Legislative Advertising Paid For by: JuliaRathgeber, Association ofElectric Companies ofTexas
1005Congress, Suite 600,Austin,TX 78701 • 512-474-6725• www.aect.net
September 14,2017
Lunch-And-Learn:
Updateon the ElectricMarket
www.aect.net (512) 474-6725
2
AECT MemberCompanies
Recovery from Hurricane Harvey
3
Utilities, Generators and Retailers Respond
HARVEY one of the Largest Storms In U.S. History
www.aect.net (512) 474-6725
4
Harvey Stats:
• First Category 4
hurricane to make
landfall in the Texas
Coastal Bend since
1961
• 51.9 inches of rain –
wettest storm in the
history of the
continental U.S.
• 13 million people
were under flood
watch
• 300,000 power
outages at Harvey’s
peak
HARVEY Damage
www.aect.net (512) 474-6725
5
HARVEY Recovery: AEP Texas
www.aect.net (512) 474-6725
6
• Most severe storm to hit
the AEP Texas service
territory in 44 years
• 220,000 customers
without power at its peak
• Lost 5,000 poles and 200
transmission structures,
such as lines and
substations
• 1,600 outages remain,
with half of those in areas
that are still flooded
HARVEY Recovery: CenterPoint Energy
www.aect.net (512) 474-6725
7
• 300,000 customers
without power at its
peak
• About 900 planned
outages are due to
flooding and cannot be
restored at this time
• Restoration included
building a temporary
substation
• About 640 unplanned
outages remain
HARVEY Recovery: TNMP
www.aect.net (512) 474-6725
8
• TNMP serves
Angleton and
Dickinson, which saw
a peak of 20,000
outages during the
storm
• About 60 outages
remain in those
communities
HARVEY Recovery: Entergy Texas
www.aect.net (512) 474-6725
9
• At the storm’s peak,
192,000 Entergy Texas
customers were without
power
• Oncor, Cleco and other
Entergy companies
provided mobile
substations
• About 4,000 customers
with extensive flooding
cannot yet be restored
• 1,600 outages remain,
including both planned
and unplanned outages
Restoration TimelineHighlightsGrid Resilience
www.aect.net (512) 474-6725
10
• Utilities must be prepared to respond to
all kinds of threats: weather events,
cyber attacks, physical attacks and
disruptions caused by animals
• The complexity of the electric grid is part
of its strength, allowing for greater
reliability and more effective recovery
• The focus of utilities is to quickly respond
to each threat, by having protocols and
replacement parts in place to recover
critical systems
• Hurricane Harvey tested the electric
grid, and utilities and generators were
able to get consumers online quickly,
given the magnitude of the event
Mutual assistance
and recovery
www.aect.net (512) 474-6725
11
• Electric companies
affected by significant
outages often receive
mutual assistance from
electric utilities
nationwide, including
employees and
stockpiled equipment
Source: EEI
• Over 10,000 workers were dedicated to Harvey
response, including mutual assistance crews
from at least 20 states
Keeping thegeneration On
www.aect.net (512) 474-6725
12
South Texas Project continued to run
• Flooding was not an issue at the nuclear plant, and
it did not face the most severe winds
• 250 storm crew workers remained on-site during
the storm, sleeping in beds on site
Coastal wind generation remained on-line
• Only one coastal wind facility was knocked off-line,
due to damage to its transmission system, not the
turbine itself
• Coastal wind provided normal to higher-than-normal
generation on August 25 through August 28
HelpingRetail Customers
www.aect.net (512) 474-6725
13
• No deposits required for
customers directly affected
by Hurricane Harvey
• Offering payment
extensions and deferred
payment plans for eligible
customers
• Based in Houston, the
company contributed $1
million in cash donations
and $1 million in in-kind
relief efforts
• Waiving late fees and
extending payment due dates
with no down payment
required
• Reducing down payments and
deferring the balances over
five equal installments
• Providing $500,000 to assist
customers who need help
paying their bills in areas hit
by Hurricane Harvey
Local utilities have agreed to a disconnection
moratorium through Sept. 29
Implementation of Electricity Legislation
14
Low-Income Programs, Ratemaking and AMI forEntergy Texas customers
SB 1976: Identificationto support Low-IncomePrograms
www.aect.net (512) 474-6725
15
Latest actions on implementation of SB 1976
• PUC Staff opened Project 47343: Rulemaking to amend Chapter 25 substantive
rules relating to the elimination of the System Benefit Fund
• The PUC filed a strawman proposal for stakeholder comment in August.
• The PUC will host a workshop on Project 47343 on October 12.
SB 735: Electric Utility Ratemaking
www.aect.net (512) 474-6725
16
SB 735 components effective immediately
• There is no longer a sunset date on the distribution cost recovery factor (DCRF),
as recommended by the PUC.
• ERCOT utilities may only utilize the DCRF once per year, but there is no longer a
four-time limit on an ERCOT utility‘s use of the DCRF between rate cases.
• The PUC now has an additional 60 days (for a total of 240 days) to evaluate a
sale, transfer or merger of a utility under its purview.
SB 735 components requiring action
• PUC Staff opened Project 47545: Rulemaking to establish filing schedule for
electric utilities pursuant to PURA.
• The PUC will host a workshop on Project 47545 on September 26.
SB 1145: AdvancedMetering for Entergy Texascustomers
www.aect.net (512) 474-6725
17
Latest actions on implementation of SB 1145
• Entergy Texas filed its application for approval of an Advanced Metering
deployment plan on July 18 in Project 47416.
• A pre-hearing conference was held on August 8, and intervenors were able to
file testimony through September 11.
• Entergy Texas expects to begin deployment in 2019 and finish in 2021.
2019 2020 2021
Electric Meters 166,000 204,000 107,000
Entergy Texas Preliminary Deployment Schedule
Sharyland Customers Moving to Oncor
18
Regulatory Timeline of asset swap
Overview of the Sharyland/Oncor Asset Swap
www.aect.net (512) 474-6725
19
• Oncor receives retail
distribution assets and
retail distribution
operations in
Sharyland’s service
territory
• Sharyland receives 258
miles of 345 kV
transmission line
located in West and
Central Texas (not
pictured)
TentativeTimelineof ActivitiesRelated to theTransition
www.aect.net (512) 474-6725
20
Legal and Regulatory Approvals
Oncor ESI ID Creation
Motion for Rehearing Period
Closing of Agreement Between SU and Oncor
Sharyland Transition Readiness Workshop
REPs Submit MVIs and MVOs for the Transition Date To Be Determined
Oncor CIS Platform Replacement
Daily Transition Market Calls
Oncor Completes MVIs on Transition Date
Sharyland Completes MVOs on Transition Date
November 2017 December 2017September 2017 October 2017
Q&A on Sharyland Customer Transition
www.aect.net (512) 474-6725
21
How many customers will be impacted?
Approximately 54,000 customers will be transitioned from Sharyland
Utilities to Oncor for T&D service.
When will the transition be complete?
Oncor and Sharyland anticipate that all Sharyland retail customers will be
transitioned to the Oncor electric grid by January 5, 2018, pending
approval from the PUC.
Will Sharyland customers see their electric bills go down?
Sharyland customers will receive Oncor’s T&D rate, which is significantly
lower than Sharyland’s T&D rate.
Sempra to purchase Oncor
22
Latest Updates
Sempra outbidsBerkshirefor Oncor
www.aect.net (512) 474-6725
23
July 6: Berkshire Hathaway Energy announces intent to purchase
Oncor in a deal worth $18.1 billion (including debt).
July 13: Elliott Management Group, which owns debt in EFH,
announces intent to offer a bid of $18.4 billion. That
offer never materialized.
Aug. 20: Berkshire withdraws offer as Sempra Energy announces
$18.8 billion offer for Oncor.
Sept. 6: Sempra Energy receives approval from the U.S. Bankruptcy
Court in Delaware to pursue the purchase.
Next: Sempra Energy will file for approval from the Public Utility
Commission of Texas.
Once the filing is made, the PUC has 240 days to approve or
deny the transaction.
How To Reach Us
www.aect.net (512) 474-6725
24
For background on electric
markets, environmental data and
Electricity 101
Regular updates from AECT and its
member companies
Keep up with pictures and links to
latest documents released by
AECT
AECT.net
@aectnet
AECT Advocacy on Facebook
An easy way to receive updates
from AECT
TheAECT App

AECT Lunch-and-Learn: Update on the Electric Market

  • 1.
    Legislative Advertising PaidFor by: JuliaRathgeber, Association ofElectric Companies ofTexas 1005Congress, Suite 600,Austin,TX 78701 • 512-474-6725• www.aect.net September 14,2017 Lunch-And-Learn: Updateon the ElectricMarket
  • 2.
  • 3.
    Recovery from HurricaneHarvey 3 Utilities, Generators and Retailers Respond
  • 4.
    HARVEY one ofthe Largest Storms In U.S. History www.aect.net (512) 474-6725 4 Harvey Stats: • First Category 4 hurricane to make landfall in the Texas Coastal Bend since 1961 • 51.9 inches of rain – wettest storm in the history of the continental U.S. • 13 million people were under flood watch • 300,000 power outages at Harvey’s peak
  • 5.
  • 6.
    HARVEY Recovery: AEPTexas www.aect.net (512) 474-6725 6 • Most severe storm to hit the AEP Texas service territory in 44 years • 220,000 customers without power at its peak • Lost 5,000 poles and 200 transmission structures, such as lines and substations • 1,600 outages remain, with half of those in areas that are still flooded
  • 7.
    HARVEY Recovery: CenterPointEnergy www.aect.net (512) 474-6725 7 • 300,000 customers without power at its peak • About 900 planned outages are due to flooding and cannot be restored at this time • Restoration included building a temporary substation • About 640 unplanned outages remain
  • 8.
    HARVEY Recovery: TNMP www.aect.net(512) 474-6725 8 • TNMP serves Angleton and Dickinson, which saw a peak of 20,000 outages during the storm • About 60 outages remain in those communities
  • 9.
    HARVEY Recovery: EntergyTexas www.aect.net (512) 474-6725 9 • At the storm’s peak, 192,000 Entergy Texas customers were without power • Oncor, Cleco and other Entergy companies provided mobile substations • About 4,000 customers with extensive flooding cannot yet be restored • 1,600 outages remain, including both planned and unplanned outages
  • 10.
    Restoration TimelineHighlightsGrid Resilience www.aect.net(512) 474-6725 10 • Utilities must be prepared to respond to all kinds of threats: weather events, cyber attacks, physical attacks and disruptions caused by animals • The complexity of the electric grid is part of its strength, allowing for greater reliability and more effective recovery • The focus of utilities is to quickly respond to each threat, by having protocols and replacement parts in place to recover critical systems • Hurricane Harvey tested the electric grid, and utilities and generators were able to get consumers online quickly, given the magnitude of the event
  • 11.
    Mutual assistance and recovery www.aect.net(512) 474-6725 11 • Electric companies affected by significant outages often receive mutual assistance from electric utilities nationwide, including employees and stockpiled equipment Source: EEI • Over 10,000 workers were dedicated to Harvey response, including mutual assistance crews from at least 20 states
  • 12.
    Keeping thegeneration On www.aect.net(512) 474-6725 12 South Texas Project continued to run • Flooding was not an issue at the nuclear plant, and it did not face the most severe winds • 250 storm crew workers remained on-site during the storm, sleeping in beds on site Coastal wind generation remained on-line • Only one coastal wind facility was knocked off-line, due to damage to its transmission system, not the turbine itself • Coastal wind provided normal to higher-than-normal generation on August 25 through August 28
  • 13.
    HelpingRetail Customers www.aect.net (512)474-6725 13 • No deposits required for customers directly affected by Hurricane Harvey • Offering payment extensions and deferred payment plans for eligible customers • Based in Houston, the company contributed $1 million in cash donations and $1 million in in-kind relief efforts • Waiving late fees and extending payment due dates with no down payment required • Reducing down payments and deferring the balances over five equal installments • Providing $500,000 to assist customers who need help paying their bills in areas hit by Hurricane Harvey Local utilities have agreed to a disconnection moratorium through Sept. 29
  • 14.
    Implementation of ElectricityLegislation 14 Low-Income Programs, Ratemaking and AMI forEntergy Texas customers
  • 15.
    SB 1976: Identificationtosupport Low-IncomePrograms www.aect.net (512) 474-6725 15 Latest actions on implementation of SB 1976 • PUC Staff opened Project 47343: Rulemaking to amend Chapter 25 substantive rules relating to the elimination of the System Benefit Fund • The PUC filed a strawman proposal for stakeholder comment in August. • The PUC will host a workshop on Project 47343 on October 12.
  • 16.
    SB 735: ElectricUtility Ratemaking www.aect.net (512) 474-6725 16 SB 735 components effective immediately • There is no longer a sunset date on the distribution cost recovery factor (DCRF), as recommended by the PUC. • ERCOT utilities may only utilize the DCRF once per year, but there is no longer a four-time limit on an ERCOT utility‘s use of the DCRF between rate cases. • The PUC now has an additional 60 days (for a total of 240 days) to evaluate a sale, transfer or merger of a utility under its purview. SB 735 components requiring action • PUC Staff opened Project 47545: Rulemaking to establish filing schedule for electric utilities pursuant to PURA. • The PUC will host a workshop on Project 47545 on September 26.
  • 17.
    SB 1145: AdvancedMeteringfor Entergy Texascustomers www.aect.net (512) 474-6725 17 Latest actions on implementation of SB 1145 • Entergy Texas filed its application for approval of an Advanced Metering deployment plan on July 18 in Project 47416. • A pre-hearing conference was held on August 8, and intervenors were able to file testimony through September 11. • Entergy Texas expects to begin deployment in 2019 and finish in 2021. 2019 2020 2021 Electric Meters 166,000 204,000 107,000 Entergy Texas Preliminary Deployment Schedule
  • 18.
    Sharyland Customers Movingto Oncor 18 Regulatory Timeline of asset swap
  • 19.
    Overview of theSharyland/Oncor Asset Swap www.aect.net (512) 474-6725 19 • Oncor receives retail distribution assets and retail distribution operations in Sharyland’s service territory • Sharyland receives 258 miles of 345 kV transmission line located in West and Central Texas (not pictured)
  • 20.
    TentativeTimelineof ActivitiesRelated totheTransition www.aect.net (512) 474-6725 20 Legal and Regulatory Approvals Oncor ESI ID Creation Motion for Rehearing Period Closing of Agreement Between SU and Oncor Sharyland Transition Readiness Workshop REPs Submit MVIs and MVOs for the Transition Date To Be Determined Oncor CIS Platform Replacement Daily Transition Market Calls Oncor Completes MVIs on Transition Date Sharyland Completes MVOs on Transition Date November 2017 December 2017September 2017 October 2017
  • 21.
    Q&A on SharylandCustomer Transition www.aect.net (512) 474-6725 21 How many customers will be impacted? Approximately 54,000 customers will be transitioned from Sharyland Utilities to Oncor for T&D service. When will the transition be complete? Oncor and Sharyland anticipate that all Sharyland retail customers will be transitioned to the Oncor electric grid by January 5, 2018, pending approval from the PUC. Will Sharyland customers see their electric bills go down? Sharyland customers will receive Oncor’s T&D rate, which is significantly lower than Sharyland’s T&D rate.
  • 22.
    Sempra to purchaseOncor 22 Latest Updates
  • 23.
    Sempra outbidsBerkshirefor Oncor www.aect.net(512) 474-6725 23 July 6: Berkshire Hathaway Energy announces intent to purchase Oncor in a deal worth $18.1 billion (including debt). July 13: Elliott Management Group, which owns debt in EFH, announces intent to offer a bid of $18.4 billion. That offer never materialized. Aug. 20: Berkshire withdraws offer as Sempra Energy announces $18.8 billion offer for Oncor. Sept. 6: Sempra Energy receives approval from the U.S. Bankruptcy Court in Delaware to pursue the purchase. Next: Sempra Energy will file for approval from the Public Utility Commission of Texas. Once the filing is made, the PUC has 240 days to approve or deny the transaction.
  • 24.
    How To ReachUs www.aect.net (512) 474-6725 24 For background on electric markets, environmental data and Electricity 101 Regular updates from AECT and its member companies Keep up with pictures and links to latest documents released by AECT AECT.net @aectnet AECT Advocacy on Facebook An easy way to receive updates from AECT TheAECT App