Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
2-3_3. tok
1. Jaroslav Pollert
Czech Technical University in Prague
Faculty of Civil Engineering
Department of Sanitary and Ecological Engineering
2. Outline
Ecological and economical
motivation
Development
Design description and
operational principle
Mathematical and
physical modelling
Installation
First specimens
Comparison with
conventional types
Conclusion and future
3. CSO - motivation
Collaboration with
HOBAS company
Using their production
Environmental pollution
from CSO
Decreasing of
suspended solids load
European Water
Framework directive
2000/60/EC
Easy installation and
operation
4. Development
Development in CTU
Physical model
Mathematical model
Main aim of the
development:
Simple construction
Cheap production
Easy installation
Decrease pollution load to
environment
Easy operation
Trouble free and safe
operation
5. TOK – Tube Combined Sewer Overflow
1200
Inflow part leads to
20
R1 0
accumulation chamber 600 600
100
R1 0
Scumboard protect overflow
against flotables which are
100
1200
R1
0
stored in accumulation chamer 600 600
R1 0
Shape of the overflow slit were
under development 200
1200
R1 0
200
6. Developing TOK
– mathematical and physical model
Overflow slit
Shape development for
decreasing suspended
solids overflow
Contraction of the slit
on the end of CSO
decrease turbulences
Comparison of
mathematical model
and physical model
7. Mathematical model
1200 1200
R10 R10
20
20
slit
Normal shape, scumboard, not too Normal shape, no scumboard, not too
linear pathlines linear pathlines
1200
R10
20 0
slit
20 0
R10
1200
Open shape on the end, scumboard, Open shape on the begining,
high turbulences on the end scumboard, linear pathlines
8. TOK Moravský Krumlov
Easy installation
2 pieces prepared in factory
2 manholes
Scumboard x cofferdam
Temporary outflow
13. Conclusion and future
Development of new CSO
Main aims were achieved
Mathematical model and physical model were
compared
Shape of the overflow slit were developed
Several TOKs were installed and more are planned
Moravský Krumlov, Děčín, Teplice …
Future – further development and improvement