SlideShare a Scribd company logo
www.aarsleff.com
Road project Tanzania
Rehabilitation of 218 kilometres of road from Iyovi to Mafinga
In cooperation with Dutch Inter-
beton b.v., Aarsleff has rehabili-
tated the 150-kilometre-long road
stretch between Iyovi and Irin-
ga in Tanzania in East Africa in
the period from 2008 to 2011. In
2011, the contract was extended,
and up to August 2013 we are
rehabilitating 68 kilometres of
trunk road from Iringa to Maf-
inga. The projects are financed
by Danida’s mixed credits. The
road stretch is part of the Tan-
zam Highway; 1,000 kilometres
from the capital Dar es Salaam
to Tunduma on the border to
Zambia.
Extensive road rehabilitation
Our job is to carry out a com-
plete reconstruction of the entire
218-km-long road stretch. We
are to reconstruct a 6.7-metre-
wide existing road with shoul-
ders of 1.75 metres on both sides
of the road, establish a climbing
lane for heavy traffic and carry
out bus-bays and lay-bys for
police checkpoints. The existing
road bed is to be cement-sta-
bilised and will receive a new
base course gravel and asphalt
surfacing. At the same time, we
are extending the road with new
layers of base course grav-
el and asphalt. On a stretch of
22 kilometres, we have to drill
and blast the existing rock wall
on one side of the road to make
room for the extended design.
Renewal of drainage system
We are to carry out extensive
improvements of the drainage
system with new concrete box
culverts cast in situ and with
precast pipes of DN900 mm and
DN600 mm. In addition, we are
to renew and extend the existing
drainage systems to match the
new extended road. Finally, we
will establish lined side drains
and install steel and concrete
guard rails.
The joint venture has estab-
lished a quarry and produces all
stone ma-erials for gravel, con-
crete and asphalt in-house.
We use our own machinery and
equipment for all major con-
struction work. 650 Tanzanians
and a number of Danish and
Dutch engineers, technicians
and foremen are employed dur-
ing the 58-months construction
period.
www.aarsleff.com
Per Aarsleff A/S
Main office
Lokesvej 15
DK-8230 Aabyhoej
Denmark
Tel 	 +45 8744 2222
Fax	+45 8744 2249
Copenhagen office
Industriholmen 2
DK-2650 Hvidovre
Denmark
Tel 	 +45 3679 3333
Fax 	+45 3679 3300
Data
•	 Rehabilitation of 218 km of
trunk road
•	 1,025,000 m3
of earthwork
•	 390,000 m3
of crushed
aggregate road base
•	 315,000 tons of production
and placing of asphalt
pavement
•	 61 concrete box culverts
with 1 or 2 cells
•	 5,000 m of DN600 and DN900
mm precast reinforced con-
crete pipes
•	 10,000 m3
of lined side drains.
Client
Tanroads, Tanzania National
Roads Agency
Type of contract
Main contract
Contractor
Aarsleff Interbeton
Joint Venture
Partner
Interbeton b.v.,
the Netherlands
Construction period
2008-2013
Contract value
DKK 857 million
Contact
Construction
Estimation & Tender
kalkulation@aarsleff.com
Tel +45 8744 2222
ANLÆG-126UK-rev.5

More Related Content

What's hot

1 Drewry appreciation
1  Drewry appreciation1  Drewry appreciation
1 Drewry appreciation
Anil Seth
 
PROJECT NEWS Hilsea Bus Depot Sml
PROJECT NEWS Hilsea Bus Depot SmlPROJECT NEWS Hilsea Bus Depot Sml
PROJECT NEWS Hilsea Bus Depot Sml
Simon Tennent
 
Dane Street Play Area
Dane Street Play AreaDane Street Play Area
Dane Street Play Area
James Jeyes
 
Case Study - Court Buckingham, 94 New Cavendish St. London
Case Study - Court Buckingham, 94 New Cavendish St. LondonCase Study - Court Buckingham, 94 New Cavendish St. London
Case Study - Court Buckingham, 94 New Cavendish St. London
Steve Mandry
 
Russell Noanoa resume for 2015
Russell Noanoa resume for 2015Russell Noanoa resume for 2015
Russell Noanoa resume for 2015
Russell Noanoa
 
Case Study - 34 Elvaston Place
Case Study - 34 Elvaston PlaceCase Study - 34 Elvaston Place
Case Study - 34 Elvaston Place
Steve Mandry
 
CV John Brown - Jan 2015
CV John Brown - Jan 2015CV John Brown - Jan 2015
CV John Brown - Jan 2015
John Brown
 
Article for Africon FACET
Article for Africon FACETArticle for Africon FACET
Article for Africon FACET
Christo Beukes
 

What's hot (20)

1 Drewry appreciation
1  Drewry appreciation1  Drewry appreciation
1 Drewry appreciation
 
BlockMaster – The Solution for Handling Brick, Block Flag and Kerb from B&B A...
BlockMaster – The Solution for Handling Brick, Block Flag and Kerb from B&B A...BlockMaster – The Solution for Handling Brick, Block Flag and Kerb from B&B A...
BlockMaster – The Solution for Handling Brick, Block Flag and Kerb from B&B A...
 
PROJECT NEWS Hilsea Bus Depot Sml
PROJECT NEWS Hilsea Bus Depot SmlPROJECT NEWS Hilsea Bus Depot Sml
PROJECT NEWS Hilsea Bus Depot Sml
 
Dane Street Play Area
Dane Street Play AreaDane Street Play Area
Dane Street Play Area
 
Case Study - Court Buckingham, 94 New Cavendish St. London
Case Study - Court Buckingham, 94 New Cavendish St. LondonCase Study - Court Buckingham, 94 New Cavendish St. London
Case Study - Court Buckingham, 94 New Cavendish St. London
 
Russell Noanoa resume for 2015
Russell Noanoa resume for 2015Russell Noanoa resume for 2015
Russell Noanoa resume for 2015
 
Case Study - 34 Elvaston Place
Case Study - 34 Elvaston PlaceCase Study - 34 Elvaston Place
Case Study - 34 Elvaston Place
 
CV John Brown - Jan 2015
CV John Brown - Jan 2015CV John Brown - Jan 2015
CV John Brown - Jan 2015
 
Get the best Garage Conversions in Southall
Get the best Garage Conversions in SouthallGet the best Garage Conversions in Southall
Get the best Garage Conversions in Southall
 
Article for Africon FACET
Article for Africon FACETArticle for Africon FACET
Article for Africon FACET
 
Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018
Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018
Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018
 
Forklift Side loaders
Forklift Side loadersForklift Side loaders
Forklift Side loaders
 
Road priming
Road primingRoad priming
Road priming
 
Povazadi makitu production good
Povazadi makitu   production goodPovazadi makitu   production good
Povazadi makitu production good
 
Asphalt Paving | Asphalt Repair
Asphalt Paving | Asphalt RepairAsphalt Paving | Asphalt Repair
Asphalt Paving | Asphalt Repair
 
Siemens train vinyl wrapping, full train painting in central, western harbour...
Siemens train vinyl wrapping, full train painting in central, western harbour...Siemens train vinyl wrapping, full train painting in central, western harbour...
Siemens train vinyl wrapping, full train painting in central, western harbour...
 
Tristan Sandquist resume
Tristan Sandquist resumeTristan Sandquist resume
Tristan Sandquist resume
 
JAYERS Enterprises
JAYERS EnterprisesJAYERS Enterprises
JAYERS Enterprises
 
Chester Development Update: Phil Mayall, Muse Developments
Chester Development Update: Phil Mayall, Muse DevelopmentsChester Development Update: Phil Mayall, Muse Developments
Chester Development Update: Phil Mayall, Muse Developments
 
Josh 2
Josh 2Josh 2
Josh 2
 

Similar to 126_Vejprojekt_Tanzania_UK_5(1)

PIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase IPIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase I
Sven Maedler
 
N160143 - A1CH2MC Opening Ceremony Leaflet Binder
N160143 - A1CH2MC Opening Ceremony Leaflet BinderN160143 - A1CH2MC Opening Ceremony Leaflet Binder
N160143 - A1CH2MC Opening Ceremony Leaflet Binder
David Weston
 
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
Candice Spiroski
 
MCD_Oil & Gas Profile 2017.pdf
MCD_Oil & Gas Profile 2017.pdfMCD_Oil & Gas Profile 2017.pdf
MCD_Oil & Gas Profile 2017.pdf
KAWMAW
 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
Crosstown TO
 
Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)
Crosstown TO
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
Crosstown TO
 
NGRprojectfactsheetJan2014
NGRprojectfactsheetJan2014NGRprojectfactsheetJan2014
NGRprojectfactsheetJan2014
Glenn Post
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
May Begum
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
Hayley Sharp
 
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
Pavitter Virdi
 

Similar to 126_Vejprojekt_Tanzania_UK_5(1) (20)

PIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase IPIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase I
 
N160143 - A1CH2MC Opening Ceremony Leaflet Binder
N160143 - A1CH2MC Opening Ceremony Leaflet BinderN160143 - A1CH2MC Opening Ceremony Leaflet Binder
N160143 - A1CH2MC Opening Ceremony Leaflet Binder
 
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
 
Assignment Week 6
Assignment Week 6Assignment Week 6
Assignment Week 6
 
MCD_Oil & Gas Profile 2017.pdf
MCD_Oil & Gas Profile 2017.pdfMCD_Oil & Gas Profile 2017.pdf
MCD_Oil & Gas Profile 2017.pdf
 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
 
Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)
 
Exhibition boards 2
Exhibition boards 2Exhibition boards 2
Exhibition boards 2
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 
Central West Open House
Central West Open HouseCentral West Open House
Central West Open House
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
 
BigHertsBigIdeas for Business Network Event 31/1/14
BigHertsBigIdeas for Business Network Event 31/1/14BigHertsBigIdeas for Business Network Event 31/1/14
BigHertsBigIdeas for Business Network Event 31/1/14
 
NGRprojectfactsheetJan2014
NGRprojectfactsheetJan2014NGRprojectfactsheetJan2014
NGRprojectfactsheetJan2014
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
 
Multigas Brochure
Multigas BrochureMultigas Brochure
Multigas Brochure
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Atkins' tunnelling projects
Atkins' tunnelling projectsAtkins' tunnelling projects
Atkins' tunnelling projects
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.v
 

126_Vejprojekt_Tanzania_UK_5(1)

  • 1. www.aarsleff.com Road project Tanzania Rehabilitation of 218 kilometres of road from Iyovi to Mafinga In cooperation with Dutch Inter- beton b.v., Aarsleff has rehabili- tated the 150-kilometre-long road stretch between Iyovi and Irin- ga in Tanzania in East Africa in the period from 2008 to 2011. In 2011, the contract was extended, and up to August 2013 we are rehabilitating 68 kilometres of trunk road from Iringa to Maf- inga. The projects are financed by Danida’s mixed credits. The road stretch is part of the Tan- zam Highway; 1,000 kilometres from the capital Dar es Salaam to Tunduma on the border to Zambia. Extensive road rehabilitation Our job is to carry out a com- plete reconstruction of the entire 218-km-long road stretch. We are to reconstruct a 6.7-metre- wide existing road with shoul- ders of 1.75 metres on both sides of the road, establish a climbing lane for heavy traffic and carry out bus-bays and lay-bys for police checkpoints. The existing road bed is to be cement-sta- bilised and will receive a new base course gravel and asphalt surfacing. At the same time, we are extending the road with new layers of base course grav- el and asphalt. On a stretch of 22 kilometres, we have to drill and blast the existing rock wall on one side of the road to make room for the extended design. Renewal of drainage system We are to carry out extensive improvements of the drainage system with new concrete box culverts cast in situ and with precast pipes of DN900 mm and DN600 mm. In addition, we are to renew and extend the existing drainage systems to match the new extended road. Finally, we will establish lined side drains and install steel and concrete guard rails. The joint venture has estab- lished a quarry and produces all stone ma-erials for gravel, con- crete and asphalt in-house. We use our own machinery and equipment for all major con- struction work. 650 Tanzanians and a number of Danish and Dutch engineers, technicians and foremen are employed dur- ing the 58-months construction period.
  • 2. www.aarsleff.com Per Aarsleff A/S Main office Lokesvej 15 DK-8230 Aabyhoej Denmark Tel +45 8744 2222 Fax +45 8744 2249 Copenhagen office Industriholmen 2 DK-2650 Hvidovre Denmark Tel +45 3679 3333 Fax +45 3679 3300 Data • Rehabilitation of 218 km of trunk road • 1,025,000 m3 of earthwork • 390,000 m3 of crushed aggregate road base • 315,000 tons of production and placing of asphalt pavement • 61 concrete box culverts with 1 or 2 cells • 5,000 m of DN600 and DN900 mm precast reinforced con- crete pipes • 10,000 m3 of lined side drains. Client Tanroads, Tanzania National Roads Agency Type of contract Main contract Contractor Aarsleff Interbeton Joint Venture Partner Interbeton b.v., the Netherlands Construction period 2008-2013 Contract value DKK 857 million Contact Construction Estimation & Tender kalkulation@aarsleff.com Tel +45 8744 2222 ANLÆG-126UK-rev.5