SlideShare a Scribd company logo
1 of 53
CONSTRUCTION OF PATENGA CONTAINER
TERMINAL (PCT) WHARF JETTY.
PROJECT INFORMATION :
 Project Owner : 34 EC BDE
 Mother Concern : CHITTAGONG PORT AUTHORITY
 Consultant : BRTC, BUET
 Contractor (JV) : CRBC – EEL CONSORTIUM
 Contract Agreement : 16 September’18
 Contract Value : 416.99 Crore Taka
 Revised value (Partly): 525.00 Crore Taka
 Length of Jetty : 72.80 m @ 08 nos BAY = 582.40 m
 Width of jetty : Variable from 45.4m to 69.4m
 Handed Over : 22nd September,2021 (As per revised schedule)
Scope of Work :
Yard development for construction of precast segment.
 RC sheet pile casting and driving.
 Casting of precast girder & Slab.
 PHC pile supply and driving.
 Pile cap casting i/c ins. of berthing block where it is required.
 Slope protection.
Scope of Work :
 Installation of Precast girder & Casting of cast in situ girder
 Installation of Precast Slab
 Installation of Fender
 Installation of Bollard
 Installation of QA Rail
 Installation of Ladder & Railing
Topography Map :
Work Progress
Yard Development (7.45 Acre):
(A) Dyke Development and project fencing
(B) Sand Filling and Land Compaction
(C) Palisading Works
(D) 60 & 35 Batching Plant (02 Nos) Installation
(E) Materials Stack Yard With Retaining Wall
(F) Employee Residence With Others Facility
(G) Labor Shed, Security Shed With Others Facility
RE - DESIGN AND Additional Works of Jetty
Increase volumn of Jetty Work:
SL No Major Items Unit
Previous Design
(Contract
Agreement)
Increased
Revised Design
(Additional &
Revised BOQ)
Increase %
1 Area of Jetty Sqm 25043 5951 30994 23.76%
2 Ø 1000 PHC Pile Nos 432 24 456 5.56%
3 Ø 900 PHC Pile Nos 344 152 496 44.19%
4 Pile Cap Nos 776 160 936 20.62%
5 Precast Slab Nos 904 126 1030 13.94%
6 Precast Beam Nos 552 136 688 24.64%
RE - DESIGN AND Additional Works of Jetty
Increase volumn of Jetty Work:
SL
No
Major Items Unit
Previous
Design
(Contract
Agreement)
Increased
Revised Design
( Additional &
Revised BOQ)
Increase %
7
Arranging for pile integrity test
(PIT)
Nos 0.00 952 952 100%
8 Boreholes and soil investigation Nos 0.00 8 8 100%
9
Additional trial piles includes 6
static load test piles and 18
Auxiliary piles, in total 24 piles.
LS 0.00 1 1 100%
RE - DESIGN AND Additional Works of Jetty
Increase volumn of Jetty Work:
SL
No
Major Items Unit
Previous Design
(Contract
Agreement)
Increased
Revised Design
( Additional &
Revised BOQ)
Increase
%
10
Manufacturing of RC Sheet pile
(each pile length 15.4 m)
Rm 0.00 18,668 18,668 100%
11
Driving of RC Sheet pile (each
pile length 15.4 m)
Nos 0.00 18,668 18,668 100%
12
Breast Wall of Retaining
Structure
Cum 1609.65
6,376 7,986 79.83%
Work Progress
Jetty Work:
(A) PHC (Anchor pile & Trial pile) Pile 24 nos has been driven in BAY B & BAY F (100%)
(B) Static Load test on trial pile = 06 nos / 06 nos (100%)
(C) RC sheet pile (450mm x 600mm x 15.4m) casting = 1173 pcs /1212 pcs (Complete)
(D) RC sheet pile driving = 1173 pcs /1212 pcs (Complete)
(E) PHC pile supply = 952 nos /952nos (100%)
(900 dia = 496 nos & 1000 dia = 456 nos, Total = 952 nos)
(F) PHC pile driving = 952 nos / 952 nos (100%)
(G) Precast Slab Casting = 394 nos / 1022 nos (38.55%)
(H) Precast Girder Casting = 442 nos / 688 nos (64.24%)
(I) Pile integrity test (PIT) = 537 nos / 952 nos (56.40%)
Work Progress
Jetty Work:
(J) High strain test = 48 nos / 48 nos (100%)
(K) Pile cap casting = 521 pcs / 936 pcs (55.66%)
(L) Precast girder placing = 271 pcs / 688 pcs (39.39%)
(M) Cast in situ girder casting = 880 rm / 6270 rm (14%)
(N) Breast wall casting = 577 rm / 772 rm (74.74%)
(O) Anchor wall casting = 457 rm / 772 rm (59.20%)
(P) Tie Rod Placing works = 108 nos / 644 nos (16.77%)
(Q) Dredging Works = 100666 cum / 139380 cum (72.22%)
(R) Riprap cleaning = 41500 sqm / 41500 sqm (100%)
Work Progress
PHC (TRIAL) PILE DRIVING RECORD IN BAY - B:
SL BAY TYPE OF PHC PILE
DIA OF PILE
(MM)
LENGTH OF PILE
(M)
TYPE OF SHOE PIT LOAD TEST
SETTLEMENT
(MM)
REMARKS
1
BAY
-
B
ANCHOR PILE, M1 1000 40 OPEN DONE
2 ANCHOR PILE, M2 1000 40 OPEN DONE
3 ANCHOR PILE, M3 1000 40 OPEN DONE
4 ANCHOR PILE, M4 1000 40 OPEN DONE
5 ANCHOR PILE, M5 900 40 OPEN DONE
6 ANCHOR PILE, M6 900 40 OEN DONE
7 ANCHOR PILE, M7 900 40 OPEN DONE
8 ANCHOR PILE, M8 900 40 OPEN DONE
9 ANCHOR PILE, M17 1000 40 OPEN
10 TRIAL PILE, S1 1000 39 CLOSE DONE 9.80
11 TRIAL PILE, S2 900 39 OPEN BROKEN
12 TRIAL PILE, S3 900 30 OPEN DONE 11.77
13 TRIAL PILE, S2 - 1 900 40 OPEN DONE 15.22
Work Progress
PHC (TRIAL) PILE DRIVING RECORD IN BAY - F:
SL BAY TYPE OF PHC PILE
DIA OF PILE
(MM)
LENGTH OF PILE
(M)
TYPE OF SHOE PIT LOAD TEST
SETTLEMENT
(MM)
REMARKS
14
BAY
-
F
ANCHOR PILE, M9 1000 40 OPEN
15 ANCHOR PILE, M10 1000 40 OPEN
16 ANCHOR PILE, M11 1000 40 OPEN
17 ANCHOR PILE, M12 1000 40 OPEN BROKEN
18 ANCHOR PILE, M13 900 40 OPEN
19 ANCHOR PILE, M14 900 40 OPEN
20 ANCHOR PILE, M15 900 40 OPEN
21 ANCHOR PILE, M16 900 40 OPEN
22 TRIAL PILE, S4 1000 40 OPEN DONE 10.33
23 TRIAL PILE, S5 900 38 CLOSE DONE 17.23
24 TRIAL PILE, S7 900 28 CLOSE DONE 10.96
Excavation, Dyke making & Protection at PCT ConstructionYard:
Sand Filling,Land Compaction & Palisading Works at PCT Yard:
60 & 35 Batching Plant (02 Nos) Installation at PCT Yard:
Materials Stack Yard With Retaining Wall:
Employee Residence, Canteen and Labor Shed with necessary
facility:
PHC Pile has driven in Jetty Side:
Static Load Test on PHC Pile & Pile Integrity Test in Jetty Side:
RC Sheet Pile Casting and Driving in Jetty Side:
Precast Slab and Girder casting in Yard Side:
RC Sheet Pile Head Breaking in Jetty Side:
Pile cap casting in Jetty Side:
Precast girder placing in Jetty Side:
Cast in situ girder casting in Jetty Side:
Dredging works in Jetty Side:
Dredging post survey and riprap cleaning works in Jetty Side:
Breast wall and Anchor wall works in Jetty Side:
Tie Rod Placing and FDD test for Gr. Improvement Works in Jetty Side:
380 Ton Crane Lifting Capacity as follows:
Weight Of Girder : 20.50 tons and lifting distance = 42 mtr.
length
Latest Revised Work Schedule:
Equipment/Assets Statement:
LIST OF EQUIPMENTS STATUS
Name Of Month:
September -2020
Date: 07.09.2020
SL.
No.
Name of
Equipment
EEL Code Model No
Present
Condition
Operator Name
Received
Date
Present
Location
Remarks
PCT Project
1 Batching Plant BP-01 POWERPAC-PBP350S Running Md Talab PCT Yard
2 Batching Plant BP-02 Zoomlion- JS1000 Running Md Khairul 14.02.2019 PCT Yard
3 Crawler Crane CR.C-01 Zoomlion- QUY380CL Running Md Raju 17.02.2019 Jetty Site
4 Crawler Crane CR.C-02 Zoomlion- QUY180CL Running
Md Saidul
Rahman
14.02.2019 Jetty Site
5 Crawler Crane CR.C-03 XCMG- XGC85 Running Md Ripon Miah 08.03.2019 Jetty Site
6 Crawler Crane CR.C-04 XCMG- XGC85 Running Md Juwel Sheikh 08.03.2019 Jetty Site
Equipment/ Assets Statement:
7 Rough Crane RT-01 Zoomlion-RT75 Running
Md Forhad
Hossain
14.02.2019 PCT Yard
8 Rough Crane RT-02 Zoomlion-RT35 Running
Md Rohul
Amin
14.02.2019 PCT Yard
9 Excavator EX-04 Zoomlion ZE210E Running
Md Jahirul
Hoque
14.02.2019 Jetty Site
10 Excavator NEW XCMG- XE370CA Running 27.04.2019 PCT Yard
Use Vibro
Hammer
11 Excavator NEW XCMG- XE370CA Running 27.04.2019 PCT Yard
Use Vibro
Hammer
12
Excavator (Long
Boom)
EX.LB-01 Zoomlion ZE360ELR Running
Md Bablu
Molla
14.03.2019 PCT Yard
Equipment/ Assets Statement:
13 Excavator EX.AM-01
TAKEUCHI
TB285CH
Running
Md
Mayuddin
12.04.2019 PCT Yard
14 Excavator EX.AM-02
TAKEUCHI
TB285CH
Running
Md
Jamaluddin
12.04.2019 PCT Yard
15 Wheel Loader WL-04 Lonking- ZL50C Running
Md Babul
Sarder
13.02.2019 PCT Yard
16 Wheel Loader WL-05 Lonking- ZL50C Running
Md Nurul
Parmanik
13.02.2019 PCT Yard
17 Vibrator Roller VR-02 ACE-ASD-115 Running
Md Asraful
Islam Sofi
PCT Yard
18 Bull Dozer BD-02 Zoomlion ZD160-3 Running Md Shamim 14.02.2019 PCT Yard
19 Concrete Pump CP-01
Zoomlion-
HBT60.174RSU
Running Abu Talab 14.02.2019 PCT Yard
Equipment/ Assets Statement:
20 Concrete Pump CP-02
Zoomlion-
HBT60.174RSU
Running
Md
Naseruddin
14.02.2019 PCT Yard
21 Boom Pump BP-01 ZOOMLION 49X-6RZ Running Md Anwor 07.04.2019 PCT Yard
22 Tailer (Primover) TL-01 SINO- ZZ425N341W Running Abdul Rahman 07.03.2019 PCT Yard
23 Tailer (Primover) TL-02 SINO- ZZ425N341W Running Iqubal Hosan 07.03.2019 PCT Yard
24 Mixture Truck MT-01 Zoomlion-9JBH-R Running
Md Nazrul
Islam
15.02.2019 PCT Yard
25 Mixture Truck MT-02 Zoomlion-9JBH-R Running Md Joynal 15.02.2019 PCT Yard
26 Mixture Truck MT-03 Zoomlion-9JBH-R Running Gulam Rosul 15.02.2019 PCT Yard
27 Mixture Truck MT-04 Zoomlion-9JBH-R Running
Md Habibur
Rahman
15.02.2019 PCT Yard
Equipment/ Assets Statement:
28 Dump Truck DT-01
SINO-
ZZ325N3647A
Running Md Shohid 07.03.2019 PCT Yard
29 Dump Truck DT-07
SINO-
ZZ3168G3615CIR
Running Md Billal Miah 07.03.2019 PCT Yard
30 Generator-329KVA DG-01
TEKSAN-
TJ329DW5L/SL-
CMM3484
Running Abu Talab PCT Yard
31 Generator-329KVA DG-02
TEKSAN-
TJ329DW5L/SL-
CMM3484
Running Abu Talab PCT Yard
32 Generator-180KVA DG-04 TJ180BWO5A Running Engr: Hadi 17.03.2019 Jetty Site
33 Generator-65KVA DG-05 PRAMAC GSW65 Running Engr: Sddam 17.03.2019 PCT Yard
34 Generator-21KVA DG-03 TJ21MS5A Running Engr: Hadi Jetty Site
Equipment/ Assets Statement:
35 Pick up PK-9034 Toyota Running Md Mostafa PCT Yard
36 Diesel Hammer DH-01 Running Md Jalil 21.03.2019 Jetty Site
37 Diesel Hammer DH-02 Running Md Shofiq 01.04.2019 Jetty Site
38 Hydraulic Breaker HB-01 Soosan (SB81A) Running
Md Jahirul
Hoque
18.03.2019 Jetty Site
39 Hydraulic Breaker HB-02 Soosan (SB81A) Running 18.03.2019 PCT Yard
40 Vibro Hammer VH-01 V400 Running 30.04.2019 PCT Yard
41 Vibro Hammer VH-02 V400 Running 30.04.2019 PCT Yard
42
Mini Mixture
Machine
MMM-01 (Z170 4HP) 1602 Running Lab Office PCT Yard
Client Observation - 03: Necessary steps on horizontal & vertical deviation on PHC
piles
REPLY- 03 FROM CRBC-EEL CONSORTIUM:
CRBC-EEL Consortium’s representative sending data and other related necessary information to consultant
representative of BRTC, BUET through email. Out of 952 piles, we already send data for 730 nos. piles (in Bays C, D,
E, F, G and H). See attachment in Annex-I. We have sent these data to 34ECBDE, Team Leader of top supervision
consultant & other members of BRTC, BUET as well as PM of supervision consultant.
BAY – A: Yet not done, because another contractor of PCT project is engaged for ground improvement work.
BAY – B: not done, because another contractor of PCT project is engaged for ground improvement work.
BAY – C: Sending data through mail dated on 25th July,2020. (Total no. of pile = 122 nos)
BAY – D Sending data through mail dated on 31st March,2020. (Total no. of pile = 122 nos)
BAY – E: Sending data through mail dated on 14th March,2020. (Total no. of pile = 111 nos)
BAY – F: Sending data through mail dated on 14th December,2019. (Total no. of pile = 111 nos)
BAY – G: Sending data through mail dated on 30th December,2019. (Total no. of pile = 128 nos)
BAY – H: Sending data through mail dated on 15th January,2020. (Total no. of pile = 136 nos)
A MEETING WAS HELD AT THE DEPARTMENT OF CIVIL ENGINEERING, BUET DATED ON 8TH SEPTEMBER, 2018
(MINUTES IS ATTACHED IN ANNEX-II), AND IT WAS DECIDED THAT CHINESE STANDARD WILL BE
FOLLOWED/ACCEPTED WHERE DEVIATION LIMIT AS FOLLOWS:
 An analysis of the (radial) deviation of the pile position, based on the provided data, is attached in Annex-III.
It shows that about 1.1% of these piles (out of 730 nos. piles) have a deviation greater than the tolerable
limit of 250 mm (As per Chinese Standard that is approved on 8th September, 2018 at BUET meeting).
• Since, another contractor is working at Bay-A and at Bay-B, so we cannot move our crane to these bays &
thereby we can’t take deviation data for rest 222 nos. of piles. As soon as we get access to these two bays,
we will take deviation data and submit to BUET accordingly. 77% (730/952) of pile deviation data is shared
with BUET. Also, out of 730 pile deviation data, only 8 nos. pile have a deviation greater than acceptable
limit of 250 mm (accuracy 722/730 = 98.90%).
• It has been decided in the meeting which was held at the department of Civil Engineering, BUET dated on
1st September, 2020 that “a Third-party survey team (approved by BRTC, BUET)” is engaged and they will
conduct survey for vertical alignment of PHC pile. And if necessary, they can check deviation of pile as well.
Client Observation - 04: Quality assurance on pile cap casting
REPLY- 04 FROM CRBC-EEL CONSORTIUM:
• It is mentionable that till now CRBC-EEL Consortium has completed concreting works of 514 nos. (55%) pile cap
in presence of client representative (34 EC BDE) and consultant representative (BRTC, BUET) as well. Out of 936
nos. pile cap, presence of moderate honeycomb formations was found in 05 nos. (0.97%) pile caps.
• Reference to email dated on 17th July,2020, we have already submitted “method statement i/c technical data
sheet of Rendoroc HS Xtra” to client (34 EC BDE). Also, we have repaired a pile cap in presence of consultant’s
representative (BRTC, BUET) dated on 19th July, 2020. We have also provided sample photographs of repaired
honeycomb in pile cap (Annex-IV)
• We are really dis-hearted for the comments of the surface honeycomb of pile cap. We have achieved almost 64%
of the project progress (as per revised BOQ). Is it possible to work in a such complicated project for an
unprofessional contractor without technically sound manpower? Concrete is a very unpredictable material.
Honeycomb type problem is very common in concreting work. We have to work day & night considering many
factors such as high-tide/low-tide, frequent tropical rain etc.
Client Observation - 05: Impact of deviation of pile alignment
REPLY- 05 FROM CRBC-EEL CONSORTIUM:
As per approved meeting minutes which was held on 8th September,2018 which is attached in Annex-II and
also as per Chinese Standard, we have analysis the radial deviation of the pile position with respect to
provided data, which is attached in Annex-III and it was found about 1.1% (08 nos.) piles have a deviation
greater than the tolerable limit of 250 mm. And these 08 nos. piles are located in different bays.
Client Observation - 06: Future difficulties of precast segment placing in jetty
REPLY- 06 FROM CRBC-EEL CONSORTIUM:
 A detail shop drawing (soft copy) using AutoCAD was submitted to client (34 EC BDE) and also consultant
representative (BRTC, BUET) through email with respect to each bay before starting construction of jetty
works.
 After completion of pile driving work, the shop detail has updated using the installed pile location and
necessary modification has also updated where it was required and submitted to consultant representative
(BRTC, BUET) for approval. Pile cap casting was done by adjusting of pile cap top to attain the desired slope
of top surface as per original design.
 After completion of pile cap with proper levels, the shop detail is updated phase by phase to fix the
dimension and size of precast elements (such as slabs & girder) with proper seating arrangement.
 After placing of precast girder on proper seating location with proper levels, cast in situ girder casting work
is ongoing at site phase by phase to fix the dimension and size as per approved design with respect to
reference grid line.
 Till now no abnormal issue has occurred. If required any modification or changes, contractor will do the
necessary change of precast elements after taking approval from client (34 EC BDE) and also from
supervision consultant (BRTC, BUET) through shop drawing (soft copy) using AutoCAD.
Client Observation - 07: Absence of lead partner
REPLY- 07 FROM CRBC-EEL CONSORTIUM:
Most of the time during construction, lead partner representatives of CRBC-EEL Consortium was present in
construction site. But very recently due to spreading situation of COVID-19, they are unable to present in
construction site for few days. We communicate with them and they will come back very soon at PCT site.
Client Observation - 08: INABILITY TO PRODUCE SHOP DRAWING OF JETTY
REPLY- 08 FROM CRBC-EEL CONSORTIUM:
 Time to time, we have to submit shop drawing for approval from client (34 EC BDE) and also from consultant
representative (BRTC, BUET) before starting construction of jetty works.
 Till now we have successfully completed 64% jetty works with quality with respect to approved shop
drawing.
 As per consultant (BRTC, BUET) opinion and also as per their suggestion, we will find out the more effective
way and also apply it to improve our shop drawing ability. And also, we will engage more CAD professional to
produce shop drawing effectively
Client Observation - 09: INABILITY TO GENERATE AND SUBMIT PROPER “ALTERNATE DESIGN
DRAWINGS”, AND FOLLOW UP ON INSTRUCTIONS.
REPLY- 09 FROM CRBC-EEL CONSORTIUM:
As per consultant (BRTC, BUET) opinion and also as per their suggestion, we will find out the more effective
way for generating “alternate design drawings”.
Client Observation - 10: INABILITY TO SHARE DATA (DEVIATION, VERTICALITY OF DRIVEN
PILES) AND TEST REPORTS
REPLY- 10 FROM CRBC-EEL CONSORTIUM:
 CRBC-EEL Consortium representative send deviation data and other related other information to consultant
representative, BRTC, BUET through email. Out of 952 driven pile, 730 nos. PHC pile data (in Bays C, D, E, F, G and H) is
attached in Annex-I. Here client (34 EC BDE) and Team leader of BRTC, BUET with his team member were available in
that email.
 Simultaneously it was not possible to collect data for BAY-A & BAY-B by using crane because another contractor of PCT
project was engaged for ground improvement work. After completion their work, we will take immediate action to
collect necessary all data and accordingly send it to you for your necessary information and action please.
 We already provide the following test reports to client (34 EC BDE) and consultant representative, BRTC, BUET phase by
phase which is attached in Annex-V.
a) Concrete cylinder observation test report for every concrete element,
b) Pile integrity test report on PHC pile,
c) High strain dynamic test report on PHC pile,
d) Static load test report on 06 nos. trial piles,
e) Any other necessary report etc.
Client Observation - 11: PILE LOAD TESTING – NOT ACCORDING TO SPECIFICATION AND
BOQ
REPLY- 11 FROM CRBC-EEL CONSORTIUM:
 We have executed 06 nos. static load test on additional trial piles and report was
submitted to client (34 EC BDE) and consultant representative, BRTC, BUET.
 There is no provision of Static Load Test in our approved BOQ.
 As per Chinese Standard, there is no provision to do static load test on service
pile.
 We will do the static load test (to be applied up to 1.5 times the design capacity)
on the service piles on the following conditions:
a) If there is any scope to do the static load test.
b) If required any modification or changes or re-arrangement for the effects of
static load test execution on service pile, there is any scope or not.
c) If client (34 EC BDE) and consultant BRTC, BUET gives work execution approval.
d) Rate approval is essential for execution of newly static load test on service pile.
Client Observation - 12: QUALITY OF MANPOWER OF CRBC-EEL CONSORTIUM AND THE
IMPLEMENTING AGENCY.
REPLY- 12 FROM CRBC-EEL CONSORTIUM:
As per consultant (BRTC, BUET) opinion and also as per their suggestion, CRBC-EEL Consortium will deploy
additionally qualified manpower in the field to increase the productivity maintaining quality.
Client Observation – 1 (Part – A): Work Progress of jetty work
REPLY- 1 (Part – A) FROM CRBC-EEL CONSORTIUM:
REPLY- 1 (Part – B) FROM CRBC-EEL CONSORTIUM:
• Unavailability of space for construction of precast segment.
• Delay in PHC pile design approval.
• Delay in tie rod approval and subsequently delay in commencement of retaining structure.
• Delay in Pilot jetty, Buoy and anchor chain removal from different Bays.
• Delay due to natural phenomena such as Cyclone Fani, Cyclone Amphan, tropical rain and tidal effects etc.
• Delay in pile cap decision and its approval.
• Delay in lapping decision for CIS girder.
• Unavailability of worker due to bad effects of COVID-19.
• High mast tower decision not yet get approval.
• Placing of Riprap decision yet not settled. As a result, it is not possible to go for precast slab placing on girder.
• Utility design and decision yet not finalized.
• Due to unavailability of space, it is not possible to go for any more precast slab casting.
• De – shuttering and de – staging works not possible in time due to decision problem. As a result, these materials are
rusted due to long time stay under saline water and simultaneously we have to increase shuttering and staging materials
to increase the work productivity and complete the work in time and hence finally cost and time schedule both are
increased.
Client Observation – 1 (Part – B): Problem facing during works:
PCT Presentation 08.09.2020.pptx

More Related Content

Similar to PCT Presentation 08.09.2020.pptx

Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...ze3xiandiao
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...f7usuejkdkddm3
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...ufs89eodkdmdm
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...jdkskmmdmd1
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...jdkksmemmd
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...fskekkdmdmdm3e
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...fjisejkdmd8id
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...ifkkdkmdmd
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...f8sejdkdmdijd
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...jjfksekdmejik
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Munir Hussain
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...hhfjksekmm
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...fjjskqazxedmmem
 
2022-01-13-ALALAMEEN 08-WR08.docx
2022-01-13-ALALAMEEN 08-WR08.docx2022-01-13-ALALAMEEN 08-WR08.docx
2022-01-13-ALALAMEEN 08-WR08.docxMohammedSalah424258
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxsyedaliabl2023
 
KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2Brian Quan (Minh)
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002Minh Bui Si
 

Similar to PCT Presentation 08.09.2020.pptx (20)

Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
SISCO - Presentation
SISCO - PresentationSISCO - Presentation
SISCO - Presentation
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019
 
Connecting Bridge
Connecting BridgeConnecting Bridge
Connecting Bridge
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
 
2022-01-13-ALALAMEEN 08-WR08.docx
2022-01-13-ALALAMEEN 08-WR08.docx2022-01-13-ALALAMEEN 08-WR08.docx
2022-01-13-ALALAMEEN 08-WR08.docx
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptx
 
KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 

Recently uploaded

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 

PCT Presentation 08.09.2020.pptx

  • 1. CONSTRUCTION OF PATENGA CONTAINER TERMINAL (PCT) WHARF JETTY.
  • 2. PROJECT INFORMATION :  Project Owner : 34 EC BDE  Mother Concern : CHITTAGONG PORT AUTHORITY  Consultant : BRTC, BUET  Contractor (JV) : CRBC – EEL CONSORTIUM  Contract Agreement : 16 September’18  Contract Value : 416.99 Crore Taka  Revised value (Partly): 525.00 Crore Taka  Length of Jetty : 72.80 m @ 08 nos BAY = 582.40 m  Width of jetty : Variable from 45.4m to 69.4m  Handed Over : 22nd September,2021 (As per revised schedule)
  • 3. Scope of Work : Yard development for construction of precast segment.  RC sheet pile casting and driving.  Casting of precast girder & Slab.  PHC pile supply and driving.  Pile cap casting i/c ins. of berthing block where it is required.  Slope protection.
  • 4. Scope of Work :  Installation of Precast girder & Casting of cast in situ girder  Installation of Precast Slab  Installation of Fender  Installation of Bollard  Installation of QA Rail  Installation of Ladder & Railing
  • 6. Work Progress Yard Development (7.45 Acre): (A) Dyke Development and project fencing (B) Sand Filling and Land Compaction (C) Palisading Works (D) 60 & 35 Batching Plant (02 Nos) Installation (E) Materials Stack Yard With Retaining Wall (F) Employee Residence With Others Facility (G) Labor Shed, Security Shed With Others Facility
  • 7. RE - DESIGN AND Additional Works of Jetty Increase volumn of Jetty Work: SL No Major Items Unit Previous Design (Contract Agreement) Increased Revised Design (Additional & Revised BOQ) Increase % 1 Area of Jetty Sqm 25043 5951 30994 23.76% 2 Ø 1000 PHC Pile Nos 432 24 456 5.56% 3 Ø 900 PHC Pile Nos 344 152 496 44.19% 4 Pile Cap Nos 776 160 936 20.62% 5 Precast Slab Nos 904 126 1030 13.94% 6 Precast Beam Nos 552 136 688 24.64%
  • 8. RE - DESIGN AND Additional Works of Jetty Increase volumn of Jetty Work: SL No Major Items Unit Previous Design (Contract Agreement) Increased Revised Design ( Additional & Revised BOQ) Increase % 7 Arranging for pile integrity test (PIT) Nos 0.00 952 952 100% 8 Boreholes and soil investigation Nos 0.00 8 8 100% 9 Additional trial piles includes 6 static load test piles and 18 Auxiliary piles, in total 24 piles. LS 0.00 1 1 100%
  • 9. RE - DESIGN AND Additional Works of Jetty Increase volumn of Jetty Work: SL No Major Items Unit Previous Design (Contract Agreement) Increased Revised Design ( Additional & Revised BOQ) Increase % 10 Manufacturing of RC Sheet pile (each pile length 15.4 m) Rm 0.00 18,668 18,668 100% 11 Driving of RC Sheet pile (each pile length 15.4 m) Nos 0.00 18,668 18,668 100% 12 Breast Wall of Retaining Structure Cum 1609.65 6,376 7,986 79.83%
  • 10. Work Progress Jetty Work: (A) PHC (Anchor pile & Trial pile) Pile 24 nos has been driven in BAY B & BAY F (100%) (B) Static Load test on trial pile = 06 nos / 06 nos (100%) (C) RC sheet pile (450mm x 600mm x 15.4m) casting = 1173 pcs /1212 pcs (Complete) (D) RC sheet pile driving = 1173 pcs /1212 pcs (Complete) (E) PHC pile supply = 952 nos /952nos (100%) (900 dia = 496 nos & 1000 dia = 456 nos, Total = 952 nos) (F) PHC pile driving = 952 nos / 952 nos (100%) (G) Precast Slab Casting = 394 nos / 1022 nos (38.55%) (H) Precast Girder Casting = 442 nos / 688 nos (64.24%) (I) Pile integrity test (PIT) = 537 nos / 952 nos (56.40%)
  • 11. Work Progress Jetty Work: (J) High strain test = 48 nos / 48 nos (100%) (K) Pile cap casting = 521 pcs / 936 pcs (55.66%) (L) Precast girder placing = 271 pcs / 688 pcs (39.39%) (M) Cast in situ girder casting = 880 rm / 6270 rm (14%) (N) Breast wall casting = 577 rm / 772 rm (74.74%) (O) Anchor wall casting = 457 rm / 772 rm (59.20%) (P) Tie Rod Placing works = 108 nos / 644 nos (16.77%) (Q) Dredging Works = 100666 cum / 139380 cum (72.22%) (R) Riprap cleaning = 41500 sqm / 41500 sqm (100%)
  • 12. Work Progress PHC (TRIAL) PILE DRIVING RECORD IN BAY - B: SL BAY TYPE OF PHC PILE DIA OF PILE (MM) LENGTH OF PILE (M) TYPE OF SHOE PIT LOAD TEST SETTLEMENT (MM) REMARKS 1 BAY - B ANCHOR PILE, M1 1000 40 OPEN DONE 2 ANCHOR PILE, M2 1000 40 OPEN DONE 3 ANCHOR PILE, M3 1000 40 OPEN DONE 4 ANCHOR PILE, M4 1000 40 OPEN DONE 5 ANCHOR PILE, M5 900 40 OPEN DONE 6 ANCHOR PILE, M6 900 40 OEN DONE 7 ANCHOR PILE, M7 900 40 OPEN DONE 8 ANCHOR PILE, M8 900 40 OPEN DONE 9 ANCHOR PILE, M17 1000 40 OPEN 10 TRIAL PILE, S1 1000 39 CLOSE DONE 9.80 11 TRIAL PILE, S2 900 39 OPEN BROKEN 12 TRIAL PILE, S3 900 30 OPEN DONE 11.77 13 TRIAL PILE, S2 - 1 900 40 OPEN DONE 15.22
  • 13. Work Progress PHC (TRIAL) PILE DRIVING RECORD IN BAY - F: SL BAY TYPE OF PHC PILE DIA OF PILE (MM) LENGTH OF PILE (M) TYPE OF SHOE PIT LOAD TEST SETTLEMENT (MM) REMARKS 14 BAY - F ANCHOR PILE, M9 1000 40 OPEN 15 ANCHOR PILE, M10 1000 40 OPEN 16 ANCHOR PILE, M11 1000 40 OPEN 17 ANCHOR PILE, M12 1000 40 OPEN BROKEN 18 ANCHOR PILE, M13 900 40 OPEN 19 ANCHOR PILE, M14 900 40 OPEN 20 ANCHOR PILE, M15 900 40 OPEN 21 ANCHOR PILE, M16 900 40 OPEN 22 TRIAL PILE, S4 1000 40 OPEN DONE 10.33 23 TRIAL PILE, S5 900 38 CLOSE DONE 17.23 24 TRIAL PILE, S7 900 28 CLOSE DONE 10.96
  • 14. Excavation, Dyke making & Protection at PCT ConstructionYard:
  • 15. Sand Filling,Land Compaction & Palisading Works at PCT Yard:
  • 16. 60 & 35 Batching Plant (02 Nos) Installation at PCT Yard:
  • 17. Materials Stack Yard With Retaining Wall:
  • 18. Employee Residence, Canteen and Labor Shed with necessary facility:
  • 19. PHC Pile has driven in Jetty Side:
  • 20. Static Load Test on PHC Pile & Pile Integrity Test in Jetty Side:
  • 21. RC Sheet Pile Casting and Driving in Jetty Side:
  • 22. Precast Slab and Girder casting in Yard Side:
  • 23. RC Sheet Pile Head Breaking in Jetty Side:
  • 24. Pile cap casting in Jetty Side:
  • 25. Precast girder placing in Jetty Side:
  • 26. Cast in situ girder casting in Jetty Side:
  • 27. Dredging works in Jetty Side:
  • 28. Dredging post survey and riprap cleaning works in Jetty Side:
  • 29. Breast wall and Anchor wall works in Jetty Side:
  • 30. Tie Rod Placing and FDD test for Gr. Improvement Works in Jetty Side:
  • 31. 380 Ton Crane Lifting Capacity as follows: Weight Of Girder : 20.50 tons and lifting distance = 42 mtr. length
  • 32. Latest Revised Work Schedule:
  • 33. Equipment/Assets Statement: LIST OF EQUIPMENTS STATUS Name Of Month: September -2020 Date: 07.09.2020 SL. No. Name of Equipment EEL Code Model No Present Condition Operator Name Received Date Present Location Remarks PCT Project 1 Batching Plant BP-01 POWERPAC-PBP350S Running Md Talab PCT Yard 2 Batching Plant BP-02 Zoomlion- JS1000 Running Md Khairul 14.02.2019 PCT Yard 3 Crawler Crane CR.C-01 Zoomlion- QUY380CL Running Md Raju 17.02.2019 Jetty Site 4 Crawler Crane CR.C-02 Zoomlion- QUY180CL Running Md Saidul Rahman 14.02.2019 Jetty Site 5 Crawler Crane CR.C-03 XCMG- XGC85 Running Md Ripon Miah 08.03.2019 Jetty Site 6 Crawler Crane CR.C-04 XCMG- XGC85 Running Md Juwel Sheikh 08.03.2019 Jetty Site
  • 34. Equipment/ Assets Statement: 7 Rough Crane RT-01 Zoomlion-RT75 Running Md Forhad Hossain 14.02.2019 PCT Yard 8 Rough Crane RT-02 Zoomlion-RT35 Running Md Rohul Amin 14.02.2019 PCT Yard 9 Excavator EX-04 Zoomlion ZE210E Running Md Jahirul Hoque 14.02.2019 Jetty Site 10 Excavator NEW XCMG- XE370CA Running 27.04.2019 PCT Yard Use Vibro Hammer 11 Excavator NEW XCMG- XE370CA Running 27.04.2019 PCT Yard Use Vibro Hammer 12 Excavator (Long Boom) EX.LB-01 Zoomlion ZE360ELR Running Md Bablu Molla 14.03.2019 PCT Yard
  • 35. Equipment/ Assets Statement: 13 Excavator EX.AM-01 TAKEUCHI TB285CH Running Md Mayuddin 12.04.2019 PCT Yard 14 Excavator EX.AM-02 TAKEUCHI TB285CH Running Md Jamaluddin 12.04.2019 PCT Yard 15 Wheel Loader WL-04 Lonking- ZL50C Running Md Babul Sarder 13.02.2019 PCT Yard 16 Wheel Loader WL-05 Lonking- ZL50C Running Md Nurul Parmanik 13.02.2019 PCT Yard 17 Vibrator Roller VR-02 ACE-ASD-115 Running Md Asraful Islam Sofi PCT Yard 18 Bull Dozer BD-02 Zoomlion ZD160-3 Running Md Shamim 14.02.2019 PCT Yard 19 Concrete Pump CP-01 Zoomlion- HBT60.174RSU Running Abu Talab 14.02.2019 PCT Yard
  • 36. Equipment/ Assets Statement: 20 Concrete Pump CP-02 Zoomlion- HBT60.174RSU Running Md Naseruddin 14.02.2019 PCT Yard 21 Boom Pump BP-01 ZOOMLION 49X-6RZ Running Md Anwor 07.04.2019 PCT Yard 22 Tailer (Primover) TL-01 SINO- ZZ425N341W Running Abdul Rahman 07.03.2019 PCT Yard 23 Tailer (Primover) TL-02 SINO- ZZ425N341W Running Iqubal Hosan 07.03.2019 PCT Yard 24 Mixture Truck MT-01 Zoomlion-9JBH-R Running Md Nazrul Islam 15.02.2019 PCT Yard 25 Mixture Truck MT-02 Zoomlion-9JBH-R Running Md Joynal 15.02.2019 PCT Yard 26 Mixture Truck MT-03 Zoomlion-9JBH-R Running Gulam Rosul 15.02.2019 PCT Yard 27 Mixture Truck MT-04 Zoomlion-9JBH-R Running Md Habibur Rahman 15.02.2019 PCT Yard
  • 37. Equipment/ Assets Statement: 28 Dump Truck DT-01 SINO- ZZ325N3647A Running Md Shohid 07.03.2019 PCT Yard 29 Dump Truck DT-07 SINO- ZZ3168G3615CIR Running Md Billal Miah 07.03.2019 PCT Yard 30 Generator-329KVA DG-01 TEKSAN- TJ329DW5L/SL- CMM3484 Running Abu Talab PCT Yard 31 Generator-329KVA DG-02 TEKSAN- TJ329DW5L/SL- CMM3484 Running Abu Talab PCT Yard 32 Generator-180KVA DG-04 TJ180BWO5A Running Engr: Hadi 17.03.2019 Jetty Site 33 Generator-65KVA DG-05 PRAMAC GSW65 Running Engr: Sddam 17.03.2019 PCT Yard 34 Generator-21KVA DG-03 TJ21MS5A Running Engr: Hadi Jetty Site
  • 38. Equipment/ Assets Statement: 35 Pick up PK-9034 Toyota Running Md Mostafa PCT Yard 36 Diesel Hammer DH-01 Running Md Jalil 21.03.2019 Jetty Site 37 Diesel Hammer DH-02 Running Md Shofiq 01.04.2019 Jetty Site 38 Hydraulic Breaker HB-01 Soosan (SB81A) Running Md Jahirul Hoque 18.03.2019 Jetty Site 39 Hydraulic Breaker HB-02 Soosan (SB81A) Running 18.03.2019 PCT Yard 40 Vibro Hammer VH-01 V400 Running 30.04.2019 PCT Yard 41 Vibro Hammer VH-02 V400 Running 30.04.2019 PCT Yard 42 Mini Mixture Machine MMM-01 (Z170 4HP) 1602 Running Lab Office PCT Yard
  • 39. Client Observation - 03: Necessary steps on horizontal & vertical deviation on PHC piles REPLY- 03 FROM CRBC-EEL CONSORTIUM: CRBC-EEL Consortium’s representative sending data and other related necessary information to consultant representative of BRTC, BUET through email. Out of 952 piles, we already send data for 730 nos. piles (in Bays C, D, E, F, G and H). See attachment in Annex-I. We have sent these data to 34ECBDE, Team Leader of top supervision consultant & other members of BRTC, BUET as well as PM of supervision consultant. BAY – A: Yet not done, because another contractor of PCT project is engaged for ground improvement work. BAY – B: not done, because another contractor of PCT project is engaged for ground improvement work. BAY – C: Sending data through mail dated on 25th July,2020. (Total no. of pile = 122 nos) BAY – D Sending data through mail dated on 31st March,2020. (Total no. of pile = 122 nos) BAY – E: Sending data through mail dated on 14th March,2020. (Total no. of pile = 111 nos) BAY – F: Sending data through mail dated on 14th December,2019. (Total no. of pile = 111 nos) BAY – G: Sending data through mail dated on 30th December,2019. (Total no. of pile = 128 nos) BAY – H: Sending data through mail dated on 15th January,2020. (Total no. of pile = 136 nos)
  • 40. A MEETING WAS HELD AT THE DEPARTMENT OF CIVIL ENGINEERING, BUET DATED ON 8TH SEPTEMBER, 2018 (MINUTES IS ATTACHED IN ANNEX-II), AND IT WAS DECIDED THAT CHINESE STANDARD WILL BE FOLLOWED/ACCEPTED WHERE DEVIATION LIMIT AS FOLLOWS:
  • 41.  An analysis of the (radial) deviation of the pile position, based on the provided data, is attached in Annex-III. It shows that about 1.1% of these piles (out of 730 nos. piles) have a deviation greater than the tolerable limit of 250 mm (As per Chinese Standard that is approved on 8th September, 2018 at BUET meeting).
  • 42. • Since, another contractor is working at Bay-A and at Bay-B, so we cannot move our crane to these bays & thereby we can’t take deviation data for rest 222 nos. of piles. As soon as we get access to these two bays, we will take deviation data and submit to BUET accordingly. 77% (730/952) of pile deviation data is shared with BUET. Also, out of 730 pile deviation data, only 8 nos. pile have a deviation greater than acceptable limit of 250 mm (accuracy 722/730 = 98.90%). • It has been decided in the meeting which was held at the department of Civil Engineering, BUET dated on 1st September, 2020 that “a Third-party survey team (approved by BRTC, BUET)” is engaged and they will conduct survey for vertical alignment of PHC pile. And if necessary, they can check deviation of pile as well.
  • 43. Client Observation - 04: Quality assurance on pile cap casting REPLY- 04 FROM CRBC-EEL CONSORTIUM: • It is mentionable that till now CRBC-EEL Consortium has completed concreting works of 514 nos. (55%) pile cap in presence of client representative (34 EC BDE) and consultant representative (BRTC, BUET) as well. Out of 936 nos. pile cap, presence of moderate honeycomb formations was found in 05 nos. (0.97%) pile caps. • Reference to email dated on 17th July,2020, we have already submitted “method statement i/c technical data sheet of Rendoroc HS Xtra” to client (34 EC BDE). Also, we have repaired a pile cap in presence of consultant’s representative (BRTC, BUET) dated on 19th July, 2020. We have also provided sample photographs of repaired honeycomb in pile cap (Annex-IV) • We are really dis-hearted for the comments of the surface honeycomb of pile cap. We have achieved almost 64% of the project progress (as per revised BOQ). Is it possible to work in a such complicated project for an unprofessional contractor without technically sound manpower? Concrete is a very unpredictable material. Honeycomb type problem is very common in concreting work. We have to work day & night considering many factors such as high-tide/low-tide, frequent tropical rain etc.
  • 44. Client Observation - 05: Impact of deviation of pile alignment REPLY- 05 FROM CRBC-EEL CONSORTIUM: As per approved meeting minutes which was held on 8th September,2018 which is attached in Annex-II and also as per Chinese Standard, we have analysis the radial deviation of the pile position with respect to provided data, which is attached in Annex-III and it was found about 1.1% (08 nos.) piles have a deviation greater than the tolerable limit of 250 mm. And these 08 nos. piles are located in different bays.
  • 45. Client Observation - 06: Future difficulties of precast segment placing in jetty REPLY- 06 FROM CRBC-EEL CONSORTIUM:  A detail shop drawing (soft copy) using AutoCAD was submitted to client (34 EC BDE) and also consultant representative (BRTC, BUET) through email with respect to each bay before starting construction of jetty works.  After completion of pile driving work, the shop detail has updated using the installed pile location and necessary modification has also updated where it was required and submitted to consultant representative (BRTC, BUET) for approval. Pile cap casting was done by adjusting of pile cap top to attain the desired slope of top surface as per original design.  After completion of pile cap with proper levels, the shop detail is updated phase by phase to fix the dimension and size of precast elements (such as slabs & girder) with proper seating arrangement.  After placing of precast girder on proper seating location with proper levels, cast in situ girder casting work is ongoing at site phase by phase to fix the dimension and size as per approved design with respect to reference grid line.  Till now no abnormal issue has occurred. If required any modification or changes, contractor will do the necessary change of precast elements after taking approval from client (34 EC BDE) and also from supervision consultant (BRTC, BUET) through shop drawing (soft copy) using AutoCAD.
  • 46. Client Observation - 07: Absence of lead partner REPLY- 07 FROM CRBC-EEL CONSORTIUM: Most of the time during construction, lead partner representatives of CRBC-EEL Consortium was present in construction site. But very recently due to spreading situation of COVID-19, they are unable to present in construction site for few days. We communicate with them and they will come back very soon at PCT site. Client Observation - 08: INABILITY TO PRODUCE SHOP DRAWING OF JETTY REPLY- 08 FROM CRBC-EEL CONSORTIUM:  Time to time, we have to submit shop drawing for approval from client (34 EC BDE) and also from consultant representative (BRTC, BUET) before starting construction of jetty works.  Till now we have successfully completed 64% jetty works with quality with respect to approved shop drawing.  As per consultant (BRTC, BUET) opinion and also as per their suggestion, we will find out the more effective way and also apply it to improve our shop drawing ability. And also, we will engage more CAD professional to produce shop drawing effectively
  • 47. Client Observation - 09: INABILITY TO GENERATE AND SUBMIT PROPER “ALTERNATE DESIGN DRAWINGS”, AND FOLLOW UP ON INSTRUCTIONS. REPLY- 09 FROM CRBC-EEL CONSORTIUM: As per consultant (BRTC, BUET) opinion and also as per their suggestion, we will find out the more effective way for generating “alternate design drawings”.
  • 48. Client Observation - 10: INABILITY TO SHARE DATA (DEVIATION, VERTICALITY OF DRIVEN PILES) AND TEST REPORTS REPLY- 10 FROM CRBC-EEL CONSORTIUM:  CRBC-EEL Consortium representative send deviation data and other related other information to consultant representative, BRTC, BUET through email. Out of 952 driven pile, 730 nos. PHC pile data (in Bays C, D, E, F, G and H) is attached in Annex-I. Here client (34 EC BDE) and Team leader of BRTC, BUET with his team member were available in that email.  Simultaneously it was not possible to collect data for BAY-A & BAY-B by using crane because another contractor of PCT project was engaged for ground improvement work. After completion their work, we will take immediate action to collect necessary all data and accordingly send it to you for your necessary information and action please.  We already provide the following test reports to client (34 EC BDE) and consultant representative, BRTC, BUET phase by phase which is attached in Annex-V. a) Concrete cylinder observation test report for every concrete element, b) Pile integrity test report on PHC pile, c) High strain dynamic test report on PHC pile, d) Static load test report on 06 nos. trial piles, e) Any other necessary report etc.
  • 49. Client Observation - 11: PILE LOAD TESTING – NOT ACCORDING TO SPECIFICATION AND BOQ REPLY- 11 FROM CRBC-EEL CONSORTIUM:  We have executed 06 nos. static load test on additional trial piles and report was submitted to client (34 EC BDE) and consultant representative, BRTC, BUET.  There is no provision of Static Load Test in our approved BOQ.  As per Chinese Standard, there is no provision to do static load test on service pile.  We will do the static load test (to be applied up to 1.5 times the design capacity) on the service piles on the following conditions: a) If there is any scope to do the static load test. b) If required any modification or changes or re-arrangement for the effects of static load test execution on service pile, there is any scope or not. c) If client (34 EC BDE) and consultant BRTC, BUET gives work execution approval. d) Rate approval is essential for execution of newly static load test on service pile.
  • 50. Client Observation - 12: QUALITY OF MANPOWER OF CRBC-EEL CONSORTIUM AND THE IMPLEMENTING AGENCY. REPLY- 12 FROM CRBC-EEL CONSORTIUM: As per consultant (BRTC, BUET) opinion and also as per their suggestion, CRBC-EEL Consortium will deploy additionally qualified manpower in the field to increase the productivity maintaining quality.
  • 51. Client Observation – 1 (Part – A): Work Progress of jetty work REPLY- 1 (Part – A) FROM CRBC-EEL CONSORTIUM:
  • 52. REPLY- 1 (Part – B) FROM CRBC-EEL CONSORTIUM: • Unavailability of space for construction of precast segment. • Delay in PHC pile design approval. • Delay in tie rod approval and subsequently delay in commencement of retaining structure. • Delay in Pilot jetty, Buoy and anchor chain removal from different Bays. • Delay due to natural phenomena such as Cyclone Fani, Cyclone Amphan, tropical rain and tidal effects etc. • Delay in pile cap decision and its approval. • Delay in lapping decision for CIS girder. • Unavailability of worker due to bad effects of COVID-19. • High mast tower decision not yet get approval. • Placing of Riprap decision yet not settled. As a result, it is not possible to go for precast slab placing on girder. • Utility design and decision yet not finalized. • Due to unavailability of space, it is not possible to go for any more precast slab casting. • De – shuttering and de – staging works not possible in time due to decision problem. As a result, these materials are rusted due to long time stay under saline water and simultaneously we have to increase shuttering and staging materials to increase the work productivity and complete the work in time and hence finally cost and time schedule both are increased. Client Observation – 1 (Part – B): Problem facing during works: