SlideShare a Scribd company logo
Business processes supported
by BIM Methodology:
scheduling and progress
monitoring
Prof. Nashwan Dawood
Teesside University, UK
n.n.dawood@tees.ac.uk
Speaker Name

1
Scheduling and Monitoring Processes
• Scheduling: what, when, by whom,
how, what-if, etc
• WBS is the standard for scheduling
practices. Network analysis, barchat and LoB are typical techniques
• To update schedules, monitoring of
construction activities will be
conducted on weekly or monthly
intervals.
• New paradigm of integrating WBS
with PBS for 4D planning.

Whole schedule

2
Scheduling Systems

3
Issues with traditional scheduling
Site
congestions

Crowded
areas

CAD Design Drawings

Project
Schedule

Design

Plan/Tender

Access
blockage
Build

4

4
Concept of 4D Scheduling
• Integration of BIM (mainly 3D
models) and schedules (4D)
• Shows progress of
construction activities at any
time.
• Visualisation of construction
products through time.
• Site Logistics.
5

5
4D and construction processes
•
•
•
•
•
•
•
•

Initiation
Preliminary
Design and developments
Detailed design
Contracts and planning
Production
Commissioning
Operation

4D scheduling

Sequence of tasks

6
Integration processes
Process

BIM

Schedule

3D models

Integration of 3D
And schedule
4D software

7
BIM & 4D Scheduling
• Schedule analysis
(constructability, spatial
constraints, complex sequences,
what-if)
• Schedule Review (planned vs
actual)
• Communication and marketing
(main contractor with client, main
contractor with subcontractors)
• Subcontractors coordination on
site/work-flow planning
• Track Construction progress.
8
Building Information Modelling
4D planning examples

video

4D_preview_03.mp4

Speaker Name

9
Schedules Analysis, process conflict
Steel Beam and
In-situ Ground
Slab
Visualisation

(A) Work progress
Visualisation

Key
Finished

In progress

Workspace

Conflict
10

10
Schedule Analysis
Steel Beam and
In-situ Ground
Slab Space
Conflicts

(C) Workspace
conflicts Visualisation

Key
Finished

11

In progress

Workspace

11

Conflict
Schedule analysis; execution space
congestions

Critical Space

Spatial Overload

Spatial Slack

12

12
Monitoring

13

13
Value of 4D planning
 Analysis

of 3 Major
projects (combined value
of £400 million)
 Development of
Measurement
methodology for KPIs
 Progress monitoring and
data anlysis

94%

Time

92%

Safety
82%

Communication

80%

Cost

7%

Planning Efficiency
Client Satisfaction
Team Performance

70%
65%
62%
60%

Productivity
52%

Quality
0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

%

14
Value

15

15
Research projects in the coming 10 years: automated and flexible
visual scheduling.
BIM

KB Rules about
Work methods
and temp
activities

Extension
of BIM
(ground
models,

16
Conclusions
• BIM has had very limited use in scheduling
processes
• 4D has been taken up with contracting
organisation but as visual tool.
• 4D has the potential to be developed to cover
the control processes and utilised at workface.
• New paradigm for utilising BIM for scheduling
has been presented.
17

More Related Content

Viewers also liked

2nd Qatar BIM User Day Scheduling, QTO and Estimating Technology
2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology
2nd Qatar BIM User Day Scheduling, QTO and Estimating Technology
BIM User Day
 
4th Qatar BIM User Day, BIM Solutions and Strategies
4th Qatar BIM User Day, BIM Solutions and Strategies4th Qatar BIM User Day, BIM Solutions and Strategies
4th Qatar BIM User Day, BIM Solutions and Strategies
BIM User Day
 
4th Qatar BIM User Day, Collaboration or Co-Operation
4th Qatar BIM User Day, Collaboration or Co-Operation4th Qatar BIM User Day, Collaboration or Co-Operation
4th Qatar BIM User Day, Collaboration or Co-Operation
BIM User Day
 
3rd Qatar BIM User Day - The BIM Manager within the Project Organisation
3rd Qatar BIM User Day - The BIM Manager within the Project Organisation3rd Qatar BIM User Day - The BIM Manager within the Project Organisation
3rd Qatar BIM User Day - The BIM Manager within the Project Organisation
BIM User Day
 
1st Qatar BIM User DAY BIM processes Case Study #2
1st Qatar BIM User DAY  BIM processes Case Study #21st Qatar BIM User DAY  BIM processes Case Study #2
1st Qatar BIM User DAY BIM processes Case Study #2
BIM User Day
 
4th Qatar BIM User Day, Market Outlook
4th Qatar BIM User Day, Market Outlook4th Qatar BIM User Day, Market Outlook
4th Qatar BIM User Day, Market Outlook
BIM User Day
 
3rd Qatar BIM User Day - Certification systems for BIM software training
3rd Qatar BIM User Day - Certification systems for BIM software training3rd Qatar BIM User Day - Certification systems for BIM software training
3rd Qatar BIM User Day - Certification systems for BIM software training
BIM User Day
 
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
BIM User Day
 
1st Qatar BIM User Day BIM processes Case Study #1
1st Qatar BIM User Day BIM processes Case Study #11st Qatar BIM User Day BIM processes Case Study #1
1st Qatar BIM User Day BIM processes Case Study #1
BIM User Day
 
2nd Qatar BIM User Day BIM Technology Market Demand
2nd Qatar BIM User Day  BIM Technology  Market Demand2nd Qatar BIM User Day  BIM Technology  Market Demand
2nd Qatar BIM User Day BIM Technology Market Demand
BIM User Day
 
1st Qatar BIM User DAY Market demand/requirements
1st Qatar BIM User DAY  Market demand/requirements1st Qatar BIM User DAY  Market demand/requirements
1st Qatar BIM User DAY Market demand/requirements
BIM User Day
 
4th Qatar BIM User Day, BIM Protocols for Qatar
4th Qatar BIM User Day, BIM Protocols for Qatar4th Qatar BIM User Day, BIM Protocols for Qatar
4th Qatar BIM User Day, BIM Protocols for Qatar
BIM User Day
 
4th Qatar BIM User Day, BIM in Contracts
4th Qatar BIM User Day, BIM in Contracts4th Qatar BIM User Day, BIM in Contracts
4th Qatar BIM User Day, BIM in Contracts
BIM User Day
 
5th Qatar BIM User Day, BIM process implementation and management on Qatar me...
5th Qatar BIM User Day, BIM process implementation and management on Qatar me...5th Qatar BIM User Day, BIM process implementation and management on Qatar me...
5th Qatar BIM User Day, BIM process implementation and management on Qatar me...
BIM User Day
 
4th Qatar BIM User Day, Case Study
4th Qatar BIM User Day, Case Study4th Qatar BIM User Day, Case Study
4th Qatar BIM User Day, Case Study
BIM User Day
 
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
BIM User Day
 
2nd Qatar BIM User Day Document Control and Collaboration Technologies
2nd Qatar BIM User Day  Document Control and Collaboration Technologies2nd Qatar BIM User Day  Document Control and Collaboration Technologies
2nd Qatar BIM User Day Document Control and Collaboration Technologies
BIM User Day
 
5th Qatar BIM User Day, RICS – Decision making, training and BIM
5th Qatar BIM User Day, RICS – Decision making, training and BIM5th Qatar BIM User Day, RICS – Decision making, training and BIM
5th Qatar BIM User Day, RICS – Decision making, training and BIM
BIM User Day
 
4th Qatar BIM User Day, BIM Guides and Standards
4th Qatar BIM User Day, BIM Guides and Standards4th Qatar BIM User Day, BIM Guides and Standards
4th Qatar BIM User Day, BIM Guides and Standards
BIM User Day
 

Viewers also liked (19)

2nd Qatar BIM User Day Scheduling, QTO and Estimating Technology
2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology
2nd Qatar BIM User Day Scheduling, QTO and Estimating Technology
 
4th Qatar BIM User Day, BIM Solutions and Strategies
4th Qatar BIM User Day, BIM Solutions and Strategies4th Qatar BIM User Day, BIM Solutions and Strategies
4th Qatar BIM User Day, BIM Solutions and Strategies
 
4th Qatar BIM User Day, Collaboration or Co-Operation
4th Qatar BIM User Day, Collaboration or Co-Operation4th Qatar BIM User Day, Collaboration or Co-Operation
4th Qatar BIM User Day, Collaboration or Co-Operation
 
3rd Qatar BIM User Day - The BIM Manager within the Project Organisation
3rd Qatar BIM User Day - The BIM Manager within the Project Organisation3rd Qatar BIM User Day - The BIM Manager within the Project Organisation
3rd Qatar BIM User Day - The BIM Manager within the Project Organisation
 
1st Qatar BIM User DAY BIM processes Case Study #2
1st Qatar BIM User DAY  BIM processes Case Study #21st Qatar BIM User DAY  BIM processes Case Study #2
1st Qatar BIM User DAY BIM processes Case Study #2
 
4th Qatar BIM User Day, Market Outlook
4th Qatar BIM User Day, Market Outlook4th Qatar BIM User Day, Market Outlook
4th Qatar BIM User Day, Market Outlook
 
3rd Qatar BIM User Day - Certification systems for BIM software training
3rd Qatar BIM User Day - Certification systems for BIM software training3rd Qatar BIM User Day - Certification systems for BIM software training
3rd Qatar BIM User Day - Certification systems for BIM software training
 
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
 
1st Qatar BIM User Day BIM processes Case Study #1
1st Qatar BIM User Day BIM processes Case Study #11st Qatar BIM User Day BIM processes Case Study #1
1st Qatar BIM User Day BIM processes Case Study #1
 
2nd Qatar BIM User Day BIM Technology Market Demand
2nd Qatar BIM User Day  BIM Technology  Market Demand2nd Qatar BIM User Day  BIM Technology  Market Demand
2nd Qatar BIM User Day BIM Technology Market Demand
 
1st Qatar BIM User DAY Market demand/requirements
1st Qatar BIM User DAY  Market demand/requirements1st Qatar BIM User DAY  Market demand/requirements
1st Qatar BIM User DAY Market demand/requirements
 
4th Qatar BIM User Day, BIM Protocols for Qatar
4th Qatar BIM User Day, BIM Protocols for Qatar4th Qatar BIM User Day, BIM Protocols for Qatar
4th Qatar BIM User Day, BIM Protocols for Qatar
 
4th Qatar BIM User Day, BIM in Contracts
4th Qatar BIM User Day, BIM in Contracts4th Qatar BIM User Day, BIM in Contracts
4th Qatar BIM User Day, BIM in Contracts
 
5th Qatar BIM User Day, BIM process implementation and management on Qatar me...
5th Qatar BIM User Day, BIM process implementation and management on Qatar me...5th Qatar BIM User Day, BIM process implementation and management on Qatar me...
5th Qatar BIM User Day, BIM process implementation and management on Qatar me...
 
4th Qatar BIM User Day, Case Study
4th Qatar BIM User Day, Case Study4th Qatar BIM User Day, Case Study
4th Qatar BIM User Day, Case Study
 
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
 
2nd Qatar BIM User Day Document Control and Collaboration Technologies
2nd Qatar BIM User Day  Document Control and Collaboration Technologies2nd Qatar BIM User Day  Document Control and Collaboration Technologies
2nd Qatar BIM User Day Document Control and Collaboration Technologies
 
5th Qatar BIM User Day, RICS – Decision making, training and BIM
5th Qatar BIM User Day, RICS – Decision making, training and BIM5th Qatar BIM User Day, RICS – Decision making, training and BIM
5th Qatar BIM User Day, RICS – Decision making, training and BIM
 
4th Qatar BIM User Day, BIM Guides and Standards
4th Qatar BIM User Day, BIM Guides and Standards4th Qatar BIM User Day, BIM Guides and Standards
4th Qatar BIM User Day, BIM Guides and Standards
 

Similar to 1st Qatar BIM User Day Business processes supported by BIM methodology, part 3

Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
HafixFarhan
 
Cordoba Corp: Best Practices for Security Camera Implementation
Cordoba Corp: Best  Practices for Security Camera ImplementationCordoba Corp: Best  Practices for Security Camera Implementation
Cordoba Corp: Best Practices for Security Camera Implementation
Cordoba Corp
 
BIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionBIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuction
Reshma Philip
 
3rd Qatar BIM User Day - Establishing International BIM Certification System
3rd Qatar BIM User Day - Establishing International BIM Certification System3rd Qatar BIM User Day - Establishing International BIM Certification System
3rd Qatar BIM User Day - Establishing International BIM Certification System
BIM User Day
 
Bussiness planning process
Bussiness planning processBussiness planning process
Bussiness planning process
Dr Fereidoun Dejahang
 
Construction ​Visualization​: 4D BIM Scheduling & Simulation​
Construction ​Visualization​: 4D BIM Scheduling & Simulation​Construction ​Visualization​: 4D BIM Scheduling & Simulation​
Construction ​Visualization​: 4D BIM Scheduling & Simulation​
Top BIM Company
 
S3.2_PRES_Single_Source_of_Truth_BMcCallum
S3.2_PRES_Single_Source_of_Truth_BMcCallumS3.2_PRES_Single_Source_of_Truth_BMcCallum
S3.2_PRES_Single_Source_of_Truth_BMcCallum
Bruce McCallum
 
06 project time management
06  project time management06  project time management
06 project time management
Ala Ibrahim
 
Building Information Modelling (BIM) Lessons at University of Hull's Student ...
Building Information Modelling (BIM) Lessons at University of Hull's Student ...Building Information Modelling (BIM) Lessons at University of Hull's Student ...
Building Information Modelling (BIM) Lessons at University of Hull's Student ...
Sewell Construction
 
Foundation works norwich - 15th october 2012
Foundation works   norwich - 15th october 2012Foundation works   norwich - 15th october 2012
Foundation works norwich - 15th october 2012
carolmcnulty
 
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
Aconex
 
SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptx
Sushant895574
 
L2_Scope Management.ppt
L2_Scope Management.pptL2_Scope Management.ppt
L2_Scope Management.ppt
MUST
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
DavidMcLachlan1
 
American Electric Power Ercot kickoff
American Electric Power Ercot kickoffAmerican Electric Power Ercot kickoff
American Electric Power Ercot kickoff
John Napier
 
Make BIM work for you
Make BIM work for youMake BIM work for you
Make BIM work for you
CCT International
 
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanhVGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
Vietnam Green Building Council
 
atb-brochure.pdf
atb-brochure.pdfatb-brochure.pdf
atb-brochure.pdf
AllthingsBIM
 
GTB-brochure.pdf
GTB-brochure.pdfGTB-brochure.pdf
GTB-brochure.pdf
Mandeep Singh
 
L2_Scope Management.ppt
L2_Scope Management.pptL2_Scope Management.ppt
L2_Scope Management.ppt
MUST
 

Similar to 1st Qatar BIM User Day Business processes supported by BIM methodology, part 3 (20)

Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
 
Cordoba Corp: Best Practices for Security Camera Implementation
Cordoba Corp: Best  Practices for Security Camera ImplementationCordoba Corp: Best  Practices for Security Camera Implementation
Cordoba Corp: Best Practices for Security Camera Implementation
 
BIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionBIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuction
 
3rd Qatar BIM User Day - Establishing International BIM Certification System
3rd Qatar BIM User Day - Establishing International BIM Certification System3rd Qatar BIM User Day - Establishing International BIM Certification System
3rd Qatar BIM User Day - Establishing International BIM Certification System
 
Bussiness planning process
Bussiness planning processBussiness planning process
Bussiness planning process
 
Construction ​Visualization​: 4D BIM Scheduling & Simulation​
Construction ​Visualization​: 4D BIM Scheduling & Simulation​Construction ​Visualization​: 4D BIM Scheduling & Simulation​
Construction ​Visualization​: 4D BIM Scheduling & Simulation​
 
S3.2_PRES_Single_Source_of_Truth_BMcCallum
S3.2_PRES_Single_Source_of_Truth_BMcCallumS3.2_PRES_Single_Source_of_Truth_BMcCallum
S3.2_PRES_Single_Source_of_Truth_BMcCallum
 
06 project time management
06  project time management06  project time management
06 project time management
 
Building Information Modelling (BIM) Lessons at University of Hull's Student ...
Building Information Modelling (BIM) Lessons at University of Hull's Student ...Building Information Modelling (BIM) Lessons at University of Hull's Student ...
Building Information Modelling (BIM) Lessons at University of Hull's Student ...
 
Foundation works norwich - 15th october 2012
Foundation works   norwich - 15th october 2012Foundation works   norwich - 15th october 2012
Foundation works norwich - 15th october 2012
 
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
 
SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptx
 
L2_Scope Management.ppt
L2_Scope Management.pptL2_Scope Management.ppt
L2_Scope Management.ppt
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
American Electric Power Ercot kickoff
American Electric Power Ercot kickoffAmerican Electric Power Ercot kickoff
American Electric Power Ercot kickoff
 
Make BIM work for you
Make BIM work for youMake BIM work for you
Make BIM work for you
 
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanhVGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
 
atb-brochure.pdf
atb-brochure.pdfatb-brochure.pdf
atb-brochure.pdf
 
GTB-brochure.pdf
GTB-brochure.pdfGTB-brochure.pdf
GTB-brochure.pdf
 
L2_Scope Management.ppt
L2_Scope Management.pptL2_Scope Management.ppt
L2_Scope Management.ppt
 

More from BIM User Day

5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
BIM User Day
 
5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project
BIM User Day
 
5th Qatar BIM User Day, BIM Interoperability Issues: Lessons learned from PLM
5th Qatar BIM User Day, BIM Interoperability Issues: Lessons learned from PLM5th Qatar BIM User Day, BIM Interoperability Issues: Lessons learned from PLM
5th Qatar BIM User Day, BIM Interoperability Issues: Lessons learned from PLM
BIM User Day
 
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIM5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
BIM User Day
 
5th Qatar BIM User Day, Defining the role of the BIM Manager
5th Qatar BIM User Day, Defining the role of the BIM Manager5th Qatar BIM User Day, Defining the role of the BIM Manager
5th Qatar BIM User Day, Defining the role of the BIM Manager
BIM User Day
 
5th Qatar BIM User Day, BIM Introduction
5th Qatar BIM User Day, BIM Introduction5th Qatar BIM User Day, BIM Introduction
5th Qatar BIM User Day, BIM Introduction
BIM User Day
 
1st Qatar BIM User Day Business processes supported by BIM methodology, part 1
1st Qatar BIM User Day Business processes supported by BIM methodology, part 11st Qatar BIM User Day Business processes supported by BIM methodology, part 1
1st Qatar BIM User Day Business processes supported by BIM methodology, part 1
BIM User Day
 

More from BIM User Day (7)

5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
 
5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project
 
5th Qatar BIM User Day, BIM Interoperability Issues: Lessons learned from PLM
5th Qatar BIM User Day, BIM Interoperability Issues: Lessons learned from PLM5th Qatar BIM User Day, BIM Interoperability Issues: Lessons learned from PLM
5th Qatar BIM User Day, BIM Interoperability Issues: Lessons learned from PLM
 
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIM5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
 
5th Qatar BIM User Day, Defining the role of the BIM Manager
5th Qatar BIM User Day, Defining the role of the BIM Manager5th Qatar BIM User Day, Defining the role of the BIM Manager
5th Qatar BIM User Day, Defining the role of the BIM Manager
 
5th Qatar BIM User Day, BIM Introduction
5th Qatar BIM User Day, BIM Introduction5th Qatar BIM User Day, BIM Introduction
5th Qatar BIM User Day, BIM Introduction
 
1st Qatar BIM User Day Business processes supported by BIM methodology, part 1
1st Qatar BIM User Day Business processes supported by BIM methodology, part 11st Qatar BIM User Day Business processes supported by BIM methodology, part 1
1st Qatar BIM User Day Business processes supported by BIM methodology, part 1
 

Recently uploaded

June Patch Tuesday
June Patch TuesdayJune Patch Tuesday
June Patch Tuesday
Ivanti
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Tosin Akinosho
 
Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)
Jakub Marek
 
GenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizationsGenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizations
kumardaparthi1024
 
How to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For FlutterHow to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For Flutter
Daiki Mogmet Ito
 
Recommendation System using RAG Architecture
Recommendation System using RAG ArchitectureRecommendation System using RAG Architecture
Recommendation System using RAG Architecture
fredae14
 
UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6
DianaGray10
 
WeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation TechniquesWeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation Techniques
Postman
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
panagenda
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
danishmna97
 
UI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentationUI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentation
Wouter Lemaire
 
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Jeffrey Haguewood
 
Project Management Semester Long Project - Acuity
Project Management Semester Long Project - AcuityProject Management Semester Long Project - Acuity
Project Management Semester Long Project - Acuity
jpupo2018
 
Mariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceXMariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceX
Mariano Tinti
 
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
akankshawande
 
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdfHow to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
Chart Kalyan
 
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial IntelligenceAI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
IndexBug
 
Digital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying AheadDigital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying Ahead
Wask
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
Zilliz
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
ssuserfac0301
 

Recently uploaded (20)

June Patch Tuesday
June Patch TuesdayJune Patch Tuesday
June Patch Tuesday
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
 
Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)
 
GenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizationsGenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizations
 
How to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For FlutterHow to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For Flutter
 
Recommendation System using RAG Architecture
Recommendation System using RAG ArchitectureRecommendation System using RAG Architecture
Recommendation System using RAG Architecture
 
UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6
 
WeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation TechniquesWeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation Techniques
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
 
UI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentationUI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentation
 
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
 
Project Management Semester Long Project - Acuity
Project Management Semester Long Project - AcuityProject Management Semester Long Project - Acuity
Project Management Semester Long Project - Acuity
 
Mariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceXMariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceX
 
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
 
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdfHow to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
 
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial IntelligenceAI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
 
Digital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying AheadDigital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying Ahead
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
 

1st Qatar BIM User Day Business processes supported by BIM methodology, part 3

  • 1. Business processes supported by BIM Methodology: scheduling and progress monitoring Prof. Nashwan Dawood Teesside University, UK n.n.dawood@tees.ac.uk Speaker Name 1
  • 2. Scheduling and Monitoring Processes • Scheduling: what, when, by whom, how, what-if, etc • WBS is the standard for scheduling practices. Network analysis, barchat and LoB are typical techniques • To update schedules, monitoring of construction activities will be conducted on weekly or monthly intervals. • New paradigm of integrating WBS with PBS for 4D planning. Whole schedule 2
  • 4. Issues with traditional scheduling Site congestions Crowded areas CAD Design Drawings Project Schedule Design Plan/Tender Access blockage Build 4 4
  • 5. Concept of 4D Scheduling • Integration of BIM (mainly 3D models) and schedules (4D) • Shows progress of construction activities at any time. • Visualisation of construction products through time. • Site Logistics. 5 5
  • 6. 4D and construction processes • • • • • • • • Initiation Preliminary Design and developments Detailed design Contracts and planning Production Commissioning Operation 4D scheduling Sequence of tasks 6
  • 8. BIM & 4D Scheduling • Schedule analysis (constructability, spatial constraints, complex sequences, what-if) • Schedule Review (planned vs actual) • Communication and marketing (main contractor with client, main contractor with subcontractors) • Subcontractors coordination on site/work-flow planning • Track Construction progress. 8
  • 9. Building Information Modelling 4D planning examples video 4D_preview_03.mp4 Speaker Name 9
  • 10. Schedules Analysis, process conflict Steel Beam and In-situ Ground Slab Visualisation (A) Work progress Visualisation Key Finished In progress Workspace Conflict 10 10
  • 11. Schedule Analysis Steel Beam and In-situ Ground Slab Space Conflicts (C) Workspace conflicts Visualisation Key Finished 11 In progress Workspace 11 Conflict
  • 12. Schedule analysis; execution space congestions Critical Space Spatial Overload Spatial Slack 12 12
  • 14. Value of 4D planning  Analysis of 3 Major projects (combined value of £400 million)  Development of Measurement methodology for KPIs  Progress monitoring and data anlysis 94% Time 92% Safety 82% Communication 80% Cost 7% Planning Efficiency Client Satisfaction Team Performance 70% 65% 62% 60% Productivity 52% Quality 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% % 14
  • 16. Research projects in the coming 10 years: automated and flexible visual scheduling. BIM KB Rules about Work methods and temp activities Extension of BIM (ground models, 16
  • 17. Conclusions • BIM has had very limited use in scheduling processes • 4D has been taken up with contracting organisation but as visual tool. • 4D has the potential to be developed to cover the control processes and utilised at workface. • New paradigm for utilising BIM for scheduling has been presented. 17