SlideShare a Scribd company logo
Improve Quality in
 MS and Brazing
     Rollators Area
DMAIC




            1
          DEFINE




IMPROVE
Project
                                                      Signature Page:
           Sponsor:    I commit to support the successful completion of this project by:
                       • Ensuring that the project is aligned with overall organization goals
                       • Providing personnel and resources
                       • Removing roadblocks and barriers
                       • Allotting time to hear progress reports from the team and provide meaningful feedback




Approval
                       Signed:       Imelda Salas
                                     Name                                              Date
                                     Director of Operations
                                     Title
           Champion: I commit to support the successful completion of this project by:
                     • Arranging Lean Sigma training for the team, as necessary
                     • Coordinating available resources and support
                     • Conducting frequent reviews of the team's progress


                       Signed:         Javier Estrada
                                       Name                                            Date
                                       Engineering and Lean Manager
                                       Title
           Team:       We commit to contributing to the successful completion of this project by:
                       • Applying the Lean Sigma methodology to make sustainable improvements to key metrics
                       • Contributing our knowledge, ideas, and experiences
                       • Attending scheduled meetings and events
                       • Completing all assigned action items
                       • Communicating project progress to the Champion and Sponsor
           Signed:

           Gladys Quiroz                                      Mfg. Engineer / Floor Support
           Name                                               Title / Role                                  Date

           Eusebia cedillo                                    Quality Engineer / Floor Support
           Name                                               Title / Role                                  Date

           Jorge Sanchez                                      Gral. Supervisor / Prodcution
           Name                                               Title / Role                                  Date

           Alejandro Perez                                    Project Engineer / Projects
           Name                                               Title / Role                                  Date

           Jorge Castellanos                                  Lean Department / Plant
           Name                                               Title / Role                                  Date

           Ramon Garcia                                       Gral. Supervisor / Tool Room
           Name                                               Title / Role                                  Date


           Name                                               Title / Role                                  Date
Project contract
                    Lean Six Sigma Project Contract

    Name of Project:        Improve Quality in MS and Brazing Area - Rollator Models

   Business Driver(s):      Examples include Production Increase, Cost Reduction, Capital Avoidance

  Estimated Start Date:      10/15/2010              Estimated Completion Date:           5/15/2011

    Estimated COPQ:                                       Metric(s) to be Improved:
                                                     List the metric(s) that you expect to affect and whether
Provide an estimated cost of poor quality.           you expect them to increase, decrease, etc. (IPO
                                                     ouptuts)
Project Objective

Reduce the dimensional variation on the frame and cross bar of the rollators model.



Business Objective

Invrease Productivity, Delivery and Reduce Cost


 Definition of a Defect:



Eliminate mis balance and three wheeling




    In Project Scope:                                Not in Project Scope:



Tubing, Tube benders, Piercing, Notching and
                                                     Painting, purchased components and Final Assembly
welding



   Vision of Success:




Apply some Lean Manufacturing concepts such as 5"S, Quick Set Ups, Overproduction,etc,. Then we will
recolect data from the equipment mentioned above in order to find the root cause using statatistic tools, the
reduce the variation of the processes.
Dolomite Rollator
Core Team
                 • Sponsor – Imelda Salas
               • Champion – Javier Estrada
                  Black Belt – Mario Ruiz
Team members                          Support Members
–   Gladys Quiroz    ( Engineering)   – Carlos Gonzalez (Finance)
–   Eusebia Cedillo (Quality)         – Hector Elizondo (Maintenance)
–   Jorge Sanchez (Production)        – Edilberto Reyes (HR & Safety)
–   Alejandro Perez (Engineering)
–   Jorge Castellanos (Lean Mfg)
–   Ramon Garcia     (Tool Room)
–   Jesus Fonseca (Production)
PROJECT SCOPE

●
    Objective: Reduce the dimensional variation on the
    frame and cross bar of the rollator models
●
    Business Objective: Increase productivity, delivery and
    reduce cost
●
    Problem Statement (s):
    – Reduce rejects at the Final Assembly area
    – Increase delivery time
    – Increase production base on the resources assigned
    – Reduce scrap
Project Timeline
VOC
Customer Interview
1.   What process are we working on?
      • Rollators (Machine Shop & Brazing)
1.   What is the process objective (voice of the customer and/or business)?
      • Reduce and Eliminate rework and scrap due cross folding and three
         wheeling
1.   Has the customer been interviewed to confirm the VOC?
      • Yes
1.   What is the project business objective (COPQ)?
      • While eliminating this type of defects we minimize the chances of shipping
         bad product to our customers. We will also improve our safety and
         ergonomics eliminating the risk for a long term injuries. We can increase
         our production velocity, reduce the inspection time and material handling.
1.   What does success look like (project goals)?
      • Hit Target: What is the target?
          – Feb 2011 for hand off training and Owner sign off
      • Minimize: to what level, cost or effort?
          – 80% Rework / Scrap reduction for cross folding and three wheeling
      • Robustness: To what degree?
          – Maxi and Legacy Rollators regardless of the customer
VOC
 6. How long had this issue been present?
    Employee and supervisors interviews states that three wheeling has been since
    product initiated production, and cross folding control became due a some customer
    complains.
    What has been done about it so far?
    Some tooling and process correction and 100% inspection at final assembly thru kaizen
    events.
 7. Construct an Input, Process, Output diagram of the process. Outputs need to be
    measurable, in units, and possibly normalized. Use continuous data when
    possible. All outputs need to represent the voice of the customer or business.

  SUPPLIER               INPUT         PROCESS           OUTPUT                          CUSTOMER
                                                                          Target
Materials        Raw Material

H.Resources      SOP's                             Delivery increase   95% <= 2 Days     Government
Process Eng.     Manpower           Machine Shop                                         Airlines

Maintenance      Training                          Scrap Reduction                 70%   Parks

Industrial Eng   Equipment            Brazing                                            Farmacies

Prod. Sup.       Machines                          FPY                             98%   Warehouses

                 Safety Parameter                                                        Homecare

                 Utilities                         WIP Reduction                 60%     DC’s
VOC
8. Do you have baseline data for the outputs?
      •    Yes, there are scrap and first pass yield reports
      •    Measurements of the product were given but new parameters needed to be
           set up due to new tooling for bender equipment.
9. Can the project be completed (new controls in place) in 4-6 months?

      •    Yes, it can be completed
10. What are the problem statement(s)?
     • Cross folding
     • Three wheeling
     • Dimensional capability
11. Do you have an idea of what is causing these issues?
      •    Yes, potential dimensional variation during the machining and welding
           processes.
      Can that be supported with data?
      •    Not at this time, we have to collect data from the source.
12. What prevents us from being in the desired state?
      •    Machine capabilities
      •    Process operator dependable
13.       Is this process within our realm of influence?
      •    Yes, if a major investment is required a Cap Ex must be issue and approved
           prior implementation
VOC
14. Who are the stakeholders in this process?

    Suppliers         Process         Customers           Others
                     Participants
   Warehouse           Cutting        Paint Line     Production Control
    Planning          Bending       Final Assembly        Quality
Production control    Punching

  Maintenance         Welding

   Tool Room          Piercing

   Engineering

15. Who should be on the project team?
    • Core Team – multi-task employees with experience in this
      product.
Value Stream Map (Current
          state)
Cost of Poor Quality
$70,000                                                            Total $119,997
$60,000
$50,000

$40,000

$30,000

$20,000
                  8




                               3




                                                          8
                19




                             13




                                          08




                                                        60




                                                                     46




                                                                                   16
$10,000

                                        ,4




                                                                   ,1




                                                                                 ,5
             3,




                          0,




                                                     4,
           $2




                        $6




                                      $8




                                                   $1




                                                                 $4




                                                                               $3
   $-
          F.A. Rework F.A. Scrap cost   Brazing   Brazing Scrap Bend Rework   Bend Scrap
              cost                    Rework cost      cost        cost          cost



                          Yearly rework cost: $35,663
                          Yearly Scrap cost: $84,335
Units
  In
     c   or
            r   ec




                                       0
                                    1000
                                    1500
                                    2000
                                    2500
                                    3000
                                    3500
                                    4000




                                     500
                   t   Be
    Se                   nd
      t -u
          pf
M
                                                         3508


 at            ai
                  lur
    er
       ial            e


                                           857
            re
               lat
  Be               ed
      nd
           fl a
               tn                        503
                   es
    To
        ol            s
           in
                                     440


              gd
                   en
                      t
                                    209




 we                   Ox
    l                   id
         di                e
           ng
                                    92




              f      ai
                          lur
        Ba                    e
          d
                                    68




                 fo
In                    rm
   c   or                  in
          r   ec                g
                 t
                                    40




                     len
                                                                Defects Pareto




                 gt
          M         h
                                    37




           et
             al
                de
                   nt
                                    25
Bend Defect Pareto
90%
         77%           Incorrect Bend degree
80%
70%
60%
50%
40%
30%
20%                     13%
                                          7%
10%                                                3%
 0%
      Bender D-11    Press P54         Welding    Chrome
                                       fixture



77% of bend defects relates to bender equipment
FMEA
               Process: Machine Shop                Process Responsibility: Alejandro Perez
             Component: 13347 BACK FRAME LEGACY 600                                     Creation Date: 4/07/2010
                 Team: Rollator TEAM                                                    Revision Date: 9/10/2010


 Requirements       Failure Mode(s)        Effect(s) of Failure            Cause(s) of              Process Control(s)                         Recommended Solution(s)                               Resp & Target Date




                                                                     SEV




                                                                                         OCC




                                                                                                                               DET

                                                                                                                                     RPN




                                                                                                                                                                             SEV

                                                                                                                                                                                   OCC

                                                                                                                                                                                         DET

                                                                                                                                                                                               RPN
                                                                             Failure

                                                                                                                                    -Bring tubing cut to length from
                                                                                                                                                                                                       M. Granados
                                                                                         4 First piece and last piece audit 4 64    supplier -Cut machine set-up              4    4     4     64
                     short or long    Misalignment of side tubes on         Bad cut                                                                                                                    Manufacturing
Tube cut length                                                     4                                                                           check list
                     cut to length      13192 weldment fixture              length
                                                                                                                                    Make sampling plan to use Go no                                  Manufacturing/Qu
                                                                                         2       -Use of fixture Go no Go      3 24                                           4    2     3     24
                                                                                                                                                   Go                                                      ality
                                                                       Bender miss-            -Monitoring pressure levels
                                                                                    4                                          3 60                  TPM program              5    4     3     60      Maintenance
                                       Back frame will not match         adjusted                      on bender
                                       with the front frame. The         Incorrect             preferably Use of Protractor                   Sampling program to verify                          Manufacturing/Eng
Angles within +/-   Angles out of                                                   3                                          3 45                                           5    3     3     45
                                         Rollator will not have      5 bender set-               Go no Go as a secondary                        correct bend on tubing.                               ineering
0.5 degree Spec      Spec limits                                         Go no Go
                                        symmetrical structure.                                                                             Check list to verify Go no Go uses.                       Manufacturing/Eng
                                       Potential Three wheeling.        fixture not 4              Training/Supervision        3 60                                            5   4     3     60
                                                                                                                                            State in the work instructions.                              ineering
                                                                           in use
                                                                                               Sampling plan or revalidation
holes location & Incorrect holes                                                         4                                     3 60              Process re-validation        5    4     3     60       Engineering
                                       Bad function of the folding         Die miss-                     process.
  orientation      location &                                        5
                                              mechanism.                   adjusted                                                          State Go no Go use on work                              Manufacturing/Eng
 withing Spec.     orientation                                                           2       -Use of fixture Go no Go      2 20                                           5    2     2     20
                                                                                                                                                     instructions                                        ineering
                                                                             Wrong
                                                                                                -Identify bending dies per                 Put marks on bending dies & state
                                                                            bending      4                                     3 48                                          4     4     3     48      Manufacturing
                                                                                                      tubing to use                             on set-up instructions
                                                                             tools
                                                                                                                        warehouse location for this tube                      4    4     2     32       Warehouse
                    Flatten bends       -Customer Dissatisfaction    4       Wrong
                                                                                   4 -Identify tubing on warehouse 2 32 Tube cut to length from supplier
                                                                             tubing                                                                                           4    4     2     32      M. Granados
   Apearance                                                                                                               to prevent mixed material
                                                                       Bender non      -Monitoring pressure levels
                                                                                   4                               3 48           TPM program                                 4    4     3     48      Maintenance
                                                                        adjusted                on bender
                                                                           Un-                                           paint inspection before send to
                                       -Scrap, Quality complaints,                                                                                                                                   Manufacturing/Qu
                     Paint defects                                   3 appropriate 4 Quality inspection check list 3 36 final assembly & final assembly                       3    4     3     36
                                        Customer dissatisfaction                                                                                                                                           ality
                                                                        paint rack                                      area inspection before assemble.
Measure Plan
●
    Team will measure the part numbers as follow:
    – Bend process: Angle on 1149178 y 1149181 left & right sides
    – Punching: Distance between holes and angles on 1150607 &
      1150608 left and right sides
    – Welding: distance between sides and between holes on 1149177
●
    Procedure:
    – Production will send 5 pieces of each run to metrology for 2
      weeks
        • 1st piece, 3 more during the run and the last piece.
        • Set up Tech will record all process changes during the run in order to
          understand where is the variation.
    – The pieces will be delivered to metrology technician one by one;
      the measured pieces will be picked up and sent back to line.
    – Metrology lab will maintain the record and at the end of each shift,
      the record will be sent to the quality engineer.
    – Quality engineer will process the data and obtain the graphics
2010 Defects
        12,000                                                                                            M.S. Defects      Brazing Defects    F.A. Defects



        10,000

                                          04
                                       4,3
         8,000
                                                                                                               29
                                                                                                            3,4
                                                                18         28
Units




         6,000                                       78      3,1        3,1                    3,   059                         9
                                                  2,9                                                                    2,8
                                                                                                                            7

                                                                                       9   1
                    0   7      46         9   7                                     2,2
                 2,2        2,2        3,9
         4,000
                                                                                                               84                      39
                                                         5      9   5      0   4                  41        3,1                     2,5
                                                  2,7
                                                     6       2,8        2,9                    2,8                          73
                                                                                                                         2,6
                    4   9      8   6
                                                                                    2,1
                                                                                       27                                                     385 4 1
         2,000   2,0        2,0                                                                                                                  6 556
                                                                                                                                       16
                                                                                                                                    1,0                  264 329 6
                                          60                                                                                                                   29
                                       2,4           02         82         87                       748        59           45
                    61         84                 1,7        1,7        1,7            09      1,           1,9          1,6           70
                 1,2        1,2                                                     1,3                                             1,2
            0
                 Jan        Feb        Mar        Apr        May        Jun         Jul        Aug          Sep          Oct        Nov        Dec        Jan-11

                                                                                   2010


  Significative improvement achieved for production to control runs and
  avoid mixing set-ups has helped reduce three wheeling.
Three wheeling Defect Trend

9.00%                                                                                    8%         9%
                                                                                   8.3        8.1              4%
8.00%                                                                                                    7.3
7.00%
6.00%                    3%
                   4.8                       8%                               9%
5.00%                                    4.2                            4.4
                                                        0%         0%
                                                  3.7        3.6
4.00%         2%
        2.9                         4%
3.00%                         2.5
                                                                                                                          5%
                                                                                                                    1.9
2.00%
                                                                                                                                      5%         0%
1.00%                                                                                                                          0 .3        0.3
0.00%
        Jan        Feb        Mar        Apr      May        Jun         Jul       Aug        Sep        Oct        Nov        Dec Jan-11
                                                                        2010


    Nov 2010 Production started to control production orders for
    left and right sides of the frame.
DMAIC




IMPROVE
IPO Grid Bender
                                              Output Variables
                                                  Distance
            Tube bend operation          Bend     between
                                         angle     bends     Length   Total
                   Weigh Factor           9          5           1
                   Speed                  9          5           1     107
                   Die penetration        9          1           1       87
                   Pressure               9          5           1     107
                   Stops position         1          9           9       63
   Process input
                   Temperature            5          1           1       51
     variables
                   Lubrication            5          1           1       51
                   Forming dies           5          5           1       71
                   Tube strength          9          1           1       87
                   Tube position          1          5           5       39

Per our pareto graphs we weighed bend angle as our output
variable to focus
Time Series Plot 610 angle
Run trial to establish our start point.
•   20 pieces in Bend & Punch operations
•   Measured the 4 angles of the piece after each operation
•   Graph each Angle to compare
               Ti me Ser i es Pl ot of Angl e 1 , Max 1 , Mi n 1 , Punch 1 , Spec 1
        62.0
                                                                         Variable
                                                                         Angle 1
                                                                         Max 1
        61.5                                                             Min 1
                                                                         Punch 1
                                                                         Spec 1


        61.0
  D a
   at




        60.5



        60.0



        59.5
                    2       4       6      8       10       12    14      16        18   20
                                                   I ndex
Interval plot 600 Angle
               6 0 degr ee Bend Bef or e and Af t er bei ng pi er ced
                                95% CI for the Mean
        61.0

        60.9

        60.8

        60.7
Dat a




        60.6

        60.5

        60.4

        60.3

        60.2
                          60                              after pierce 1



         Delta of mean = 0.255 degrees
Hypothesis test for piercing process
      ●
          The Angle deformation made during piercing operation is
          statistically significant to deviate in +/-0.5 degrees
            H0-0.50<m0>+0.50
                                                                                                   Box pl ot of Z-t est

            H1-0.50>m1<+0.50                                              (with Ho and 95% Z-confidence interval for the Mean, and StDev = 0.25)




One-Sample T: Z-test
Test of mu = 0.5 vs not = 0.5
Variable N Mean StDev SE Mean         95% CI        T     P
Z-test 59 -0.0458 0.3164 0.0412 (-0.1282, 0.0367) -13.25 0.009
                                                                                                             _
One-Sample T: Z-test                                                                                         X
                                                                                                                                              Ho
Test of mu = -0.5 vs not = -0.5
Variable N Mean StDev SE Mean         95% CI        T     P
Z-test 59 -0.0458 0.3164 0.0412 (-0.1282, 0.0367) 11.03 0.009      -0.75        -0.50          -0.25            0.00          0.25           0.50
                                                                                                          Z- t est


P-values range from 0 to 1. The smaller the p-value, the smaller
the probability that rejecting the null hypothesis is a mistake


    Conclusion:
    The H0 is rejected as P value in both tests are 0.009
Cause and effect analysis
                          Cause-and-Ef f ect Di agr am
Measurements                         Material                        Personnel



                                            Lenght
         Go-no go out of spec
                                                                                 Lack of t raining
                                                Mat erial hardness
              lack of calibrat ion
                                                  Mat erial inconsistency
                                                                                     No experience
                  improper
                  measurement t ools                 walnut out of t olerance
                                                                                                                  Bend
                                                                                                                Three
                                                                                                                  Angle
                                                                                                                Wheeling
                                                                                                                  Three
                                                      process cont rols                                          Wheeling
                                                                                        equipment check up
                                                     Welding process
                Safety factors
                                                   t ooling lifecycle records        prevent ive maint enance
                                                 Operat or dependant
                                                set up parameters                 tooling condit ion
          Temperature
                                            t ube posit ion
                                                                                unstable pressure
                                           Set up t ools


Environment                          Methods                         Machines
Bend Data Sheet
            ●
                Pieces from the bend operation were measured
                and the results Ser i esshown 5in a ee
                           Ti me
                                 are Pl ot of 5 degr control chart
            56.5


            56.0


            55.5                                                          USL
55 degree




            55.0                                                          Mean



            54.5                                                          LSL


            54.0



                   1   13   26   39   52      65    78   91   104   117
                                           I ndex
Gage R&R                                    Measure
●
    Gage R&R was performed to evaluate our
    measure system on:
    – Precision         Gage Run Char t of Measur ement by Unit , Oper at or
                                                                                Reported by :   Mario Ruiz
                        Gage name:                A ngle                        Tolerance:


    – Repeatability
                        Date of study :           12/23/2010                    Misc:




    – Reproducibility                                  1       2       3                   4                 5          O perator
                                                                                                                        A
                                                                                                                        B
                                          35.25


                                          35.10
                          Measur em ent


                                                                                                                 Mean

                                          34.95


                                          34.80


                                          34.65


                                          34.50
                                                                   Oper at or
                         Panel variable: Unit




Graph Shows measurement system is consistent between Operators
using the Faro measurement tool
ANOVA of Gage R&R
                             Gage R& R ( A NOVA ) f or Measur ement
                                                                                                                                                                                                 Variation of the pieces, OK
                                                                                                                                                 Reported by :            Mario Ruiz
                             Gage name:                            A ngle measurement                                                            Tolerance:               1
  Major contributor of       Date of study :                       12/23/2010                                                                    Misc:
 variation is the parts,
 means, the measuring                                                     Com ponents of Variat ion                                                                                         Measurem ent by Unit
   system is correct                            100                                                                                  % Cont ribut ion
                                                                                                                                     % St udy Var
                                                                                                                                                           35.1



                                  Percent
                                                 50
                                                                                                                                                           34.8

                                                                                                                                                           34.5
                                                  0
                                                           Gage R&R          Repeat                  Reprod       Par t-to-Part                                            1                2           3           4       5
                                                                                                                                                                                                       Unit

 system is on control,                                                      R Chart by Operat or
                                                                                                                                                                                        Measurem ent by Operator
                                                           A                                     B
 means operators are                            0.10                                                                              UCL= 0.1004
                                Sam ple Range




 measuring almost the                                                                                                             _                        35.1
                                                0.05                                                                              R= 0.044
       same,                                                                                                                                               34.8
                                                0.00                                                                              LCL= 0
                                                       1       2      3       4       5          1       2    3        4      5                            34.5
                                                                                          Unit                                                                                         A                                B
                                                                                                                                                                                                   Operat or
                                                                          Xbar Chart by Operat or
                                                           A                                     B                                                                                 Unit * Operat or I nteract ion
Pieces are out of control,
                                Sam ple Mean




                                                                                                                                  _
                                                                                                                                  _                                                                                         Operat or
 meaning measurement                            35.1                                                                              UCL= 35.0761
                                                                                                                                  X= 35.044
                                                                                                                                  LCL= 35.0119                     35.1
                                                                                                                                                                                                                            A




                                                                                                                                                        Aver age
                                                                                                                                                                                                                            B
     system is valid                            34.8
                                                                                                                                                                   34.8
                                                34.5
                                                       1       2      3       4       5          1       2    3        4      5                                    34.5
                                                                                          Unit                                                                                 1        2        3            4     5
                                                                                                                                                                                                Unit


                                                                                                                           No interaction of operator
                                                                                                                           if lines are almost parallel


ANOVA to the measuring system shows our measurement system to be
reliable
Six pack Bender Analysis

                            Process sigma, CP and Cpk wasi tdetermined C5
                                            Pr ocess Capabi l y Si xpack of
                                                  Xbar Char t                                                       Capabilit y Hist ogr am
                                                                                                                      Data shows a
                                                                                                                                 LSL        USL
                            56                                                             UCL= 55.994
                                                                                                                      dispersion from                             Specif
      Sam ple Mean




                                                                                           _
                                                                                           _                           53.83 to 55.99                              LSL
                            55                                                             X= 54.913                                                               USL

                            54                                   1
                                                                                           LCL= 53.833

                      Pr 5ocess Capabi 15i t y Si xpack of C5
                                71   39    11
       Tests performed with unequal sample sizes
                                                 13
                                                    l 17 19 21 23                                              53.4      54.0     54.6   55.2     55.8     56.4

                             Xbar Char t                                               Capabilit y Hist ogr am
                                                    R Char t                                        LSL         USL
                                                                                                                                   Nor mal Pr ob Plot
                                                                UCL= 55.994                                                        A D: 0.421, P: 0.320
                                                                                                                                      Specifications
           Sa m ple Range




                            2                                   _
                                                                _                          UCL= 1.877                                   LSL 54.5
                                         Xbar shows data to     X= 54.913                                                               USL 55.5
                            1             be normal as well                                _
                                                                                           R= 0.574
                            0
                                          as the histogram
                                               1
                                                                LCL= 53.833
                                                                                           LCL= 0
  7          11    139   15    17     19   21    23
              1    3    5     7     9    11    13 15             17   19      21   23
equal sample sizes                                                                  53.4    54.0      54.6   55.2     55.8      56.4
     Tests performed with unequal sample sizes                                                                                    54.0                   55.5

                                 R Char t      Last 2 4 Subgr oups                                     Nor mal Pr ob Plot
                                                                                                                        Capabilit y Plot
                                                                                                       A D: 0.421, P: 0.320
                                                                                                                Within                    Within                    Over
                            56
Specifications
                                                                    _
                                                                    _                                                                LSL 54.5
                                                                    X= 54.913                                                        USL 55.5

                                         1
                                                   Six pack Bender Analysis
                                                                    LCL= 53.833
3    5     7    9        11   13    15   17   19        21   23
d with unequal sample sizes                                                           53.4   54.0   54.6   55.2   55.8     56.4

                   R Char t                                                                          Nor mal Pr ob Plot
         Defect opportunities                                            2                           A D: 0.421, P: 0.320
         Events observed                                             140
                                                                    UCL= 1.877

         Defects made (include defects fixed)                       _ 56
                                                                    R= 0.574

         DPO (defects per opportunity)                              LCL= 0
                                                                   0.200
3    5     7    9        11   13    15   17   19        21   23
       Yield
d with unequal sample sizes                                       80.00%                            54.0                 55.5                57.0

         Process Sigma oups
             Last 2 4 Subgr                                       ~2.4                               Capabilit y Plot
                                                                                       Within               Within                     Over all
                                                                                  StDev 0.5092                                    StDev 0.5987
                                                                                  Cp    0.33                                      Pp     0.28
                                                                                  Cpk   0.27               O v erall              Ppk    0.23
                                                                                  PPM   333124.40                                 Cpm    *
                                                                                                                                  PPM    408572.88
                                                                                                            Specs
     5              10              15             20
                          Sam ple


                         Our Bender D-11 is not capable to perform within +/-.5 degree specs
DMAIC




                    Measure




                                               s
                                            es s
                                          oc
                                        Pr alysi
                       2




                                         an
        Define




                                                   ari
                                              lti-V
          1




                                           Mu
                                            Cause
                                                       on
                                            organizati
                              Analyze
                                 3
                                            Hipotesis
                                            verification
        Control




                                          Reg
          5




                  Improve                     re   s ion
                                        Do
                                          E
                     4
Multi-vari analysis
                               Mai n Ef f ect s Pl ot f or Cur r ent
                                               Data Means
                          Angle parameter                                           date
        55.50


        55.25


        55.00
 Mean




        54.75


        54.50



                  .3     .5      .6       .7        .8         v v v v ec ec ec e c ec ec e c ec ec ec
                11     11      11      11         11         No No No No D D D D D D D D D D
                                                         2 4- 25 - 26- 30- 1- 2- 3- 8 - 9- 1 0- 13 - 14- 15- 1 6-



The Encoder misread angle position, We use a cross reference table to set the angle
Time series Plot by angle
                                         set
                               Ti me Ser i es Pl ot of Cur r ent
          56.5                                                                     Angle
                                                                               parameter
                                                                                    11.3
          56.0
                                                                                    11.5
                                                                                    11.6
                                                                                    11.7
          55.5
                                                                                    11.8


          55.0
 urrent




          54.5
C




          54.0

          53.5

          53.0
                 1   14   28   42   56      70  84    98   112     126   140
                                         I ndex



We will likely look for extremes in order to see potential DOE variable
Facts about Bend precision
●
    Angle Precision vs Speed
    – Equipment states that Angle precision and speed are
      inversely proportional; If we increase speed, the
      result angle is less precise.
    – the equipment is capable to decelerate the upper
      piston speed almost at the end of the bend cycle.
    – The set up is obtained by the constants of
      deceleration and proportional of speed.
    – More details can be found in the equipment’s display.
    – Based on this, we determine the variables to use in
      our DOE.
DOE Matrix and Results.
 Std    Center    Run                                     Prop.       Result   Result
Order     Pt     Order   Blocks   P1    P2     Speed   deceleration     1        2
 14       1        1       1      950   1600    0.8        10.00       89.3     89.3
  3       1        2       1      700   1800    0.5        1.00        83.3     85.2
 13       1        3       1      700   1600    0.8        10.00       89.1     88.4
  4       1        4       1      950   1800    0.5        1.00        85.4     86.2
 11       1        5       1      700   1800    0.5        10.00       89.6     88.9
 15       1        6       1      700   1800    0.8        10.00       89.6     89.2
  8       1        7       1      950   1800    0.8        1.00        84.3     87.1
 16       1        8       1      950   1800    0.8        10.00        89      89.6
  6       1        9       1      950   1600    0.8        1.00        86.4      87
 10       1       10       1      950   1600    0.5        10.00       89.6     89.6
  7       1       11       1      700   1800    0.8        1.00        84.6     86.1
 12       1       12       1      950   1800    0.5        10.00       89.4     89.5
  2       1       13       1      950   1600    0.5        1.00        86.4     88.1
  1       1       14       1      700   1600    0.5        1.00        84.7     86.4
  9       1       15       1      700   1600    0.5        10.00       88.8     89.7
  5       1       16       1      700   1600    0.8        1.00        84.8     86.3
Results of DOE
                          Ti me Ser i es Pl ot of Resul t
         90


         89


         88


         87
Result




         86


         85

         84

         83
              3    6      9     12     15      18     21    24   27    30
                                         I ndex
                                      Sample order



              Results of DOE to be normal due variation as expected.
Marginal Plots
                     Mai n Ef f ect s Pl ot f or Resul t
                                   Data Means
                    P1                                      P2
       89

       88

       87

       86
Mean




            700              950                 1600              1800
                   Speed                                   Prop.
       89

       88

       87

       86

            0.5              0.8                  1.00             10.00



Proportional deceleration has the main effect for the desired result
Interaction Plot
             I nt er act i on Pl ot f or Resul t     Data Means
              1600        1800   0.5           0.8   1.00           10.00
                                                                            90.0




                                                                            87.5
   P1
                                                                                    P1
                                                                                   700
                                                                            85.0
                                                                            90.0
                                                                                   950



                                                                            87.5     P2
                     P2
                                                                                   1600
                                                                                   1800
                                                                            85.0
                                                                            90.0


                                                                                   Speed
                                                                            87.5      0.5
                                       Speed
                                                                                      0.8

                                                                            85.0




                                                            Prop.



Between Factors, Proportional of deceleration has the main effect for the
desired result
Conclusion of DOE
                    Dot Pl ot of Pr opor t i onal of decel er at i on
                                  95% CI for the Mean
            90



            89



            88
    Dat a




            87



            86



            85
                          1                                       10



Higher proportional of deceleration factor has the main effect for the desired
result
Time Series of DOE
                                Ti me Ser i es Pl ot
                           Proportional deceleration change
          90

          89

          88

          87
Degr ee




          86

          85

          84

          83
               3   6       9     12     15      18      21    24        27   30
                       1                                           10
DMAIC




                                      5               1
                                   CONTROL          DEFINE

Soluti
         ons

                                   4
                                IMPROVE                  2
 FMEA                                                 MEASURE

                 s
         t   test
    Pilo                                     3
                                          ANALYZE
                           an
                      pl
                  n
                io
             Act
Pilot test Results
                                 Ti me Ser i es Pl ot of Cur r ent -pi l ot
                 56.5

                 56.0
                                                                                                UCL
                 55.5
  urrent-pilot




                 55.0                                                                           Mean

                                                                                                LCL
                 54.5
 C




                 54.0

                 53.5

                 53.0
                        1   17   34     51      68       85     102    119    136   153   170
                                                       I ndex




Pilot Test results show and improvement in bend accuracy.
Box Plot Pilot
                                     Box pl ot of Cur r ent , Pi l ot
             56.5


             56.0

                                                                                      USL
             55.5

                                                                                      Mean
             55.0
     Dat a




             54.5                                                                     LSL


             54.0
                    IQ Range = 0.8                           IQ Range = 0.4

             53.5


             53.0
                                 Current                                      Pilot




Box Plot shows IQ range improvement of 0.4
Solution Grid
                             Solution                            Status      Responsible    Due date           Comments

Run pilot test to validate constant of deceleration sets. 60
                                                                 Closed        Team           3/7
Pieces run thru all process
                                                                             Jorge
Conduct a SMED event in D-11 Bender to improve set-up time       Closed                      5/18
                                                                           Castellanos
Setup all part numbers parameters and save them in the                                                 Set-up technitians were
equipment to avoid missing information due set up technician     Closed   Jesus Fonseca      3/25      trained to load and save
change/absence.                                                                                           parts in equipment
                                                                                                       Parameters reviewed and
Bender Equipment Parameters training to personnel                Closed     Mario Ruiz       3/15
                                                                                                         saved in equipment
Perform TPM to assure proper bender operation and set
preventive maintenance schedule (oil leaks repair, change worn   Closed   Ramon Garcia
parts)
                                                                                                           Trouble shooting
                                                                                                        completed, will prepare
Develop a trouble shooting manual for Bender equipment           Closed   Ramon Garcia
                                                                                                        info in binder to deliver
                                                                                                               production
Welding fixtures maintenance and verification to assure                                                Welding fixtures reviewed
                                                                 Closed   Ramon Garcia       3/25
dimensions                                                                                                 and pass specs.
                                                                                                       Review with Pines model
Reset Encoder to absolute 0 degrees                              Closed   Hector Elizondo    4/05
                                                                                                          & serial number.

Develop new inspection fixtures (go-no go).                      Closed     Mario Ruiz                  QC certified the fixture
Summary
 Description     Before   After    Results   Annual savings   Improvement
                                                                   %
Monthly Lost     $292      $3       $288          $3,461        98.92%
  hours
Scrap Report     $3,102   $852     $2,250        $27,000        72.53%
Incorrect Bend   $1,705    $14     $1,691        $20,292        99.16%
 Rework cost     $2,972    $32     $2,940        $35,279        98.91%

                    Lean Initiatives cost reduction
                                                 Annual       Improvement
    Model        Before    After   Results
                                                 savings           %
12050-37-85VA    $62.09   $59.61    $2.48         $8,683        4.00%
12050-37-86VA    $66.84   $65.31    $1.53        $52,044        2.29%
12120-37-746     $85.07   $83.34    $1.73        $23,793        2.03%
12122-37-746     $84.25   $82.53    $1.71         $2,142        2.03%
 12122-37-23     $88.47   $86.67    $1.80         $2,249        2.03%


                 Annual cost Savings                       $171,482.00
DMAIC




                                 1
                               DEFINE           2
                                             MEASURE

Monit
      or   i ng

                              5                      3
Evaluating                 CONTROL                ANALYZE
 results


            ion
        ntat
    ume
 Doc                                       4
                                        IMPROVE
                      re
                  o su
             Cl
Monitoring
●
    As a method to constantly review bend
    performance, Team has implemented to
    check the bend at the beginning of the run,
    every 10 pieces and the last piece, this has
    helped understand variation and correct as
    necessary.
●
    Scrap and Rework has been dramatically
    reduced.
Scrap monitoring
$6,000.00

$5,000.00
                     2010        2011
$4,000.00

$3,000.00

$2,000.00

$1,000.00

   $0.00
            Ja n   Feb   Ma r   Apr   Ma y   Jun   Jul   Aug   Sep   Oct   Nov   Dec



Average 2010 scrap related to Bend defects was $ 1,979.44
2011 up-to-date scrap average $110. 37
Rework cost
                           Rework cos ts 2011

  $60.00

  $50.00

  $40.00

  $30.00

  $20.00

  $10.00

    $-
            Ja n     Feb        Ma r            Apr   Ma y   Jun



Average 2010 rework cost related to Bend defects was $ 2,971.92
2011 up-to-date scrap average $35.39
6 sigma rollators update for my blog

More Related Content

What's hot

Ssmfpl ppt vj
Ssmfpl ppt vjSsmfpl ppt vj
Sherif Labib Resume
Sherif Labib Resume Sherif Labib Resume
Sherif Labib Resume
Rabso
 
Rap presentation
Rap presentationRap presentation
Rap presentation
RAP
 
My talk at PMI Sweden Congress 2013 on Agile and Large Software Products
My talk at PMI Sweden Congress 2013 on Agile and Large Software ProductsMy talk at PMI Sweden Congress 2013 on Agile and Large Software Products
My talk at PMI Sweden Congress 2013 on Agile and Large Software Products
Svante Lidman
 
Agile Is From Mars Usability is From Venus
Agile Is From Mars Usability is From VenusAgile Is From Mars Usability is From Venus
Agile Is From Mars Usability is From Venus
Teale Shapcott
 
Omnext Source2VALUE
Omnext Source2VALUEOmnext Source2VALUE
Omnext Source2VALUE
meijerandre
 
DfSS Webinar Part 1: An Introduction to DFSS
DfSS Webinar Part 1: An Introduction to DFSSDfSS Webinar Part 1: An Introduction to DFSS
DfSS Webinar Part 1: An Introduction to DFSS
mjames1
 
Product Development
Product  DevelopmentProduct  Development
Product Development
Udit C
 
Vidhya Sr QC Resume
Vidhya Sr QC ResumeVidhya Sr QC Resume
Vidhya Sr QC Resume
Vidya Chandodi
 
Exp Engineering Oil Gas
Exp Engineering Oil GasExp Engineering Oil Gas
Exp Engineering Oil Gas
Eric Wilkinson
 
Icc Broadband Presintation
Icc Broadband PresintationIcc Broadband Presintation
Icc Broadband Presintation
guestab1691
 
TAI Food &amp; Beverage
TAI Food &amp; BeverageTAI Food &amp; Beverage
TAI Food &amp; Beverage
elyarrick
 
Exp Engineering Oil Gas
Exp Engineering Oil GasExp Engineering Oil Gas
Exp Engineering Oil Gas
Akturner1
 
Ch03 the requirements_specification
Ch03 the requirements_specificationCh03 the requirements_specification
Ch03 the requirements_specification
Napex Terra
 
GourangDeshpande_JDE_Technical_CV
GourangDeshpande_JDE_Technical_CVGourangDeshpande_JDE_Technical_CV
GourangDeshpande_JDE_Technical_CV
Gourang Deshpande
 

What's hot (15)

Ssmfpl ppt vj
Ssmfpl ppt vjSsmfpl ppt vj
Ssmfpl ppt vj
 
Sherif Labib Resume
Sherif Labib Resume Sherif Labib Resume
Sherif Labib Resume
 
Rap presentation
Rap presentationRap presentation
Rap presentation
 
My talk at PMI Sweden Congress 2013 on Agile and Large Software Products
My talk at PMI Sweden Congress 2013 on Agile and Large Software ProductsMy talk at PMI Sweden Congress 2013 on Agile and Large Software Products
My talk at PMI Sweden Congress 2013 on Agile and Large Software Products
 
Agile Is From Mars Usability is From Venus
Agile Is From Mars Usability is From VenusAgile Is From Mars Usability is From Venus
Agile Is From Mars Usability is From Venus
 
Omnext Source2VALUE
Omnext Source2VALUEOmnext Source2VALUE
Omnext Source2VALUE
 
DfSS Webinar Part 1: An Introduction to DFSS
DfSS Webinar Part 1: An Introduction to DFSSDfSS Webinar Part 1: An Introduction to DFSS
DfSS Webinar Part 1: An Introduction to DFSS
 
Product Development
Product  DevelopmentProduct  Development
Product Development
 
Vidhya Sr QC Resume
Vidhya Sr QC ResumeVidhya Sr QC Resume
Vidhya Sr QC Resume
 
Exp Engineering Oil Gas
Exp Engineering Oil GasExp Engineering Oil Gas
Exp Engineering Oil Gas
 
Icc Broadband Presintation
Icc Broadband PresintationIcc Broadband Presintation
Icc Broadband Presintation
 
TAI Food &amp; Beverage
TAI Food &amp; BeverageTAI Food &amp; Beverage
TAI Food &amp; Beverage
 
Exp Engineering Oil Gas
Exp Engineering Oil GasExp Engineering Oil Gas
Exp Engineering Oil Gas
 
Ch03 the requirements_specification
Ch03 the requirements_specificationCh03 the requirements_specification
Ch03 the requirements_specification
 
GourangDeshpande_JDE_Technical_CV
GourangDeshpande_JDE_Technical_CVGourangDeshpande_JDE_Technical_CV
GourangDeshpande_JDE_Technical_CV
 

Similar to 6 sigma rollators update for my blog

About Agile & PMI Agile Certified Practitioner (PMI-ACP) Overview
About Agile & PMI Agile Certified Practitioner (PMI-ACP) OverviewAbout Agile & PMI Agile Certified Practitioner (PMI-ACP) Overview
About Agile & PMI Agile Certified Practitioner (PMI-ACP) Overview
Aleem Khan
 
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
John Carter
 
C V
C VC V
Rosalin Ghosh_Resume_Testing_8 Yrs Experience
Rosalin Ghosh_Resume_Testing_8 Yrs ExperienceRosalin Ghosh_Resume_Testing_8 Yrs Experience
Rosalin Ghosh_Resume_Testing_8 Yrs Experience
Rosalin Ghosh
 
PMBOK and Scrum: Best of both worlds
PMBOK and Scrum: Best of both worldsPMBOK and Scrum: Best of both worlds
PMBOK and Scrum: Best of both worlds
Silvana Wasitova, Scrum & Agile Coach
 
Strategies for Implementing Aras Innovator
Strategies for Implementing Aras InnovatorStrategies for Implementing Aras Innovator
Strategies for Implementing Aras Innovator
Aras
 
Hi Performance Manufacturing
Hi Performance ManufacturingHi Performance Manufacturing
Hi Performance Manufacturing
Alex Diong
 
Vehicle cost weight process improvement 2011
Vehicle cost weight process improvement 2011Vehicle cost weight process improvement 2011
Vehicle cost weight process improvement 2011
tmtrnr
 
Luis Leyva-Flores Plastics
Luis Leyva-Flores PlasticsLuis Leyva-Flores Plastics
Luis Leyva-Flores Plastics
Luis LeyvaFlores
 
Resume
ResumeResume
Lightweighting , Vehicle,
Lightweighting , Vehicle,Lightweighting , Vehicle,
Lightweighting , Vehicle,
tmtrnr
 
CV_Sreenivas_Halappa
CV_Sreenivas_HalappaCV_Sreenivas_Halappa
CV_Sreenivas_Halappa
Sreenivas H
 
Influences on Agile Practise Tailoring in Enterprise Software Development
Influences on Agile Practise Tailoring in Enterprise Software DevelopmentInfluences on Agile Practise Tailoring in Enterprise Software Development
Influences on Agile Practise Tailoring in Enterprise Software Development
Agile Software Community of India
 
QM-009-Design for Six Sigma 2
QM-009-Design for Six Sigma 2QM-009-Design for Six Sigma 2
QM-009-Design for Six Sigma 2
handbook
 
Engineering solutions
Engineering solutionsEngineering solutions
Engineering solutions
Genpact Ltd
 
Alan Berow Process Engineer Resume
Alan Berow Process Engineer ResumeAlan Berow Process Engineer Resume
Alan Berow Process Engineer Resume
AlanBerowLSSGBCSM
 
Resume
ResumeResume
Steve Taylor Resume
Steve Taylor ResumeSteve Taylor Resume
Steve Taylor Resume
bucki4life94
 
Synergy6.5 Change4.7 Ecp
Synergy6.5 Change4.7 EcpSynergy6.5 Change4.7 Ecp
Synergy6.5 Change4.7 Ecp
Bill Duncan
 
Agile Development Overview
Agile Development OverviewAgile Development Overview
Agile Development Overview
guestb4c770
 

Similar to 6 sigma rollators update for my blog (20)

About Agile & PMI Agile Certified Practitioner (PMI-ACP) Overview
About Agile & PMI Agile Certified Practitioner (PMI-ACP) OverviewAbout Agile & PMI Agile Certified Practitioner (PMI-ACP) Overview
About Agile & PMI Agile Certified Practitioner (PMI-ACP) Overview
 
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
 
C V
C VC V
C V
 
Rosalin Ghosh_Resume_Testing_8 Yrs Experience
Rosalin Ghosh_Resume_Testing_8 Yrs ExperienceRosalin Ghosh_Resume_Testing_8 Yrs Experience
Rosalin Ghosh_Resume_Testing_8 Yrs Experience
 
PMBOK and Scrum: Best of both worlds
PMBOK and Scrum: Best of both worldsPMBOK and Scrum: Best of both worlds
PMBOK and Scrum: Best of both worlds
 
Strategies for Implementing Aras Innovator
Strategies for Implementing Aras InnovatorStrategies for Implementing Aras Innovator
Strategies for Implementing Aras Innovator
 
Hi Performance Manufacturing
Hi Performance ManufacturingHi Performance Manufacturing
Hi Performance Manufacturing
 
Vehicle cost weight process improvement 2011
Vehicle cost weight process improvement 2011Vehicle cost weight process improvement 2011
Vehicle cost weight process improvement 2011
 
Luis Leyva-Flores Plastics
Luis Leyva-Flores PlasticsLuis Leyva-Flores Plastics
Luis Leyva-Flores Plastics
 
Resume
ResumeResume
Resume
 
Lightweighting , Vehicle,
Lightweighting , Vehicle,Lightweighting , Vehicle,
Lightweighting , Vehicle,
 
CV_Sreenivas_Halappa
CV_Sreenivas_HalappaCV_Sreenivas_Halappa
CV_Sreenivas_Halappa
 
Influences on Agile Practise Tailoring in Enterprise Software Development
Influences on Agile Practise Tailoring in Enterprise Software DevelopmentInfluences on Agile Practise Tailoring in Enterprise Software Development
Influences on Agile Practise Tailoring in Enterprise Software Development
 
QM-009-Design for Six Sigma 2
QM-009-Design for Six Sigma 2QM-009-Design for Six Sigma 2
QM-009-Design for Six Sigma 2
 
Engineering solutions
Engineering solutionsEngineering solutions
Engineering solutions
 
Alan Berow Process Engineer Resume
Alan Berow Process Engineer ResumeAlan Berow Process Engineer Resume
Alan Berow Process Engineer Resume
 
Resume
ResumeResume
Resume
 
Steve Taylor Resume
Steve Taylor ResumeSteve Taylor Resume
Steve Taylor Resume
 
Synergy6.5 Change4.7 Ecp
Synergy6.5 Change4.7 EcpSynergy6.5 Change4.7 Ecp
Synergy6.5 Change4.7 Ecp
 
Agile Development Overview
Agile Development OverviewAgile Development Overview
Agile Development Overview
 

6 sigma rollators update for my blog

  • 1. Improve Quality in MS and Brazing Rollators Area
  • 2. DMAIC 1 DEFINE IMPROVE
  • 3. Project Signature Page: Sponsor: I commit to support the successful completion of this project by: • Ensuring that the project is aligned with overall organization goals • Providing personnel and resources • Removing roadblocks and barriers • Allotting time to hear progress reports from the team and provide meaningful feedback Approval Signed: Imelda Salas Name Date Director of Operations Title Champion: I commit to support the successful completion of this project by: • Arranging Lean Sigma training for the team, as necessary • Coordinating available resources and support • Conducting frequent reviews of the team's progress Signed: Javier Estrada Name Date Engineering and Lean Manager Title Team: We commit to contributing to the successful completion of this project by: • Applying the Lean Sigma methodology to make sustainable improvements to key metrics • Contributing our knowledge, ideas, and experiences • Attending scheduled meetings and events • Completing all assigned action items • Communicating project progress to the Champion and Sponsor Signed: Gladys Quiroz Mfg. Engineer / Floor Support Name Title / Role Date Eusebia cedillo Quality Engineer / Floor Support Name Title / Role Date Jorge Sanchez Gral. Supervisor / Prodcution Name Title / Role Date Alejandro Perez Project Engineer / Projects Name Title / Role Date Jorge Castellanos Lean Department / Plant Name Title / Role Date Ramon Garcia Gral. Supervisor / Tool Room Name Title / Role Date Name Title / Role Date
  • 4. Project contract Lean Six Sigma Project Contract Name of Project: Improve Quality in MS and Brazing Area - Rollator Models Business Driver(s): Examples include Production Increase, Cost Reduction, Capital Avoidance Estimated Start Date: 10/15/2010 Estimated Completion Date: 5/15/2011 Estimated COPQ: Metric(s) to be Improved: List the metric(s) that you expect to affect and whether Provide an estimated cost of poor quality. you expect them to increase, decrease, etc. (IPO ouptuts) Project Objective Reduce the dimensional variation on the frame and cross bar of the rollators model. Business Objective Invrease Productivity, Delivery and Reduce Cost Definition of a Defect: Eliminate mis balance and three wheeling In Project Scope: Not in Project Scope: Tubing, Tube benders, Piercing, Notching and Painting, purchased components and Final Assembly welding Vision of Success: Apply some Lean Manufacturing concepts such as 5"S, Quick Set Ups, Overproduction,etc,. Then we will recolect data from the equipment mentioned above in order to find the root cause using statatistic tools, the reduce the variation of the processes.
  • 6. Core Team • Sponsor – Imelda Salas • Champion – Javier Estrada Black Belt – Mario Ruiz Team members Support Members – Gladys Quiroz ( Engineering) – Carlos Gonzalez (Finance) – Eusebia Cedillo (Quality) – Hector Elizondo (Maintenance) – Jorge Sanchez (Production) – Edilberto Reyes (HR & Safety) – Alejandro Perez (Engineering) – Jorge Castellanos (Lean Mfg) – Ramon Garcia (Tool Room) – Jesus Fonseca (Production)
  • 7. PROJECT SCOPE ● Objective: Reduce the dimensional variation on the frame and cross bar of the rollator models ● Business Objective: Increase productivity, delivery and reduce cost ● Problem Statement (s): – Reduce rejects at the Final Assembly area – Increase delivery time – Increase production base on the resources assigned – Reduce scrap
  • 9. VOC Customer Interview 1. What process are we working on? • Rollators (Machine Shop & Brazing) 1. What is the process objective (voice of the customer and/or business)? • Reduce and Eliminate rework and scrap due cross folding and three wheeling 1. Has the customer been interviewed to confirm the VOC? • Yes 1. What is the project business objective (COPQ)? • While eliminating this type of defects we minimize the chances of shipping bad product to our customers. We will also improve our safety and ergonomics eliminating the risk for a long term injuries. We can increase our production velocity, reduce the inspection time and material handling. 1. What does success look like (project goals)? • Hit Target: What is the target? – Feb 2011 for hand off training and Owner sign off • Minimize: to what level, cost or effort? – 80% Rework / Scrap reduction for cross folding and three wheeling • Robustness: To what degree? – Maxi and Legacy Rollators regardless of the customer
  • 10. VOC 6. How long had this issue been present? Employee and supervisors interviews states that three wheeling has been since product initiated production, and cross folding control became due a some customer complains. What has been done about it so far? Some tooling and process correction and 100% inspection at final assembly thru kaizen events. 7. Construct an Input, Process, Output diagram of the process. Outputs need to be measurable, in units, and possibly normalized. Use continuous data when possible. All outputs need to represent the voice of the customer or business. SUPPLIER INPUT PROCESS OUTPUT CUSTOMER Target Materials Raw Material H.Resources SOP's Delivery increase 95% <= 2 Days Government Process Eng. Manpower Machine Shop Airlines Maintenance Training Scrap Reduction 70% Parks Industrial Eng Equipment Brazing Farmacies Prod. Sup. Machines FPY 98% Warehouses Safety Parameter Homecare Utilities WIP Reduction 60% DC’s
  • 11. VOC 8. Do you have baseline data for the outputs? • Yes, there are scrap and first pass yield reports • Measurements of the product were given but new parameters needed to be set up due to new tooling for bender equipment. 9. Can the project be completed (new controls in place) in 4-6 months? • Yes, it can be completed 10. What are the problem statement(s)? • Cross folding • Three wheeling • Dimensional capability 11. Do you have an idea of what is causing these issues? • Yes, potential dimensional variation during the machining and welding processes. Can that be supported with data? • Not at this time, we have to collect data from the source. 12. What prevents us from being in the desired state? • Machine capabilities • Process operator dependable 13. Is this process within our realm of influence? • Yes, if a major investment is required a Cap Ex must be issue and approved prior implementation
  • 12. VOC 14. Who are the stakeholders in this process? Suppliers Process Customers Others Participants Warehouse Cutting Paint Line Production Control Planning Bending Final Assembly Quality Production control Punching Maintenance Welding Tool Room Piercing Engineering 15. Who should be on the project team? • Core Team – multi-task employees with experience in this product.
  • 13. Value Stream Map (Current state)
  • 14. Cost of Poor Quality $70,000 Total $119,997 $60,000 $50,000 $40,000 $30,000 $20,000 8 3 8 19 13 08 60 46 16 $10,000 ,4 ,1 ,5 3, 0, 4, $2 $6 $8 $1 $4 $3 $- F.A. Rework F.A. Scrap cost Brazing Brazing Scrap Bend Rework Bend Scrap cost Rework cost cost cost cost Yearly rework cost: $35,663 Yearly Scrap cost: $84,335
  • 15. Units In c or r ec 0 1000 1500 2000 2500 3000 3500 4000 500 t Be Se nd t -u pf M 3508 at ai lur er ial e 857 re lat Be ed nd fl a tn 503 es To ol s in 440 gd en t 209 we Ox l id di e ng 92 f ai lur Ba e d 68 fo In rm c or in r ec g t 40 len Defects Pareto gt M h 37 et al de nt 25
  • 16. Bend Defect Pareto 90% 77% Incorrect Bend degree 80% 70% 60% 50% 40% 30% 20% 13% 7% 10% 3% 0% Bender D-11 Press P54 Welding Chrome fixture 77% of bend defects relates to bender equipment
  • 17. FMEA Process: Machine Shop Process Responsibility: Alejandro Perez Component: 13347 BACK FRAME LEGACY 600 Creation Date: 4/07/2010 Team: Rollator TEAM Revision Date: 9/10/2010 Requirements Failure Mode(s) Effect(s) of Failure Cause(s) of Process Control(s) Recommended Solution(s) Resp & Target Date SEV OCC DET RPN SEV OCC DET RPN Failure -Bring tubing cut to length from M. Granados 4 First piece and last piece audit 4 64 supplier -Cut machine set-up 4 4 4 64 short or long Misalignment of side tubes on Bad cut Manufacturing Tube cut length 4 check list cut to length 13192 weldment fixture length Make sampling plan to use Go no Manufacturing/Qu 2 -Use of fixture Go no Go 3 24 4 2 3 24 Go ality Bender miss- -Monitoring pressure levels 4 3 60 TPM program 5 4 3 60 Maintenance Back frame will not match adjusted on bender with the front frame. The Incorrect preferably Use of Protractor Sampling program to verify Manufacturing/Eng Angles within +/- Angles out of 3 3 45 5 3 3 45 Rollator will not have 5 bender set- Go no Go as a secondary correct bend on tubing. ineering 0.5 degree Spec Spec limits Go no Go symmetrical structure. Check list to verify Go no Go uses. Manufacturing/Eng Potential Three wheeling. fixture not 4 Training/Supervision 3 60 5 4 3 60 State in the work instructions. ineering in use Sampling plan or revalidation holes location & Incorrect holes 4 3 60 Process re-validation 5 4 3 60 Engineering Bad function of the folding Die miss- process. orientation location & 5 mechanism. adjusted State Go no Go use on work Manufacturing/Eng withing Spec. orientation 2 -Use of fixture Go no Go 2 20 5 2 2 20 instructions ineering Wrong -Identify bending dies per Put marks on bending dies & state bending 4 3 48 4 4 3 48 Manufacturing tubing to use on set-up instructions tools warehouse location for this tube 4 4 2 32 Warehouse Flatten bends -Customer Dissatisfaction 4 Wrong 4 -Identify tubing on warehouse 2 32 Tube cut to length from supplier tubing 4 4 2 32 M. Granados Apearance to prevent mixed material Bender non -Monitoring pressure levels 4 3 48 TPM program 4 4 3 48 Maintenance adjusted on bender Un- paint inspection before send to -Scrap, Quality complaints, Manufacturing/Qu Paint defects 3 appropriate 4 Quality inspection check list 3 36 final assembly & final assembly 3 4 3 36 Customer dissatisfaction ality paint rack area inspection before assemble.
  • 18. Measure Plan ● Team will measure the part numbers as follow: – Bend process: Angle on 1149178 y 1149181 left & right sides – Punching: Distance between holes and angles on 1150607 & 1150608 left and right sides – Welding: distance between sides and between holes on 1149177 ● Procedure: – Production will send 5 pieces of each run to metrology for 2 weeks • 1st piece, 3 more during the run and the last piece. • Set up Tech will record all process changes during the run in order to understand where is the variation. – The pieces will be delivered to metrology technician one by one; the measured pieces will be picked up and sent back to line. – Metrology lab will maintain the record and at the end of each shift, the record will be sent to the quality engineer. – Quality engineer will process the data and obtain the graphics
  • 19. 2010 Defects 12,000 M.S. Defects Brazing Defects F.A. Defects 10,000 04 4,3 8,000 29 3,4 18 28 Units 6,000 78 3,1 3,1 3, 059 9 2,9 2,8 7 9 1 0 7 46 9 7 2,2 2,2 2,2 3,9 4,000 84 39 5 9 5 0 4 41 3,1 2,5 2,7 6 2,8 2,9 2,8 73 2,6 4 9 8 6 2,1 27 385 4 1 2,000 2,0 2,0 6 556 16 1,0 264 329 6 60 29 2,4 02 82 87 748 59 45 61 84 1,7 1,7 1,7 09 1, 1,9 1,6 70 1,2 1,2 1,3 1,2 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan-11 2010 Significative improvement achieved for production to control runs and avoid mixing set-ups has helped reduce three wheeling.
  • 20. Three wheeling Defect Trend 9.00% 8% 9% 8.3 8.1 4% 8.00% 7.3 7.00% 6.00% 3% 4.8 8% 9% 5.00% 4.2 4.4 0% 0% 3.7 3.6 4.00% 2% 2.9 4% 3.00% 2.5 5% 1.9 2.00% 5% 0% 1.00% 0 .3 0.3 0.00% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan-11 2010 Nov 2010 Production started to control production orders for left and right sides of the frame.
  • 22. IPO Grid Bender Output Variables Distance Tube bend operation Bend between angle bends Length Total Weigh Factor 9 5 1 Speed 9 5 1 107 Die penetration 9 1 1 87 Pressure 9 5 1 107 Stops position 1 9 9 63 Process input Temperature 5 1 1 51 variables Lubrication 5 1 1 51 Forming dies 5 5 1 71 Tube strength 9 1 1 87 Tube position 1 5 5 39 Per our pareto graphs we weighed bend angle as our output variable to focus
  • 23. Time Series Plot 610 angle Run trial to establish our start point. • 20 pieces in Bend & Punch operations • Measured the 4 angles of the piece after each operation • Graph each Angle to compare Ti me Ser i es Pl ot of Angl e 1 , Max 1 , Mi n 1 , Punch 1 , Spec 1 62.0 Variable Angle 1 Max 1 61.5 Min 1 Punch 1 Spec 1 61.0 D a at 60.5 60.0 59.5 2 4 6 8 10 12 14 16 18 20 I ndex
  • 24. Interval plot 600 Angle 6 0 degr ee Bend Bef or e and Af t er bei ng pi er ced 95% CI for the Mean 61.0 60.9 60.8 60.7 Dat a 60.6 60.5 60.4 60.3 60.2 60 after pierce 1 Delta of mean = 0.255 degrees
  • 25. Hypothesis test for piercing process ● The Angle deformation made during piercing operation is statistically significant to deviate in +/-0.5 degrees  H0-0.50<m0>+0.50 Box pl ot of Z-t est  H1-0.50>m1<+0.50 (with Ho and 95% Z-confidence interval for the Mean, and StDev = 0.25) One-Sample T: Z-test Test of mu = 0.5 vs not = 0.5 Variable N Mean StDev SE Mean 95% CI T P Z-test 59 -0.0458 0.3164 0.0412 (-0.1282, 0.0367) -13.25 0.009 _ One-Sample T: Z-test X Ho Test of mu = -0.5 vs not = -0.5 Variable N Mean StDev SE Mean 95% CI T P Z-test 59 -0.0458 0.3164 0.0412 (-0.1282, 0.0367) 11.03 0.009 -0.75 -0.50 -0.25 0.00 0.25 0.50 Z- t est P-values range from 0 to 1. The smaller the p-value, the smaller the probability that rejecting the null hypothesis is a mistake Conclusion: The H0 is rejected as P value in both tests are 0.009
  • 26. Cause and effect analysis Cause-and-Ef f ect Di agr am Measurements Material Personnel Lenght Go-no go out of spec Lack of t raining Mat erial hardness lack of calibrat ion Mat erial inconsistency No experience improper measurement t ools walnut out of t olerance Bend Three Angle Wheeling Three process cont rols Wheeling equipment check up Welding process Safety factors t ooling lifecycle records prevent ive maint enance Operat or dependant set up parameters tooling condit ion Temperature t ube posit ion unstable pressure Set up t ools Environment Methods Machines
  • 27. Bend Data Sheet ● Pieces from the bend operation were measured and the results Ser i esshown 5in a ee Ti me are Pl ot of 5 degr control chart 56.5 56.0 55.5 USL 55 degree 55.0 Mean 54.5 LSL 54.0 1 13 26 39 52 65 78 91 104 117 I ndex
  • 28. Gage R&R Measure ● Gage R&R was performed to evaluate our measure system on: – Precision Gage Run Char t of Measur ement by Unit , Oper at or Reported by : Mario Ruiz Gage name: A ngle Tolerance: – Repeatability Date of study : 12/23/2010 Misc: – Reproducibility 1 2 3 4 5 O perator A B 35.25 35.10 Measur em ent Mean 34.95 34.80 34.65 34.50 Oper at or Panel variable: Unit Graph Shows measurement system is consistent between Operators using the Faro measurement tool
  • 29. ANOVA of Gage R&R Gage R& R ( A NOVA ) f or Measur ement Variation of the pieces, OK Reported by : Mario Ruiz Gage name: A ngle measurement Tolerance: 1 Major contributor of Date of study : 12/23/2010 Misc: variation is the parts, means, the measuring Com ponents of Variat ion Measurem ent by Unit system is correct 100 % Cont ribut ion % St udy Var 35.1 Percent 50 34.8 34.5 0 Gage R&R Repeat Reprod Par t-to-Part 1 2 3 4 5 Unit system is on control, R Chart by Operat or Measurem ent by Operator A B means operators are 0.10 UCL= 0.1004 Sam ple Range measuring almost the _ 35.1 0.05 R= 0.044 same, 34.8 0.00 LCL= 0 1 2 3 4 5 1 2 3 4 5 34.5 Unit A B Operat or Xbar Chart by Operat or A B Unit * Operat or I nteract ion Pieces are out of control, Sam ple Mean _ _ Operat or meaning measurement 35.1 UCL= 35.0761 X= 35.044 LCL= 35.0119 35.1 A Aver age B system is valid 34.8 34.8 34.5 1 2 3 4 5 1 2 3 4 5 34.5 Unit 1 2 3 4 5 Unit No interaction of operator if lines are almost parallel ANOVA to the measuring system shows our measurement system to be reliable
  • 30. Six pack Bender Analysis Process sigma, CP and Cpk wasi tdetermined C5 Pr ocess Capabi l y Si xpack of Xbar Char t Capabilit y Hist ogr am Data shows a LSL USL 56 UCL= 55.994 dispersion from Specif Sam ple Mean _ _ 53.83 to 55.99 LSL 55 X= 54.913 USL 54 1 LCL= 53.833 Pr 5ocess Capabi 15i t y Si xpack of C5 71 39 11 Tests performed with unequal sample sizes 13 l 17 19 21 23 53.4 54.0 54.6 55.2 55.8 56.4 Xbar Char t Capabilit y Hist ogr am R Char t LSL USL Nor mal Pr ob Plot UCL= 55.994 A D: 0.421, P: 0.320 Specifications Sa m ple Range 2 _ _ UCL= 1.877 LSL 54.5 Xbar shows data to X= 54.913 USL 55.5 1 be normal as well _ R= 0.574 0 as the histogram 1 LCL= 53.833 LCL= 0 7 11 139 15 17 19 21 23 1 3 5 7 9 11 13 15 17 19 21 23 equal sample sizes 53.4 54.0 54.6 55.2 55.8 56.4 Tests performed with unequal sample sizes 54.0 55.5 R Char t Last 2 4 Subgr oups Nor mal Pr ob Plot Capabilit y Plot A D: 0.421, P: 0.320 Within Within Over 56
  • 31. Specifications _ _ LSL 54.5 X= 54.913 USL 55.5 1 Six pack Bender Analysis LCL= 53.833 3 5 7 9 11 13 15 17 19 21 23 d with unequal sample sizes 53.4 54.0 54.6 55.2 55.8 56.4 R Char t Nor mal Pr ob Plot Defect opportunities 2 A D: 0.421, P: 0.320 Events observed 140 UCL= 1.877 Defects made (include defects fixed) _ 56 R= 0.574 DPO (defects per opportunity) LCL= 0 0.200 3 5 7 9 11 13 15 17 19 21 23 Yield d with unequal sample sizes 80.00% 54.0 55.5 57.0 Process Sigma oups Last 2 4 Subgr ~2.4 Capabilit y Plot Within Within Over all StDev 0.5092 StDev 0.5987 Cp 0.33 Pp 0.28 Cpk 0.27 O v erall Ppk 0.23 PPM 333124.40 Cpm * PPM 408572.88 Specs 5 10 15 20 Sam ple Our Bender D-11 is not capable to perform within +/-.5 degree specs
  • 32. DMAIC Measure s es s oc Pr alysi 2 an Define ari lti-V 1 Mu Cause on organizati Analyze 3 Hipotesis verification Control Reg 5 Improve re s ion Do E 4
  • 33. Multi-vari analysis Mai n Ef f ect s Pl ot f or Cur r ent Data Means Angle parameter date 55.50 55.25 55.00 Mean 54.75 54.50 .3 .5 .6 .7 .8 v v v v ec ec ec e c ec ec e c ec ec ec 11 11 11 11 11 No No No No D D D D D D D D D D 2 4- 25 - 26- 30- 1- 2- 3- 8 - 9- 1 0- 13 - 14- 15- 1 6- The Encoder misread angle position, We use a cross reference table to set the angle
  • 34. Time series Plot by angle set Ti me Ser i es Pl ot of Cur r ent 56.5 Angle parameter 11.3 56.0 11.5 11.6 11.7 55.5 11.8 55.0 urrent 54.5 C 54.0 53.5 53.0 1 14 28 42 56 70 84 98 112 126 140 I ndex We will likely look for extremes in order to see potential DOE variable
  • 35. Facts about Bend precision ● Angle Precision vs Speed – Equipment states that Angle precision and speed are inversely proportional; If we increase speed, the result angle is less precise. – the equipment is capable to decelerate the upper piston speed almost at the end of the bend cycle. – The set up is obtained by the constants of deceleration and proportional of speed. – More details can be found in the equipment’s display. – Based on this, we determine the variables to use in our DOE.
  • 36. DOE Matrix and Results. Std Center Run Prop. Result Result Order Pt Order Blocks P1 P2 Speed deceleration 1 2 14 1 1 1 950 1600 0.8 10.00 89.3 89.3 3 1 2 1 700 1800 0.5 1.00 83.3 85.2 13 1 3 1 700 1600 0.8 10.00 89.1 88.4 4 1 4 1 950 1800 0.5 1.00 85.4 86.2 11 1 5 1 700 1800 0.5 10.00 89.6 88.9 15 1 6 1 700 1800 0.8 10.00 89.6 89.2 8 1 7 1 950 1800 0.8 1.00 84.3 87.1 16 1 8 1 950 1800 0.8 10.00 89 89.6 6 1 9 1 950 1600 0.8 1.00 86.4 87 10 1 10 1 950 1600 0.5 10.00 89.6 89.6 7 1 11 1 700 1800 0.8 1.00 84.6 86.1 12 1 12 1 950 1800 0.5 10.00 89.4 89.5 2 1 13 1 950 1600 0.5 1.00 86.4 88.1 1 1 14 1 700 1600 0.5 1.00 84.7 86.4 9 1 15 1 700 1600 0.5 10.00 88.8 89.7 5 1 16 1 700 1600 0.8 1.00 84.8 86.3
  • 37. Results of DOE Ti me Ser i es Pl ot of Resul t 90 89 88 87 Result 86 85 84 83 3 6 9 12 15 18 21 24 27 30 I ndex Sample order Results of DOE to be normal due variation as expected.
  • 38. Marginal Plots Mai n Ef f ect s Pl ot f or Resul t Data Means P1 P2 89 88 87 86 Mean 700 950 1600 1800 Speed Prop. 89 88 87 86 0.5 0.8 1.00 10.00 Proportional deceleration has the main effect for the desired result
  • 39. Interaction Plot I nt er act i on Pl ot f or Resul t Data Means 1600 1800 0.5 0.8 1.00 10.00 90.0 87.5 P1 P1 700 85.0 90.0 950 87.5 P2 P2 1600 1800 85.0 90.0 Speed 87.5 0.5 Speed 0.8 85.0 Prop. Between Factors, Proportional of deceleration has the main effect for the desired result
  • 40. Conclusion of DOE Dot Pl ot of Pr opor t i onal of decel er at i on 95% CI for the Mean 90 89 88 Dat a 87 86 85 1 10 Higher proportional of deceleration factor has the main effect for the desired result
  • 41. Time Series of DOE Ti me Ser i es Pl ot Proportional deceleration change 90 89 88 87 Degr ee 86 85 84 83 3 6 9 12 15 18 21 24 27 30 1 10
  • 42. DMAIC 5 1 CONTROL DEFINE Soluti ons 4 IMPROVE 2 FMEA MEASURE s t test Pilo 3 ANALYZE an pl n io Act
  • 43. Pilot test Results Ti me Ser i es Pl ot of Cur r ent -pi l ot 56.5 56.0 UCL 55.5 urrent-pilot 55.0 Mean LCL 54.5 C 54.0 53.5 53.0 1 17 34 51 68 85 102 119 136 153 170 I ndex Pilot Test results show and improvement in bend accuracy.
  • 44. Box Plot Pilot Box pl ot of Cur r ent , Pi l ot 56.5 56.0 USL 55.5 Mean 55.0 Dat a 54.5 LSL 54.0 IQ Range = 0.8 IQ Range = 0.4 53.5 53.0 Current Pilot Box Plot shows IQ range improvement of 0.4
  • 45. Solution Grid Solution Status Responsible Due date Comments Run pilot test to validate constant of deceleration sets. 60 Closed Team 3/7 Pieces run thru all process Jorge Conduct a SMED event in D-11 Bender to improve set-up time Closed 5/18 Castellanos Setup all part numbers parameters and save them in the Set-up technitians were equipment to avoid missing information due set up technician Closed Jesus Fonseca 3/25 trained to load and save change/absence. parts in equipment Parameters reviewed and Bender Equipment Parameters training to personnel Closed Mario Ruiz 3/15 saved in equipment Perform TPM to assure proper bender operation and set preventive maintenance schedule (oil leaks repair, change worn Closed Ramon Garcia parts) Trouble shooting completed, will prepare Develop a trouble shooting manual for Bender equipment Closed Ramon Garcia info in binder to deliver production Welding fixtures maintenance and verification to assure Welding fixtures reviewed Closed Ramon Garcia 3/25 dimensions and pass specs. Review with Pines model Reset Encoder to absolute 0 degrees Closed Hector Elizondo 4/05 & serial number. Develop new inspection fixtures (go-no go). Closed Mario Ruiz QC certified the fixture
  • 46. Summary Description Before After Results Annual savings Improvement % Monthly Lost $292 $3 $288 $3,461 98.92% hours Scrap Report $3,102 $852 $2,250 $27,000 72.53% Incorrect Bend $1,705 $14 $1,691 $20,292 99.16% Rework cost $2,972 $32 $2,940 $35,279 98.91% Lean Initiatives cost reduction Annual Improvement Model Before After Results savings % 12050-37-85VA $62.09 $59.61 $2.48 $8,683 4.00% 12050-37-86VA $66.84 $65.31 $1.53 $52,044 2.29% 12120-37-746 $85.07 $83.34 $1.73 $23,793 2.03% 12122-37-746 $84.25 $82.53 $1.71 $2,142 2.03% 12122-37-23 $88.47 $86.67 $1.80 $2,249 2.03% Annual cost Savings $171,482.00
  • 47. DMAIC 1 DEFINE 2 MEASURE Monit or i ng 5 3 Evaluating CONTROL ANALYZE results ion ntat ume Doc 4 IMPROVE re o su Cl
  • 48. Monitoring ● As a method to constantly review bend performance, Team has implemented to check the bend at the beginning of the run, every 10 pieces and the last piece, this has helped understand variation and correct as necessary. ● Scrap and Rework has been dramatically reduced.
  • 49. Scrap monitoring $6,000.00 $5,000.00 2010 2011 $4,000.00 $3,000.00 $2,000.00 $1,000.00 $0.00 Ja n Feb Ma r Apr Ma y Jun Jul Aug Sep Oct Nov Dec Average 2010 scrap related to Bend defects was $ 1,979.44 2011 up-to-date scrap average $110. 37
  • 50. Rework cost Rework cos ts 2011 $60.00 $50.00 $40.00 $30.00 $20.00 $10.00 $- Ja n Feb Ma r Apr Ma y Jun Average 2010 rework cost related to Bend defects was $ 2,971.92 2011 up-to-date scrap average $35.39

Editor's Notes

  1. La VOC es el último paso en la fase de Definir Desarrollar caso de negocio y directrices de equipo Esquema del proceso actual Escuchar la voz del cliente (VOC)