2. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: HILAS
Client: Procter and Gamble (P&G)
Location: Cornflake building, P&G 6th of October Plant, Giza, Egypt
Scope of Work:
Replace two steel paddle mixers by two Stainless steel paddle mixers.
Replace the old pumps by new pumps.
Replace the old Heat exchangers by new Heat Exchangers.
Supply, fabricate and install supply and two return pipe lines.
Supply, fabricate and install air receiver.
Duration: 4 months
Replace two Steel Paddle mixers by two Stainless Steel paddle mixers
one Steel Paddle Mixer before un-installation it weighs about 6 tons
A hole opened in the building structure to pass the steel paddle
mixers from the first floor to the ground floor and vise verse for
the Stainless steel paddle mixers.
A supports added to support the steel structure after
modifications done to pass the paddle mixers.
4. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Installation of the new stainless steel paddle mixers
5. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Replace Pumps and Heat Exchangers by new ones
Replaced Pumps Replaced Heat Exchangers
New pumps Heat Exchangers
6. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
lifting and install the Air Receiver
7. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: Inter Connecting Piping
Client: Metito
Location: Total Solutions Yard
Scope of Work:
Phase One: Fabricate 300 inches of Alloy 20 pipe line.
Phase two: Fabricate 3000 inches of Stainless Steel .
Phase Three: Fabricate 1500 inches of Carbon Steel.
Duration: 2 months
8. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Phase One
Alloy 20
Packing for finished pipe lines
9. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Phase two
Stainless Steel
10. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Phase Three
Carbon Steel
11. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: Pipe Line
Client: AL Mansoori
Location: Total Solutions Yard
Scope of Work:
Fabricate 400 meters of Piping and 375 Fittings.
Duration: 2 months
13. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: 500 bbl tanks
Client: AL-Mansoori
Location: Total Solutions Yard
Scope of Work:
Fabricate Four atmospheric 500 bbl Tanks.
Duration: 2 months
14. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: Modification and relocation for packing lines
Client: L'Oreal
Location: L'Oreal factory at industrial zone A7, 10th of Ramadan City
Scope of Work:
Modify and relocate three Packing Lines .
Duration: Three Weeks.
15. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: Stainless Steel Tanks
Client: L'Oreal
Location: Total Solutions Yard.
Scope of Work:
Fabricate 8 stainless Steel tanks with 2 tons capacity for each tank .
Duration: 2 Months.
16. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: J-Tubes Commissioning
Client: Saipem
Location: REMAS deck, Aboqir Port, Alexandria.
Scope of Work:
Commissioning of J-tubes fixation frames on REMAS deck.
Fixation J-Tubes on steel frames.
Duration: 24 hours.
17. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Project: Bourbon Pearl
Client: Saipem
Location:
Fabrication: At Total Solutions Yard.
Commissioning: Bourbon Pearl deck, Abouqir Port, Alexandria.
Scope of Work:
Fabrication of steel structure platforms more than 260 tons.
Commissioning of the fabricated Steel Structure on Bourbon Pearl deck
Duration:
Fabrication: 4 months.
Commissioning: 15 days.
Fabricated structures while fabrication Fabricated structure after commssioning on deck
Auxiliary Platform
19. Eng. Ahmad Samir
Mail: ahmad.samir4@gmail.com Mob.: 0100-0292239
Commissioning of fabricated steel structures on Bourbon Pearl deck
Night shift crew preparations before starting the shift
Welding and commissioning operations