SlideShare a Scribd company logo
1 of 34
ENGINEERING & MAINTENANCE DEPARTMENT
Prepared by,
Anu Chandran
Senior Manager
Engineering & Maintenance
MAR SLEEVA medicity palai
Engineering department in a healthcare
facilities ??
 To provide a safe environment and uninterrupted
utility services to the patients, bystanders and staffs.
 To keep the building and equipment operationally
and cost-effective.
Engineering Services
 ELECTRICAL
 HVAC ( HEAT VENTILATION & AIR CONDITIONING )
 PLUMBING SYSTEM ( WTP , RO , STP )
 MEDICAL GAS
 LIFT
 BOILERS
 PNUEMATIC TUBE SYSTEM
 SOLAR PLANT & SOLAR WATER HEATER
 GENERAL ENGINEERING WORKS
ELECTRICAL SYSTEM
DG SYNCRONIZATION
PANEL
2X 1600KVA,11KV/433V
INDOOR TRANSFORMER
1X1250KVA, 3X750KVA ,415V
DG INCOMER
KSEB 11 kV
FEEDER
MSB
COMMON LOAD
SOLAR INVERTERS
200KVA SOLAR PANEL
UPS LOAD
KIDANGOOR 33KV
SUBSTATION
ELECTRICAL INSTALLATIONS
• 24 Hrs Raw Power supply with minimum interruptions with automatic tap changer
• Equipped with 1600 KVA x 2 Transformers with automatic tap changer ( to avoid
voltage fluctuations)
• Full Electrical power Supply back up with 3 no's of 750 KVA Diesel Generators, with
shycronisation facility
• Uninterrupted Power supply through UPS for IT, Emergency lighting and to all
Critical Medical Equipment's.( 430 KVA, installed @ site, provision for future
expansion- 830kva)
• Variable Frequency drive for the Hydro Pneumatic Pumps, chiller plant pumps
• Almost 100% light fittings are LED the building.
• 200 kw solar plant which generate 900 kwh per day
HT Panel INDOOR TX
SYNCHRONISATION PANEL & MSB
• KSEB : 18 - 19,000 kwh / day
• Energy Charge : Normal – 7.8 , Peak – 11.7, Off Peak – 5.85
SOLAR POWER PLANT
• Installed capacity – 205KWp
• 900kwh - Units / day generation, it is 5% of the total consumption
• Directly connected to the grid
DIESEL GENERATOR
• Backup purpose
• 750KVA X 3 NOS, 1250KVA X 1NOS
• Diesel Consumption - 180 - 230 L/H for 3 DG
UPS FLOW DIAGRAM
Main UPS installation :330 kva and 100 kva for OT
Total Capacity : 830 kva
MAIN UPS INCOMER PANEL
UPS-ME
150/300 kVA
UPS-OT
100/200 kVA
UPS – L & P
150/300kVA
UPS-IT
SERVER
30 kVA
ISOLATION TRANSFORMER
MEDICAL
EQUIPMENT
OT PANEL L & P PANEL IT SERVER DB
ISOLATION TRANSFORMER
CENTRALISED MODULAR UPS
HVAC CHILLER PLANT
CAPACITY - 1150 TONS OF REFRIGERATION.
HVAC PLANT
• Chiller Plant – a centralized cooling system which provides cooling for
a building
• Capacity : 460TR X 2 NOS , 200TR – 1 NOS ( 1120 TR )
Energy conservation - SALIENT FEATURES OF THE
HVAC SYSTEM
• CHILLERS ARE HIGH EFFICIENCY TYPE, RATED AT 0.6 KW/TON
OF AIRCONDITIONING
• CHILLED WATER PUMPS RUN ON VARIABLE FREQUENCY
DRIVES
• COOLING TOWERS MOTORS RUN ON VARIABLE FREQUENCY
DRIVES
• ALL AHU MOTORS AND ALL PUMPS ARE OF THE HIGH
EFFICIENCY TYPE, RATED MORE THAN 85%
• TREATED FRESH AIR HANDLING UNITS FEED COOLED, AND
FILTERED AIR TO ALL AREAS
• TREATED FRESH AIR UNITS HAVE HEAT RECOVERY SYSTEMS IN
BUILT FOR ENERGY SAVINGS
AIR HANDLING UNITS (AHU)
• AHUs are used to cool the air in a floor by
passing air through chilled water coil .
• Our hospital currently have 76 AHUs that cools
the lobbys,ICUS,Operation theatres and other
areas. ( Critical and Non Critical areas )
• Our hospital also has 294 FCUs that for cools
the in patient and consulting / IP rooms
• All AHUs are provided with actuator valves and
BMS integration for automated temperature
control.
• Critical area AHUs are equipped with heating
coils along with fine filters for controlling
humidity
FAN COIL UNITS(FCU)
• FCU are used for cooling independent room like IP rooms,
small cabins, OP consulting rooms etc.
• FCUs are used in small closed rooms with low heat loads.
• Temperature settings in FCUs are controlled through a remote
thermostat fixed in the serving room itself.
FCU
FCU thermostat
HEAT RECOVERY WHEEL(HRW)
Heat recovery wheel is type of energy recovery heat
exchanger positioned with in the supply and exhaust air
stream of an air handling system for improving the
system efficiency
DESIRED AIR CONDITIONS IN HOSPITAL
• COMFORT CONDITIONS- 24+/- 1 DEG C
• ICU’S- 22+/-1 DEG C
• OT- 21+/-3 DEG C, RH NOT EXCEEDING 60%
• MRI, CT, CATH LAB- 21+/-1 DEG C
• LAB- 22+/- 1 DEG C
• AIR CHANGES IN OT- 5 ACH PER HOUR
• AIR CHANGES IN ICU’S- 2 ACH PER HOUR
• Consumption : 700 TR
•
WATER MANAGEMENT SYSTEM
• The process of planning, developing, and managing water resources,
in terms of both water quantity and quality, across all water uses.
• WTP, RO,STP
WATER STORAGE CAPACITY
In Pump Room
• RAW WATER DOMESTIC - 90 CUM / 90,000 L - 2 NOS
• TREATED WATER DOMESTIC TANK -90 CUM / 90,000 L - 2 NOS
• RAW WATER FLUSH TANK - 58 CUM / 58,000 L - 2 NOS
• TREATED WATER FLUSH TANK – 55 CUM / 55,000 L - 2 NOS
• FIRE TANK – 75 CUM / 75,000 L x 2 NOS
• COOLING TOWER MAKE UP TANK – 118.80 CUM / 1,18,800 L
• R O WATER PLANT CAPACITY - 3000 LITRES PER HOUR
• DIALYSIS R O WATER TANK CAPACITY - 5000 LTR
• CSSD AND ICU RO WATER TANK CAPACITY - 8000 LT
OVER HEAD TANK DETAILS
• COOLING MAKE UP -50 CUM
• FIRE TANK -140 CUM ( 80 & 60 )
• DOMESTIC 20 CUM
FILTERING SYSTEM AND RO PLANT
FIRE PROTECTION AND PROTECTION SYSTEM
We have fire pump room equipped with 2 X 100HP with 5.3 HP JOCKEY to
maintain the line pressure of 6bar. We have an additional diesel pump of 110HP
to ensure the protection when there is no electricity.
12 hydrant valves- to ensure complete fire protection and suppression
PA system- to ensure complete addressing and evacuation
MEDICAL GAS PLANT
 Oxygen ( O2 )
 Nitrous oxide ( N2O )
 Carbon Di Oxide ( CO2 )
 Compressed Air &
Vacuum
MEDICAL GAS PLANT
Oxygen Manifold ( 18 X 18Cylinder -
(Two banks)
 Emergency Manifold ( 12 Cylinder )
 N2O Manifold ( 5 X 5 Cylinder –
(Two banks)
Emergency Manifold ( 4 Cylinder )
CO2 Manifold ( 3 X 3 Cylinder-
(Two banks )
O2 Cylinders ( Black & White colour)
D Type ( 7 CUM)
B Type ( 1.6 CUM )
A Type (1 CUM )
N2O Cylinders ( Blue colour )
D Type ( 16.5 Kg )
A Type ( 1.7 Kg )
CO2 Cylinder ( Black & Gray colour)
D Type ( 30 Kg )
 Liquid Medical Oxygen ( LMO ) –
13KL
LIFTS
Total no's of lifts-14
(13 passengers +1 service lift )
Five out of Fourteen are considered Fire lift)
2 Nos. Dumb Waiters
( sterile & un-sterile)
ALL lifts are equipped with ARD ( Automatic Rescue Device)
BOILER
WE HAVE A BOILER OF 1000L/HR CAPACITY
Good steam is the heart of a successful laundry operation, for
optimum production and cost effective operations.
PNUEMATIC TUBE SYSTEM(PTS)
Main purpose Pneumatic
Tube System for the
transportation on demand
of urgent and ordinary
samples in Healthcare
facilities. The
PTS system allows the
management of blood bags,
drugs and analysis samples
APPROCHES TO SAVE ENERGY
• Self Energy Audits – Identify best practices within your depts.
• Identify those areas that use the most energy – Remember
HVAC accounts for 60%+ of your energy consumption, Make a
plan, set some goals
• Involve the whole staff, cultivate a behavior save energy. Save
Power , Save Water.
HOW TO SAVE ENERGY INSIDE THE HOSPITAL
• SWITCH OF MONITORS AFTER USAGE
• KEEP ALL DOORS CLOSED WHEN NOT IN USE
• OPENING DOORS MULTIPLE NUMBER OF TIMES TO BE AVOIDED
• SWITCH OFF LIGHTS WHEN NOT NEEDED
• SWITCH OFF POWER TO AC’s,
• USE MAXIMUM DAYLIGHT DURING THE DAY
• TRY TO CALL THE NEAREST LIFT INSTEAD OF CALLING MULTIPLE LIFTS
WATER- HOW TO SAVE?
• REPORT TO THE ENGINEERING
DEPARTMENT WHEN YOU SEE A TAP
LEAKING/ SHOWER LEAKING
• CLOSE WATER TAP WHEN NOT IN
NEED
• ALL CLOSETS ARE WITH DUAL
SWITCH CISTERNS, USE THEM
ECONOMICALLY
• ALL URINALS ARE WITH SENSORS
ENGINEERING DEPARTMENT FUTURE
PROJECTIONS
• COMMISSIONING OF NEW 1250KVA DIESEL GENERATOR.
• GARBAGE STORE BUILDING / HAZARDOUS BUILDING – WASTE
MANAGEMENT
• DISASTER RECOVERY DATA CENTER - IT
• WE ARE INSPECTING AND RECTIFYING SNAGS ON EACH RESPECTIVE AREAS
TO ENSURE SMOOTH OPERATION
Contact Details
MAINTENANCE – 8802 / 8606966496
THANK YOU
ANU CHANDRAN
Senior Manager
Engineering & Maintenance
Mar Sleeva Medicity Palai

More Related Content

Similar to About engineering department and its installations

Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
Nipak Banerjee
 
FF DESIGN BASIS REPORT.pdf
FF DESIGN BASIS REPORT.pdfFF DESIGN BASIS REPORT.pdf
FF DESIGN BASIS REPORT.pdf
ssuser0aa2d5
 

Similar to About engineering department and its installations (20)

Exhaust heat utility system copy
Exhaust heat utility system   copyExhaust heat utility system   copy
Exhaust heat utility system copy
 
Catalog Biến tần Frenic-HVAC (Fuji Electric)
Catalog Biến tần Frenic-HVAC (Fuji Electric)Catalog Biến tần Frenic-HVAC (Fuji Electric)
Catalog Biến tần Frenic-HVAC (Fuji Electric)
 
Energy audits in action
Energy audits in action Energy audits in action
Energy audits in action
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
 
P y un50_00
P y un50_00P y un50_00
P y un50_00
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)
 
Final Presentation.pptx
Final Presentation.pptxFinal Presentation.pptx
Final Presentation.pptx
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPT
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distribution
 
Green buildings : Challange in Operation and Maintenance
Green buildings : Challange in Operation and MaintenanceGreen buildings : Challange in Operation and Maintenance
Green buildings : Challange in Operation and Maintenance
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power Plant
 
FF DESIGN BASIS REPORT.pdf
FF DESIGN BASIS REPORT.pdfFF DESIGN BASIS REPORT.pdf
FF DESIGN BASIS REPORT.pdf
 
Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014
 
Htps
HtpsHtps
Htps
 
AERMEC 2013 Presentation
AERMEC 2013 PresentationAERMEC 2013 Presentation
AERMEC 2013 Presentation
 
SUPER CRITICAL BOILER.pdf
SUPER CRITICAL BOILER.pdfSUPER CRITICAL BOILER.pdf
SUPER CRITICAL BOILER.pdf
 
AC system by Balaji K.pptx
AC system by Balaji K.pptxAC system by Balaji K.pptx
AC system by Balaji K.pptx
 
Advance Solar Water Heater
Advance Solar Water HeaterAdvance Solar Water Heater
Advance Solar Water Heater
 
Advance Solar Water Heater
Advance Solar Water HeaterAdvance Solar Water Heater
Advance Solar Water Heater
 

Recently uploaded

Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networks
IJECEIAES
 
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdfALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
Madan Karki
 
Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..
MaherOthman7
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
drjose256
 

Recently uploaded (20)

Filters for Electromagnetic Compatibility Applications
Filters for Electromagnetic Compatibility ApplicationsFilters for Electromagnetic Compatibility Applications
Filters for Electromagnetic Compatibility Applications
 
"United Nations Park" Site Visit Report.
"United Nations Park" Site  Visit Report."United Nations Park" Site  Visit Report.
"United Nations Park" Site Visit Report.
 
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfInstruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
 
Lab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docxLab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docx
 
Raashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashid final report on Embedded Systems
Raashid final report on Embedded Systems
 
Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networks
 
Introduction to Artificial Intelligence and History of AI
Introduction to Artificial Intelligence and History of AIIntroduction to Artificial Intelligence and History of AI
Introduction to Artificial Intelligence and History of AI
 
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdfALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Piping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdfPiping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdf
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligence
 
Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..
 
handbook on reinforce concrete and detailing
handbook on reinforce concrete and detailinghandbook on reinforce concrete and detailing
handbook on reinforce concrete and detailing
 
AI in Healthcare Innovative use cases and applications.pdf
AI in Healthcare Innovative use cases and applications.pdfAI in Healthcare Innovative use cases and applications.pdf
AI in Healthcare Innovative use cases and applications.pdf
 
Low Altitude Air Defense (LAAD) Gunner’s Handbook
Low Altitude Air Defense (LAAD) Gunner’s HandbookLow Altitude Air Defense (LAAD) Gunner’s Handbook
Low Altitude Air Defense (LAAD) Gunner’s Handbook
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptx
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 

About engineering department and its installations

  • 1. ENGINEERING & MAINTENANCE DEPARTMENT Prepared by, Anu Chandran Senior Manager Engineering & Maintenance MAR SLEEVA medicity palai
  • 2. Engineering department in a healthcare facilities ??
  • 3.  To provide a safe environment and uninterrupted utility services to the patients, bystanders and staffs.  To keep the building and equipment operationally and cost-effective.
  • 4. Engineering Services  ELECTRICAL  HVAC ( HEAT VENTILATION & AIR CONDITIONING )  PLUMBING SYSTEM ( WTP , RO , STP )  MEDICAL GAS  LIFT  BOILERS  PNUEMATIC TUBE SYSTEM  SOLAR PLANT & SOLAR WATER HEATER  GENERAL ENGINEERING WORKS
  • 5. ELECTRICAL SYSTEM DG SYNCRONIZATION PANEL 2X 1600KVA,11KV/433V INDOOR TRANSFORMER 1X1250KVA, 3X750KVA ,415V DG INCOMER KSEB 11 kV FEEDER MSB COMMON LOAD SOLAR INVERTERS 200KVA SOLAR PANEL UPS LOAD KIDANGOOR 33KV SUBSTATION
  • 6. ELECTRICAL INSTALLATIONS • 24 Hrs Raw Power supply with minimum interruptions with automatic tap changer • Equipped with 1600 KVA x 2 Transformers with automatic tap changer ( to avoid voltage fluctuations) • Full Electrical power Supply back up with 3 no's of 750 KVA Diesel Generators, with shycronisation facility • Uninterrupted Power supply through UPS for IT, Emergency lighting and to all Critical Medical Equipment's.( 430 KVA, installed @ site, provision for future expansion- 830kva) • Variable Frequency drive for the Hydro Pneumatic Pumps, chiller plant pumps • Almost 100% light fittings are LED the building. • 200 kw solar plant which generate 900 kwh per day
  • 8. SYNCHRONISATION PANEL & MSB • KSEB : 18 - 19,000 kwh / day • Energy Charge : Normal – 7.8 , Peak – 11.7, Off Peak – 5.85
  • 9. SOLAR POWER PLANT • Installed capacity – 205KWp • 900kwh - Units / day generation, it is 5% of the total consumption • Directly connected to the grid
  • 10. DIESEL GENERATOR • Backup purpose • 750KVA X 3 NOS, 1250KVA X 1NOS • Diesel Consumption - 180 - 230 L/H for 3 DG
  • 11. UPS FLOW DIAGRAM Main UPS installation :330 kva and 100 kva for OT Total Capacity : 830 kva MAIN UPS INCOMER PANEL UPS-ME 150/300 kVA UPS-OT 100/200 kVA UPS – L & P 150/300kVA UPS-IT SERVER 30 kVA ISOLATION TRANSFORMER MEDICAL EQUIPMENT OT PANEL L & P PANEL IT SERVER DB ISOLATION TRANSFORMER
  • 13. HVAC CHILLER PLANT CAPACITY - 1150 TONS OF REFRIGERATION.
  • 14. HVAC PLANT • Chiller Plant – a centralized cooling system which provides cooling for a building • Capacity : 460TR X 2 NOS , 200TR – 1 NOS ( 1120 TR )
  • 15. Energy conservation - SALIENT FEATURES OF THE HVAC SYSTEM • CHILLERS ARE HIGH EFFICIENCY TYPE, RATED AT 0.6 KW/TON OF AIRCONDITIONING • CHILLED WATER PUMPS RUN ON VARIABLE FREQUENCY DRIVES • COOLING TOWERS MOTORS RUN ON VARIABLE FREQUENCY DRIVES • ALL AHU MOTORS AND ALL PUMPS ARE OF THE HIGH EFFICIENCY TYPE, RATED MORE THAN 85% • TREATED FRESH AIR HANDLING UNITS FEED COOLED, AND FILTERED AIR TO ALL AREAS • TREATED FRESH AIR UNITS HAVE HEAT RECOVERY SYSTEMS IN BUILT FOR ENERGY SAVINGS
  • 16. AIR HANDLING UNITS (AHU) • AHUs are used to cool the air in a floor by passing air through chilled water coil . • Our hospital currently have 76 AHUs that cools the lobbys,ICUS,Operation theatres and other areas. ( Critical and Non Critical areas ) • Our hospital also has 294 FCUs that for cools the in patient and consulting / IP rooms • All AHUs are provided with actuator valves and BMS integration for automated temperature control. • Critical area AHUs are equipped with heating coils along with fine filters for controlling humidity
  • 17. FAN COIL UNITS(FCU) • FCU are used for cooling independent room like IP rooms, small cabins, OP consulting rooms etc. • FCUs are used in small closed rooms with low heat loads. • Temperature settings in FCUs are controlled through a remote thermostat fixed in the serving room itself. FCU FCU thermostat
  • 18. HEAT RECOVERY WHEEL(HRW) Heat recovery wheel is type of energy recovery heat exchanger positioned with in the supply and exhaust air stream of an air handling system for improving the system efficiency
  • 19. DESIRED AIR CONDITIONS IN HOSPITAL • COMFORT CONDITIONS- 24+/- 1 DEG C • ICU’S- 22+/-1 DEG C • OT- 21+/-3 DEG C, RH NOT EXCEEDING 60% • MRI, CT, CATH LAB- 21+/-1 DEG C • LAB- 22+/- 1 DEG C • AIR CHANGES IN OT- 5 ACH PER HOUR • AIR CHANGES IN ICU’S- 2 ACH PER HOUR • Consumption : 700 TR •
  • 20. WATER MANAGEMENT SYSTEM • The process of planning, developing, and managing water resources, in terms of both water quantity and quality, across all water uses. • WTP, RO,STP
  • 21. WATER STORAGE CAPACITY In Pump Room • RAW WATER DOMESTIC - 90 CUM / 90,000 L - 2 NOS • TREATED WATER DOMESTIC TANK -90 CUM / 90,000 L - 2 NOS • RAW WATER FLUSH TANK - 58 CUM / 58,000 L - 2 NOS • TREATED WATER FLUSH TANK – 55 CUM / 55,000 L - 2 NOS • FIRE TANK – 75 CUM / 75,000 L x 2 NOS • COOLING TOWER MAKE UP TANK – 118.80 CUM / 1,18,800 L • R O WATER PLANT CAPACITY - 3000 LITRES PER HOUR • DIALYSIS R O WATER TANK CAPACITY - 5000 LTR • CSSD AND ICU RO WATER TANK CAPACITY - 8000 LT OVER HEAD TANK DETAILS • COOLING MAKE UP -50 CUM • FIRE TANK -140 CUM ( 80 & 60 ) • DOMESTIC 20 CUM
  • 23. FIRE PROTECTION AND PROTECTION SYSTEM We have fire pump room equipped with 2 X 100HP with 5.3 HP JOCKEY to maintain the line pressure of 6bar. We have an additional diesel pump of 110HP to ensure the protection when there is no electricity. 12 hydrant valves- to ensure complete fire protection and suppression PA system- to ensure complete addressing and evacuation
  • 24. MEDICAL GAS PLANT  Oxygen ( O2 )  Nitrous oxide ( N2O )  Carbon Di Oxide ( CO2 )  Compressed Air & Vacuum
  • 25. MEDICAL GAS PLANT Oxygen Manifold ( 18 X 18Cylinder - (Two banks)  Emergency Manifold ( 12 Cylinder )  N2O Manifold ( 5 X 5 Cylinder – (Two banks) Emergency Manifold ( 4 Cylinder ) CO2 Manifold ( 3 X 3 Cylinder- (Two banks ) O2 Cylinders ( Black & White colour) D Type ( 7 CUM) B Type ( 1.6 CUM ) A Type (1 CUM ) N2O Cylinders ( Blue colour ) D Type ( 16.5 Kg ) A Type ( 1.7 Kg ) CO2 Cylinder ( Black & Gray colour) D Type ( 30 Kg )  Liquid Medical Oxygen ( LMO ) – 13KL
  • 26. LIFTS Total no's of lifts-14 (13 passengers +1 service lift ) Five out of Fourteen are considered Fire lift) 2 Nos. Dumb Waiters ( sterile & un-sterile) ALL lifts are equipped with ARD ( Automatic Rescue Device)
  • 27. BOILER WE HAVE A BOILER OF 1000L/HR CAPACITY Good steam is the heart of a successful laundry operation, for optimum production and cost effective operations.
  • 28. PNUEMATIC TUBE SYSTEM(PTS) Main purpose Pneumatic Tube System for the transportation on demand of urgent and ordinary samples in Healthcare facilities. The PTS system allows the management of blood bags, drugs and analysis samples
  • 29. APPROCHES TO SAVE ENERGY • Self Energy Audits – Identify best practices within your depts. • Identify those areas that use the most energy – Remember HVAC accounts for 60%+ of your energy consumption, Make a plan, set some goals • Involve the whole staff, cultivate a behavior save energy. Save Power , Save Water.
  • 30. HOW TO SAVE ENERGY INSIDE THE HOSPITAL • SWITCH OF MONITORS AFTER USAGE • KEEP ALL DOORS CLOSED WHEN NOT IN USE • OPENING DOORS MULTIPLE NUMBER OF TIMES TO BE AVOIDED • SWITCH OFF LIGHTS WHEN NOT NEEDED • SWITCH OFF POWER TO AC’s, • USE MAXIMUM DAYLIGHT DURING THE DAY • TRY TO CALL THE NEAREST LIFT INSTEAD OF CALLING MULTIPLE LIFTS
  • 31. WATER- HOW TO SAVE? • REPORT TO THE ENGINEERING DEPARTMENT WHEN YOU SEE A TAP LEAKING/ SHOWER LEAKING • CLOSE WATER TAP WHEN NOT IN NEED • ALL CLOSETS ARE WITH DUAL SWITCH CISTERNS, USE THEM ECONOMICALLY • ALL URINALS ARE WITH SENSORS
  • 32. ENGINEERING DEPARTMENT FUTURE PROJECTIONS • COMMISSIONING OF NEW 1250KVA DIESEL GENERATOR. • GARBAGE STORE BUILDING / HAZARDOUS BUILDING – WASTE MANAGEMENT • DISASTER RECOVERY DATA CENTER - IT • WE ARE INSPECTING AND RECTIFYING SNAGS ON EACH RESPECTIVE AREAS TO ENSURE SMOOTH OPERATION
  • 33. Contact Details MAINTENANCE – 8802 / 8606966496
  • 34. THANK YOU ANU CHANDRAN Senior Manager Engineering & Maintenance Mar Sleeva Medicity Palai