This document summarizes the scope of work and schedule for the installation of two unmanned wellhead platforms, T-03 and TT-01, offshore Dubai. It includes: - Lifting scopes and weights for the jackets, decks, boat landings, and piles of each platform. - The job was awarded as an amendment to an existing EPCI contract and involves fast track design and installation of the skirted pile jacket platforms. - The schedule calls for fabrication of the jackets and decks from August 2015 to January 2016, installation by float-over in 10 days during February 2016, and mechanical completion by February 20th, 2016.