This document is a 16-page decision from the Supreme Court of the Philippines regarding a dispute between Shinryo (Philippines) Company, Inc. and RRN Incorporated over unpaid accounts and overpayment from a construction project. The Construction Industry Arbitration Commission ruled in favor of RRN, awarding unpaid accounts plus interest. Shinryo appealed, arguing that RRN should pay for use of equipment and that the materials and completion costs awards were incorrect. However, the Court of Appeals and now the Supreme Court affirmed the CIAC's decision, finding that Shinryo did not prove its claims or present sufficient evidence to overturn the factual findings of the arbitration body.
The following documents were submitted by the Republic of Ecuador to the international arbitration hearing the case between Chevron/Texaco and the Republic. These documents further show the impact of Chevron/Texaco’s decades’ long oil pollution on the people of Ecuador.
Answering Brief by Newtown Estates Community AssociationAngela Kaaihue
Answering Brief by Newtown Estates Community Association
ANGELA KAAIHUE -VS- NEWTOWN ESTATES COMMUNITY ASSOCIATION- OPENING BRIEF CAAP-19-0000806
NEWTOWN ESTATES COMMUNITY ASSOCIATION
Hawaii Appellant Court Supreme Court judge castegnetti, judge jeffrey crabtree, judge karen t. nakasone, judge katherine g. leonard, judge keith hiraoka, judge lisa m. ginoza, judge sonja mccullen, judge clyde j. wadsworth, judge karen holma, judge gary W.B. chang
The following documents were submitted by the Republic of Ecuador to the international arbitration hearing the case between Chevron/Texaco and the Republic. These documents further show the impact of Chevron/Texaco’s decades’ long oil pollution on the people of Ecuador.
Answering Brief by Newtown Estates Community AssociationAngela Kaaihue
Answering Brief by Newtown Estates Community Association
ANGELA KAAIHUE -VS- NEWTOWN ESTATES COMMUNITY ASSOCIATION- OPENING BRIEF CAAP-19-0000806
NEWTOWN ESTATES COMMUNITY ASSOCIATION
Hawaii Appellant Court Supreme Court judge castegnetti, judge jeffrey crabtree, judge karen t. nakasone, judge katherine g. leonard, judge keith hiraoka, judge lisa m. ginoza, judge sonja mccullen, judge clyde j. wadsworth, judge karen holma, judge gary W.B. chang
Fisker's lawsuit against insurance companykatiefehren
A lawsuit filed by Fisker against insurance company XL for denying its claim when 338 Karmas were lost in Sandy flooding, which had a value of $33 million.
Nigerian People Vs ROYAL DUTCH SHELL PLC [2015] EWHC HT-2015-000241 & HT-2015...Richard Levicki
See Para 117 for the cowardly we can do what we want, High Court again refuses to hold UK parent companies for account as Shell blocks more than 40,000 Nigerians from holding it to account for oil spills in the English courts yesterday. Our courts have become corporate protectors and mass human rights abuse facilitators. These judgements must be challenged.
FORECLOSURE Response to JP Morgan Chase Foreclosurelauren tratar
WAKE UP AMERICA! Banks are STEALING HOUSES they do not own nor did they pay a dime for! Mortgages were PRE-SOLD to Investors of Mortgage-Backed Securities. A bank CANNOT foreclose if it has NOTHING TO LOSE! The banks shifted the risk to the Investors and the banks took the PROMISSORY NOTES cashed them into the FRAUDULENT FEDERAL RESERVE, and then SOLD the exact same NOTES to MBS Trusts MULTIPLE TIMES!!!
A motion by the City and County of Honolulu and the FTA to dismiss some plaintiffs and some claims from a federal environmental lawsuit was denied by a judge.
Motion for Summary Judgment by Kanawha Stone containing the deposition and re...Putnam Reporter
Motion For Summary Judgment with exhibit containing the depositions and resumes of the plaintiffs in the case of :
DOLORES HALBURN and MARK HALBURN,
Plaintiffs,
v.
CITY OF HURRICANE, WEST VIRGINIA,
a municipal corporation, BEN NEWHOUSE,
individually and in his capacity as City Manager
for the City of Hurricane, CLEVELAND
CONSTRUCTION, INC. dba Cleveland
Construction, Inc. Of Nevada, and KANAWHA
STONE COMPANY, INC.,
Defendants.
Putnam County WV Civil Action No. 07-C-298
The official motion filed with the New York State Court of Appeals, NY's highest court, to hear the case of Norse Energy v Town of Dryden over the town's vote to ban all fracking and drilling throughout the township.
Fisker's lawsuit against insurance companykatiefehren
A lawsuit filed by Fisker against insurance company XL for denying its claim when 338 Karmas were lost in Sandy flooding, which had a value of $33 million.
Nigerian People Vs ROYAL DUTCH SHELL PLC [2015] EWHC HT-2015-000241 & HT-2015...Richard Levicki
See Para 117 for the cowardly we can do what we want, High Court again refuses to hold UK parent companies for account as Shell blocks more than 40,000 Nigerians from holding it to account for oil spills in the English courts yesterday. Our courts have become corporate protectors and mass human rights abuse facilitators. These judgements must be challenged.
FORECLOSURE Response to JP Morgan Chase Foreclosurelauren tratar
WAKE UP AMERICA! Banks are STEALING HOUSES they do not own nor did they pay a dime for! Mortgages were PRE-SOLD to Investors of Mortgage-Backed Securities. A bank CANNOT foreclose if it has NOTHING TO LOSE! The banks shifted the risk to the Investors and the banks took the PROMISSORY NOTES cashed them into the FRAUDULENT FEDERAL RESERVE, and then SOLD the exact same NOTES to MBS Trusts MULTIPLE TIMES!!!
A motion by the City and County of Honolulu and the FTA to dismiss some plaintiffs and some claims from a federal environmental lawsuit was denied by a judge.
Motion for Summary Judgment by Kanawha Stone containing the deposition and re...Putnam Reporter
Motion For Summary Judgment with exhibit containing the depositions and resumes of the plaintiffs in the case of :
DOLORES HALBURN and MARK HALBURN,
Plaintiffs,
v.
CITY OF HURRICANE, WEST VIRGINIA,
a municipal corporation, BEN NEWHOUSE,
individually and in his capacity as City Manager
for the City of Hurricane, CLEVELAND
CONSTRUCTION, INC. dba Cleveland
Construction, Inc. Of Nevada, and KANAWHA
STONE COMPANY, INC.,
Defendants.
Putnam County WV Civil Action No. 07-C-298
The official motion filed with the New York State Court of Appeals, NY's highest court, to hear the case of Norse Energy v Town of Dryden over the town's vote to ban all fracking and drilling throughout the township.
The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...nourhaghighi
The following is DRAFT of the Major Nourhaghighi's Winning Factum before the highest court in Ontario
in which Major Nourhaghighi won a case against
the most experience Law Firm, Deacon, Spears, Fedson, & Montizambert LLP,
specialist in the Ontario Condominium Act
with $1500.00 award of Costs to Major Nourhaghighi
Court File No: M 32976
COURT OF APPEAL FOR ONTARIO
BETWEEN:
MAJOR KEYVAN NOURHAGHIGHI
Applicant (Responding Party)
-and-
CABER MANAGEMENT SERVICES INC. JOHN BEDFORD, JOHN MORIELLI,
LISA BLAIR; METRO TORONTO CONDOMINIUM CORPORATION NO. 935
Respondents (Moving Parties)
Confessions of Judgement in Kyko Global Inc vs Madhavi Vuppalapati & Prithvi ...mh37o
The judgement was passed in favour of Plaintiffs Kyko Global Inc. Confessions of Judgement in Kyko Global Inc vs Madhavi Vuppalapati & Prithvi Info Solutions Ltd
FORECLOSURE Response to JP Morgan Chase Foreclosurelauren tratar
WAKE UP AMERICA! Banks are STEALING HOUSES they do not own nor did they pay a dime for! Mortgages were PRE-SOLD to Investors of Mortgage-Backed Securities. A bank CANNOT foreclose if it has NOTHING TO LOSE! The banks shifted the risk to the Investors and the banks took the PROMISSORY NOTES cashed them into the FRAUDULENT FEDERAL RESERVE, and then SOLD the exact same NOTES to MBS Trusts MULTIPLE TIMES!!!
Sample California motion to strike complaintLegalDocsPro
This sample motion to strike portions of a complaint for California was created by a freelance paralegal who has worked in California and Federal litigation since 1995 and has used this sample for many years.
Opposition to a California summary judgment motionLegalDocsPro
This sample opposition to a motion for summary judgment in California was created by a freelance paralegal who has worked in California and Federal litigation since 1995 and has used this sample for many years.
Supporting documentation for the Motion to add 200 new plaintiffs to the Armando Montelongo Lawsuit. This outlines how attempts to Arbitrate the case failed due to Montelongo refusing to follow the American Arbitration Association Rules, thus they declined to arbitrate the case and asked he remove their name from clauses in the contract. In addition, new plaintiff's have approached the case with similar details of fraud. A synopsis of the entire suit is at http://www.jeannorton.com/armando-montelongo-rico-doubles/
Biological screening of herbal drugs: Introduction and Need for
Phyto-Pharmacological Screening, New Strategies for evaluating
Natural Products, In vitro evaluation techniques for Antioxidants, Antimicrobial and Anticancer drugs. In vivo evaluation techniques
for Anti-inflammatory, Antiulcer, Anticancer, Wound healing, Antidiabetic, Hepatoprotective, Cardio protective, Diuretics and
Antifertility, Toxicity studies as per OECD guidelines
it describes the bony anatomy including the femoral head , acetabulum, labrum . also discusses the capsule , ligaments . muscle that act on the hip joint and the range of motion are outlined. factors affecting hip joint stability and weight transmission through the joint are summarized.
Executive Directors Chat Leveraging AI for Diversity, Equity, and InclusionTechSoup
Let’s explore the intersection of technology and equity in the final session of our DEI series. Discover how AI tools, like ChatGPT, can be used to support and enhance your nonprofit's DEI initiatives. Participants will gain insights into practical AI applications and get tips for leveraging technology to advance their DEI goals.
Introduction to AI for Nonprofits with Tapp NetworkTechSoup
Dive into the world of AI! Experts Jon Hill and Tareq Monaur will guide you through AI's role in enhancing nonprofit websites and basic marketing strategies, making it easy to understand and apply.
How to Build a Module in Odoo 17 Using the Scaffold MethodCeline George
Odoo provides an option for creating a module by using a single line command. By using this command the user can make a whole structure of a module. It is very easy for a beginner to make a module. There is no need to make each file manually. This slide will show how to create a module using the scaffold method.
Delivering Micro-Credentials in Technical and Vocational Education and TrainingAG2 Design
Explore how micro-credentials are transforming Technical and Vocational Education and Training (TVET) with this comprehensive slide deck. Discover what micro-credentials are, their importance in TVET, the advantages they offer, and the insights from industry experts. Additionally, learn about the top software applications available for creating and managing micro-credentials. This presentation also includes valuable resources and a discussion on the future of these specialised certifications.
For more detailed information on delivering micro-credentials in TVET, visit this https://tvettrainer.com/delivering-micro-credentials-in-tvet/
Macroeconomics- Movie Location
This will be used as part of your Personal Professional Portfolio once graded.
Objective:
Prepare a presentation or a paper using research, basic comparative analysis, data organization and application of economic information. You will make an informed assessment of an economic climate outside of the United States to accomplish an entertainment industry objective.
2024.06.01 Introducing a competency framework for languag learning materials ...Sandy Millin
http://sandymillin.wordpress.com/iateflwebinar2024
Published classroom materials form the basis of syllabuses, drive teacher professional development, and have a potentially huge influence on learners, teachers and education systems. All teachers also create their own materials, whether a few sentences on a blackboard, a highly-structured fully-realised online course, or anything in between. Despite this, the knowledge and skills needed to create effective language learning materials are rarely part of teacher training, and are mostly learnt by trial and error.
Knowledge and skills frameworks, generally called competency frameworks, for ELT teachers, trainers and managers have existed for a few years now. However, until I created one for my MA dissertation, there wasn’t one drawing together what we need to know and do to be able to effectively produce language learning materials.
This webinar will introduce you to my framework, highlighting the key competencies I identified from my research. It will also show how anybody involved in language teaching (any language, not just English!), teacher training, managing schools or developing language learning materials can benefit from using the framework.
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Dr. Vinod Kumar Kanvaria
Exploiting Artificial Intelligence for Empowering Researchers and Faculty,
International FDP on Fundamentals of Research in Social Sciences
at Integral University, Lucknow, 06.06.2024
By Dr. Vinod Kumar Kanvaria
A Strategic Approach: GenAI in EducationPeter Windle
Artificial Intelligence (AI) technologies such as Generative AI, Image Generators and Large Language Models have had a dramatic impact on teaching, learning and assessment over the past 18 months. The most immediate threat AI posed was to Academic Integrity with Higher Education Institutes (HEIs) focusing their efforts on combating the use of GenAI in assessment. Guidelines were developed for staff and students, policies put in place too. Innovative educators have forged paths in the use of Generative AI for teaching, learning and assessments leading to pockets of transformation springing up across HEIs, often with little or no top-down guidance, support or direction.
This Gasta posits a strategic approach to integrating AI into HEIs to prepare staff, students and the curriculum for an evolving world and workplace. We will highlight the advantages of working with these technologies beyond the realm of teaching, learning and assessment by considering prompt engineering skills, industry impact, curriculum changes, and the need for staff upskilling. In contrast, not engaging strategically with Generative AI poses risks, including falling behind peers, missed opportunities and failing to ensure our graduates remain employable. The rapid evolution of AI technologies necessitates a proactive and strategic approach if we are to remain relevant.
1. Page 1 of 16
Homework Help
https://www.homeworkping.com/
Research Paper help
https://www.homeworkping.com/
Online Tutoring
https://www.homeworkping.com/
click here for freelancing tutoring sites
Republic of the Philippines
Supreme Court
Manila
SECOND DIVISION
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
2. Page 2 of 16
SHINRYO (PHILIPPINES) COMPANY,
INC.,
Petitioner,
- versus -
RRN INCORPORATED,*
Respondent.
G.R. No. 172525
Present:
CARPIO, J., Chairperson,
VELASCO, JR.,**
LEONARDO-DE CASTRO,***
PERALTA, and
MENDOZA, JJ.
Promulgated:
October 20, 2010
x-----------------------------------------------------------------------------------------x
DECISION
PERALTA, J.:
This resolves the Petition for Review on Certiorari under Rule 45 of
the Rules of Court, praying that the Decision[1]
of the Court of Appeals
(CA) dated February 22, 2006, affirming the Decision of the Construction
Industry Arbitration Commission (CIAC), and the CA Resolution[2]
dated
April 26, 2006, denying herein petitioner's motion for reconsideration,
be reversed and set aside.
The facts, as accurately narrated in the CA Decision, are as follows.
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
3. Page 3 of 16
Petitioner Shinryo (Philippines) Company, Inc.
(hereinafter petitioner) is a domestic corporation
organized under Philippine laws. Private respondent
RRN Incorporated (hereinafter respondent) is likewise a
domestic corporation organized under Philippine laws.
Respondent filed a claim for arbitration against
petitioner before CIAC for recovery of unpaid account
which consists of unpaid portions of the sub-contract,
variations and unused materials in the total sum
of P5,275,184.17 and legal interest in the amount
of P442,014.73. Petitioner filed a counterclaim for
overpayment in the amount of P2,512,997.96.
The parties admitted several facts before the
CIAC. It was shown that petitioner and respondent
executed an Agreement and Conditions of Sub-contract
(hereafter Agreement signed on June 11, 1996 and June
14, 1996, respectively. Respondent signified its
willingness to accept and perform for petitioner in any
of its projects, a part or the whole of the works more
particularly described in Conditions of Sub-Contract and
other Sub-contract documents.
On June 11, 2002, the parties executed a “Supply
of Manpower, Tools/Equipment, Consumables for the
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
4. Page 4 of 16
Electrical Works-Power and Equipment Supply, Bus Duct
Installation” for the Phillip Morris Greenfield Project
(hereafter Project) covered by Purchase Order Nos.
4501200300-000274 and 4501200300-000275
amounting to P15,724,000.00 and P9,276,000.00
respectively, or a total amount of P25,000,000.00. The
parties also agreed that respondent will perform
variation orders in the Project. In connection with the
Project, petitioner supplied manpower chargeable
against respondent.
Respondent was not able to finish the entire
works with petitioner due to financial
difficulties. Petitioner paid respondent a total amount
of P26,547,624.76. On June 25, 2005 [should read
2003], respondent, through its former counsel sent a
letter to petitioner demanding for the payment of its
unpaid balance amounting
to P5,275,184.17. Petitioner claimed material back
charges in the amount ofP4,063,633.43. On September
26, 2003, respondent only acknowledged P2,371,895.33
as material back charges. Thereafter, on October 16,
2003, respondent sent another letter to petitioner for
them to meet and settle their dispute.
On January 8, 2004, respondent sent another
letter to petitioner regarding the cost of equipment
rental and the use of scaffolding. Thereafter, on August
12, 2004, petitioner sent a letter to respondent denying
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
5. Page 5 of 16
any unpaid account and the failure in their negotiations
for amicable settlement.
On September 3, 2004, respondent, through its
new counsel, advised petitioner of their intention to
submit the matter to arbitration. Thereafter, their
dispute was submitted to arbitration. During the
preliminary conference, the parties agreed in their
Terms of Reference to resolve eight issues, to wit:
1. What should be the basis in evaluating the
variation cost?
1.1 How much is the variation cost?
2. Is the Respondent
(petitioner in the instant case) justified
in charging claimant (herein
respondent) the equipment rental fee
and for the use of the scaffoldings? If
so, how much should be charged to
Claimant?
3. What should be the basis in
evaluating the total cost of materials
supplied by Respondent to the Project
which is chargeable to Claimant?
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
6. Page 6 of 16
3.1 How much is the total cost of
materials supply chargeable to
Claimant?
4. How much is the value of
the remaining works left undone by the
Claimant in the project?
5. Is the Claimant's claim for
inventory of excess materials valid? If
so, how much is the value thereof?
6. Is the Respondent entitled
to its claim for an overpayment in the
amount of P2,512,997.96?
7. Is Claimant entitled to its
claim for interest? If so, how much?
8. Who between the parties
shall bear the cost of Arbitration?
The CIAC rendered the assailed decision
after the presentation of the parties'
evidence. [The dispositive portion of said
decision reads as follows:
WHEREFORE, judgment is hereby
rendered in favor of the claimant and
respondent is ordered to pay claimant
its unpaid account in the sum
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
7. Page 7 of 16
of P3,728,960.54 plus legal interest of
6% reckoned from June 25, 2003 up to
the filing of the case on October 11,
2004 and 12% of P3,728,960.54 from
the finality of the judgment until fully
paid and arbitration cost
of P104,333.82 representing claimant's
share of the arbitration cost which
respondent should reimburse.
SO ORDERED.]
Petitioner accepts the ruling of the CIAC only in
Issue No. 1 and Sub-Issue No. 1.1 and in Issue No. 2
in so far as the amount of P440,000.00 awarded as
back charges for the use of scaffoldings. x x x[3]
On February 22, 2006, the CA promulgated the assailed Decision
affirming the decision of the CIAC. The CA upheld the CIAC ruling that
petitioner failed to adduce sufficient proof that the parties had an
agreement regarding charges for respondent's use of the manlift. As to
the other charges for materials, the CA held that the evidence on record
amply supports the CIAC findings. Petitioner moved for reconsideration
of said ruling, but the same was denied per Resolution dated April 26,
2006.
Hence, this petition where it is alleged that:
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
8. Page 8 of 16
I. THE HONORABLE COURT OF APPEALS
COMMITTED GRAVE REVERSIBLE ERROR WHEN IT
DENIED PETITIONER'S CLAIM FOR MANLIFT EQUIPMENT
RENTAL IN THE AMOUNT OF P511,000.00 DESPITE
EVIDENCE ON RECORD THAT RESPONDENT RRN
ACTUALLY USED AND BENEFITED FROM THE MANLIFT
EQUIPMENT.
II. IN RENDERING THE QUESTIONED DECISION
AND QUESTIONED RESOLUTION, THE HONORABLE
COURT OF APPEALS HAS DECIDED A QUESTION OF
SUBSTANCE NOT IN ACCORD WITH LAW AND/OR WITH
THE APPLICABLE DECISIONS OF THE HONORABLE
SUPREME COURT.
III. THE COURT OF APPEALS COMMITTED A
GRAVE REVERSIBLE ERROR IN AFFIRMING THE CIAC
AWARD FOR THE VALUE OF INVENTORIED MATERIALS
CONSIDERING THAT:
A. RESPONDENT RRN ADMITTED THE
VALIDITY OF THE DEDUCTIONS ON
ACCOUNT OF MATERIAL SUPPLY,
WHICH INCLUDED THE INVENTORIED
MATERIALS.
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
9. Page 9 of 16
B. RESPONDENT RRN HAS NO BASIS TO
CLAIM BECAUSE ENGR. BONIFACIO
ADMITTED THAT RESPONDENT RRN
FAILED TO ESTABLISH WHETHER THE
MATERIALS CAME FROM RESPONDENT
RRN OR FROM PETITIONER AND THAT IT
WAS PETITIONER THAT ACTUALLY
INSTALLED THE SAID MATERIALS AS
PART OF REMAINING WORKS THAT
PETITIONER TOOK OVER FROM
RESPONDENT RRN.
C. THE CLAIM FOR THE VALUE OF
INVENTORIED MATERIALS IS A DOUBLE
CLAIM OR DOUBLE ENTRY BECAUSE IN
THE COMPUTATION OF THE FINAL
ACCOUNT, RESPONDENT RRN WAS
CREDITED THE FULL CONTRACT PRICE
AND THE COST OF VARIATIONS, WHICH
INCLUDED THE INVENTORIED
MATERIALS.
IV. IN RENDERING THE QUESTIONED DECISION
AND QUESTIONED RESOLUTION, THE COURT OF
APPEALS COMMITTED A GRAVE REVERSIBLE ERROR IN
THAT IT COMPLETELY DISREGARDED THE PROVISION OF
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
10. Page 10 of 16
THE SUBCONTRACT, WHICH ALLOWED PAYMENT OF
ACTUAL COST INCURRED BY PETITIONER IN
COMPLETING THE REMAINING WORKS THAT PRIVATE
RESPONDENT ADMITTEDLY FAILED TO COMPLETE.
V. THE COURT OF APPEALS COMMITTED A
GRAVE REVERSIBLE ERROR WHEN IT COMPLETELY
DISREGARDED THE EVIDENCE ON ACTUAL COST
INCURRED BY PETITIONER IN COMPLETING THE
REMAINING WORKS.
VI. THE COURT OF APPEALS COMMITTED GRAVE
REVERSIBLE ERROR WHEN IT AFFIRMED THE CIAC
AWARD FOR INTERESTS AND ARBITRATION COSTS IN
FAVOR OF RESPONDENT RRN.[4]
The petition is bereft of merit.
Despite petitioner's attempts to make it appear that it is
advancing questions of law, it is quite clear that what petitioner seeks is
for this Court to recalibrate the evidence it has presented before the
CIAC. It insists that its evidence sufficiently proves that it is entitled to
payment for respondent's use of its manlift equipment, and even absent
proof of the supposed agreement on the charges petitioner may impose
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
11. Page 11 of 16
on respondent for the use of said equipment, respondent should be
made to pay based on the principle of unjust enrichment. Petitioner
also questions the amounts awarded by the CIAC for inventoried
materials, and costs incurred by petitioner for completing the work left
unfinished by respondent.
As reiterated by the Court in IBEX International, Inc. v.
Government Service Insurance System,[5]
to wit:
It is settled that findings of fact of quasi-judicial
bodies, which have acquired expertise because their
jurisdiction is confined to specific matters, are
generally accorded not only respect, but also finality,
especially when affirmed by the Court of Appeals. In
particular, factual findings of construction arbitrators
are final and conclusive and not reviewable by this
Court on appeal.
This rule, however, admits of certain exceptions.
In Uniwide Sales Realty and Resources Corporation v.
Titan-Ikeda Construction and Development Corporation,
we said:
In David v. Construction
Industry and Arbitration Commission,
we ruled that, as exceptions, factual
findings of construction arbitrators may
be reviewed by this Court when the
petitioner proves affirmatively that: (1)
the award was procured by corruption,
fraud or other undue means; (2) there
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
12. Page 12 of 16
was evident partiality or corruption of
the arbitrators or any of them; (3) the
arbitrators were guilty of misconduct in
refusing to hear evidence pertinent and
material to the controversy; (4) one or
more of the arbitrators were disqualified
to act as such under Section nine of
Republic Act No. 876 and willfully
refrained from disclosing such
disqualifications or of any other
misbehavior by which the rights of any
party have been materially prejudiced;
or (5) the arbitrators exceeded their
powers, or so imperfectly executed
them, that a mutual, final and definite
award upon the subject matter submitted
to them was not made.
Other recognized exceptions are
as follows: (1) when there is a very clear
showing of grave abuse of discretion
resulting in lack or loss of jurisdiction as
when a party was deprived of a fair
opportunity to present its position before
the Arbitral Tribunal or when an award
is obtained through fraud or the
corruption of arbitrators, (2) when the
findings of the Court of Appeals are
contrary to those of the CIAC, and (3)
when a party is deprived of
administrative due process.[6]
A perusal of the records would reveal that none of the
aforementioned circumstances, which would justify exemption of this
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
13. Page 13 of 16
case from the general rule, are present here. Such being the case, the
Court, not being a trier of facts, is not duty-bound to examine, appraise
and analyze anew the evidence presented before the arbitration body.
[7]
Petitioner's reliance on the principle of unjust enrichment is
likewise misplaced. The ruling of the Court in University of the
Philippines v. Philab Industries, Inc.[8]
is highly instructive, thus:
Unjust enrichment claims do not lie simply
because one party benefits from the efforts or
obligations of others, but instead it must be shown that
a party was unjustly enriched in the sense that the term
unjustly could mean illegally or unlawfully.
Moreover, to substantiate a claim for unjust
enrichment, the claimant must unequivocally prove that
another party knowingly received something of value to
which he was not entitled and that the state of affairs
are such that it would be unjust for the person to keep
the benefit. Unjust enrichment is a term used to depict
result or effect of failure to make remuneration of or for
property or benefits received under circumstances that
give rise to legal or equitable obligation to account for
them; to be entitled to remuneration, one must confer
benefit by mistake, fraud, coercion, or request. Unjust
enrichment is not itself a theory of reconvey. Rather, it
is a prerequisite for the enforcement of the doctrine of
restitution.
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
14. Page 14 of 16
Article 22 of the New Civil Code reads:
Every person who, through an act
of performance by another, or any
other means, acquires or comes into
possession of something at the expense
of the latter without just or legal
ground, shall return the same to him.
In order that accion in rem verso may prosper,
the essential elements must be present: (1) that the
defendant has been enriched, (2) that the plaintiff has
suffered a loss, (3) that the enrichment of the
defendant is without just or legal ground, and (4) that
the plaintiff has no other action based on contract,
quasi-contract, crime or quasi-delict.
An accion in rem verso is considered merely an
auxiliary action, available only when there is no other
remedy on contract, quasi-contract, crime, and quasi-
delict. If there is an obtainable action under any other
institution of positive law, that action must be resorted
to, and the principle of accion in rem verso will not lie.[9]
As found by both the CIAC and affirmed by the CA, petitioner
failed to prove that respondent's free use of the manlift was without
legal ground based on the provisions of their contract. Thus, the third
requisite, i.e., that the enrichment of respondent is without just or legal
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
15. Page 15 of 16
ground, is missing. In addition, petitioner's claim is based on contract,
hence, the fourth requisite − that the plaintiff has no other action based
on contract, quasi-contract, crime or quasi-delict − is also
absent. Clearly, the principle of unjust enrichment is not applicable in
this case.
The other issues raised by petitioner all boil down to whether the
CIAC or the CA erred in rejecting its claims for costs of some materials.
Again, these issues are purely factual and cannot be properly
addressed in this petition for review on certiorari. In Hanjin Heavy
Industries and Construction Co., Ltd. v. Dynamic Planners and
Construction Corp.,[10]
it was emphasized that mathematical
computations, the propriety of arbitral awards, claims for “other costs”
and “abandonment” are factual questions. Since the discussions of the
CIAC and the CA in their respective Decisions show that its factual
findings are supported by substantial evidence, there is no reason why
this Court should not accord finality to said findings. Verily, to accede to
petitioner's request for a recalibration of its evidence, which had been
thoroughly studied by both the CIAC and the CA would result in
negating the objective of Executive Order No. 1008, which created an
arbitration body to ensure the prompt and efficient settlement of
disputes in the construction industry. Thus, the Court held in Uniwide
Sales Realty and Resources Corporation v. Titan-Ikeda Construction and
Development Corporation,[11]
that:
x x x The Court will not review the factual
findings of an arbitral tribunal upon the artful allegation
that such body had "misapprehended facts" and will not
pass upon issues which are, at bottom, issues of fact, no
matter how cleverly disguised they might be as "legal
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi
16. Page 16 of 16
questions." The parties here had recourse to arbitration
and chose the arbitrators themselves; they must have
had confidence in such arbitrators. The Court will not,
therefore, permit the parties to relitigate before it the
issues of facts previously presented and argued before
the Arbitral Tribunal, save only where a clear showing is
made that, in reaching its factual conclusions, the
Arbitral Tribunal committed an error so egregious and
hurtful to one party as to constitute a grave abuse of
discretion resulting in lack or loss of jurisdiction.[12]
As discussed above, there is nothing in the records that point to
any grave abuse of discretion committed by the CIAC.
The awards for interests and arbitration costs are, likewise, correct
as they are in keeping with prevailing jurisprudence.[13]
IN VIEW OF THE FOREGOING, the Petition is DENIED. The
Decision of the Court of Appeals dated February 22, 2006 and its
Resolution dated April 26, 2006 areAFFIRMED.
SO ORDERED. DIOSDADO M. PERALTA
Associate Justice
Lynnedelacruz
CIVLAWREV1
Atty. Legaspi