Mansoori
Location: Total Solutions Yard
Scope of Work:
 Fabricate 400 meters of Piping and 375 Fittings.
Duration: 2 months
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: 500 bbl tanks
Client: AL-Mansoori
Location: Total Solutions Yard
Scope of Work:
 Fabricate Four atmospheric 500 bbl Tanks.
Duration: 2 months
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: Modification and relocation for packing lines
Client: L'Oreal
Location: L'Oreal factory at industrial zone A7, 10th of Ramadan City
Scope of Work:
 Modify and relocate three Packing Lines .
Duration: Three Weeks.
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: Stainless Steel Tanks
Client: L'Oreal
Location: Total Solutions Yard.
Scope of Work:
 Fabricate 8 stainless Steel tanks with 2 tons capacity for each tank .
Duration: 2 Months.
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: J-Tubes Commissioning
Client: Saipem
Location: REMAS deck, Aboqir Port, Alexandria.
Scope of Work:
 Commissioning of J-tubes fixation frames on REMAS deck.
 Fixation J-Tubes on steel frames.
Duration: 24 hours.
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: Bourbon Pearl
Client: Saipem
Location:
 Fabrication: At Total Solutions Yard.
 Commissioning: Bourbon Pearl deck, Abouqir Port, Alexandria.
Scope of Work:
 Fabrication of steel structure platforms more than 260 tons.
 Commissioning of the fabricated Steel Structure on Bourbon Pearl deck
Duration:
 Fabrication: 4 months.
 Commissioning: 15 days.
Fabricated structures while fabrication Fabricated structure after commssioning on deck
Auxiliary Platform
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Commissioning of fabricated steel structures on Bourbon Pearl deck
Night shift crew preparations before starting the shift
Welding and commissioning operations
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Lifting operations while commissioning

More Related Content

What's hot

Cherlapally industries association phase iv
Cherlapally industries association  phase ivCherlapally industries association  phase iv
Cherlapally industries association phase ivPavan Reddy
 
King Street Staion: 3rd floor walls demolition
King Street Staion: 3rd floor walls demolitionKing Street Staion: 3rd floor walls demolition
King Street Staion: 3rd floor walls demolitionallieger
 
Purechem Construction Group Presentation
Purechem Construction Group PresentationPurechem Construction Group Presentation
Purechem Construction Group PresentationSUNIT DEBROY
 
Karl james davis cv new
Karl james davis cv newKarl james davis cv new
Karl james davis cv newkarl davis
 
Roof lifting...the clear solution to the clear height problem
Roof lifting...the clear solution to the clear height problemRoof lifting...the clear solution to the clear height problem
Roof lifting...the clear solution to the clear height problemguest41970
 
Continues improvement.1
Continues improvement.1Continues improvement.1
Continues improvement.1Adecco, India
 

What's hot (13)

Pho libeshengg
Pho libeshenggPho libeshengg
Pho libeshengg
 
Cherlapally industries association phase iv
Cherlapally industries association  phase ivCherlapally industries association  phase iv
Cherlapally industries association phase iv
 
King Street Staion: 3rd floor walls demolition
King Street Staion: 3rd floor walls demolitionKing Street Staion: 3rd floor walls demolition
King Street Staion: 3rd floor walls demolition
 
Aum techno-ceramics
Aum techno-ceramicsAum techno-ceramics
Aum techno-ceramics
 
Ahmed Gameel_CV
Ahmed Gameel_CVAhmed Gameel_CV
Ahmed Gameel_CV
 
Ahmed.Hassan_CV
Ahmed.Hassan_CVAhmed.Hassan_CV
Ahmed.Hassan_CV
 
SHARQ AL JAZEERA PROFILE 02
SHARQ AL JAZEERA PROFILE 02SHARQ AL JAZEERA PROFILE 02
SHARQ AL JAZEERA PROFILE 02
 
Purechem Construction Group Presentation
Purechem Construction Group PresentationPurechem Construction Group Presentation
Purechem Construction Group Presentation
 
Karl james davis cv new
Karl james davis cv newKarl james davis cv new
Karl james davis cv new
 
hussien maleh-CV
hussien maleh-CVhussien maleh-CV
hussien maleh-CV
 
Roof lifting...the clear solution to the clear height problem
Roof lifting...the clear solution to the clear height problemRoof lifting...the clear solution to the clear height problem
Roof lifting...the clear solution to the clear height problem
 
-TGK -KFC-PROFILE
-TGK -KFC-PROFILE-TGK -KFC-PROFILE
-TGK -KFC-PROFILE
 
Continues improvement.1
Continues improvement.1Continues improvement.1
Continues improvement.1
 

Similar to Ahmad Samir Portfolio

Project Mechanical Engineer C.V
Project Mechanical Engineer C.VProject Mechanical Engineer C.V
Project Mechanical Engineer C.Vali ibrahim
 
Project mechanical engineer c.v
Project mechanical engineer c.vProject mechanical engineer c.v
Project mechanical engineer c.vali ibrahim
 
Robert Apilado updated resume
Robert Apilado updated resumeRobert Apilado updated resume
Robert Apilado updated resumeRobert Apilado
 
AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015Ahmed Yehia
 
eng. khaled sonbol (cv)
eng. khaled sonbol (cv)eng. khaled sonbol (cv)
eng. khaled sonbol (cv)khaled sonbol
 
Mohamed Ahmed (2008)
Mohamed Ahmed  (2008)Mohamed Ahmed  (2008)
Mohamed Ahmed (2008)Mohamed Ahmed
 
RIL DIAZ edited
RIL DIAZ editedRIL DIAZ edited
RIL DIAZ editedRil diaz
 
Ramy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad
 
Structure home emeco steel presentation (final)
Structure home emeco steel presentation (final)Structure home emeco steel presentation (final)
Structure home emeco steel presentation (final)structurehomeQatar
 
Terry CV June 2015
Terry CV June 2015Terry CV June 2015
Terry CV June 2015Terry Harvey
 
C V ALAA AMMAR 2
C V   ALAA AMMAR 2 C V   ALAA AMMAR 2
C V ALAA AMMAR 2 Alaa Ammar
 
M.I.G. Services
M.I.G. ServicesM.I.G. Services
M.I.G. ServicesSHIMENG
 

Similar to Ahmad Samir Portfolio (20)

Project Mechanical Engineer C.V
Project Mechanical Engineer C.VProject Mechanical Engineer C.V
Project Mechanical Engineer C.V
 
Project mechanical engineer c.v
Project mechanical engineer c.vProject mechanical engineer c.v
Project mechanical engineer c.v
 
Robert Apilado updated resume
Robert Apilado updated resumeRobert Apilado updated resume
Robert Apilado updated resume
 
AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015
 
eng. khaled sonbol (cv)
eng. khaled sonbol (cv)eng. khaled sonbol (cv)
eng. khaled sonbol (cv)
 
Mohamed Ahmed (2008)
Mohamed Ahmed  (2008)Mohamed Ahmed  (2008)
Mohamed Ahmed (2008)
 
RIL DIAZ edited
RIL DIAZ editedRIL DIAZ edited
RIL DIAZ edited
 
CV+
CV+CV+
CV+
 
reda cv EN
reda cv ENreda cv EN
reda cv EN
 
Reda cv en
Reda cv enReda cv en
Reda cv en
 
Ramy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad C.V Project Engineer
Ramy Emad C.V Project Engineer
 
Muhammad_Aslam_CV
Muhammad_Aslam_CVMuhammad_Aslam_CV
Muhammad_Aslam_CV
 
Ashrafsupervisor
AshrafsupervisorAshrafsupervisor
Ashrafsupervisor
 
Ibrahim CV nz
Ibrahim CV nz Ibrahim CV nz
Ibrahim CV nz
 
Structure home emeco steel presentation (final)
Structure home emeco steel presentation (final)Structure home emeco steel presentation (final)
Structure home emeco steel presentation (final)
 
Terry CV June 2015
Terry CV June 2015Terry CV June 2015
Terry CV June 2015
 
Hesham Elmalah
Hesham ElmalahHesham Elmalah
Hesham Elmalah
 
C V ALAA AMMAR 2
C V   ALAA AMMAR 2 C V   ALAA AMMAR 2
C V ALAA AMMAR 2
 
M.I.G. Services
M.I.G. ServicesM.I.G. Services
M.I.G. Services
 
MANOJ RESUME
MANOJ RESUMEMANOJ RESUME
MANOJ RESUME
 

Ahmad Samir Portfolio

  • 1. Portfolio This portfolio contains most projects managed by Eng. Ahmad Samir in Total solutions; integrated services Company .
  • 2. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Project: HILAS Client: Procter and Gamble (P&G) Location: Cornflake building, P&G 6th of October Plant, Giza, Egypt Scope of Work:  Replace two steel paddle mixers by two Stainless steel paddle mixers.  Replace the old pumps by new pumps.  Replace the old Heat exchangers by new Heat Exchangers.  Supply, fabricate and install supply and two return pipe lines.  Supply, fabricate and install air receiver. Duration: 4 months Replace two Steel Paddle mixers by two Stainless Steel paddle mixers one Steel Paddle Mixer before un-installation it weighs about 6 tons A hole opened in the building structure to pass the steel paddle mixers from the first floor to the ground floor and vise verse for the Stainless steel paddle mixers. A supports added to support the steel structure after modifications done to pass the paddle mixers.
  • 3. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
  • 4. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Installation of the new stainless steel paddle mixers
  • 5. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Replace Pumps and Heat Exchangers by new ones Replaced Pumps Replaced Heat Exchangers New pumps Heat Exchangers
  • 6. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 lifting and install the Air Receiver
  • 7. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Project: Inter Connecting Piping Client: Metito Location: Total Solutions Yard Scope of Work:  Phase One: Fabricate 300 inches of Alloy 20 pipe line.  Phase two: Fabricate 3000 inches of Stainless Steel .  Phase Three: Fabricate 1500 inches of Carbon Steel. Duration: 2 months
  • 8. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Phase One Alloy 20 Packing for finished pipe lines
  • 9. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Phase two Stainless Steel
  • 10. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Phase Three Carbon Steel
  • 11. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Project: Pipe Line Client: AL Mansoori Location: Total Solutions Yard Scope of Work:  Fabricate 400 meters of Piping and 375 Fittings. Duration: 2 months
  • 12. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
  • 13. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Project: 500 bbl tanks Client: AL-Mansoori Location: Total Solutions Yard Scope of Work:  Fabricate Four atmospheric 500 bbl Tanks. Duration: 2 months
  • 14. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Project: Modification and relocation for packing lines Client: L'Oreal Location: L'Oreal factory at industrial zone A7, 10th of Ramadan City Scope of Work:  Modify and relocate three Packing Lines . Duration: Three Weeks.
  • 15. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Project: Stainless Steel Tanks Client: L'Oreal Location: Total Solutions Yard. Scope of Work:  Fabricate 8 stainless Steel tanks with 2 tons capacity for each tank . Duration: 2 Months.
  • 16. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Project: J-Tubes Commissioning Client: Saipem Location: REMAS deck, Aboqir Port, Alexandria. Scope of Work:  Commissioning of J-tubes fixation frames on REMAS deck.  Fixation J-Tubes on steel frames. Duration: 24 hours.
  • 17. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Project: Bourbon Pearl Client: Saipem Location:  Fabrication: At Total Solutions Yard.  Commissioning: Bourbon Pearl deck, Abouqir Port, Alexandria. Scope of Work:  Fabrication of steel structure platforms more than 260 tons.  Commissioning of the fabricated Steel Structure on Bourbon Pearl deck Duration:  Fabrication: 4 months.  Commissioning: 15 days. Fabricated structures while fabrication Fabricated structure after commssioning on deck Auxiliary Platform
  • 18. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
  • 19. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Commissioning of fabricated steel structures on Bourbon Pearl deck Night shift crew preparations before starting the shift Welding and commissioning operations
  • 20. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
  • 21. Eng. Ahmad Samir Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239 Lifting operations while commissioning