* Deputy Manager, Adriyala Longwall Project, SCCL
**Manager, Adriyala Longwall Project, SCCL
***Project Officer, Adriyala Longwall Project, SCCL
****General Manager, Adriyala Project Area, SCCL
Adriyala Longwall A Perspective of Future Indian Underground
Coal Mining Mechanization
U. Siva Sankar*
, Md.Abdul Khadir**
, K.Nageswar Rao***
, B.Veera Reddy****
Abstract
Coal continues to be the major key growth driver for India for at least a few decades to come,
inspite of the global concerns against the use of fossil fuels, as it is the prime energy source in
India. Coal meets around 55% of primary commercial energy needs in India against 29% the world
over
1
. In order to achieve economic growth of 8-9% in terms of GDP, country's total coal demand
has been projected to ~ 2,000 million tons in 2031-32
2
. During the past few decades, the opencast
mining has attained dominant share (~90%) of Coal production as it is safe, economical and
productive. But increasing striping ratios, depletion of shallow reserves and constraints in land
acquisitions, etc., will make opencast mining give its way again to underground mining at least
partially to reduce the gap between domestic coal production and demand.
The Longwall technology is the world over proven underground method of extraction of coal for
bulk and economic production. It is believed that the method makes its due share in meeting
Indian coal demand, when the technology is introduced in number of mines at a large phase.
India had its first mechanized Longwall face in 1978 at Moonidih Colliery, Coal India Limited (CIL)
3
.
Subsequently 33 Longwall faces, including 10 Longwall packages in Singareni Collieries Company
Limited (SCCL) was introduced with foreign collaboration to
2.3 Mt in the year 1996-97, but later it went a steep decline. In 2008, except GDK 10A Mine in
SCCL and two Longwall faces in CIL, no other Longwall face was operative in India. The major
reasons for this decline are attributable to under rated Powered Roof Supports, Strata
Management issues, Spares Management issues, lack of indigenous manufacturing facilities and
lack of skilled man power etc
3,4,5,6
. After the Long gap, i.e., in 2014 SCCL introduced Bulk
Production Longwall technology in Adriyala Longwall Project to overcome the past issues and
paved the way for the introduction of Longwall Technology in Indian coal Mining industry.
Keywords: Longwall, Bulk Production, Underground
Introduction:
The Singareni Collieries Company Limited (SCCL) is a Government coal mining company jointly
owned by the Government of Telangana and Government of India on a 51:49 equity basis. The
Singareni coal reserves stretch across 350 km of the Pranahita Godavari Valley of Telangana
with proven geological reserves aggregating to whopping 8791Mt. SCCL is currently operating 17
opencast mines and 30 underground mines in six districts of Telangana with manpower around
56,282. SCCL is contributing 9.5% in the all India domestic production. The share of underground
production in SCCL reduced from 36% ( 2004-05) to 15% (2016-17) and opencast attained
dominant share in production. The opencast projects were planned upto 420m depth with a
stripping ratio of 1:6.5. With increased stripping ratios and environmental concerns, the share of
underground production need to be increased to compensate loss from unviable opencast projects
in future. For bulk production of coal at faster rate from underground coal mining particularly at
depths, the proven technology world over is Longwall. History of Longwall Technology in SCCL:
Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 88
SCCL is pioneered in introduction of the latest mining technologies since its inception. SCCL
embarked upon LW technology for extraction of coal in 1983. First Longwall was commissioned in
GDK-7 incline in 1983 and after successful completion of two faces equipment was shifted to GDK-
9 Incline in 1986, where the Longwall face collapsed due to inadequacy of the support capacity.
Second Longwall was installed in VK-7in 1985.
The above Longwall faces were equipped with low capacity supports (4x360t). Later the technology
4x450t IFS were introduced in GDK-11A and JK-5. Later higher rated supports one set in each
GDK-10A, GDK-9 Inclines and two sets in PVK 5 Incline were introduced. The support capacity in
the above mines is of 4x800t and 4x760t with a support density of 110 to 120 t/m
2
.
Before the introduction of Longwall Technology in Adriyala, 10 Longwall packages have been
introduced in seven mines with collaboration of foreign countries like UK and China. Presently the
old generation Longwall units were surveyed off /not in working condition.
The faces at SCCL in GDK-7 and VK-7 Inclines did well in comparison with other faces, which
experienced caving difficulties. In early nineties with the introduction of higher rated supports the
performance of Longwalls improved to some extent. Barring the catastrophic failure of Longwall
faces of Churcha, Kottadih and Dhemomain of Coal India Ltd., faces at GDK-10A, PVK, JK-5 and
VK-7 gave consistently good results.
Adriyala Longwall Project (ALP):
As a part of the recent Underground Mechanization Planning initiative, SCCL successfully
commissioned a state of art High capacity automated Longwall Project at Adriyala Longwall
Project (ALP) mine in 2014. The Adriyala Longwall Geological block area is more or less free
from any major faults. The project is having 78.597Mt of extractable reserves within the depth
range of 294 to 644m. The project life is about 35 years with a rated production of 2.817MTPA.
To Finalize the Mine Design by eliminating earlier problems, SCCL appointed the Technical
Consultants:
M/s CSIRO, Australia entered in to Collaborative research agreement with SCCL - for detailed
geo-tech studies, Support capacity estimation and finalization of tech. specification for modern
high capacity Longwalls in SCCL.
Mr. Andy Rutherford, Australia for formulating Specifications, testing, drawings and
commissioning of Longwall project.
Mr. Russell Firth, Australia, for Geo-Technical Studies.
Additionally, various Indian Institutes assisted in scientific studies and investigations.
A team of senior officers of Singareni visited Australia and inspected various high productive
Longwall Mines and Mines with access/operation through Punch Entries in the highwall of
Opencast Mines.
The Longwall equipment consists of EL3000 Shearer with 2245kW installed capacity, Armoured
Face Conveyor(AFC) with installed capacity of 2565kW, Beam Stage Loader(BSL) of 400kW, 146
shields of capacity 2x1150t and 1.75m width, 2x4.5MW of 11kV/3.3kV transwitches and 1600mm
wide three kilometers long gate belt with 3x315 kW drives. The package includes SCADA
(Supervisory Control and Data Acquisition System). The Longwall equipment was provided by
CATERPILLAR, Germany.
The automation of the Longwall face equipment is Shearer Initiated Roof Support Advance (SIRSA)
with batch control and auto horizon control. For automati
as shown in Fig.1, which offers a tailored control unit for each of the various Longwall functions:
-R for roof support systems
-D as drive control (AFC)
Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 89
-V for visualization and parameter setup of the drive system
-P node computer to act as interface between the Cat controller network, third-party
systems and the mine computer. The module implements data transmission to the surface via
optical fiber, modem or copper wire.
zation and control of all Longwall operations at the surface or with an explosion-
proof computer underground
Figure-1 Longwall Automation PMC Layout
The VCU comprises a PC or ExPC (ruggedized Cat PC for use in explosion-hazard areas) and a
suite of programs that are easy to learn and use. The VCU can also be used as a mining control
center on the surface.
There are visualization programs for the various control tasks. They allow parameters to be read
and set as well as visualization of operational data. Each component also allows logging of
operational data and has a replay function for visualization.
allows convenient local or Longwall-wide setting of roof support parameters.
: Allows parameter setting and visualization of operational parameters and status of a
Cat shearer.
displayed graphically and all parameters can be changed.
failures
There has been much difference in equipment specifications as well as gate roads and panel
dimensions between existing Adriyala Longwall Project in comparison to old Longwalls as shown in
below Table.1.
Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 90
Table.1. Brief Comparison between ALP and Old Longwalls of SCCL
Earlier Longwalls in SCCL Adriyala Longwall Project
Depth Range (m) 60 to 225 400 to 650
Support Type,
Capacity (tonnes),
Width (m) and
Life (Cycles)
4 Leg Chock Shield,
360 to 800,
1.5, and
10,000.
2 Leg Shield,
1152,
1.75, and
60,000.
Panel Length (Km) 0.2 to 1.0 2.0 to 2.5
Face Width (m) 60 to150 250
Face Automation No Automation Automated
Capacity (MTPA) 0.4 to 0.7 2.817
Installed Capacity
Shearer (kW) 750 2245
AFC (kW) 300 2565
Name plate capacity (TPH) 600-1000 3000
The unique feature of the project is that the main entries were planned through the adjacent rise
side open cast mine. A platform of about 200mx150m is prepared adjacent to highwall at No.1
Seam floor (120m depth from surface).
The drivage of Trunk road ways (5.50mx3.60m) and Gate road ways (5.20mx3.60m) was made
using twin bolters mounted Road Headers (DOSCO, LH 1400 Model). 25Kms of drivage was
made during last five years using five Road headers. The gate roadways are supported with 2.4m,
Ø22mm shear pin bolts with full column resin grout and rigid wire mesh. Secondary supporting
was done in gate road ways with 6.1m long pre-tensioned bulbed cable bolts to take care of
Longwall abutments ahead of face. The installation face widened to 8 m and could be successfully
supported by adopting pre-tensioned cable bolts, for the first time without erecting vertical support.
The details of underground workings are shown in Fig.2.
Figure 2. Layout of Adriyala Longwall Project
Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 91
Punch Entries (PE) was meant for specific purpose such as coal, men and material transport
besides ventilation. Chairlift System is laid in PE-1 for men transport, Main Belt Conveyor is laid in
PE-2 for coal transport, and Concrete road is laid in PE-3 for the movement of multi utility Diesel
vehicles (men and material transport), Haulage track is laid in PE-5 for men transport using Chair
car system and haulage for material transport.
Uniqueness of ALP:
Adriyala Longwall project is a unique project which introduced several technologies, machineries,
plant and equipment for the first time in India.
Punch entry to access coal seam directly from Opencast high wall
11 kV Power transmission to belowground to reduce power interruptions due to voltage drop
A total of 7.5 km overhead lines and 19 km of 185 Sq.mm XLPE cable is laid to meet the
huge power requirements. Auto power factor correction unit was installed for the first time to
curtail the wasteful energy loss. The total connected load of the project was 24 MW and
increased to 30 MW with the addition of Air Chilling, Nitrogen and Compressor plants.
Pre-tensioned Cable bolting for effective roof support and to eliminate standing supports in
gate roads
400 kW High capacity fan commissioned to supply 15000 Cu.m/min air with high water gauge
Air chilling Plant
To meet the requirement of Longwall face, outsourced air chilling plant of 1624TR was
installed at mouth of Punch Entry-5. 50Cu.m/sec of air quantity, chilled from ambient with 50
to 75% relative humidity to 9
0
C at discharge point is being supplied, at the entry of PE-5.
From there cooled air is ventilated to Longwall face through a dedicated air way via PE-5 and
Longwall Main gate. After commissioning of air chilling plant and supply of cool air, the
temperature has been brought down by 3 to 40
C. Efficiency and effectiveness of men and
machinery increased considerably.
Floor Concreting in underground
To facilitate transport of Longwall equipment using diesel vehicles, one of the trunk road ways
with weak floor was concreted with M-40 grade self-compacting concrete (SCC) for a length
of about 2.5 Km with a gradient not more than 1 in 4. Longwall panel top gates were also
concreted for about 200m length near coal floor from trunk roadway to reach of stone floor in
bottom section. In gate roadways, stone floor is strong enough to take load of heavy Longwall
equipment. It was proposed to do concreting in gates where stone floor disturbed due to
water flow to facilitate movement of mine cruiser up to Longwall face.
Diesel transport vehicles for speedy & safe transportation of heavy Longwall equipment and
other mine material supplies.
High capacity Belt conveyor
Conveyor system of 9.30 km long from Longwall gate belt discharge below ground to Coal
Screening Plant (CSP) is installed and commissioned with 11 Conveyor belts with installed
capacity of about 12 MW. The conveyor system consists of nine Steel cord belts (800 to 2500
ST) & two PVC belts (Type-15) of 1600mm width, 3500TPH capacity, 4.0m/s speed and
Variable Frequency Drives (VFDs). The system includes one Booster belt or Tripper drive belt
conveyor too, in below ground. The above entire system was provided by CODCO.
VFD controlled un-manned Belt conveyor system for soft start and power conservation
Automation Systems for sequence control/less manual intervention
Mine Cruiser for faster transport of men
Pan line bolter for speedy roof and rib bolting & use of Plastic wire mesh during salvage of
Longwall panel
Bolter Miner for Speedy development of Gate roads for Longwalls
Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 92
RO plant to supply treated water to improve powered support hydraulics
Chairlift man riding system laid on overburden ramp to facilitate men transport.
High Capacity Pump (820HP, 1000GPM, and 500m head) introduced for pumping mine water
directly to surface.
Membrane type N2 Plant of 1200 Cfm capacity to flush Longwall goaf with inert Nitrogen gas
consisting N2-98% and O2-2%.
Challenges faced during Construction and Operation of the Project:
Gate roads Drivage
Initially there were some apprehensions on workability of Bolter Miner (BM) at Adriyala
Longwall Project due to its steep gradient and stone cutting in the floor in the gate roadways.
Hence it was decided to use newly supplied Road Headers (RH) for drivage of roadways to
avoid surprises with BM as RH technology is well established system for decades. For the first
two Longwall panels, Gate roads were driven with road headers and cross connections
between two level galleries were developed by Drilling and blasting using SDLs for coal
cleaning. However, RHs progress was not meeting the project requirements due to their
inherently low development rates, inability to provide a quality roadway conditions suitable for
High capacity LW equipment and requirement of more man power. Hence a decision was taken
to introduce BM for drivage of roadways and 12ED30 Bolter Miner was deployed for
development of gate roads of Longwall panel- .
Strata Control Management during Development:
Gate roadways: Initially roof disturbances were observed and on two occasions cavities
occurred in gate road ways driven in bottom section taking middle clay in to working section.
Later geological mapping and lithological study was done and working section has been
changed by leaving middle clay in the overlying strata with 1m coal underneath it, which
improved the stability of gate roadways.
Cut Throughs (X-Slit): The cut throughs were driven in between two gate roadways at 200m
interval. Initially cut throughs were driven across the major horizontal stress direction, in which
severe strata control problems were encountered and cavities also taken place. Later the
direction of cut throughs has been changed and aligned with major horizontal stress direction
which eliminated major strata problems.
Initially gate roadways were supported with roof bolting with linked wire mesh in the roof. Later
rigid wire mesh has been introduced in place of linked wire mesh to reduce supporting cycle
time and to improve the supporting efficiency of the system. The roof conditions and drivage
rates have been improved with introduction of rigid wire mesh.
Face dip widening: Strata problems were encountered while widening Longwall installation
face with 8m width. As per the recommendation of Geotech consultant, Pre- tensioned cable
bolting (6.1m) was introduced for the first time for better strata control and to eliminate vertical
support in face dip to facilitate the movement of Diesel Vehicles. After supporting with cable
bolts, the face dip was widened to 8m without any strata control problems.
Laying of Civil foundations on loose overburden for Conveyor belts
For laying civil foundations for Conveyor belts, existing loose overburden soil was dug out and
replaced with soil recommended by experts. The soil was compacted layer by layer for a
recommended length and depth during filling to obtain the required soil strength around the
Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 93
foundation. Thereafter concrete foundations were made by excavating the above compacted
soil for the required foundation dimensions.
Transport of Shearer
Shearer body is nearly 60 tonnes weight and 11m in length. Shearer was transported using two
60 tonnes capacity Shield Haulers (SH660) provided with slew able cookie plates to its forks,
on either end of shearer body. Initially binding of shearer body to SH660s was not successful
with belt binders; later binding was redesigned using I- section beams and steel chains. While
transporting such heavy load, naturally there was a steering control problem and much co-
ordination is to be maintained between operators.
The binding chains needs to be slackened to some extent to prevent breakage, while
negotiating curves, and these need to be tightened after negotiating curves. For the first-time
shearer transportation was done with the help of Expert foreign operators, later for the 2
nd
panel
it was done with mine operators.
Provision of Air Chilling Plant
Adriyala Project was planned to work in the depth range of 300m to 640m. The geothermic
gradient is about 69m/
0
C. It was envisaged to introduce air chilling plant but order could not be
placed due to technical reasons. Initially, when Longwall panel started wet bulb temperature
was about 28
0
C. But after working for 450m retreat, the face wet bulb temperature gradually
increased to 320
C due to heat generation from working machinery, large goaf area, hot strata
water (35
0
C) flowing along the bottom gate roadways and large volumes of coal cutting in the
face. After the insufficiency of number of measures taken to reduce temperature in Longwall
face, 1624TR air chilling plant was finally installed on surface near PE-5, to supply chilled air to
Longwall face.
Dealing with Goaf Water
In Longwall, an abnormal flow of water of about 1400 GPM was observed once, against the
normal flow of 600 to 700 GPM from the goaf. Accumulation of Longwall fine cuttings and water
in dip side gate, i.e., tailgate of next panel caused difficulty in movement of diesel vehicles due
to nearness of sump and frequent pumping problems with sludge water. However, for the 2
nd
panel exclusive drainage gallery is provided and sump was placed well away from Longwall
panel.
Performance of Longwall Panel No.1:
Dimensions of Panel : 2333m X 250m
Reserves in the Panel : 3.37 Mt
Total Coal Extracted : 3.37 Mt
Highest Daily Production : 13187 t (29.02.2016)
Highest Monthly Production : 2.53 Lt (Jan,2016)
Initially, the performance was not satisfactory due to failure of Variable Frequency Drives (VFD)
and Loop-Take-up (LTU) winch hydraulic motors on gate belt and few components in face load
centre electricals. Gradually the production stabilised and produced 8000 to 9000 tonnes per day
and Longwall panel was successfully extracted. The cost of production for Longwall is about 1420
rupees per tonne. The OMS of Longwall and total mine are about 10 and 5 respectively. The V-
Shield visualisation layout showing face and Shearer position, Shield pressures, Length of AFC
advancing rams and flippers, of Longwall panel displayed in Computer located at Face load centre
as well as at Control room on surface is as shown below Fig.3.
Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 94
Figure-3. V-Shield Layout of Longwall Panel
Further Issues to be addressed:
The following are to be addressed for the further improvement of production and productivity
The technology is yet to be fully absorbed with the cooperation of OEM.
Longwall automation is to be fully established and utilised.
Adequate training for further improving skills of the operating crew.
Spares management to be improved with the indigenisation of spares.
Expediting Preparation of Longwall panels with bolter miner, and
Motivation of Longwall Team in the form of Incentives, Special payment to encourage the
team to involve heartily in the success of Longwall.
New technologies Still to be introduced at ALP:
Tube bundle system for monitoring of Longwall as well as other mine environmental
conditions including gob out/sealed off areas.
Refugee chamber for escape of persons in case of fire or other hazards in underground.
Pneumatic wipers/suitable wipers for high capacity and high-speed belting system.
Small diesel vehicles for cleaning of debris / slush / spillage coal along belting system in
underground.
Monolithic seals for Isolation stoppings to prevent damage of stoppings due to abutment load
during Longwall retreat, and
Pneumatic or electrical pumps for handling slushy/sludge water.
Conclusion:
Longwall should be promoted as a technology mission, thrust areas are to be given due
consideration to succeed Longwall technology as in other countries like Australia, USA and China.
Longwall mining is done successfully in all major coal producing countries even in difficult
conditions like highly gassy, hard roof and steeply inclined Seams. It is proved beyond doubt that
Longwall as an Underground Mining method is successful in India also where it was introduced
with true spirit. The suitable underground Geological blocks need to be identified for introduction of
high capacity Longwalls on large scale with the help of Global operators. CIL, SCCL and private
operators who are allotted coal blocks for underground coal mining must plan to introduce as
many Longwall as possible and LTCC for thick Seams in the blocks which are feasible for bulk
production.
Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 95
References:
[1] Committee on Public Undertakings, 2014-2015, Fourth Report, Sixteenth Lok Sabha, Coal
India Limited, Ministry Of Coal.
[2] India Energy Book, 2012, World Energy Council
[3] A collating the decadal experience (1978-
1987). Journal of mines, Metals & Fuels, June, 1988 pp 267-273.
[4]
High Capacity Long
Delhi, India,2015.
[5]
Assesssment Of Longwall Mining With A Focus On Successful Mechanised Underground
Geological and Metallurgical Institute of India (MGMI).
[6] B. Ramesh Kumar, S Chandras
High Capacity Longwall Project -
Advances in Rock Engineering - 2016 at Bangalore, India.
********
Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 96

More Related Content

What's hot

Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc minesSATYANARAYANA I
 
Side Discharge Loader (SDL) / Layout of SDL
Side Discharge Loader (SDL) / Layout of SDLSide Discharge Loader (SDL) / Layout of SDL
Side Discharge Loader (SDL) / Layout of SDLJãyësh Kùmär
 
Bord Pillar
Bord PillarBord Pillar
Bord PillarVR M
 
Method of working of continuous miner in underground coal
Method of working of     continuous miner in underground coalMethod of working of     continuous miner in underground coal
Method of working of continuous miner in underground coalSafdar Ali
 
Longwall technology in india, SCCL
Longwall technology in india, SCCLLongwall technology in india, SCCL
Longwall technology in india, SCCLUlimella Siva Sankar
 
Design of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesDesign of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesaashutosh chhirolya
 
Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous minerSafdar Ali
 
Selection of longwall powered roof support
Selection of longwall powered roof supportSelection of longwall powered roof support
Selection of longwall powered roof supportUlimella Siva Sankar
 
Highwall Mining Technology
Highwall Mining TechnologyHighwall Mining Technology
Highwall Mining TechnologyVR M
 
Mining Machinery Learning Material for DEegree and Diploma
Mining Machinery Learning Material for DEegree and DiplomaMining Machinery Learning Material for DEegree and Diploma
Mining Machinery Learning Material for DEegree and DiplomaBhaskar Naidu
 
Mining Machinery Learning Material
Mining Machinery Learning MaterialMining Machinery Learning Material
Mining Machinery Learning MaterialBhaskar Naidu
 

What's hot (20)

Longwall mining
Longwall miningLongwall mining
Longwall mining
 
Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
 
Side Discharge Loader (SDL) / Layout of SDL
Side Discharge Loader (SDL) / Layout of SDLSide Discharge Loader (SDL) / Layout of SDL
Side Discharge Loader (SDL) / Layout of SDL
 
Highwall mining
Highwall miningHighwall mining
Highwall mining
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
longwall mining
longwall mininglongwall mining
longwall mining
 
Longwall
LongwallLongwall
Longwall
 
Opencast mining machineries
Opencast mining machineriesOpencast mining machineries
Opencast mining machineries
 
Bord Pillar
Bord PillarBord Pillar
Bord Pillar
 
Method of working of continuous miner in underground coal
Method of working of     continuous miner in underground coalMethod of working of     continuous miner in underground coal
Method of working of continuous miner in underground coal
 
Longwall technology in india, SCCL
Longwall technology in india, SCCLLongwall technology in india, SCCL
Longwall technology in india, SCCL
 
Design of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesDesign of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal mines
 
Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous miner
 
Selection of longwall powered roof support
Selection of longwall powered roof supportSelection of longwall powered roof support
Selection of longwall powered roof support
 
Side discharge loader
Side discharge loaderSide discharge loader
Side discharge loader
 
Highwall Mining Technology
Highwall Mining TechnologyHighwall Mining Technology
Highwall Mining Technology
 
Mining Machinery Learning Material for DEegree and Diploma
Mining Machinery Learning Material for DEegree and DiplomaMining Machinery Learning Material for DEegree and Diploma
Mining Machinery Learning Material for DEegree and Diploma
 
High Wall Mining
High Wall MiningHigh Wall Mining
High Wall Mining
 
Mining Machinery Learning Material
Mining Machinery Learning MaterialMining Machinery Learning Material
Mining Machinery Learning Material
 
Pillar design in coal mines
Pillar design in coal minesPillar design in coal mines
Pillar design in coal mines
 

Similar to Adriyala longwall paper

Longwall - The road ahead
Longwall - The road aheadLongwall - The road ahead
Longwall - The road aheadVR M
 
A critical study on availability and capacity utilization of side discharge l...
A critical study on availability and capacity utilization of side discharge l...A critical study on availability and capacity utilization of side discharge l...
A critical study on availability and capacity utilization of side discharge l...eSAT Journals
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersVR M
 
HIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case StudyHIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case Studyknowledge stuff
 
A critical review of indian underground thick coal seam mining technologie...
A   critical review  of indian underground thick coal seam mining technologie...A   critical review  of indian underground thick coal seam mining technologie...
A critical review of indian underground thick coal seam mining technologie...nasina balasubrahmayam
 
Vedantaindiaoperationssitevisit aluminiumandpowerpresentation-25sep2012 final
Vedantaindiaoperationssitevisit aluminiumandpowerpresentation-25sep2012 finalVedantaindiaoperationssitevisit aluminiumandpowerpresentation-25sep2012 final
Vedantaindiaoperationssitevisit aluminiumandpowerpresentation-25sep2012 finalVedanta Group
 
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...IRJET Journal
 
Er.aad cv new 20151208
Er.aad cv new 20151208Er.aad cv new 20151208
Er.aad cv new 20151208AADARSH JILKA
 
Selection of powered roof supports – 2 leg shields vis-à-vis
Selection of powered roof supports – 2 leg shields vis-à-visSelection of powered roof supports – 2 leg shields vis-à-vis
Selection of powered roof supports – 2 leg shields vis-à-visUlimella Siva Sankar
 
CCTEG Drill equipment and technology
CCTEG Drill equipment and technologyCCTEG Drill equipment and technology
CCTEG Drill equipment and technologyOwen Ji
 
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesA Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesIRJET Journal
 
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...Follow me on Twitter @Stockshaman
 
Turnkey Company Presentation Feb 2024.pptx
Turnkey Company Presentation Feb 2024.pptxTurnkey Company Presentation Feb 2024.pptx
Turnkey Company Presentation Feb 2024.pptxandre538649
 
Mike Chapman - Belt Splicer - Feb 2016
Mike Chapman - Belt Splicer - Feb 2016Mike Chapman - Belt Splicer - Feb 2016
Mike Chapman - Belt Splicer - Feb 2016Michael Chapman
 
Dankuni Coal Complex
Dankuni Coal ComplexDankuni Coal Complex
Dankuni Coal ComplexKumar Saurabh
 
ORIENTATION FINAL REPORT
ORIENTATION FINAL REPORTORIENTATION FINAL REPORT
ORIENTATION FINAL REPORTAkash Agrawal
 

Similar to Adriyala longwall paper (20)

Longwall - The road ahead
Longwall - The road aheadLongwall - The road ahead
Longwall - The road ahead
 
A critical study on availability and capacity utilization of side discharge l...
A critical study on availability and capacity utilization of side discharge l...A critical study on availability and capacity utilization of side discharge l...
A critical study on availability and capacity utilization of side discharge l...
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of Papers
 
HIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case StudyHIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case Study
 
A critical review of indian underground thick coal seam mining technologie...
A   critical review  of indian underground thick coal seam mining technologie...A   critical review  of indian underground thick coal seam mining technologie...
A critical review of indian underground thick coal seam mining technologie...
 
Vedantaindiaoperationssitevisit aluminiumandpowerpresentation-25sep2012 final
Vedantaindiaoperationssitevisit aluminiumandpowerpresentation-25sep2012 finalVedantaindiaoperationssitevisit aluminiumandpowerpresentation-25sep2012 final
Vedantaindiaoperationssitevisit aluminiumandpowerpresentation-25sep2012 final
 
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...
 
Er.aad cv new 20151208
Er.aad cv new 20151208Er.aad cv new 20151208
Er.aad cv new 20151208
 
Selection of powered roof supports – 2 leg shields vis-à-vis
Selection of powered roof supports – 2 leg shields vis-à-visSelection of powered roof supports – 2 leg shields vis-à-vis
Selection of powered roof supports – 2 leg shields vis-à-vis
 
CCTEG Drill equipment and technology
CCTEG Drill equipment and technologyCCTEG Drill equipment and technology
CCTEG Drill equipment and technology
 
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesA Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
 
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
 
Alstom india
Alstom indiaAlstom india
Alstom india
 
Turnkey Company Presentation Feb 2024.pptx
Turnkey Company Presentation Feb 2024.pptxTurnkey Company Presentation Feb 2024.pptx
Turnkey Company Presentation Feb 2024.pptx
 
Mike Chapman - Belt Splicer - Feb 2016
Mike Chapman - Belt Splicer - Feb 2016Mike Chapman - Belt Splicer - Feb 2016
Mike Chapman - Belt Splicer - Feb 2016
 
SAIL
SAIL SAIL
SAIL
 
Power distribution
Power distribution Power distribution
Power distribution
 
Dankuni Coal Complex
Dankuni Coal ComplexDankuni Coal Complex
Dankuni Coal Complex
 
Kptl final report
Kptl final reportKptl final report
Kptl final report
 
ORIENTATION FINAL REPORT
ORIENTATION FINAL REPORTORIENTATION FINAL REPORT
ORIENTATION FINAL REPORT
 

More from Ulimella Siva Sankar

Safety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineSafety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineUlimella Siva Sankar
 
Theories of interaction of rock cutting tools
Theories of interaction of rock cutting toolsTheories of interaction of rock cutting tools
Theories of interaction of rock cutting toolsUlimella Siva Sankar
 
Ground control in undergound mines
Ground control in undergound minesGround control in undergound mines
Ground control in undergound minesUlimella Siva Sankar
 
Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...Ulimella Siva Sankar
 
Physico-Mechanical properties of rock materials
Physico-Mechanical properties of rock materialsPhysico-Mechanical properties of rock materials
Physico-Mechanical properties of rock materialsUlimella Siva Sankar
 
Numerical modelling in Geo mechanics
Numerical modelling in Geo mechanicsNumerical modelling in Geo mechanics
Numerical modelling in Geo mechanicsUlimella Siva Sankar
 

More from Ulimella Siva Sankar (20)

Road Header and Bolter Miner
Road Header and Bolter MinerRoad Header and Bolter Miner
Road Header and Bolter Miner
 
Tube bundle gas monitoring system
Tube bundle gas monitoring systemTube bundle gas monitoring system
Tube bundle gas monitoring system
 
Aircooling underground coal mine
 Aircooling underground coal mine Aircooling underground coal mine
Aircooling underground coal mine
 
Safety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineSafety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall Mine
 
Pneumoconiosis
PneumoconiosisPneumoconiosis
Pneumoconiosis
 
insitu Horizontal stress
insitu Horizontal stressinsitu Horizontal stress
insitu Horizontal stress
 
Ug mechanical excavation
Ug mechanical excavationUg mechanical excavation
Ug mechanical excavation
 
Theories of interaction of rock cutting tools
Theories of interaction of rock cutting toolsTheories of interaction of rock cutting tools
Theories of interaction of rock cutting tools
 
Design of openings
Design of openingsDesign of openings
Design of openings
 
Subsidence in coal mines
Subsidence in coal minesSubsidence in coal mines
Subsidence in coal mines
 
Slopestability
SlopestabilitySlopestability
Slopestability
 
strata monitoring Instrumentation
strata monitoring Instrumentationstrata monitoring Instrumentation
strata monitoring Instrumentation
 
Insitu stresses and measurement
Insitu stresses and measurementInsitu stresses and measurement
Insitu stresses and measurement
 
Ground control in undergound mines
Ground control in undergound minesGround control in undergound mines
Ground control in undergound mines
 
Strike dip rise longwall panels
Strike dip rise longwall panelsStrike dip rise longwall panels
Strike dip rise longwall panels
 
Selection of viable ug technology
Selection of viable ug technologySelection of viable ug technology
Selection of viable ug technology
 
2leg vs4leg
2leg vs4leg2leg vs4leg
2leg vs4leg
 
Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...
 
Physico-Mechanical properties of rock materials
Physico-Mechanical properties of rock materialsPhysico-Mechanical properties of rock materials
Physico-Mechanical properties of rock materials
 
Numerical modelling in Geo mechanics
Numerical modelling in Geo mechanicsNumerical modelling in Geo mechanics
Numerical modelling in Geo mechanics
 

Recently uploaded

TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessPixlogix Infotech
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 

Recently uploaded (20)

TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 

Adriyala longwall paper

  • 1. _______________________________________________________________________________ * Deputy Manager, Adriyala Longwall Project, SCCL **Manager, Adriyala Longwall Project, SCCL ***Project Officer, Adriyala Longwall Project, SCCL ****General Manager, Adriyala Project Area, SCCL Adriyala Longwall A Perspective of Future Indian Underground Coal Mining Mechanization U. Siva Sankar* , Md.Abdul Khadir** , K.Nageswar Rao*** , B.Veera Reddy**** Abstract Coal continues to be the major key growth driver for India for at least a few decades to come, inspite of the global concerns against the use of fossil fuels, as it is the prime energy source in India. Coal meets around 55% of primary commercial energy needs in India against 29% the world over 1 . In order to achieve economic growth of 8-9% in terms of GDP, country's total coal demand has been projected to ~ 2,000 million tons in 2031-32 2 . During the past few decades, the opencast mining has attained dominant share (~90%) of Coal production as it is safe, economical and productive. But increasing striping ratios, depletion of shallow reserves and constraints in land acquisitions, etc., will make opencast mining give its way again to underground mining at least partially to reduce the gap between domestic coal production and demand. The Longwall technology is the world over proven underground method of extraction of coal for bulk and economic production. It is believed that the method makes its due share in meeting Indian coal demand, when the technology is introduced in number of mines at a large phase. India had its first mechanized Longwall face in 1978 at Moonidih Colliery, Coal India Limited (CIL) 3 . Subsequently 33 Longwall faces, including 10 Longwall packages in Singareni Collieries Company Limited (SCCL) was introduced with foreign collaboration to 2.3 Mt in the year 1996-97, but later it went a steep decline. In 2008, except GDK 10A Mine in SCCL and two Longwall faces in CIL, no other Longwall face was operative in India. The major reasons for this decline are attributable to under rated Powered Roof Supports, Strata Management issues, Spares Management issues, lack of indigenous manufacturing facilities and lack of skilled man power etc 3,4,5,6 . After the Long gap, i.e., in 2014 SCCL introduced Bulk Production Longwall technology in Adriyala Longwall Project to overcome the past issues and paved the way for the introduction of Longwall Technology in Indian coal Mining industry. Keywords: Longwall, Bulk Production, Underground Introduction: The Singareni Collieries Company Limited (SCCL) is a Government coal mining company jointly owned by the Government of Telangana and Government of India on a 51:49 equity basis. The Singareni coal reserves stretch across 350 km of the Pranahita Godavari Valley of Telangana with proven geological reserves aggregating to whopping 8791Mt. SCCL is currently operating 17 opencast mines and 30 underground mines in six districts of Telangana with manpower around 56,282. SCCL is contributing 9.5% in the all India domestic production. The share of underground production in SCCL reduced from 36% ( 2004-05) to 15% (2016-17) and opencast attained dominant share in production. The opencast projects were planned upto 420m depth with a stripping ratio of 1:6.5. With increased stripping ratios and environmental concerns, the share of underground production need to be increased to compensate loss from unviable opencast projects in future. For bulk production of coal at faster rate from underground coal mining particularly at depths, the proven technology world over is Longwall. History of Longwall Technology in SCCL: Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 88
  • 2. SCCL is pioneered in introduction of the latest mining technologies since its inception. SCCL embarked upon LW technology for extraction of coal in 1983. First Longwall was commissioned in GDK-7 incline in 1983 and after successful completion of two faces equipment was shifted to GDK- 9 Incline in 1986, where the Longwall face collapsed due to inadequacy of the support capacity. Second Longwall was installed in VK-7in 1985. The above Longwall faces were equipped with low capacity supports (4x360t). Later the technology 4x450t IFS were introduced in GDK-11A and JK-5. Later higher rated supports one set in each GDK-10A, GDK-9 Inclines and two sets in PVK 5 Incline were introduced. The support capacity in the above mines is of 4x800t and 4x760t with a support density of 110 to 120 t/m 2 . Before the introduction of Longwall Technology in Adriyala, 10 Longwall packages have been introduced in seven mines with collaboration of foreign countries like UK and China. Presently the old generation Longwall units were surveyed off /not in working condition. The faces at SCCL in GDK-7 and VK-7 Inclines did well in comparison with other faces, which experienced caving difficulties. In early nineties with the introduction of higher rated supports the performance of Longwalls improved to some extent. Barring the catastrophic failure of Longwall faces of Churcha, Kottadih and Dhemomain of Coal India Ltd., faces at GDK-10A, PVK, JK-5 and VK-7 gave consistently good results. Adriyala Longwall Project (ALP): As a part of the recent Underground Mechanization Planning initiative, SCCL successfully commissioned a state of art High capacity automated Longwall Project at Adriyala Longwall Project (ALP) mine in 2014. The Adriyala Longwall Geological block area is more or less free from any major faults. The project is having 78.597Mt of extractable reserves within the depth range of 294 to 644m. The project life is about 35 years with a rated production of 2.817MTPA. To Finalize the Mine Design by eliminating earlier problems, SCCL appointed the Technical Consultants: M/s CSIRO, Australia entered in to Collaborative research agreement with SCCL - for detailed geo-tech studies, Support capacity estimation and finalization of tech. specification for modern high capacity Longwalls in SCCL. Mr. Andy Rutherford, Australia for formulating Specifications, testing, drawings and commissioning of Longwall project. Mr. Russell Firth, Australia, for Geo-Technical Studies. Additionally, various Indian Institutes assisted in scientific studies and investigations. A team of senior officers of Singareni visited Australia and inspected various high productive Longwall Mines and Mines with access/operation through Punch Entries in the highwall of Opencast Mines. The Longwall equipment consists of EL3000 Shearer with 2245kW installed capacity, Armoured Face Conveyor(AFC) with installed capacity of 2565kW, Beam Stage Loader(BSL) of 400kW, 146 shields of capacity 2x1150t and 1.75m width, 2x4.5MW of 11kV/3.3kV transwitches and 1600mm wide three kilometers long gate belt with 3x315 kW drives. The package includes SCADA (Supervisory Control and Data Acquisition System). The Longwall equipment was provided by CATERPILLAR, Germany. The automation of the Longwall face equipment is Shearer Initiated Roof Support Advance (SIRSA) with batch control and auto horizon control. For automati as shown in Fig.1, which offers a tailored control unit for each of the various Longwall functions: -R for roof support systems -D as drive control (AFC) Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 89
  • 3. -V for visualization and parameter setup of the drive system -P node computer to act as interface between the Cat controller network, third-party systems and the mine computer. The module implements data transmission to the surface via optical fiber, modem or copper wire. zation and control of all Longwall operations at the surface or with an explosion- proof computer underground Figure-1 Longwall Automation PMC Layout The VCU comprises a PC or ExPC (ruggedized Cat PC for use in explosion-hazard areas) and a suite of programs that are easy to learn and use. The VCU can also be used as a mining control center on the surface. There are visualization programs for the various control tasks. They allow parameters to be read and set as well as visualization of operational data. Each component also allows logging of operational data and has a replay function for visualization. allows convenient local or Longwall-wide setting of roof support parameters. : Allows parameter setting and visualization of operational parameters and status of a Cat shearer. displayed graphically and all parameters can be changed. failures There has been much difference in equipment specifications as well as gate roads and panel dimensions between existing Adriyala Longwall Project in comparison to old Longwalls as shown in below Table.1. Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 90
  • 4. Table.1. Brief Comparison between ALP and Old Longwalls of SCCL Earlier Longwalls in SCCL Adriyala Longwall Project Depth Range (m) 60 to 225 400 to 650 Support Type, Capacity (tonnes), Width (m) and Life (Cycles) 4 Leg Chock Shield, 360 to 800, 1.5, and 10,000. 2 Leg Shield, 1152, 1.75, and 60,000. Panel Length (Km) 0.2 to 1.0 2.0 to 2.5 Face Width (m) 60 to150 250 Face Automation No Automation Automated Capacity (MTPA) 0.4 to 0.7 2.817 Installed Capacity Shearer (kW) 750 2245 AFC (kW) 300 2565 Name plate capacity (TPH) 600-1000 3000 The unique feature of the project is that the main entries were planned through the adjacent rise side open cast mine. A platform of about 200mx150m is prepared adjacent to highwall at No.1 Seam floor (120m depth from surface). The drivage of Trunk road ways (5.50mx3.60m) and Gate road ways (5.20mx3.60m) was made using twin bolters mounted Road Headers (DOSCO, LH 1400 Model). 25Kms of drivage was made during last five years using five Road headers. The gate roadways are supported with 2.4m, Ø22mm shear pin bolts with full column resin grout and rigid wire mesh. Secondary supporting was done in gate road ways with 6.1m long pre-tensioned bulbed cable bolts to take care of Longwall abutments ahead of face. The installation face widened to 8 m and could be successfully supported by adopting pre-tensioned cable bolts, for the first time without erecting vertical support. The details of underground workings are shown in Fig.2. Figure 2. Layout of Adriyala Longwall Project Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 91
  • 5. Punch Entries (PE) was meant for specific purpose such as coal, men and material transport besides ventilation. Chairlift System is laid in PE-1 for men transport, Main Belt Conveyor is laid in PE-2 for coal transport, and Concrete road is laid in PE-3 for the movement of multi utility Diesel vehicles (men and material transport), Haulage track is laid in PE-5 for men transport using Chair car system and haulage for material transport. Uniqueness of ALP: Adriyala Longwall project is a unique project which introduced several technologies, machineries, plant and equipment for the first time in India. Punch entry to access coal seam directly from Opencast high wall 11 kV Power transmission to belowground to reduce power interruptions due to voltage drop A total of 7.5 km overhead lines and 19 km of 185 Sq.mm XLPE cable is laid to meet the huge power requirements. Auto power factor correction unit was installed for the first time to curtail the wasteful energy loss. The total connected load of the project was 24 MW and increased to 30 MW with the addition of Air Chilling, Nitrogen and Compressor plants. Pre-tensioned Cable bolting for effective roof support and to eliminate standing supports in gate roads 400 kW High capacity fan commissioned to supply 15000 Cu.m/min air with high water gauge Air chilling Plant To meet the requirement of Longwall face, outsourced air chilling plant of 1624TR was installed at mouth of Punch Entry-5. 50Cu.m/sec of air quantity, chilled from ambient with 50 to 75% relative humidity to 9 0 C at discharge point is being supplied, at the entry of PE-5. From there cooled air is ventilated to Longwall face through a dedicated air way via PE-5 and Longwall Main gate. After commissioning of air chilling plant and supply of cool air, the temperature has been brought down by 3 to 40 C. Efficiency and effectiveness of men and machinery increased considerably. Floor Concreting in underground To facilitate transport of Longwall equipment using diesel vehicles, one of the trunk road ways with weak floor was concreted with M-40 grade self-compacting concrete (SCC) for a length of about 2.5 Km with a gradient not more than 1 in 4. Longwall panel top gates were also concreted for about 200m length near coal floor from trunk roadway to reach of stone floor in bottom section. In gate roadways, stone floor is strong enough to take load of heavy Longwall equipment. It was proposed to do concreting in gates where stone floor disturbed due to water flow to facilitate movement of mine cruiser up to Longwall face. Diesel transport vehicles for speedy & safe transportation of heavy Longwall equipment and other mine material supplies. High capacity Belt conveyor Conveyor system of 9.30 km long from Longwall gate belt discharge below ground to Coal Screening Plant (CSP) is installed and commissioned with 11 Conveyor belts with installed capacity of about 12 MW. The conveyor system consists of nine Steel cord belts (800 to 2500 ST) & two PVC belts (Type-15) of 1600mm width, 3500TPH capacity, 4.0m/s speed and Variable Frequency Drives (VFDs). The system includes one Booster belt or Tripper drive belt conveyor too, in below ground. The above entire system was provided by CODCO. VFD controlled un-manned Belt conveyor system for soft start and power conservation Automation Systems for sequence control/less manual intervention Mine Cruiser for faster transport of men Pan line bolter for speedy roof and rib bolting & use of Plastic wire mesh during salvage of Longwall panel Bolter Miner for Speedy development of Gate roads for Longwalls Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 92
  • 6. RO plant to supply treated water to improve powered support hydraulics Chairlift man riding system laid on overburden ramp to facilitate men transport. High Capacity Pump (820HP, 1000GPM, and 500m head) introduced for pumping mine water directly to surface. Membrane type N2 Plant of 1200 Cfm capacity to flush Longwall goaf with inert Nitrogen gas consisting N2-98% and O2-2%. Challenges faced during Construction and Operation of the Project: Gate roads Drivage Initially there were some apprehensions on workability of Bolter Miner (BM) at Adriyala Longwall Project due to its steep gradient and stone cutting in the floor in the gate roadways. Hence it was decided to use newly supplied Road Headers (RH) for drivage of roadways to avoid surprises with BM as RH technology is well established system for decades. For the first two Longwall panels, Gate roads were driven with road headers and cross connections between two level galleries were developed by Drilling and blasting using SDLs for coal cleaning. However, RHs progress was not meeting the project requirements due to their inherently low development rates, inability to provide a quality roadway conditions suitable for High capacity LW equipment and requirement of more man power. Hence a decision was taken to introduce BM for drivage of roadways and 12ED30 Bolter Miner was deployed for development of gate roads of Longwall panel- . Strata Control Management during Development: Gate roadways: Initially roof disturbances were observed and on two occasions cavities occurred in gate road ways driven in bottom section taking middle clay in to working section. Later geological mapping and lithological study was done and working section has been changed by leaving middle clay in the overlying strata with 1m coal underneath it, which improved the stability of gate roadways. Cut Throughs (X-Slit): The cut throughs were driven in between two gate roadways at 200m interval. Initially cut throughs were driven across the major horizontal stress direction, in which severe strata control problems were encountered and cavities also taken place. Later the direction of cut throughs has been changed and aligned with major horizontal stress direction which eliminated major strata problems. Initially gate roadways were supported with roof bolting with linked wire mesh in the roof. Later rigid wire mesh has been introduced in place of linked wire mesh to reduce supporting cycle time and to improve the supporting efficiency of the system. The roof conditions and drivage rates have been improved with introduction of rigid wire mesh. Face dip widening: Strata problems were encountered while widening Longwall installation face with 8m width. As per the recommendation of Geotech consultant, Pre- tensioned cable bolting (6.1m) was introduced for the first time for better strata control and to eliminate vertical support in face dip to facilitate the movement of Diesel Vehicles. After supporting with cable bolts, the face dip was widened to 8m without any strata control problems. Laying of Civil foundations on loose overburden for Conveyor belts For laying civil foundations for Conveyor belts, existing loose overburden soil was dug out and replaced with soil recommended by experts. The soil was compacted layer by layer for a recommended length and depth during filling to obtain the required soil strength around the Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 93
  • 7. foundation. Thereafter concrete foundations were made by excavating the above compacted soil for the required foundation dimensions. Transport of Shearer Shearer body is nearly 60 tonnes weight and 11m in length. Shearer was transported using two 60 tonnes capacity Shield Haulers (SH660) provided with slew able cookie plates to its forks, on either end of shearer body. Initially binding of shearer body to SH660s was not successful with belt binders; later binding was redesigned using I- section beams and steel chains. While transporting such heavy load, naturally there was a steering control problem and much co- ordination is to be maintained between operators. The binding chains needs to be slackened to some extent to prevent breakage, while negotiating curves, and these need to be tightened after negotiating curves. For the first-time shearer transportation was done with the help of Expert foreign operators, later for the 2 nd panel it was done with mine operators. Provision of Air Chilling Plant Adriyala Project was planned to work in the depth range of 300m to 640m. The geothermic gradient is about 69m/ 0 C. It was envisaged to introduce air chilling plant but order could not be placed due to technical reasons. Initially, when Longwall panel started wet bulb temperature was about 28 0 C. But after working for 450m retreat, the face wet bulb temperature gradually increased to 320 C due to heat generation from working machinery, large goaf area, hot strata water (35 0 C) flowing along the bottom gate roadways and large volumes of coal cutting in the face. After the insufficiency of number of measures taken to reduce temperature in Longwall face, 1624TR air chilling plant was finally installed on surface near PE-5, to supply chilled air to Longwall face. Dealing with Goaf Water In Longwall, an abnormal flow of water of about 1400 GPM was observed once, against the normal flow of 600 to 700 GPM from the goaf. Accumulation of Longwall fine cuttings and water in dip side gate, i.e., tailgate of next panel caused difficulty in movement of diesel vehicles due to nearness of sump and frequent pumping problems with sludge water. However, for the 2 nd panel exclusive drainage gallery is provided and sump was placed well away from Longwall panel. Performance of Longwall Panel No.1: Dimensions of Panel : 2333m X 250m Reserves in the Panel : 3.37 Mt Total Coal Extracted : 3.37 Mt Highest Daily Production : 13187 t (29.02.2016) Highest Monthly Production : 2.53 Lt (Jan,2016) Initially, the performance was not satisfactory due to failure of Variable Frequency Drives (VFD) and Loop-Take-up (LTU) winch hydraulic motors on gate belt and few components in face load centre electricals. Gradually the production stabilised and produced 8000 to 9000 tonnes per day and Longwall panel was successfully extracted. The cost of production for Longwall is about 1420 rupees per tonne. The OMS of Longwall and total mine are about 10 and 5 respectively. The V- Shield visualisation layout showing face and Shearer position, Shield pressures, Length of AFC advancing rams and flippers, of Longwall panel displayed in Computer located at Face load centre as well as at Control room on surface is as shown below Fig.3. Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 94
  • 8. Figure-3. V-Shield Layout of Longwall Panel Further Issues to be addressed: The following are to be addressed for the further improvement of production and productivity The technology is yet to be fully absorbed with the cooperation of OEM. Longwall automation is to be fully established and utilised. Adequate training for further improving skills of the operating crew. Spares management to be improved with the indigenisation of spares. Expediting Preparation of Longwall panels with bolter miner, and Motivation of Longwall Team in the form of Incentives, Special payment to encourage the team to involve heartily in the success of Longwall. New technologies Still to be introduced at ALP: Tube bundle system for monitoring of Longwall as well as other mine environmental conditions including gob out/sealed off areas. Refugee chamber for escape of persons in case of fire or other hazards in underground. Pneumatic wipers/suitable wipers for high capacity and high-speed belting system. Small diesel vehicles for cleaning of debris / slush / spillage coal along belting system in underground. Monolithic seals for Isolation stoppings to prevent damage of stoppings due to abutment load during Longwall retreat, and Pneumatic or electrical pumps for handling slushy/sludge water. Conclusion: Longwall should be promoted as a technology mission, thrust areas are to be given due consideration to succeed Longwall technology as in other countries like Australia, USA and China. Longwall mining is done successfully in all major coal producing countries even in difficult conditions like highly gassy, hard roof and steeply inclined Seams. It is proved beyond doubt that Longwall as an Underground Mining method is successful in India also where it was introduced with true spirit. The suitable underground Geological blocks need to be identified for introduction of high capacity Longwalls on large scale with the help of Global operators. CIL, SCCL and private operators who are allotted coal blocks for underground coal mining must plan to introduce as many Longwall as possible and LTCC for thick Seams in the blocks which are feasible for bulk production. Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 95
  • 9. References: [1] Committee on Public Undertakings, 2014-2015, Fourth Report, Sixteenth Lok Sabha, Coal India Limited, Ministry Of Coal. [2] India Energy Book, 2012, World Energy Council [3] A collating the decadal experience (1978- 1987). Journal of mines, Metals & Fuels, June, 1988 pp 267-273. [4] High Capacity Long Delhi, India,2015. [5] Assesssment Of Longwall Mining With A Focus On Successful Mechanised Underground Geological and Metallurgical Institute of India (MGMI). [6] B. Ramesh Kumar, S Chandras High Capacity Longwall Project - Advances in Rock Engineering - 2016 at Bangalore, India. ******** Emerging Coal/Lignite Mining Scenario & Mine Closure Activities - 2018 96