The Chief Engineer (Construction) South,
Office of Chief Administrative Officer (Construction),
Southern Railway (Ernakulam),
Ernakulam Junction Railway Station
PEMS ENGINEERING CONSULTANTS PVT. LTD.
Thiruvananthapuram
BALAJI RAILROAD SYSTEMS PVT. LTD.
Hyderabad
In JV with
Tender Ref No: CE-CN-ERS-SD-09-2022 dated 23/06/2022
Appointment of Authority Engineer for
Providing Project Management Services for
Redevelopment of Ernakulam Junction Railway Station
• Authority : The Chief Engineer (Construction), North,
Southern Railway, Ernakulam
• Contractor : M/s. Bridge and Roof Company (India) Ltd ,
Chennai vide LOA dated 13th July 2022
• Contract Value : INR 299.52 Crores
• Design Director : M/s CP & DS Associates, Plot No. 31, Vaishali,
Ghaziabad vide letter dated 05th August 2022
• Proof Consultant : IIT Madras vide letter dated 05th August 2022
• Authority Engineer : M/s PEMS Engineering Consultants Pvt Ltd
in JV with Balaji Railroad Systems Pvt Ltd
vide LOA dated 27th September 2022
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
3
PROJECT DATA:
• LOA Date : 27th September 2022
• Duration/period of completion : 48 months (24 months construction period
and 24 months DLP) (Ref: LOA -3rd para,
Page 2 of 4)
• Commencement of PMS/Effective date : 27th September 2022(Ref: LOA- 6th para,
Page 2 of 4 & Cl 3.8 of RFP, Page 3 0f
132
• Contractual End date : 26th September 2026 incl. DLP (Ref: LOA
-3rd para, Page 2 of 4)
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
4
PROJECT DATA:
Important Clauses:
Performance Security : Cl. 2.15. of RFP, Page 18 of 123
Submission-Within 15 days of issue of Letter of Award (LOA)
3% of the Cost of PMS , In favour of: FA&CAO, Southern Railway Payable at: Chennai
Shall be valid until 60 (sixty) days of the expiry of the DLP
Released after two months after the payment of the final bill and submission of NOC.
shall be kept valid for three months or for such period, as may be decided by Authority, over and
above the scheduled period of completion of work. Cl.4.2 of Schedule I, page 41 of 132
Signing of Agreement : LOA-5th para, Page 2 of 4
• Within 15 days of submission of Performance Security 27th September 2022
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
5
Important Clauses: Continues…………….
Authority Engineer’s Services : Cl. 3. of Schedule – 1: Form of Agreement , Page 36 of 123
Adhere-Internal target dates/Project Milestones and other days/duration as specified in the EPC
Agreement
Hold meetings
Liaison
Report -in writing of progress to the Authority
Provide Unrestricted access to AE & its personnel- inspect the services, interact with personnel,
verify records etc.
Accounting, Inspection ad auditing
ensure optimal utilization of resources/contractual provisions with a view to bring economy in
execution.
implementation of various labour rules, regulations and welfare measures as per the rules in force
and laid down provisions
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
6
Important Clauses: Continues…………….
Authority Engineer’s Services : Continues ------------
Obtain Approval of Authority in writing – Cl. 3. of Schedule – 1: Form of Agreement , Page 36 of
132 and Cl. 3 of Annexure –I, Schedule – 1: Form of Agreement , Page 62 of 132
appointing Key Personnel as are not listed in the Technical Bid ,
determining :
a) any Time Extension
b) any additional cost to be paid by the Authority to the Contractor;
c) the Termination Payment;
d) providing Power Block or Traffic Block or necessary disconnections to the Contractor;
e) approval of disconnections for modification of signaling and telecom works, or any
other matter which is not specified in (a); (b), (c), (d) or (e) above and which creates an
obligation or liability on either Party for a sum exceeding Rs. 50,00,000 (Rs.Fifty Lakhs).
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
7
Important Clauses: Continues…………….
Authority Engineer’s Services : Continues------------
Responsible for documents accuracy- correcting, at its own cost and risk,-the works/the documents
-including any re-survey/ investigations/supervision.
Non Performance/ compliance of any of the provisions of the Agreement- a deduction of
Rs.25,000/- or higher but not exceeding 1% of the monthly payment for PMS to AE shall be
applicable for each instance(Ref-Cl. 3.9.31 , PAGE 37 of 132) – more than 5 incidents- Termination
by Authority
Ensuring safety- Railway assets, Rolling stocks and Railway users on the works being carried out –
Accidenthappens- in loss of life -after inquiry conducted Authority/Railway/Commissioner of
Railway Safety(CRS) that safety measures were lacking-impose a penalty @ Rs. 5 Lacs on the AE
for every such incident
Failure - certification of Stage, Interim or Final payment by the AE---deduction of Rs 25,000/- per
day of delay
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
8
Important Clauses: Continues…………….
Authority Engineer’s Services : Continues------------
Obtain Approval of personnel- Authority may approve /reject proposal within 14 days of receipt -
does not reject within 14 days -deemed to approved by the Authority.
Substitution of Key Personnel: Cl. 3.11. of Schedule – 1: Form of Agreement , Page 39of 132
Expects all personnel to be engaged during implementation –non commencemnt upto180 days
due to reasons by Authority- permitted for replacement –max 50% Key Personnel with Key
Personnel of equivalent/ better qualifications -without considering the same as
replacement/substitution and without any deduction- Apart from above not consider except
for reasons of any incapacity, death or any reasons beyond the reasonable control of the
Authority Engineer- shall be subject to equally or better qualified and experienced personnel ,
Condition;
replacement upto 40% - reduction of remuneration – 5%
replacement above 40% and upto 65%, -reduction of remuneration – 10%
Above 65% -reduction of remuneration – 15%
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
9
Important Clauses: Continues…………….
Any taking of leave by any personnel Cl. 3.12 of Schedule I, Page 40 of 132
 -exceeding 3 (three) days -the prior approval of the Authority, and AE ensure that leave will not
delay the progress and quality of the Services
Manpower deployment : Cl.10 of Schedule-1, page 80 of 132)
List of manpower, No.s required, and their Minimum required Educational qualifications and/or
experience are provided
Deployment of personnel other than those mentioned :(Cl. 10.3 of Schedule-I, Page 86 of 132)
The AE may be required to deploy other personnel who are experts in their field also for the
project for specific needs. Their deployment shall be arranged by the AE on specific requisition
from the Authority and the payment shall be made as per the actual deployment. Such specialist
experts shall be paid at the rate of remuneration payable to such new AE’s personnel based on
the rates for other position which require similar qualifications and experience with mutual
consent. If required, Authority may require/agree for additional deployment of similar personnel
identified in the bid and in such cases payment to the AE shall be based on the remuneration of
such personnel in the Agreement.
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
10
Important Clauses: Continues…………….
Terms & Conditions of Payment and Deployment:(Cl. 11 of Schedule-I, Page 86 of 132)
Remuneration for the Key Personnel shall be determined on the basis of the Deployment Schedule
and days actually spent as deployed by such Key Personnel in the performance of the Services from
Effective Date. Remuneration for periods of less than one month shall be calculated on a calendar
day basis for the period deployed for part of the month. A copy of monthly attendance records
shall be attached with Monthly Status Report
The Key Personnel shall be considered to be inadequately deployed -if he/she is not present for
atleast 80% (eighty percent) of the days stipulated in that calendar month, as per the Man Months
Input in the Terms of Reference and the Deployment Schedule proposed by the Authority Engineer
and approved/modified by the Authority. The reduction or deduction of the amount @20%
(twenty percent) of the monthly payment due as the case may be shall be made against such Key
Personnel during the monthly billing
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
11
Important Clauses: Continues…………….
Delays- performance/ commencement of its contractual obligation/Non-submission of final
report by due date (Cl. 4.3 of Schedule-I, page 41 of 132
Imposition of L.D.- @ 0.5% of the Agreement Value per week-subject to max- 5% of the
Agreement Value. This may also include forfeiture of Performance Security.
Termination of contract
Extension of time- Cl. 4.4 of Schedule-I, page 41 of 132
Applicable – in case situation arises- notify Authority in writing -fact of the delay, its likely
duration and its causes-Authority shall evaluate & may extend the Authority Engineer’s time
for performance-by amendment of the Contract.
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
12
Important Clauses: Continues…………….
Variation- Cl. 4.6 of Schedule-I, page 41 of 132) –
Applicable
The Authority may notify the to alter, amend, omit, add to, or otherwise vary the Services upto
25% increase of the contract value or upto 50% increase of the original completion period
stipulated in the contract, whichever is earlier, on the same rates, terms and conditions and the
Authority Engineer shall be bound by such variations.
Beyond 25% increase of the Contract Value or beyond 50% increase of the original completion
period, whichever is earlier, new rates shall be agreed between Authority and Authority Engineer.
In such an event, the Authority Engineer shall submit an estimate for proposed changes in rates
along with justification for such rates to the Authority:
1) within fourteen (14) calendar days of receipt of a notice of variation in case of proposed
increase of the contract value beyond 25%;
2) atleast 60 days in advance of reaching limit of 50% increase in completion period, if it is
anticipated that consultancy contract period shall need to be extended beyond 50% of the
original completion period
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
13
Important Clauses: Continues…………….
Payment to the Authority Engineer- Cl. 4.7 of Schedule-I, page 42 of 132)
As per renumeration rates; -Price Adjustment applicable- first 12 months from the date of
commencement of services shall remain the same- From the beginning of 13th month from the
date of commencement of services, remuneration rates shall be adjusted as per the formula for
every 12 months.
in case any personnel is continuing for more than 12 months from date of his/her deployment then
the AE shall be entitled for increase in monthly remuneration rate @ 3% of the accepted monthly
remuneration rate of such personnel, on completion of every 12 months
Price Adjustment shall not be applicable during the extension period for which extension is
sanctioned for reasons attributable to the AE.
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
14
Important Clauses: Continues…………….
Force Majeure: Cl. 5 of Schedule-I, page 44 of 132
Applicable; shall not be liable for forfeiture of its Performance Security, liquidated damages or
termination for default, to the extent that, delay in performance or other failure to perform its
obligations under the Contract
If a Force Majeure situation arises, either party shall promptly notify the other party in writing of
such conditions and the cause thereof
However, Authority may terminate this Agreement by giving a written notice of minimum 7 days to
the Authority Engineer, if as a result of Force Majeure, the Authority Engineer is unable to perform
the services for a period of more than 30 days.
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
15
Important Clauses: Continues…………….
Agreement Termination : Cl. 6 of Schedule-I, page 44 of 132
Stands terminated - the Authority Engineer has rendered all the services to the satisfaction of the
Authority and the same are accepted by Authority.
Termination by Authority : Cl. 6 of Schedule-I, page 44 of 132
Breaches any of the terms of this Agreement & not remedied within 10 days of receipt of a notice
persistent default in the provision of the Services, the disclosure of any Confidential Information.
commits any offence under the Prevention of Corruption Act 1988.
Fails or refuses to provide the Services after written warning
delay in commencement of services or delay in performance of its contractual obligations.
AE becomes / is in jeopardy of becoming insolvent/bankrupt/has a receiving order made against it,
/compounds with its creditors, or any of them
Authority also reserves the right to short close the Agreement any time.
 No compensation shall be payable beyond the services payable as per Payment Schedule.
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
16
Important Clauses: Continues…………….
Termination by Authority Engineer : Cl. 6.7 of Schedule-I, page 45 of 132
not less than 30 (thirty) days’ written notice to the Authority, after the occurrence of any of the
events specified in this clause,
the Authority fails to pay any money due to the AE pursuant to this Agreement and not
subject to dispute within 60 (sixty) days after receiving written notice from the AE that such
payment is overdue;
as the result of Force Majeure, the AE is unable to perform a material portion of the Services
for a period of not less than 60 (sixty) days;
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
17
Important Clauses: Continues…………….
Insurance: Cl. 8 of Schedule-I, page 46 of 132
The AE shall, for the duration of this Agreement, take out and maintain, at its own cost, but on
terms and conditions approved by the Authority, insurance against the risks, and for the
coverages, as shall be specified in the Agreement -3rd party liability insurance -of Rs. 50 Lakhs for
the period of this Agreement , 3rd party motor vehicle insurance, Global Indemnity Insurance,
Employer’s liability & workers’ compensation insurance -life, health, accident, travel or other
insurance as may be appropriate; -, and in accordance with good industry practice
Within 15 (fifteen) days of receiving any insurance policy certificate in respect of insurances
required to be obtained and maintained under this clause, the AE shall furnish to Authority, copies
of such policy certificates, copies of the insurance policies and evidence that the insurance premia
have been paid in respect of such insurance.
Except in case of Third-Party liabilities, the insurance policies so procured shall mention the
Authority as the beneficiary of the Authority Engineer and the Authority Engineer shall procure
an undertaking from the insurance company in this regard.
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
18
Important Clauses: Continues…………….
Disputes: Cl. 10 of Schedule-I, page 48 of 132
IN CASE ARISES- either party may request the other to participate in a meeting of their respective
senior officials -in order to discuss the dispute and to agree to a strategy to resolve it- arrange and
implement the meeting within 10 days - exchange statements at least 3 days prior to the date of
the meeting, setting out their respective views of the issues, which are in dispute.
unresolved within 1 MONTH of the date on which the dispute arose, then the matter shall be
resolved through conciliation process as per the Settlement of Disputes – Indian Railway
Arbitration and Conciliation Rules provided under the Indian Railways Standard General Conditions
of Contract 2022 (GCC April 2022) issued by Engineering Department, including any correction slips
as updated from time to time. Notice of Dispute-shall be served later than 30 days after the date
of issue of Completion Certificate by the Authority- Chief Engineer or Divisional Railway Manager-
within 30 days after receipt of the AE ’s “Notice”, notify the name of conciliator(s) to the
Authority Engineer who shall assist in amicable settlement If the parties reach agreement on a
settlement of the dispute, they shall draw up and sign a written settlement agreement duly signed
by the Authority representative, Authority Engineer and conciliator(s).
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
19
Important Clauses: Continues…………….
Matters Finally Determined by the Authority /Excepted matter(matters no arbitrable, and decisions
of the Railway authority, thereon shall be final and binding on the Authority Engineer; ) : Cl. 10.4 of
Schedule-I, page 48 of 132)
In case arises, AE shall referred to the General Manager (GM) and the GM shall, within 120
days make and notify decisions on all matters referred to by the Authority Engineer in writing:
AE’s personnel performance
Illegal Gratification
Monetary dealings/ transactions with Authority personnel
Ambiguity in Meaning and Intent of Specification and Drawings
Rates for Extra Items of Works
Signing "No Claim" Certificate- not entitled to claim
Accuracy of measurement
provisions of the Contract Labour (Regulation and Abolition) Act, 1970,Payments of Wages
Act,Workmen’s Compensation Act,Mines Act
Right of authority to determine the contract and its payment
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
20
Important Clauses: Continues…………….
Arbitration: Cl. 10.5 of Schedule-I, page 52 of 132
unresolved dispute - within the time period, then the dispute shall be subject to arbitration
process as per the Settlement of Disputes – Indian Railway Arbitration and Conciliation Rules
provided under the Indian Railways Standard General Conditions of Contract 2022 (GCC April
2022) issued by Engineering Department, including any correction slips as updated from time
to time- after 120 days but within 180 days of his presenting his final claim on disputed
matters shall demand in writing that the dispute or difference be referred to arbitration.
The claimant shall submit his claims stating the facts supporting the claims along with all the
relevant documents and the relief or remedy sought against each claim within a period of 30
days from the date of appointment of the Arbitral Tribunal.
The Authority shall submit its defence statement and counter claim(s), if any, within a period
of 60 days of receipt of copy of claims from Tribunal, unless otherwise extension has been
granted by Tribunal.
No new claim shall be added during proceedings by either party. However, a party may amend
or supplement the original claim or defense thereof during the course of arbitration
proceedings subject to acceptance by Tribunal having due regard to the delay in making it.
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
21
Important Clauses: Continues…………….
Place of Arbitration: Cl. 10.5.1 iii d) of Schedule-I, page 53 of 132
The place of arbitration would be within the geographical limits of the Division of the Railway
where the cause of action arose or the Headquarters of the concerned Authority or any other place
with the written consent of both the parties.
Obligation During Pendency of Arbitration: Cl. 10.5.2 of Schedule-I, page 53 of 132
Work under the contract shall, unless otherwise directed by the Authority, continue during the
arbitration proceedings, and no payment due or payable by the Authority shall be withheld on
account of such proceedings, provided, however, it shall be open for Arbitral Tribunal to consider
and decide whether or not such work should continue during arbitration proceedings.
Appointment of Arbitrator: Cl. 10.5.3 of Schedule-I, page 53 of 132
According to arbitration and conciliation act
Governing Law : Cl. 14of Schedule-I, page 57 of 132
governed by and construed in accordance with the substantive laws of India.
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
22
Important Clauses: Continues…………….
Reports to be submitted by AE, Cl. 3.3 of Annexure I of Schedule-1, page 62 of 132/ Cl. 4.5i of
Annexure I of Schedule-1, page 66 of 132
Daily report- event/happening which is likely to affect the progress, quality of work and safety if
any on previous day
Monthly progress report- within 7-10 days the beginning of every month in respect of its duties
and functions under this Agreement
Quarterly progress report- within 14 days of the end of each quarter & include a description of
project activities illustrated by progress/completion photographs, status of any delays and detailed
plan to make up any shortfall or deficiency, status of contractual claims, and details of all latest
financial projections
Setting up of Project Management Office , Cl.4.1 of Annexure I of Schedule-1, page 63of 132
within two months from the date of commencement of the works. Failure to establish the
facilities will invite a penalty of Rs.10,000/- per week
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
23
Important Clauses: Continues…………….
Review of drawings: Cl.4.11,4.12 of Annexure-1, Schedule-1, page 73 of 132
the AE shall complete such review and send its observations to the Authority and the Contractor
within 15 (fifteen) days of receipt of such Drawings
The Authority Engineer shall review any revised -within 10 (ten) days of receiving such Drawings;
provided, however that in case of Structures, airspace development at railway stations including
concourse and any other specified item the aforesaid period, the days may be extended as per the
time limit
Review of Quality Assurance Plan : Cl.4.13 of Annexure-1, Schedule-1, page 73 of 132
convey its comments to the Contractor within a period of 21 days as mentioned in the EPC
Agreement stating the modifications;
Review of Methodology proposed: Cl.4.15 of Annexure-1, Schedule-1, page 74 of 132
convey its comments to the Contractor within a period of 10 (ten) days or as mentioned in the EPC
Agreement from the date of receipt of the proposed methodology from the Contractor
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
24
Important Clauses: Continues…………….
Review of Monthly progress report: Cl.4.16 of Annexure-1, Schedule-1, page 73 of 132
send its comments thereon to the Authority and the Contractor within 7 (seven) days of receipt of such
report.
Monthly Inspection Report : Cl.4.17 of Annexure-1, Schedule-1, page 73 of 132
bringing out the results of inspections and the remedial action taken by the Contractor in respect of
Defects or deficiencies. In particular, the compliance of the recommendations made by the Safety
Consultant.
Failure to achieve milestones by Contractor: Cl.4.32 of Annexure-1, Schedule-1, page 76 of 132
undertake a review of the progress of construction and identify potential delays; if any. If the
Authority Engineer shall determine that completion of the Project is not feasible within the time
specified in the EPC Agreement; it shall require the Contractor to indicate within the days as mentioned
in the EPC Agreement, the steps proposed to expedite progress; and the period within which the
Project Completion Date shall be achieved. Upon receipt of a report from the Contractor; the Authority
Engineer shall review the same and send its comments to the Authority and the Contractor forthwith.
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
25
Important Clauses: Continues…………….
Quality control Records: Cl.4.33 of Annexure-1, Schedule-1, page 77 of 132
obtain from the Contractor a copy of all the Contractor’s quality control records and documents
before the Completion Certificate
Final Documentation: Cl.4.38 of Annexure-1, Schedule-1, page 77 of 132
Authority Engineer shall compile a complete and indexed set of project documentation files. The
files shall include as built documentation and shall contain documents delivered by
sanctioning/approval, authorities, Authority, Consultant, and vendors/contractors
Payments for Contractor: Cl.6 of Annexure-1, Schedule-1, page 79 of 132
within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor determine
the amount due and recommend the release of 80 (eighty) percent of the amount as part
payment; pending issue of the Interim Payment Certificate
within 20 (twenty) days of the receipt of the Stage Payment Statement deliver an Interim Payment
Certificate certifying the amount due and payable to the Contractor; after adjustments
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
26
Important Clauses: Continues…………….
As built drawings: Cl.8.3 of Annexure-I,Schedule-1, page 80 of 132
Within 90 (ninety) days of the Project Completion Date; the Authority Engineer shall obtain a
complete set of as-built Drawings; in 2 (two) hard copies and in micro film form or in such other
medium as may be acceptable to the Authority; reflecting the Project as actually designed;
engineered and constructed; including an as-built survey illustrating the layout of the Project and
setback lines; if any; of the buildings and structures forming part of Project Facilities; and shall
hand them over to the Authority against receipt thereof.
Event of contractor’s default: Cl.8.5 of Annexure-I,Schedule-1, page 80 of 132
The AE shall inform the Authority and the Contractor within one week of its occurrence.
Weekly & Monthly Meetings: Cl.9 of Schedule-1, page 80 of 132
to be held at site and Authority HQ-required personnel shall participate. In case key personnel
required to visit outstation - travel, boarding and lodging expenses will be reimbursed as per
financial bid
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
27
Important Clauses: Continues…………….
Payment Schedule of AE: Annexure 3 of Schedule-2, page 89 of 132)
not later than 15 days after the end of each calendar month during the period of the Services, the
AE shall submit to the Authority, induplicate, itemized statements, and other appropriate
supporting materials, of the amounts payable for such month, Payment- Within 30 days of receipt
by authority –cause the payment periodically after deduction / add , if any
The final payment -after the final report and a final statement, -, shall have been submitted by the
AE and approved as satisfactory by the Authority. -ninety (90) calendar days after receipt of the
final report and final statement by the Authority unless the Authority, within such ninety (90)day
period, gives written notice specifying in detail deficiencies in the PMS
Any amount which the Authority has paid or caused to be paid in excess shall be reimbursed by
the AE to the Authority within30 (thirty) days after receipt by the AE of notice thereof.Any such
claim by the Authority for reimbursement must be made within 12 (twelve) calendar months after
receipt by the Authority of a final report and a final statement approved by the Authority in
accordance with the above
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
28
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
29
LOA
Enter into Agreement
with Authority
Mobilization Initial Data Verification
Prepare PIP
Set up Project
Management Office
Kickoff Meeting
Project Planning:
Approval of Methodology,
Preparing Policies and Standards
Project Execution &
Project Monitoring
Review of Design &
Drawings
Change
Management
Approval of
Authority
Cost Analysis &
Forecast
Review &
Approval of Bills
Payment to
Contractor
Issue of Provisional
Certificate & Start of DLP
DLP Completion
Project Closure &
Value Engineering
Flow Chart of Activities
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
30
Review meetings &
Report Preparation
Approach
Phases of PMC Services:
• Initiation & Mobilization
• Project Planning
• Project Execution and Monitoring
• Technical Audit and Quality Assurance & Quality Control
• Document Control System
• Project Completion
• Services during Defects Liability Period
Methodology & Work Plan
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
31
In JV with
Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
32

More Related Content

Similar to 1. ERS PPT - 20 OCT 2022.ppt

result of 10 th class tf76 uyf7tf fydu v57 fu6fi
result of 10 th class tf76 uyf7tf fydu v57 fu6firesult of 10 th class tf76 uyf7tf fydu v57 fu6fi
result of 10 th class tf76 uyf7tf fydu v57 fu6fi
jahanzaibrauf02
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreement
Chirag Jain
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
Avinash Kumar Gupta
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
Shivam Sood
 
Railway recruitment, Jobs (20 job vacancies in konkan railway)
Railway recruitment, Jobs (20 job vacancies in konkan railway)Railway recruitment, Jobs (20 job vacancies in konkan railway)
Railway recruitment, Jobs (20 job vacancies in konkan railway)
Freshersworld.com
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
MANTHAN CHAUHAN
 
Indirect Tax_Latest Judicial Precedents_ October 2016
Indirect Tax_Latest Judicial Precedents_ October 2016Indirect Tax_Latest Judicial Precedents_ October 2016
Indirect Tax_Latest Judicial Precedents_ October 2016
Ashish Chaudhary
 
Advance planning of works programme in Indian Railways alongwith with related...
Advance planning of works programme in Indian Railways alongwith with related...Advance planning of works programme in Indian Railways alongwith with related...
Advance planning of works programme in Indian Railways alongwith with related...
SrinivasaRao Guduru
 
Rajasthan Solar Roof Top tender 2014-2015
Rajasthan Solar Roof Top tender 2014-2015Rajasthan Solar Roof Top tender 2014-2015
Rajasthan Solar Roof Top tender 2014-2015
Headway Solar
 
nbccindia.com NBCC Recruitment 2014
nbccindia.com NBCC Recruitment 2014 nbccindia.com NBCC Recruitment 2014
nbccindia.com NBCC Recruitment 2014
Ramanareddy Anathapur
 
IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET- Comperative Analysis of Three Major Type of Contracts with Case StudyIRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET Journal
 
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Gensol Engineering Limited
 
Rules and regulation of Pakistan Engineering Council (PEC)
Rules and regulation of Pakistan Engineering Council (PEC)Rules and regulation of Pakistan Engineering Council (PEC)
Rules and regulation of Pakistan Engineering Council (PEC)
Amir Khan
 
Navi mumbai metro new
Navi mumbai metro newNavi mumbai metro new
Navi mumbai metro new
Rashid Kaskar
 
Vishrantwadi & Ghorpadi Tender documents
Vishrantwadi & Ghorpadi Tender documentsVishrantwadi & Ghorpadi Tender documents
Vishrantwadi & Ghorpadi Tender documents
SachinPawar510423
 

Similar to 1. ERS PPT - 20 OCT 2022.ppt (20)

result of 10 th class tf76 uyf7tf fydu v57 fu6fi
result of 10 th class tf76 uyf7tf fydu v57 fu6firesult of 10 th class tf76 uyf7tf fydu v57 fu6fi
result of 10 th class tf76 uyf7tf fydu v57 fu6fi
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreement
 
td_arr.pdf
td_arr.pdftd_arr.pdf
td_arr.pdf
 
Kartik CV
Kartik CVKartik CV
Kartik CV
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 
Reluctance
ReluctanceReluctance
Reluctance
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
 
Railway recruitment, Jobs (20 job vacancies in konkan railway)
Railway recruitment, Jobs (20 job vacancies in konkan railway)Railway recruitment, Jobs (20 job vacancies in konkan railway)
Railway recruitment, Jobs (20 job vacancies in konkan railway)
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
 
Indirect Tax_Latest Judicial Precedents_ October 2016
Indirect Tax_Latest Judicial Precedents_ October 2016Indirect Tax_Latest Judicial Precedents_ October 2016
Indirect Tax_Latest Judicial Precedents_ October 2016
 
Advance planning of works programme in Indian Railways alongwith with related...
Advance planning of works programme in Indian Railways alongwith with related...Advance planning of works programme in Indian Railways alongwith with related...
Advance planning of works programme in Indian Railways alongwith with related...
 
Rajasthan Solar Roof Top tender 2014-2015
Rajasthan Solar Roof Top tender 2014-2015Rajasthan Solar Roof Top tender 2014-2015
Rajasthan Solar Roof Top tender 2014-2015
 
nbccindia.com NBCC Recruitment 2014
nbccindia.com NBCC Recruitment 2014 nbccindia.com NBCC Recruitment 2014
nbccindia.com NBCC Recruitment 2014
 
IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET- Comperative Analysis of Three Major Type of Contracts with Case StudyIRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
 
CV_Cost Engineer
CV_Cost EngineerCV_Cost Engineer
CV_Cost Engineer
 
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
 
Rules and regulation of Pakistan Engineering Council (PEC)
Rules and regulation of Pakistan Engineering Council (PEC)Rules and regulation of Pakistan Engineering Council (PEC)
Rules and regulation of Pakistan Engineering Council (PEC)
 
Navi mumbai metro new
Navi mumbai metro newNavi mumbai metro new
Navi mumbai metro new
 
resume_milind___3_
resume_milind___3_resume_milind___3_
resume_milind___3_
 
Vishrantwadi & Ghorpadi Tender documents
Vishrantwadi & Ghorpadi Tender documentsVishrantwadi & Ghorpadi Tender documents
Vishrantwadi & Ghorpadi Tender documents
 

Recently uploaded

Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 

Recently uploaded (20)

Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 

1. ERS PPT - 20 OCT 2022.ppt

  • 1. 1 In JV with The Chief Engineer (Construction) South, Office of Chief Administrative Officer (Construction), Southern Railway (Ernakulam), Ernakulam Junction Railway Station PEMS ENGINEERING CONSULTANTS PVT. LTD. Thiruvananthapuram BALAJI RAILROAD SYSTEMS PVT. LTD. Hyderabad
  • 2. In JV with Tender Ref No: CE-CN-ERS-SD-09-2022 dated 23/06/2022 Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station
  • 3. • Authority : The Chief Engineer (Construction), North, Southern Railway, Ernakulam • Contractor : M/s. Bridge and Roof Company (India) Ltd , Chennai vide LOA dated 13th July 2022 • Contract Value : INR 299.52 Crores • Design Director : M/s CP & DS Associates, Plot No. 31, Vaishali, Ghaziabad vide letter dated 05th August 2022 • Proof Consultant : IIT Madras vide letter dated 05th August 2022 • Authority Engineer : M/s PEMS Engineering Consultants Pvt Ltd in JV with Balaji Railroad Systems Pvt Ltd vide LOA dated 27th September 2022 In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 3 PROJECT DATA:
  • 4. • LOA Date : 27th September 2022 • Duration/period of completion : 48 months (24 months construction period and 24 months DLP) (Ref: LOA -3rd para, Page 2 of 4) • Commencement of PMS/Effective date : 27th September 2022(Ref: LOA- 6th para, Page 2 of 4 & Cl 3.8 of RFP, Page 3 0f 132 • Contractual End date : 26th September 2026 incl. DLP (Ref: LOA -3rd para, Page 2 of 4) In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 4 PROJECT DATA:
  • 5. Important Clauses: Performance Security : Cl. 2.15. of RFP, Page 18 of 123 Submission-Within 15 days of issue of Letter of Award (LOA) 3% of the Cost of PMS , In favour of: FA&CAO, Southern Railway Payable at: Chennai Shall be valid until 60 (sixty) days of the expiry of the DLP Released after two months after the payment of the final bill and submission of NOC. shall be kept valid for three months or for such period, as may be decided by Authority, over and above the scheduled period of completion of work. Cl.4.2 of Schedule I, page 41 of 132 Signing of Agreement : LOA-5th para, Page 2 of 4 • Within 15 days of submission of Performance Security 27th September 2022 In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 5
  • 6. Important Clauses: Continues……………. Authority Engineer’s Services : Cl. 3. of Schedule – 1: Form of Agreement , Page 36 of 123 Adhere-Internal target dates/Project Milestones and other days/duration as specified in the EPC Agreement Hold meetings Liaison Report -in writing of progress to the Authority Provide Unrestricted access to AE & its personnel- inspect the services, interact with personnel, verify records etc. Accounting, Inspection ad auditing ensure optimal utilization of resources/contractual provisions with a view to bring economy in execution. implementation of various labour rules, regulations and welfare measures as per the rules in force and laid down provisions In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 6
  • 7. Important Clauses: Continues……………. Authority Engineer’s Services : Continues ------------ Obtain Approval of Authority in writing – Cl. 3. of Schedule – 1: Form of Agreement , Page 36 of 132 and Cl. 3 of Annexure –I, Schedule – 1: Form of Agreement , Page 62 of 132 appointing Key Personnel as are not listed in the Technical Bid , determining : a) any Time Extension b) any additional cost to be paid by the Authority to the Contractor; c) the Termination Payment; d) providing Power Block or Traffic Block or necessary disconnections to the Contractor; e) approval of disconnections for modification of signaling and telecom works, or any other matter which is not specified in (a); (b), (c), (d) or (e) above and which creates an obligation or liability on either Party for a sum exceeding Rs. 50,00,000 (Rs.Fifty Lakhs). In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 7
  • 8. Important Clauses: Continues……………. Authority Engineer’s Services : Continues------------ Responsible for documents accuracy- correcting, at its own cost and risk,-the works/the documents -including any re-survey/ investigations/supervision. Non Performance/ compliance of any of the provisions of the Agreement- a deduction of Rs.25,000/- or higher but not exceeding 1% of the monthly payment for PMS to AE shall be applicable for each instance(Ref-Cl. 3.9.31 , PAGE 37 of 132) – more than 5 incidents- Termination by Authority Ensuring safety- Railway assets, Rolling stocks and Railway users on the works being carried out – Accidenthappens- in loss of life -after inquiry conducted Authority/Railway/Commissioner of Railway Safety(CRS) that safety measures were lacking-impose a penalty @ Rs. 5 Lacs on the AE for every such incident Failure - certification of Stage, Interim or Final payment by the AE---deduction of Rs 25,000/- per day of delay In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 8
  • 9. Important Clauses: Continues……………. Authority Engineer’s Services : Continues------------ Obtain Approval of personnel- Authority may approve /reject proposal within 14 days of receipt - does not reject within 14 days -deemed to approved by the Authority. Substitution of Key Personnel: Cl. 3.11. of Schedule – 1: Form of Agreement , Page 39of 132 Expects all personnel to be engaged during implementation –non commencemnt upto180 days due to reasons by Authority- permitted for replacement –max 50% Key Personnel with Key Personnel of equivalent/ better qualifications -without considering the same as replacement/substitution and without any deduction- Apart from above not consider except for reasons of any incapacity, death or any reasons beyond the reasonable control of the Authority Engineer- shall be subject to equally or better qualified and experienced personnel , Condition; replacement upto 40% - reduction of remuneration – 5% replacement above 40% and upto 65%, -reduction of remuneration – 10% Above 65% -reduction of remuneration – 15% In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 9
  • 10. Important Clauses: Continues……………. Any taking of leave by any personnel Cl. 3.12 of Schedule I, Page 40 of 132  -exceeding 3 (three) days -the prior approval of the Authority, and AE ensure that leave will not delay the progress and quality of the Services Manpower deployment : Cl.10 of Schedule-1, page 80 of 132) List of manpower, No.s required, and their Minimum required Educational qualifications and/or experience are provided Deployment of personnel other than those mentioned :(Cl. 10.3 of Schedule-I, Page 86 of 132) The AE may be required to deploy other personnel who are experts in their field also for the project for specific needs. Their deployment shall be arranged by the AE on specific requisition from the Authority and the payment shall be made as per the actual deployment. Such specialist experts shall be paid at the rate of remuneration payable to such new AE’s personnel based on the rates for other position which require similar qualifications and experience with mutual consent. If required, Authority may require/agree for additional deployment of similar personnel identified in the bid and in such cases payment to the AE shall be based on the remuneration of such personnel in the Agreement. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 10
  • 11. Important Clauses: Continues……………. Terms & Conditions of Payment and Deployment:(Cl. 11 of Schedule-I, Page 86 of 132) Remuneration for the Key Personnel shall be determined on the basis of the Deployment Schedule and days actually spent as deployed by such Key Personnel in the performance of the Services from Effective Date. Remuneration for periods of less than one month shall be calculated on a calendar day basis for the period deployed for part of the month. A copy of monthly attendance records shall be attached with Monthly Status Report The Key Personnel shall be considered to be inadequately deployed -if he/she is not present for atleast 80% (eighty percent) of the days stipulated in that calendar month, as per the Man Months Input in the Terms of Reference and the Deployment Schedule proposed by the Authority Engineer and approved/modified by the Authority. The reduction or deduction of the amount @20% (twenty percent) of the monthly payment due as the case may be shall be made against such Key Personnel during the monthly billing In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 11
  • 12. Important Clauses: Continues……………. Delays- performance/ commencement of its contractual obligation/Non-submission of final report by due date (Cl. 4.3 of Schedule-I, page 41 of 132 Imposition of L.D.- @ 0.5% of the Agreement Value per week-subject to max- 5% of the Agreement Value. This may also include forfeiture of Performance Security. Termination of contract Extension of time- Cl. 4.4 of Schedule-I, page 41 of 132 Applicable – in case situation arises- notify Authority in writing -fact of the delay, its likely duration and its causes-Authority shall evaluate & may extend the Authority Engineer’s time for performance-by amendment of the Contract. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 12
  • 13. Important Clauses: Continues……………. Variation- Cl. 4.6 of Schedule-I, page 41 of 132) – Applicable The Authority may notify the to alter, amend, omit, add to, or otherwise vary the Services upto 25% increase of the contract value or upto 50% increase of the original completion period stipulated in the contract, whichever is earlier, on the same rates, terms and conditions and the Authority Engineer shall be bound by such variations. Beyond 25% increase of the Contract Value or beyond 50% increase of the original completion period, whichever is earlier, new rates shall be agreed between Authority and Authority Engineer. In such an event, the Authority Engineer shall submit an estimate for proposed changes in rates along with justification for such rates to the Authority: 1) within fourteen (14) calendar days of receipt of a notice of variation in case of proposed increase of the contract value beyond 25%; 2) atleast 60 days in advance of reaching limit of 50% increase in completion period, if it is anticipated that consultancy contract period shall need to be extended beyond 50% of the original completion period In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 13
  • 14. Important Clauses: Continues……………. Payment to the Authority Engineer- Cl. 4.7 of Schedule-I, page 42 of 132) As per renumeration rates; -Price Adjustment applicable- first 12 months from the date of commencement of services shall remain the same- From the beginning of 13th month from the date of commencement of services, remuneration rates shall be adjusted as per the formula for every 12 months. in case any personnel is continuing for more than 12 months from date of his/her deployment then the AE shall be entitled for increase in monthly remuneration rate @ 3% of the accepted monthly remuneration rate of such personnel, on completion of every 12 months Price Adjustment shall not be applicable during the extension period for which extension is sanctioned for reasons attributable to the AE. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 14
  • 15. Important Clauses: Continues……………. Force Majeure: Cl. 5 of Schedule-I, page 44 of 132 Applicable; shall not be liable for forfeiture of its Performance Security, liquidated damages or termination for default, to the extent that, delay in performance or other failure to perform its obligations under the Contract If a Force Majeure situation arises, either party shall promptly notify the other party in writing of such conditions and the cause thereof However, Authority may terminate this Agreement by giving a written notice of minimum 7 days to the Authority Engineer, if as a result of Force Majeure, the Authority Engineer is unable to perform the services for a period of more than 30 days. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 15
  • 16. Important Clauses: Continues……………. Agreement Termination : Cl. 6 of Schedule-I, page 44 of 132 Stands terminated - the Authority Engineer has rendered all the services to the satisfaction of the Authority and the same are accepted by Authority. Termination by Authority : Cl. 6 of Schedule-I, page 44 of 132 Breaches any of the terms of this Agreement & not remedied within 10 days of receipt of a notice persistent default in the provision of the Services, the disclosure of any Confidential Information. commits any offence under the Prevention of Corruption Act 1988. Fails or refuses to provide the Services after written warning delay in commencement of services or delay in performance of its contractual obligations. AE becomes / is in jeopardy of becoming insolvent/bankrupt/has a receiving order made against it, /compounds with its creditors, or any of them Authority also reserves the right to short close the Agreement any time.  No compensation shall be payable beyond the services payable as per Payment Schedule. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 16
  • 17. Important Clauses: Continues……………. Termination by Authority Engineer : Cl. 6.7 of Schedule-I, page 45 of 132 not less than 30 (thirty) days’ written notice to the Authority, after the occurrence of any of the events specified in this clause, the Authority fails to pay any money due to the AE pursuant to this Agreement and not subject to dispute within 60 (sixty) days after receiving written notice from the AE that such payment is overdue; as the result of Force Majeure, the AE is unable to perform a material portion of the Services for a period of not less than 60 (sixty) days; In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 17
  • 18. Important Clauses: Continues……………. Insurance: Cl. 8 of Schedule-I, page 46 of 132 The AE shall, for the duration of this Agreement, take out and maintain, at its own cost, but on terms and conditions approved by the Authority, insurance against the risks, and for the coverages, as shall be specified in the Agreement -3rd party liability insurance -of Rs. 50 Lakhs for the period of this Agreement , 3rd party motor vehicle insurance, Global Indemnity Insurance, Employer’s liability & workers’ compensation insurance -life, health, accident, travel or other insurance as may be appropriate; -, and in accordance with good industry practice Within 15 (fifteen) days of receiving any insurance policy certificate in respect of insurances required to be obtained and maintained under this clause, the AE shall furnish to Authority, copies of such policy certificates, copies of the insurance policies and evidence that the insurance premia have been paid in respect of such insurance. Except in case of Third-Party liabilities, the insurance policies so procured shall mention the Authority as the beneficiary of the Authority Engineer and the Authority Engineer shall procure an undertaking from the insurance company in this regard. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 18
  • 19. Important Clauses: Continues……………. Disputes: Cl. 10 of Schedule-I, page 48 of 132 IN CASE ARISES- either party may request the other to participate in a meeting of their respective senior officials -in order to discuss the dispute and to agree to a strategy to resolve it- arrange and implement the meeting within 10 days - exchange statements at least 3 days prior to the date of the meeting, setting out their respective views of the issues, which are in dispute. unresolved within 1 MONTH of the date on which the dispute arose, then the matter shall be resolved through conciliation process as per the Settlement of Disputes – Indian Railway Arbitration and Conciliation Rules provided under the Indian Railways Standard General Conditions of Contract 2022 (GCC April 2022) issued by Engineering Department, including any correction slips as updated from time to time. Notice of Dispute-shall be served later than 30 days after the date of issue of Completion Certificate by the Authority- Chief Engineer or Divisional Railway Manager- within 30 days after receipt of the AE ’s “Notice”, notify the name of conciliator(s) to the Authority Engineer who shall assist in amicable settlement If the parties reach agreement on a settlement of the dispute, they shall draw up and sign a written settlement agreement duly signed by the Authority representative, Authority Engineer and conciliator(s). In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 19
  • 20. Important Clauses: Continues……………. Matters Finally Determined by the Authority /Excepted matter(matters no arbitrable, and decisions of the Railway authority, thereon shall be final and binding on the Authority Engineer; ) : Cl. 10.4 of Schedule-I, page 48 of 132) In case arises, AE shall referred to the General Manager (GM) and the GM shall, within 120 days make and notify decisions on all matters referred to by the Authority Engineer in writing: AE’s personnel performance Illegal Gratification Monetary dealings/ transactions with Authority personnel Ambiguity in Meaning and Intent of Specification and Drawings Rates for Extra Items of Works Signing "No Claim" Certificate- not entitled to claim Accuracy of measurement provisions of the Contract Labour (Regulation and Abolition) Act, 1970,Payments of Wages Act,Workmen’s Compensation Act,Mines Act Right of authority to determine the contract and its payment In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 20
  • 21. Important Clauses: Continues……………. Arbitration: Cl. 10.5 of Schedule-I, page 52 of 132 unresolved dispute - within the time period, then the dispute shall be subject to arbitration process as per the Settlement of Disputes – Indian Railway Arbitration and Conciliation Rules provided under the Indian Railways Standard General Conditions of Contract 2022 (GCC April 2022) issued by Engineering Department, including any correction slips as updated from time to time- after 120 days but within 180 days of his presenting his final claim on disputed matters shall demand in writing that the dispute or difference be referred to arbitration. The claimant shall submit his claims stating the facts supporting the claims along with all the relevant documents and the relief or remedy sought against each claim within a period of 30 days from the date of appointment of the Arbitral Tribunal. The Authority shall submit its defence statement and counter claim(s), if any, within a period of 60 days of receipt of copy of claims from Tribunal, unless otherwise extension has been granted by Tribunal. No new claim shall be added during proceedings by either party. However, a party may amend or supplement the original claim or defense thereof during the course of arbitration proceedings subject to acceptance by Tribunal having due regard to the delay in making it. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 21
  • 22. Important Clauses: Continues……………. Place of Arbitration: Cl. 10.5.1 iii d) of Schedule-I, page 53 of 132 The place of arbitration would be within the geographical limits of the Division of the Railway where the cause of action arose or the Headquarters of the concerned Authority or any other place with the written consent of both the parties. Obligation During Pendency of Arbitration: Cl. 10.5.2 of Schedule-I, page 53 of 132 Work under the contract shall, unless otherwise directed by the Authority, continue during the arbitration proceedings, and no payment due or payable by the Authority shall be withheld on account of such proceedings, provided, however, it shall be open for Arbitral Tribunal to consider and decide whether or not such work should continue during arbitration proceedings. Appointment of Arbitrator: Cl. 10.5.3 of Schedule-I, page 53 of 132 According to arbitration and conciliation act Governing Law : Cl. 14of Schedule-I, page 57 of 132 governed by and construed in accordance with the substantive laws of India. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 22
  • 23. Important Clauses: Continues……………. Reports to be submitted by AE, Cl. 3.3 of Annexure I of Schedule-1, page 62 of 132/ Cl. 4.5i of Annexure I of Schedule-1, page 66 of 132 Daily report- event/happening which is likely to affect the progress, quality of work and safety if any on previous day Monthly progress report- within 7-10 days the beginning of every month in respect of its duties and functions under this Agreement Quarterly progress report- within 14 days of the end of each quarter & include a description of project activities illustrated by progress/completion photographs, status of any delays and detailed plan to make up any shortfall or deficiency, status of contractual claims, and details of all latest financial projections Setting up of Project Management Office , Cl.4.1 of Annexure I of Schedule-1, page 63of 132 within two months from the date of commencement of the works. Failure to establish the facilities will invite a penalty of Rs.10,000/- per week In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 23
  • 24. Important Clauses: Continues……………. Review of drawings: Cl.4.11,4.12 of Annexure-1, Schedule-1, page 73 of 132 the AE shall complete such review and send its observations to the Authority and the Contractor within 15 (fifteen) days of receipt of such Drawings The Authority Engineer shall review any revised -within 10 (ten) days of receiving such Drawings; provided, however that in case of Structures, airspace development at railway stations including concourse and any other specified item the aforesaid period, the days may be extended as per the time limit Review of Quality Assurance Plan : Cl.4.13 of Annexure-1, Schedule-1, page 73 of 132 convey its comments to the Contractor within a period of 21 days as mentioned in the EPC Agreement stating the modifications; Review of Methodology proposed: Cl.4.15 of Annexure-1, Schedule-1, page 74 of 132 convey its comments to the Contractor within a period of 10 (ten) days or as mentioned in the EPC Agreement from the date of receipt of the proposed methodology from the Contractor In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 24
  • 25. Important Clauses: Continues……………. Review of Monthly progress report: Cl.4.16 of Annexure-1, Schedule-1, page 73 of 132 send its comments thereon to the Authority and the Contractor within 7 (seven) days of receipt of such report. Monthly Inspection Report : Cl.4.17 of Annexure-1, Schedule-1, page 73 of 132 bringing out the results of inspections and the remedial action taken by the Contractor in respect of Defects or deficiencies. In particular, the compliance of the recommendations made by the Safety Consultant. Failure to achieve milestones by Contractor: Cl.4.32 of Annexure-1, Schedule-1, page 76 of 132 undertake a review of the progress of construction and identify potential delays; if any. If the Authority Engineer shall determine that completion of the Project is not feasible within the time specified in the EPC Agreement; it shall require the Contractor to indicate within the days as mentioned in the EPC Agreement, the steps proposed to expedite progress; and the period within which the Project Completion Date shall be achieved. Upon receipt of a report from the Contractor; the Authority Engineer shall review the same and send its comments to the Authority and the Contractor forthwith. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 25
  • 26. Important Clauses: Continues……………. Quality control Records: Cl.4.33 of Annexure-1, Schedule-1, page 77 of 132 obtain from the Contractor a copy of all the Contractor’s quality control records and documents before the Completion Certificate Final Documentation: Cl.4.38 of Annexure-1, Schedule-1, page 77 of 132 Authority Engineer shall compile a complete and indexed set of project documentation files. The files shall include as built documentation and shall contain documents delivered by sanctioning/approval, authorities, Authority, Consultant, and vendors/contractors Payments for Contractor: Cl.6 of Annexure-1, Schedule-1, page 79 of 132 within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor determine the amount due and recommend the release of 80 (eighty) percent of the amount as part payment; pending issue of the Interim Payment Certificate within 20 (twenty) days of the receipt of the Stage Payment Statement deliver an Interim Payment Certificate certifying the amount due and payable to the Contractor; after adjustments In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 26
  • 27. Important Clauses: Continues……………. As built drawings: Cl.8.3 of Annexure-I,Schedule-1, page 80 of 132 Within 90 (ninety) days of the Project Completion Date; the Authority Engineer shall obtain a complete set of as-built Drawings; in 2 (two) hard copies and in micro film form or in such other medium as may be acceptable to the Authority; reflecting the Project as actually designed; engineered and constructed; including an as-built survey illustrating the layout of the Project and setback lines; if any; of the buildings and structures forming part of Project Facilities; and shall hand them over to the Authority against receipt thereof. Event of contractor’s default: Cl.8.5 of Annexure-I,Schedule-1, page 80 of 132 The AE shall inform the Authority and the Contractor within one week of its occurrence. Weekly & Monthly Meetings: Cl.9 of Schedule-1, page 80 of 132 to be held at site and Authority HQ-required personnel shall participate. In case key personnel required to visit outstation - travel, boarding and lodging expenses will be reimbursed as per financial bid In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 27
  • 28. Important Clauses: Continues……………. Payment Schedule of AE: Annexure 3 of Schedule-2, page 89 of 132) not later than 15 days after the end of each calendar month during the period of the Services, the AE shall submit to the Authority, induplicate, itemized statements, and other appropriate supporting materials, of the amounts payable for such month, Payment- Within 30 days of receipt by authority –cause the payment periodically after deduction / add , if any The final payment -after the final report and a final statement, -, shall have been submitted by the AE and approved as satisfactory by the Authority. -ninety (90) calendar days after receipt of the final report and final statement by the Authority unless the Authority, within such ninety (90)day period, gives written notice specifying in detail deficiencies in the PMS Any amount which the Authority has paid or caused to be paid in excess shall be reimbursed by the AE to the Authority within30 (thirty) days after receipt by the AE of notice thereof.Any such claim by the Authority for reimbursement must be made within 12 (twelve) calendar months after receipt by the Authority of a final report and a final statement approved by the Authority in accordance with the above In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 28
  • 29. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 29
  • 30. LOA Enter into Agreement with Authority Mobilization Initial Data Verification Prepare PIP Set up Project Management Office Kickoff Meeting Project Planning: Approval of Methodology, Preparing Policies and Standards Project Execution & Project Monitoring Review of Design & Drawings Change Management Approval of Authority Cost Analysis & Forecast Review & Approval of Bills Payment to Contractor Issue of Provisional Certificate & Start of DLP DLP Completion Project Closure & Value Engineering Flow Chart of Activities In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 30 Review meetings & Report Preparation
  • 31. Approach Phases of PMC Services: • Initiation & Mobilization • Project Planning • Project Execution and Monitoring • Technical Audit and Quality Assurance & Quality Control • Document Control System • Project Completion • Services during Defects Liability Period Methodology & Work Plan In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 31
  • 32. In JV with Appointment of Authority Engineer for Providing Project Management Services for Redevelopment of Ernakulam Junction Railway Station 32