Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011
1. Challenges Implementing
Green I f
G Infrastructure S l i
Solutions
in Onondaga County
Joanne M. Mahoney, County Executive
Joanne M Mahoney County Executive
Onondaga Lake Amended Consent Judgment (ACJ) Compliance Program
Matthew Millea, Onondaga County
Deputy County Executive for Physical Services
Matthew Marko, P.E., BCEE,
Vice President CH2M HILL
2. 10/25/11
Onondaga County,
g y, City f Syracuse
Cit of S
2
New York Onondaga Lake
Onondaga Creek
• 7,660 acres
• 49 CSOs
Harbor Brook
• ~1 Billion gallons/year CSO
g /y
3. 10/25/11
3
AGENDA
• Program History and Consent Order Overview
• G
Green I f
Infrastructure: Wh is it? and Why are we doing it?
What i i ? d Wh d i i?
• Onondaga County GI Program Compliance Summary
• City of Syracuse Civic Strip: Pledge and Action
y y p g
• 2010 Save the Rain Projects and Case Studies
• PROJECT 50! Projects and Green Initiatives
• Green Improvement Fund: Nation’s Best Public Private
Partnership
• Education and Outreach
• GI Maintenance
• Summary of Challenges Overcome and Looking Forward to 2018
▫ Questions and Answers
5. 10/25/11
Informal Survey of NYCOM PWS
PWS…
5
1. Have you ever heard of Green Infrastructure (GI)?
2.
2 If so, what d
h t does it mean t you?
to ?
(stormwater management? energy savings? other?)
3. What are your biggest fears about
implementing GI?
4. What are your biggest hurdles to implementing GI (regulatory?
management? workers/staff on the ground? financial? that's not the way
g / ff g f y
we do things around here?)
5. Will you hear anything today that helps overcome those
challenges?
Please take a moment to answer any/all of the questions on
the forms provided and we’ll collect them after the
we ll
presentation
7. 10/25/11
7
Addressing Challenges Head On:
dd h ll d
1.
1 Establish a Forum to resolve policy issues
issues,
2. Demonstrate key technologies early in the program,
3. Incentivize GI (e.g. Green Improvement Fund),
4. Add Green Infrastructure onto existing capital projects,
and
5.
5 Have a world class website.
website
www.savetherain.us
8. 10/25/11
• 1988 – Atlantic States Legal Foundation
History
8
files lawsuit against County
• 1989 – Litigation settled through
METRO consent judgment Onondaga Lake Facts
• 1998 – METRO consent judgment
replaced with Amended Consent Watershed: 285 Square Miles
Judgment (ACJ)
1 Mile Wide – 4.6 Miles Long
• 1st ACJ amendment May 1998
• 2006 ACJ Amended to include Average Depth: 35 feet
g p
consolidation of ammonia and
phosphorus treatment and Harbor Max Depth: 63 feet
Brook conveyances and RTF
y
1940 – Swimming Banned
• 3rd Amendment April 2008 (Extension)
• 2009 ACJ amended to authorize use of 1970 – Fishing Banned
Gray and Green infrastructure
9. ACJ Compliance Projects Completed to Date (
p j p (1998-2008)
)
Total Investment: $367 million
1. Aeration System Upgrade
y pg 21. Siphon Rehabilitation
p
2. Odor Control - residual handling and clarifiers 22. Teall Brook FCF
3. Chemical Storage Building and Feed System 23. West St. Sewer Separation (CSOs 057, 058, 059)
4. Digester and Lagoon Improvements 24. Water St. Sewer Separation (CSO 024)
5. Phase II Plant Improvements 25. Brighton Sewer Separation (CSOs 053, 054)
6. Ammonia Removal Pilot
l l 26.
6 Ammonia Source Trackdown Program
A i S kd
7. Phosphorus Removal Pilot – Phase I 27. Tallman/Onondaga Sewer Separation (CSOs 038, 040,
8. Digital System Upgrade 046a and 046b)
9. Ammonia Removal – BAF 28. Midland Phase II (includes Regional Storage and
Treatment Facility plus 1,000 ft. pipeline)
10. Phosphorus Removal – HRFS
29. Phosphorus Removal Pilot – Phase II
11. CSO Toxicity Evaluation Report
30. Biosolids Handling (mechanical thickeners)
12. Erie Boulevard Storage System Upgrade
Improvements – Metro
13. Franklin St. FCF
31. South Ave./Bissell St. Sewer Separation (CSOs 047 and
14. Harbor Brook FCF 048)
4 )
15. Hiawatha RTF 32. Sewer Separation 050 – Parkway/Rockland
16. Kirkpatrick St. Pump Station Upgrade 33. Clinton Conveyances Phase 1 – pipeline outside the
17. Maltbie St. FCF Trolley Lot & Armory Square
18. Midland Phase I Pipeline 34. Clinton Conveyances Phase 2A – pipeline behind the
19.
19 Newell St. Pilot Disinfection
St MOST under RR
20. Onondaga Creek FCF - Boat 35. Sewer Separation 051 – Colvin Avenue
10. 10/25/11
10
Water Quality Improvements
W t Q lit I t
Ammonia decreased from 8,000 pounds per day (ppd) to less than 50 ppd
Phosphorus decreased from 300 ppd to 50 ppd
11. 4th ACJ Amendment Authorized a 11
10/25/11
Balanced Approach to CSO Abatement
Regulatory Goals Community Impacts/Goals
• Capture and Treat 95% of the • Improve quality of life
Annual CSO Volume via Gray y • Promote Sustainability
& Green Infrastructure
• Ensure cost effectiveness in
• Achieve water quality
compliance with ACJ
standards in tributaries and
milestones
lake
Major Milestones
• 89.5% capture/elimination by 12/31/2013
• 95% capture/elimination by 12/31/2018
p / y / /
12. Gray Infrastructure Program
y g
Projects Identified in 4th Stipulation
Gray P j
G Projects
• Harbor Brook Interceptor (ARRA)
• Midland Conveyance (C O 044)
C y (CSO
• Clinton Storage Facility and Electrical
Ductbank
• H b B k St
Harbor Brook Storage F ilit
Facility
and Conveyances
• Erie Boulevard Storage System (EBSS)
Gate Ch b #3 I
G Chamber Improvement
• Sewer separation projects
• Floatables Control Facilities
13. Gray Program Construction Schedule
y g
10/25/11
13
CSO 022/045 Sewer Separation
Consent Order Milestones: Complete Construction: 12/31/12
Construction Period: October 2011 – July 2012
Clinton Storage Facility
Consent Order Milestones: Commence Construction: 10/1/11
Complete Construction: 12/31/13
Construction Period: September 2011 – December 2013
p 3
Lower Harbor Brook Conveyances:
Consent Order Milestones: Commence Construction: 12/31/11
Complete Construction: 12/31/13
Construction Period: October 2011 – July 2012
Lower Harbor Brook Storage:
Consent Order Milestones: Commence Construction: 12/31/11
Complete Construction: 12/31/13
Construction Period: November 2011 – December 2013
Electrical Duct Bank on West Fayette Street (Part of Clinton Storage Project)
Consent Order Milestones:
d il N/A
/
Construction Schedule: September 2011 – November 2011
16. 10/25/11
16
What is Green I f t t ?
Wh t i G Infrastructure?
Adaptable term used to describe an array of
products, technologies, and practices that use
natural systems – or engineered systems, that
mimic natural processes to enhance overall
environmental quality and provide utility services
What do WE use it for?
Primarily, to capture rainwater during storm events
to reduce the need for more “gray” infrastructure
18. 10/25/11
W y G ee
Why Green Infrastructure ?
ast uctu e 18
Your Water Quality Suffers
• 8 % of pollution t th aquatic environment
80% f ll ti to the ti i t
comes from land-based sources, such as
runoff pollution
• New York has identified nonpoint sources as
the i
th primary cause of water quality problems
f t lit bl
in 91% of its priority waterbodies
• Once a watershed’s impervious cover
exceeds 20%, water quality begins to suffer
19. 10/25/11
19
How GI Has Shifted the Paradigm
Paradigm…
Why are you We want GI in
spending all that the suburbs!
money in the City? “YIMBY”
NIMBY !!!
Porous Pavers at Hotel Skyler
20. 10/25/11
6% Capture Using Green Infrastructure
p g 20
- Green 470 acres and reduce 247 MG/yr of CSO by 2018
21. 10/25/11
Green Infrastructure Programs matched to 21
Impervious Area Types
Impervious Area Green Infrastructure • Streets
Type Technologies • Parks & Open
Space
Flat Roof Buildings Vegetated Roof
• Parking
Parking Areas & • Public Facilities
Porous Pavements, Bioretention
Sidewalks
• Roofs
Green Streets (Bioretention, Street • Drainage area &
Roadways
Trees) Model
M d l
Downspout Disconnection Refinements
Pitched Rooftops Rain Barrels & Cisterns • Private Lands
▫ GIF
Rain Gardens ▫ Ordinance
Combination of the Above ▫ Rate Incentive
Facilities & Schools
Technologies ▫ Strategic
Partners
P
Scattered across Public and Private Properties
22. Implementation Program Development
p g p
10/25/11
22
Framework
Review
Evaluate
Adapt
Program Where What How Who How Much
Primary GI
Target
Impervious Technology Implementation
Owner Reduction
Area
A (e.g. Rain
( g R i Strategy
St t g
/ Status
Garden)
Public
Outreach &
Partnering
Projects
Private
Planning & Engineering Resource Management
Procurement
Field Survey / Environmental
y
Tracking & Monitoring
23. Project Development Process
j p
10/25/11
23
Project Concept Development
Environmental
Assessment
Survey
ment
Infiltration Testing
Procurem
Design
Owner
Approval
pp Yes Permitting
(Y/N)
Revise Construction
Concept
SDCs
No
Evaluate / Remove
Policy Barriers
Bi Weekly
Bi-Weekly City / County Projects by
j y
Project Tracking
Meeting Others
24. System-wide GI CSO Reduction: 2011 Opportunity
10/25/11
24
CSO Reduction:
Target CSO Volume CSO Reduction: Additional CSO
Target CSO Volume Projects
Reduction 2011 Candidate Reduction Required
Reduction (gal)
(g ) Completed/ Under
p /
(% of Total)
(% f T t l) Projects (gal)
P j t ( l) through 2018 (gal)
th h 2018 ( l)
Construction (gal)
Streets 89,940,000 36% 2,165,000 13,895,000 73,880,000
Parks & Open Space
P k &O S 13,992,000
13 992 000 6% 1,069,000
1 069 000 16,711,000
16 711 000 ‐3,788,000
3 788 000
Parking 12,184,000 5% 2,543,000 2,977,000 6,664,000
Public Facilities 14,003,000 6% 418,000 9,482,000 4,103,000
Roofs 3,201,000 1% 63,000 3,657,000 519,000
Impervious Area Data 29,800,000 12% 29,800,000 0 0
Voluntary 11,372,000 5% 520,000 2,750,000 8,102,000
Green Improvement
Green Improvement
11,372,000 5% 1,132,000 1,318,000 8,922,000
Fund (GIF)
Ordinance 46,257,000 19% 3,334,000 0 42,923,000
Impervious Area
Impervious Area
3,452,000 1% 0 0 3,452,000
Based Rate Incentive
Non GIF Incentive 11,372,000 5% 305,000 1,555,000 9,512,000
TOTAL 247,000,000 100% 41,350,000 52,350,000 153,300,000
27. Onondaga County 10/25/11
27
Civic Strip
Greening County Facilities Utilizing
Multiple Green Infrastructure
p
Technologies
Showed to judge in 2009
Completed or in construction
28. OnCenter Convention Center
60,000 Square Foot Green Roof
GI Technology:
h l Green Rooff
Project Owner: Onondaga County
Capture Area: 59,000 square feet
Runoff Reduction: 1,033,000 gallons/yr
Construction Cost: $1,038,000 (bid)
bd
$/gallon: $1.00
31. Onondaga County 10/25/11
31
Civic Strip
Greening County Facilities Utilizing
Multiple Green Infrastructure
p
Technologies
32. War Memorial Water Reuse
Reusing rainwater appears to allow the ice making to occur one to two
degrees warmer than using potable water resulting in energy savings
33. War Memorial Water Reuse
GI Technology:
gy Rain cistern
Capture Area: 44,000 square feet
Runoff Reduction: 400,000 gallons/yr
Construction Cost: $1,229,000 (bid)
GI Grant: $720,000
$/gallon: $4.33 without grant
$1.79 with grant
Estimated Annual Potable Water Savings:
127,000‐300,000 gallons
34. 10/25/11
Civic Strip: Harrison Street
p 34
GI Technology:
Bioretention
Project Owner:
City of Syracuse
Capture Area:
p
10,000 square feet
Runoff Reduction:
180,000 gallons/yr
BEFORE: Stormwater enters AFTER: Stormwater is
Construction Cost:
catch basins and is directly diverted to Green Streets
connected to sewer and only overflows to sewer $121,200 (bid)
when necessary
h $/gallon: $0.67
35.
36. 10/25/11
Civic Strip: OnCenter Municipal Parking Garage
36
GI Technology:
Roof leaders to rain
R f l d i
gardens
Project Owner:
County
Capture Area:
7 ,5
72,500 square feet
q
Runoff Reduction:
1,277,000 gallons/year
Construction Cost:
C i C
$234,000 (bid)
$/gallon: $0.26
37. 10/25/11
OnCenter Surface Parking Lot
g 37
GI Technology:
Perimeter porous
asphalt and tree
h l d
infiltration trench
Project Owner:
County
Capture Area:
134,000 square feet
34, q
Runoff Reduction:
2,360,000 gallons/year
Construction Cost:
C i C
$812,000 (bid)
$/gallon: $0.48
38.
39. 10/25/11
39
Townsend Parking Lot (“Lot B”) &
Townsend Median
40. 10/25/11
40
Vegetated Infiltration Beds,
90 Trees Planted
43. County Townsend Lot:
y
10/25/11
43
Project Completion Report
• Lot construction completed on schedule
▫ Binder/base course pavement in 2010
▫ Top course and some plantings completed in spring 2011
• Technical comments
▫ Stormwater details and specifications
▫ Plant species selection (salt tolerance)
▫ Planting locations – offset more properly with parking spaces
▫ Paving
P i materials i l
• CSO reduction 692,000 gallons/year
• Cost impacts
▫ Bid $342,000 (estimated portion)
▫ Change order $0
▫ Total cost $342,000
▫ $0.51/gallon
ll
45. 10/25/11
45
Median Rehabilitation
• R
Remove i impervious
i
pavers
• Re-grade profile for
Re grade
stormwater capture
• Plant large canopy, salt
tolerant trees
• Maintain pedestrian
crosswalks
46. GI Technology:
Pavement removal
Project Owner:
County
Capture Area:
18,000 square feet
Runoff Reduction:
317,000 gallons/yr
317 000 gallons/yr
Median vegetation planted in
Spring 2011 Construction Cost:
Volume capture: 317,000 gallons/year $86,000
$/gallon: $0.38
48. Onondaga County 10/25/11
48
Civic Strip
Greening County Facilities Utilizing
Multiple Green Infrastructure
p
Technologies
5.6 Million Gallons Promised
and Delivered
51. Parking
g
10/25/11
51
How Who How Much
Where What
Target
Target CSO CSO
Area / Primary Green
Implementation Strategy
Implementation Strategy Reduction Volume
Reduction Volume
Program Impervious Infrastructure Owner
(5) Volume Reduction
Source (1) Technology (2)
(gal) (% of
Total)
03‐ Reconstruct City/County
Parking ‐ Public Porous Pavement City/County 6,510,000 3%
Parking Lots
52. 10/25/11
52
Porous Pavement / Infiltration Practices
Design Assumptions / Guidelines
• S i storage of fi i h of runoff
Static f first inch f ff • M i
Maximum surface grade change of
f d h f
• Maximum loading ratio of 10:1 1-2 feet; steeper sloped areas may
(impervious area to infiltration warrant a change in bottom
area); 5:1 is preferred elevation (via berms or other)
• Geotextile liner separating rock • U
Upper 3” of th i filt ti b d
” f the infiltration bed
from soil (non-woven or woven… or subgrade should be scarified prior
sand?) to bed installation (if necessary)
• Impervious liner where needed • Total facility depth should between
(proximity to utilities, buildings, 24-31 i h (f t consideration)
inches (frost id ti )
etc) • Protect existing utilities
• Observation well and cleanouts • Setbacks:
• Perforated distribution pipe and/or
pp / • 10ft to buildings with basements
g
underdrain • 3ft to buildings without basements
• Dewater within 72 hours • 3ft from utility structures, vents,
• Level bed/trench bottom poles, etc
• Overflows for larger storm volumes
53. 10/25/11
53
A Variety of Porous Pavement Systems
Can be Used
Porous Concrete
Porous Pavers Porous Asphalt Porous Resin Bonded Aggregate
54. City Lot #21 –
y
10/25/11
Infiltration Trench, Porous Pavers 54
Volume capture: 462,000 gallons/year
Before
55. 10/25/11
55
Case Study: City Lot #21
(formerly the “Farmer’s Market Lot”)
• Design Components: • Impervious area managed:
• 5,000sf infiltration system 26,250sf
• Tree trench (2,000sf) with porous • Infiltration area: 5,000sf (loading
pavers and 36” of CU-Structural ratio of 5.3:1)
Soil • Runoff capture goal ( ”) 2,190cf
ff l (1”): f
• Aggregate infiltration bed under • 6 new trees
standard asphalt (31” deep) • Total soil: 6,000cf (1,000cf per
• Inlet filter inserts tree)
• Entire lot repaved (standard • Total static storage capacity:
asphalt) and restriped (6 more 4,200cf
spaces) (equates to around 2.1” of runoff
• T
Two outlet control structures with
tl t t l t t ith capture)
weirs (connection to existing
storm sewer)
• Infiltration testing yielded a rate
of 20 i /h
f in/hr
60. 10/25/11
60
Case Study: City Lot #21
C St d Cit L t
• Stormwater Details and
Specifications
•C
Concrete structures preferred
t t t f d
• Overflow weir plates
• Concerns over inlet filter
inserts (maintenance)
61. 10/25/11
61
Case Study: City Lot #21
C St d Cit L t
• Trees and Plantings
• Temporary maintenance:
emphasize/enforce
temporary irrigation and
initial pruning
• Species selection and
maintenance streamlined in
the future with the
City/County A b i
Ci /C Arborist
62. 10/25/11
62
Case Study: City Lot #21
C St d Cit L t
• Subsurface Materials
• Infiltration bed stone availability: NYSDOT #3A is typically
the cleanest, most available stone i the size range d i d
h l il bl in h i desired
• CU-Structural Soil Handling/Acceptance: ensure contractor
provides appropriate cover and maintenance and perform
maintenance,
testing if needed
• Porous paver edge termination
63. 10/25/11
63
City Parking Lot #21 - Project Completion Report
• 1st GI Program Project
• C
Completed on accelerated schedule
l t d l t d h d l
• Technical comments
▫ Stormwater details and specifications
p
▫ Trees and plantings
▫ Subsurface materials
▫ Paving materials
• CSO reduction 328,000 gallons/year
• Cost impacts
▫ Bid $179,300
d
▫ Change order $8,746 (4.8%)
▫ Total cost $188,046
▫ $0.57/gallon
69. 10/25/11
DOT owner, City managed, County designed and financed 69
Over Salting
Over-Salting in Winter
70. Case Study: Pearl Street Lot
10/25/11
70
• Design Components:
• 25,300sf infiltration system
5,3 y
• Porous asphalt (1.5”) on 3” of asphalt treated permeable
base (ATPB)
• Aggregate infiltration bed under both standard and
porous asphalt (24” deep)
• I l t filter inserts and sumps
Inlet filt i t d
• Entire lot repaved (some standard asphalt), restriped
• One outlet control structure with removable weir (connection
to existing combined sewer)
• Infiltration testing was variable, but yielded an average rate of
g , y g
7 in/hr (2 in/hr used for design)
72. 10/25/11
72
Finished Porous vs. Non-Porous Asphalt Surface
73. 10/25/11
73
Case Study: Pearl Street Lot
St d :
• Design Components:
i
• Impervious area managed: 73,172sf
• I filt ti area: 25,300sf (loading ratio of 2.9:1)
Infiltration f (l di ti f )
• Runoff capture goal (1”): 6,098cf
• Total static storage capacity: 10,120cf (equates to around
10 120cf
1.7” of runoff capture)
• Dewatering time: 24 hours (
g 4 (100-year storm)
y )
76. 10/25/11
76
Pearl Street Lot
• Subsurface Utility Location – coordinate with utilities early;
y y;
lack of response or delayed response resulted in field
directives
•U f
Unforeseen C diti
Conditions
• Subsurface structure demolition: multiple building
foundations were encountered
• Balance research costs with schedule and field directive
costs
• Ample public notification
77. 10/25/11
DOT Pearl Street Lot: 77
Project Completion Report
• Completed on schedule
▫ Many new catch basins
▫ Repaired deep trunk sewer manhole
• T h i l comments
Technical t
▫ Subsurface utility location
▫ Unforeseen conditions
▫ P bli Outreach
Public O t h
• CSO reduction 915,000 gallons/year
• Cost impacts
▫ Bid $367,000
▫ Change order $29,772
▫ Total cost $396,772
▫ $0.43/gallon
$ / ll
81. City Parking Lot #3
y g After Construction
Porous Concrete
Captures over 628,000 gallons of stormwater annually
82. 10/25/11
82
City L
Ci Lot #3 – D i C
Design Components
• 8,380sf infiltration system
,3 y • Impervious area managed:
• Tree trench with 36” of CU- 38,507sf
Structural Soil • Infiltration area: 8,380sf
• 6” porous concrete / aggregate (loading ratio of 4.6:1)
infiltration bed (23” deep)
(23 • Runoff capture goal (1”): 3,209cf
(1 ): 3 209cf
• Interior tree plantings • 23 new trees
• Inlet filter inserts and sumps • Total soil: 7,650cf (333cf per
• Entire lot repaved (standard tree, not including existing soil
asphalt) and restriped volume along edge)
• One outlet control structure • Total static storage capacity:
with removable weir 3,392cf (equates to around 1.1”
(connection to existing storm of runoff capture)
sewer) • D
Dewatering ti
t i time: 72 h hours ((100-
• Infiltration testing yielded an year storm)
average rate of 0.48 in/hr (0.24
in/hr used for design)
88. 10/25/11
City Lot #3 88
• Stormwater Details and Specifications
• Inlet restoration – check if necessary
• Porous Concrete
• Test pad quality control
• Letter to contractor noting concerns with
aggregate,
aggregate water retarder water content
retarder,
• Site installation permitted as 2nd “test pad”
• Cold weather placement: 7 days curing time per
specified temperature requirements
89. 10/25/11
City Lot #3 - Project Completion Report 89
• Completed on schedule
• Technical comments
▫ Subsurface details and specifications
▫ Porous concrete quality control
q y
• CSO reduction 481,000 gallons/year
• Cost impacts
▫ Bid $235 000
$235,000
▫ Change order $4,100 (1.7%)
▫ Total cost $239,100
▫ $0.50/gallon
$ / ll
97. Rosamond Gifford Zoo
Primate Exhibit and Courtyard
Rain Barrels and Cisterns
to harvest runoff from rooftops
Porous Pavement
P P t
in Courtyard
Rain G d
R i Garden along
l
Primate Exhibit
98. 98
Rosamond Gifford Zoo
Elephant Exhibit, 2011
GI Technology:
6,000 sq.ft. Green roof
Green Roof Project Owner:
Countyy
Capture Area:
Porous pavement 6,000 square feet
and rain
barrels for Runoff Reduction:
ff d
stormwater 114,000 gallons/year
reuse
Construction Cost:
$183,900
$/gallon: $2.27
99. Creekwalk Project Greening: Jefferson to Walton
j g
Porous Asphalt
Strip in Parking Lot
Before
Bioretention
Bi i
Rain Garden
Flexi-pave
Flexi pave
Porous Walkway
Porous Asphalt Volume capture: 135,000 gallons/year
Parking Lot
101. Creekwalk Project Greening: Walton to Fayette
j g y
Porous Concrete
Porous Asphalt
Strip in
Parking Lot
Before
Re-established
Natural Stream Bank
Volume capture: 119,000 gallons/year
103. Treatment Wetland Eliminates CSO 018
10/25/11
103
(up to design storm)
• 144 Acre CSO b i
A basin
• 40 overflows / year
• Significant Nutrient
Removal
• Partner with SUNY ESF
104. Constructed Wetlands Pilot Treatment System
y
3 wetland types: 1) floating island; 2) vertical down flow; 3) surface flow
GI Technology: Constructed wetland pilot with
grit & floatables pre‐treatment
Project Owner: County
Tributary CSO Area: 145 acres
Site Area: 35 acres
Wetland Area: 2 acres
CSO Event Frequency: 40 CSOs/year
Treatment Volume: 13,600,000 gallons/year
3, , g y
Construction Cost: $2,490,000 (estimated)
$/Gallon: $0.17
Pilot Monitoring Period: 2 years
105. 10/25/11
105
H-05: Green R f at H
H 05 G Roof t Hazard B
d Branch Lib
h Library
• R f Membrane 2010
Roof M b
• Green Planting, Spring 2011
•563,000 gallons/year CSO reduction
5 3, g /y
106. 10/25/11
Erie Canal Museum and Visitor Center 106
GI Technology:
Green roof
G f
Project Owner:
County
Capture Area:
2,000 square feet
Runoff Reduction:
Runoff Reduction
39,000 gallons/year
Construction Cost:
$73,480 (bid)
8 (bid)
$/gallon: $2.62
107. 10/25/11
City Road Reconstruction: Concord Place107
GI Technology: Infiltration Bed
Project Owner: City of Syracuse
Capture Area:
C A 39,000 square feet
f
Run‐off Reduction: 955,000 gallons/year
Construction Cost: $78,970
$/gallon: $0.12
Status: completed
Concord Place (looking south)
Conceptual design showing standard asphalt with the subsurface infiltration bed
108. 10/25/11
City Road Reconstruction: 108
Geddes Street
GI Technology:
GI Technolog Bioretention
Project Owner: City of Syracuse
Capture Area: 29,700 square feet
Run‐off Reduction: 523,000 gallons/year
Construction Cost: $203,000 (bid)
$/gallon:
g $0.55
Status: completed
109. Water Street Gateway Project
y j
10/25/11
109
– under construction
GI Technology:
Infiltration trench
and porous pavers
Project Owner:
City of Syracuse
Capture Area:
53,000 square feet
f t
Runoff Reduction:
924,000 gallons/yr
Construction Cost:
$920,000 (bid)
$/gallon: $1.00
$/gallon: $1 00
110. 10/25/11
Linking with Major Transportation Reconstruction
g j p 110
Creates Green Progress (Phase 1 - 10.4 Acres)
Phase 1 – 10 4 Acres
10.4
Image – Barton & Loguidice
113. 10/25/11
E 36:
E-36: Sunnycrest Park Arena Parking Lot 113
GI Technology:
Porous pavement
Rain garden
Project Owner:
Syracuse Parks Dept.
S P k D t
Capture Area:
107,000 square feet
Run‐off Reduction:
1,876,000 gallons/year
Construction Cost:
$303,000 (bid)
$/gallon: $0.22
Map of Proposed Sunnycrest Arena Parking Lot Project
114.
115. E-16: Sunnycrest Park Golf Parking Lot
y g
10/25/11
115
•GI Technology:
Stream Inflow Removal
Rain garden
Pavement Removal
•Project Owner:
City of Syracuse Parks Dept.
City of Syracuse Parks Dept
•Capture Area:
48,000 square feet
•Run‐off Reduction:
843,000 gallons/yr
Construction Cost:
•Construction Cost:
$363,000 (bid)
•$/gallon: $0.52
116. 10/25/11
Rosamond Gifford Zoo Entrance Enhancement 116
•GI Technology:
Rain gardens
R i d
•Project Owner:
County/City
•Capture Area:
39,000 square feet
•Run off Reduction
•Run‐off Reduction:
680,000 gallons/year
•Construction Cost:
$300,000 (bid)
•$/gallon: $0.62
Green Infrastructure Concept for the Zoo Entrance
p
117. 10/25/11
117
Street Tree Plantings – 8,500 b 2018
l by
GI Technology:
600 trees
Project Owner:
various
Capture Area:
53,000 square feet
Runoff Reduction:
1,200,000 gallons/year
Construction Cost:
$122,350 (bid)
$/gallon: $0.10
118. 10/25/11
Enhanced Tree Planting:
g 118
Urban Tree Trenches
• Porous Pavers
• Structural Soil
• Pretreatment
• Overflow
• Underdrain
119. 10/25/11
Structural Soil Systems Allow 119 119
for Adequate Rooting Volume
and Provide Stormwater
Management Opportunities
Developed by Cornell’s Urban
Horticulture Institute
Meets engineering requirements for
paved surfaces
d f
Allows roots to grow freely under and
away from pavement
Silva Cell lk h i from t roots
Reduces sidewalk heaving f
R d id tree t
Made of crushed stone, clay loam, and
hydrogel stabilizer
Can extend tree life from 10 years to 50
years
StrataCell Modular St
M d l Storage U it ?
Units?
(e.g. StormTank)
Photo: Country View, Inc.
120. 10/25/11
Goal: Provide 400-1200 cubic feet of soil per120
400 1200
tree (varies depending on size & species)
Porous Hardscape or Standard or Porous
Groundcover Paving
Planting Trench Soil Cells or Structural Soil
Soil & Stormwater Infiltration Bed/ Root Zone
Rendering by Viridian Landscape Studio
121. Downtown Streetscape Project at
p j
10/25/11
121
200 Block of Montgomery Street
GI Technology:
Enhanced street
trees
Project Owner:
City of Syracuse
Cit f S
Capture Area:
17,000 square feet
Runoff Reduction:
300,000 gallons/yr
Construction Cost:
$209,000 (estimated)
$/gallon: $0.70
122. 10/25/11
Other GI Project Groups
j p 122
• Libraries: Five (5) Branches with GI site enhancements
• Schools
▫ I tit t of T h l
Institute f Technology (JSCB) *green* separation
* * ti
▫ Dr. Weeks (JCSB) bioretention (full 1 inch capture over site; roofs, parking lots)
▫ Seymour Playground; Delaware Playground
▫ Central Offices Parking Lot
▫ Hughes Magnet School Parking Lot
• Post offices: Salina Station Branch green roof
g
• Fire houses: Green Roofs not feasible; exploring site opportunities for 2012
• Parks and Community Centers:
▫ One (1) green roof
▫ Spray Fountain Volume Reduction Initiative
▫ Many other site improvements
• Vacant Lots: One (1) Pilot Project
• DPW: Pavement Removal Projects (many)
123. 10/25/11
Program Implementation Status -
g p 123
9/26/2011 and Projected CSO Capture
250
Annual Incremental Capture • 15 Projects Completed
Annual • 29 Projects Under Construction
Incremental…
• 03 Projects in Contract Phase
200
• 47 GI Projects Achieved and
Counting !
i
150
CS Reduction (MG)
• 1 Projects in Bid Phase
• 6 Projects in 90% Design Phase
n
100 • 3 Projects in 50% Design Phase
• 3 Projects in Fieldwork Phase
55 • 8 Projects to be Procured by
SO
50
37 Others
Oth
22 22 22 22 22
22 22 • 19 more projects under contract
through GIF
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 •
• 100+ Projects in Concept Phase
124. Who is Going to Take Care Of This Stuff Anyway
Anyway….
125. 10/25/11
Vegetation Management 125
• Conservation
Corps (Green
Jobs) contract
required to
maintain newly
created green
spaces
126. 10/25/11
126
City Lot #3: Revisit for Winter 2011
127. 10/25/11
127
Winter Revisit Notes:
• Pearl Street porous pavement performing well, particularly
vs. standard pavement, but is being over-salted
over salted
• Lot 3 wheel stops vs. curbs with inlets
• Lot 3 porous concrete p
p performing well
g
• Snow storage areas
129. Green Improvement Fund (GIF)
Program developed to provide financial incentives to private
and non profit property owners for the implementation of green
infrastructure.
i f
Program Highlights
• Storm water management on private
property is vital to success of green • 46 Applications submitted
infrastructure program to-date
• Grant funding for targeted sewer sheds in • 14 completed projects to
the City of Syracuse (Midland, Harbor date
Brook,
Brook Clinton) ▫ Jim and Juli Boeheim
Foundation
• GIF Program Committee created to review ▫ King & King Architects
funding opportunities for potential ▫ Dunbar Association
projects ▫ Near Westside Initiative (2)
▫ St. Lucy’s C
y Church
• A li i
Applications are reviewed b P
i d by Program ▫ Jefferson Clinton Commons
Committee for final recommendation on ▫ Hotel Skyler
funding level
• Over 25 Projects slated for
2011
130. Green Improvement Fund (GIF)
Green Basketball Courts at Skiddy Park
GIF grant award for the construction of
basketball courts at Skiddy Park on the Near
West Side of Syracuse. The project included the
installation of approximately 11,000 sq ft. of
porous asphalt. Collaboration between the
County, City of Syracuse and the Jim and Juli
Boeheim F
B h i Foundation.
d ti
Porous Pavement at Hotel Skyler
GIF grant award for the re-development of a
parking lot at Hotel Skyler in downtown
Syracuse. The construction features the use of
porous pavers that collect storm water from
approximately 10,000 sq. ft of surface lot.
131. Courts 4 Kids connects
10/25/11
131
green to kids and area
sports icons
• Skiddy Park Porous
Basketball Court
• P bli P i t P t
Public-Private Partnership
hi
▫ Jim Boeheim Foundation
▫ Courts4Kids
▫ CCarmelo A th
l Anthony
Foundation
• 11,000 sq ft porous asphalt
133. 10/25/11
Save the Rain Programs 133
Workshops
▫ Intro to GI for Homeowners and Businesses
Intro to GI for Homeowners and Businesses
Topics include basic principles of stormwater hydrology,
examples of simple GI for homes (rain barrels and rain gardens),
and other GI opportunities for the community and businesses
pp y
▫ GI for New Homeowners
Provides an introduction to green yard care and residential GI to
p
participants in Home HeadQuarters’ (HHQ) home ownership
p Q ( Q) p
program
▫ Community Workshop
Includes hands‐on training for design and implementation of
g g p
residential GI. Residential GI projects will be installed or
maintained during each workshop through assistance by
workshop participants
134. 10/25/11
Save the Rain Programs 134
Workshops
▫ GI for Youth
f h
Participants will use and develop games, skits, role‐plays, and
hands on opportunities to increase awareness about GI and
hands‐on opportunities to increase awareness about GI and
instill an appreciation for the role young people play in
reducing pollution.
▫ GI d A f Child
GI and Art for Children
combine crafts and hands‐on activities to teach elementary
and middle school age children about different kinds of GI:
g
green roof birdhouse, painting a rain barrel, etc..
135. 10/25/11
Save the Rain Programs 135
Workshops
▫ Rain Barrel
Participants at the workshops will learn proper installation
techniques, maintenance and the role of rain barrels in
reducing combined sewage overflows
▫ Landscape Professionals
includes a refresher on stormwater management principles,
GI options, examples of local projects, and strategies for
marketing GI to landscapers’ customers
k l ’
▫ Pervious Products
series of formal and hands‐on workshops on the various
pervious products available on the market will first provide
d l bl h k ll f d
an overview of the products, their uses and specifications,
and installation guidelines
136. 10/25/11
Save the Rain Programs 136
• Nature in the City
Nature in the City
• 3rd Grade classes learning about GI throughout SCS. The
lessons will be: Traveling Water Drop, Stream Exploration,
and Clean Water Matters.
d Cl W M
• ESF in the High School
• High school classrooms learning about GI throughout SCSD
High school classrooms learning about GI throughout SCSD
• Exhibiting at Events
• Local events like Blue Rain ECOFest, State Fair, WEP Open
, , p
House and more to learn about Saving the Rain!
137. 10/25/11
Save the Rain Programs 137
• Design Charrettes
Design Charrettes
▫ This process will include community members in the
visioning and decision‐making process as plans are
created to implement a neighborhood‐planned and
approved green street
• Demonstration Projects
Demonstration Projects
▫ Rain gardens, green roofs, etc.
143. 10/25/11
Other Program Components
143
• GIS and database support
• GI Maintenance Standard Operating Procedures
• Net Environmental Analysis Benefit
• Ordinance updates and permit support
• Grant applications
• Services during construction
g
• Public education and outreach
• Website support
• Presentations
P i
• SharePoint/FTP Service
144. Thank You!
Questions?
Please Visit us at
www.SaveTheRain.us