WASBOSpring Conference 2011Presented By: Mark CyganiakServiceMaster Recovery Services
AssumptionsYou have been asked to restore a school from water or fire damage.22011 ServiceMaster Clean. All right reserved.                                                                                                                                                 2011 RAM Program
AssumptionsYou have been asked to restore a school from water or fire damage.
You have been awarded the contract32011 ServiceMaster Clean. All right reserved.                                                                                                                                                 2011 RAM Program
Key informationWho is your carrier?
Have they been in contact with you?
Have they assigned an adjuster?
If  yes, contact the adjuster
Who is your broker?
What is your deductible?42011 ServiceMaster Clean. All right reserved.                                                                                                                                                 2011 RAM Program
Key information National Contract – If this is a National Contract, find out all details and requirements
Discuss clients ability to pay for the work you are going to perform
Does the customer have Business Interruption Coverage and for how long?
Identify the customers internal procedures for payment52011 ServiceMaster Clean. All right reserved.                                                                                                                                                 2011 RAM Program
Defining the money termsClearly define payment terms
1/3rd, 1/3rd, 1/3rd Draw Schedule
Up front draw is standard practices
Mobilization Costs
Materials
Supplies62011 ServiceMaster Clean. All right reserved.                                                                                                                                                 2011 RAM Program
Defining the money termsDefine how invoicing is suppose to be organized to the adjusters expectations
Inform all contractors to anticipate slower than normal payouts72011 ServiceMaster Clean. All right reserved.                                                                                                                                                 2011 RAM Program
AttachmentsCopy of Certificate of Insurance
Contract
Rate Schedule
Labor Rates, Labor Classifications & Labor Conditions
Rates for Company owned Equipment and Supplies82011 ServiceMaster Clean. All right reserved.                                                                                                                                                 2011 RAM Program
Job SpecificsAssess overall scope of work to be addressed
Assessment of critical infrastructure2011 ServiceMaster Clean. All right reserved.                                                                                                                                                 2011 RAM Program
Health and SafetyServiceMaster Health and Safety Issue
Bring in Independent Safety Coordinator
Client Health and Safety Requirements
Does client have in house safety director?
Know company safety rules182011 ServiceMaster Clean. All right reserved.                                                                                                                                                 2011 RAM Program
Health and SafetyHaz-Mat
Asbestos Survey
Be prepared for 	        to stop by
Client priorities: STATED EXPECTATIONS192011 ServiceMaster Clean. All right reserved.                                                                                                                                                 2011 RAM Program
Job SpecificsAccessibility/availability of affected areas
Subcontractors Required
Required Cleaning Protocols

2011 wasbo school

Editor's Notes

  • #3 Assessment of critical infrastructureElectricalPlumbingGas fired equipmentProduction equipmentEtc.
  • #4 Be prepared for OSHA to stop byOSHA log and MSDS sheets on site
  • #5 Subcontractors RequiredInquire about current company vendors vs. restoration vendors resources, ie. “get the facility manager on board”
  • #6 Is clearance testing being conducted?Have expectations spelled out prior to restoration beginningHave expectations spelled out as to the criteria to pass clearance
  • #7 Contents, Equipment, & MachineryClean versus replaceIs a salvage company involved?Re-CertificationIn House, Manufacturer, or authorized DealerReplacement PartsElectronics
  • #8 MobilizeMobilize equipment, materials, supplies and supervisory personnelSecure hotel rooms and vehicles (if needed)Schedule vendors and subcontractorsSchedule daily production meetings with client and subcontractors
  • #10 Schedule daily production meetingsReview progress to planned time framesAdditional work that can be capturedAnything that will have an impact of project time framesScope of workProject estimate as referred in your original scope.
  • #14 Document, Document, DocumentWrittenPhotosVideo, ieCYB)