SlideShare a Scribd company logo
1 of 36
1
Manufacturing Operations
Management
Distributed
Control
System
-
DCS
2
Objectives
• Review the ISA 95 standards and how they are being
used in companies like Eli Lilly & Company for shop
floor to top floor integration
– The standards provide a formal model for exchanged data
between business systems and manufacturing systems
– The models also include a definition of Manufacturing
Operations Management, the activities on the shop floor that
take production schedules and perform the actual work
required to manufacture products
• The Manufacturing Operations Management models
are currently being used in the development of
multiple new manufacturing facilities
Distributed
Control
System
-
DCS
3
Manufacturing in the Supply Chain
• “Make” is a significant part of the supply chain and
collaborative manufacturing, but is often the last
element to be actually integrated
– Collaboration in “Make” is usually not a “Low Hanging Fruit”
– But can offer very high ROI for high volume, or high cost
products
• However, Business IT and Manufacturing IT
organizations are often at odds as they try to
collaborate
– They have different goals and different success criteria
– They use the same terms for different elements and different
terms for the same elements
Distributed
Control
System
-
DCS
4
Collaborative Manufacturing Help
• Fortunately there are multiple standards in
place to help integrating business systems
with manufacturing systems.
– The ISA 95 Enterprise/Control System Integration
standards, also an IEC/ISO standard
– XML Schemas standards for collaborative
manufacturing from the World Batch Forum
• Will show how they are being applied to the
development of manufacturing systems
roadmap
Distributed
Control
System
-
DCS
5
Different Points of View
• Business Systems
– Time Horizons
• Long-term view
– Model detail
• Linear route structures
– Control emphasis
• Product cost and overall
profitability
– Modeling criteria:
• Accounting reference
points
• Has inventory value
changed significantly? If
not, don’t model
separately
– View from the boardroom
• Manufacturing Systems
– Time Horizons
• Real-time view
– Model detail
• Complex routes with
rework paths
– Control emphasis
• Physical movement &
accountability
– Modeling criteria:
• material movement
reference points
• Does product stop
moving? If not, don’t
model separately
– View from the workcenter
Distributed
Control
System
-
DCS
6
Philosophical Orientation
• Enterprise Management systems:
–How much is my stuff worth?
• Manufacturing Operations Systems:
–Where is my stuff?
Distributed
Control
System
-
DCS
7
ISA 95 Provides Direction
• The ANSI/ISA 95.00.01 “Enterprise - Control
System Integration - Part 1: Models and
Terminology”
– Also Draft International Standard ISO/IEC 62264-1
• ANSI/ISA 95.00.02 “Enterprise - Control
System Integration - Part 2: Object Attributes”
• Draft ISA 95.00.03 “Enterprise - Control
System Integration - Part 3: Activity Models of
Manufacturing Operations Management”
Distributed
Control
System
-
DCS
8
Business Planning & Logistics
Plant Production Scheduling,
Operational Management, etc
Manufacturing
Operations & Control
Dispatching Production, Detailed Production
Scheduling, Reliability Assurance, ...
Batch
Control
Discrete
Control
Continuous
Control
Level 4
Level 3
Levels
2,1,0
ISA95.01 Levels
Interface addressed
in the ISA 95.01 and
ISA 95.02 standard
Area addressed
in the ISA 95.03
standard
Distributed
Control
System
-
DCS
Business Planning & Logistics
Plant Production Scheduling,
Operational Management, etc
Manufacturing
Operations & Control
Dispatching Production, Detailed Production
Scheduling, Reliability Assurance, ...
Business Logistics Management (ERP)
9
Interface addressed
in the ISA 95.01 and
ISA 95.02 standard
Area addressed
in the ISA 95.03
standard
Batch
Control
Discrete
Control
Continuous
Control
Level 4
Level 3
Levels
2,1,0
ISA95.01 Levels
Manufacturing Operations Management (MES)
10
ISA 95 Part 1 and Part 2
Exchanged Information
Information that crosses the boundary between
business systems and manufacturing systems
Distributed
Control
System
-
DCS
11
Exchanged Information Categories
Enterprise Information
Plant Production Scheduling,
Operational Management, etc
Manufacturing
Control Information
Area Supervision, Production Planning,
Reliability, Assurance, etc
Product
Definition
Information
(How to make
a product)
Production
Capability
Information
(What is
available
for use)
Production
Schedule
(What to
make and
use)
Production
Performance
(What was
made and
used)
Distributed
Control
System
-
DCS
12
4x4 Object Models
• Four categories of resources
– Personnel
– Equipment
– Material (and Energy)
– Process Segments
• Four Process, Product, & Production Models
– Capability & Capacity Definition
– Product Definition
– Production Schedule
– Production Performance
Distributed
Control
System
-
DCS
13
Four Resource Object Models
People
Materials
Equipment
Personnel resources managed for production
Equipment resources managed for production
Material resources managed for production
Process Segments
Business view of production processes
Distributed
Control
System
-
DCS
14
Capability, Product, Schedule, and
Performance Information
Product
Definitions
Production
Schedule
Production
Performance
What is available for use for production
What is needed to make a product
What to make and resources to use
What was made and resources actually used
Product
Time
Capability/Capacity
Distributed
Control
System
-
DCS
15
Production Schedule
People
Materials
Equipment
Segments
Production
Schedule
What to make
- Priority and/or dates
- What materials to use
- What equipment to use
- What personnel to use
- Production parameters
(e.g. Color, Options,…)
Per location (Site, Area, …)
Per week, day,
shift, order, …
• Production Schedule
• Production Request
• Segment Request
• Expected Produced Material
• Expected Consumed Material
• Expected Personnel
• Expected Equipment
• Production Parameters
• …
Distributed
Control
System
-
DCS
16
Production Performance
People
Materials
Equipment
Segments
Production
Performance
What was made
- What material was
actually produced
- What materials were
actually consumed
- Equipment used
- Personnel used
- Production data
(e.g. Purity, density,…)
Per location (Site, Area, …)
Per shift, hour,
end of batch, …
• Production Performance
• Production Response
• Segment Response
• Produced Material Actual
• Consumed Material Actual
• Personnel Actual
• Equipment Actual
• Production Data
• …
Distributed
Control
System
-
DCS
17
XML Standard for B2M Exchanges
• The World Batch Forum has developed XML
Schemas that map to the ANSI/ISA-95
models
• Defines how to represent the ISA-95
information in XML
– Business To Manufacturing Markup Language
– B2MML
• One schema for each object model
• Formal way to exchange information
– www.wbf.org
Distributed
Control
System
-
DCS
18
<Material
<MaterialLot>
<ID> W89 </ID>
<Description> A lot of material </Description>
<MaterialDefinitionID> WXE908 </MaterialDefinitionID>
<Location> Tank 1 </Location>
<Quantity
UnitOfMeasure = "KL" > 4500
</Quantity>
<MaterialLotProperty>
<ID> dateTimeProduction </ID>
<Value> 2001-01-06T00:14:23+11:30 </Value>
</MaterialLotProperty>
<MaterialLotProperty>
<ID> Quality Status </ID>
<Value> Good </Value>
</MaterialLotProperty>
</MaterialLot>
</Material>
An XML Example – Material Lot
19
ISA95 Part 3
Activity Models of
Manufacturing Operations
In Development
Expected Release 2004
Distributed
Control
System
-
DCS
20
INVENTORY
OPERATIONS
INVENTORY
OPERATIONS
MAINTENANCE
OPERATIONS
PRODUCTION
OPERATIONS
QUALITY
ASSURANCE
OPERATIONS
Procurement
(5.0)
Production
Scheduling
(2.0)
Material and
Energy Control
(4.0)
Product
Inventory Control
(7.0)
Product Cost
Accounting
(8.0)
Quality
Assurance
(6.0)
Research
Development
and Engineering
Product
Shipping Admin
(9.0)
Order
Processing
(1.0)
Marketing
& Sales
Production
Control
(3.0)
Maintenance
Management
(10.0)
Distributed
Control
System
-
DCS
21
ISA 95.03 Manufacturing Operations Functions
Production
resource
management
Production
capability
Analysis
Production
data
collection
Production
execution
Production
dispatching
Production
tracking
Production
performance
Detailed
production
scheduling
Production
schedule
Level 2 Process Control
Product
definition
management
Product
definition
Equipment and Process
Specific Production Rules
Equipment and Process
Specific Data
Operational
Responses
Operational
Commands
Distributed
Control
System
-
DCS
22
Major
Activities
Within
Manufacturing
Operations
Quality
Operations
Maintenance
Operations
Production
Operations
Level 4
Level 3
Level 2
Management
of Configuration
Management
of Information
Management
of Security
Management
of Documentation
Management
of Compliance
Inventory
Operations
Other Enterprise Activities in
Manufacturing Operations
• Some actives are not specific to manufacturing
• ISA-95.03 lists references to standards in these
areas
Activity detailed
Activity not detailed
Activity outside scope
Distributed
Control
System
-
DCS
23
Implementations
• Nestle
– Project to use the XML schemas for schedule
exchange
• Arla Foods
– Project to use XML for standard interfaces to
multiple ERP systems and MES systems
• Empersas Polar
– Project to use XML schemas for schedule
exchange
• Eli Lilly
– Projects to use ISA 95 models for manufacturing
operations management architecture
Distributed
Control
System
-
DCS
24
Building Collaborative Manufacturing
Systems
• Process Used to Develop Solution
Architectures
– Conceptual Topology
– Functional Areas
– Standards and Guidelines
– Standard Applications
– Logical Architecture Design
– Physical Architecture Design
Distributed
Control
System
-
DCS
25
ISA 95 Control Hierarchy Levels
Level 4
Level 0
Level 1
Level 2
Level 3
Business Logistics
Plant Production Scheduling, Shipping,
Receiving, Inventory, etc
Manufacturing
Operations Management
Dispatching, Detailed Production
Scheduling, Production Tracking, ...
Batch
Production
Control
Discrete
Production
Control
Continuous
Production
Control
ISA – IEC/ISO
Interface
Standards
IEC, OPC, &
OMAC
Interface
Standards
ISA
Functional
Model
The production processes
Distributed
Control
System
-
DCS
What is the PCIMS ?
PCIMS :Process Control Information Management System
Each plant as an individual process area shall consist of an
integrated production control system and the main units of
integrated production system consist of :
UCB : Unit Control Building which is the central location for
controlling , PCB: process control building
RIB which houses all I/O’s and the controllers
Distributed
Control
System
-
DCS
DCS is Distribution Control System
Vendor ,Yokogawa centum CS3000
DCS consist of two main parts :
HIS : Human Interface Station
FCS : Field Control Station
- it is operator station that is used to monitor and control
the process .
FCS is a stand alone unite capable of performing a full
data acquisition control ,and all control function are
executed there with all I/O’s analog & digital signal.
What is the DCS ?
Distributed
Control
System
-
DCS
What is the PESS ?
PESS : Programmable electronic safety system
Vendor : ( Triconex )
which is used for emergency shutdown (ESD) function and
other equipment tripping function .
Distributed
Control
System
-
DCS What is MMS ?
MMS : Machine Monitoring system Vendor : ( Bentlt Nevada )
Machine Motoring System , the Bently Nevada system is
used to monitor the vibration of the shaft and the baring
shaft temperature , and to send a signal as hard wire to the
shut down system “ PESS” to trip the machine . Which is
used in Comp package & critical big Pump..etc.
Like :Tank gauging ,Flow computer for custody meter
and Vibration monitoring “ System 1”
Third party Equipment
Distributed
Control
System
-
DCS
What is RIB ?
RIB is Remote Instrument Building
The Remote Instrument Building RIB, which will house, the
DCS controller as FCS ,HIS ,PESS / PLC controller and their
cabinets and all other 3rd party equipment like Tank gauging
,Vibration monitoring , Flow computer , Power supply
distribution panel ,Fire and Gas panel and Uninterruptible
power supplies (UPS ) .
Distributed
Control
System
-
DCS
- DCS filed control station “ FCS “ Cabinets
- Programmable electronic shut down system “PESS Cabinets
- Machine monitoring system “ MMS Cabinets
- Programmable logic control “PLC” Cabinets
- Other equipment such as Tank Gauging , Custody metering
Cabinets
- Air unit
- Fire and gas panel
- All field instruments , wiring signals
- Marshaling panels
-Terminal blocks
-Servers cabinets
What is inside RIB’s
Distributed
Control
System
-
DCS
JB
F TA
HIS
T
B
FCU
FIO
HIS HIS HIS
Control
Room
V-net cable 10
base 5
Optical
converter
Fiber optic
cable
V-net cable 10
base 2
coaxial cable
RIB
FCS
B/N TMR PLC
Copper multi core
shielded cable
FTA or I/O's cable
twisted multi core ,as TEL cable
One pair copper
cable
Serial
communication link
Hard
wire
YNT
FOPP
YNT
FOPP
V-net converter 10 base 5 to 10
base 10
Black
box
Distributed
Control
System
-
DCS
To do down loading ,
Tag equalizing
between the
HIS,s,Trending , and
viewing DCS logic
DCS OPC server
V-net 10 Base 2
cable
Control room YNT
V-Net 10
Base 5
cable
Fiber optic cable
RIB YNT
V-Net cable 10
base 5
FIO
FCS
HIS
Distributed
Control
System
-
DCS
RIB Control Room
Fiber optic
100 MP/S
Fiber optic
1GP/S
2
copper
Fiber
PLC, PESS
PESS – PLC
OPC server
DCS OPC
server
One jacket fiber optic cable
consist of 6 orange cable which
consist of 4 wire
The total is 12 pare wire inside
one jacket
Distributed
Control
System
-
DCS
35
Conclusions
• Linked execution systems deliver results!
– Reduced direct costs; increased productivity
– Improved traceability; reduced “witch hunt” expense
– Near-theoretical cycle times: customer responsiveness,
reduced WIP inventory
– Greater agility: smaller lot sizes, more premium products in
the mix, happier customers, happier shareholders!
• S95 defines the currency for manufacturing object
and information exchange
– Faster project implementation cycles
– Flexibility to integrate and realign as corporate structures
change
Distributed
Control
System
-
DCS
36
Status
• ISA95.00.01 & ISA.95.00.02 available
• IEC/ISO 62264-1 available from IEC & ISO
• ISA 95.00.03 in draft
– Still under development in the committee
• World Batch Forum
– Developed XML Schemas for the exchanged
information
• Vendors
– Many currently using ISA-95 models in
development and current products
• Users
– Specifying ISA-95 in their RFPs

More Related Content

What's hot

MES - Manufacturing Execution System Explained
MES - Manufacturing Execution System ExplainedMES - Manufacturing Execution System Explained
MES - Manufacturing Execution System ExplainedMRPeasy
 
Smart Manufacturing
Smart ManufacturingSmart Manufacturing
Smart ManufacturingLukas Ott
 
Smart Manufacturing
Smart ManufacturingSmart Manufacturing
Smart ManufacturingAaron Zajas
 
2 Effective Manufacturing Erp Mes
2 Effective Manufacturing Erp Mes2 Effective Manufacturing Erp Mes
2 Effective Manufacturing Erp MesHieu Le Trung
 
Industry 4.0 Smart factory Application Story
Industry 4.0 Smart factory Application StoryIndustry 4.0 Smart factory Application Story
Industry 4.0 Smart factory Application StoryICPDAS
 
PharmaSuite manufacturing execution system (MES) software, the new EBR solution
PharmaSuite manufacturing execution system (MES) software, the new EBR solutionPharmaSuite manufacturing execution system (MES) software, the new EBR solution
PharmaSuite manufacturing execution system (MES) software, the new EBR solutionXavier Solà
 
MES - Preparation is the key to success
MES - Preparation is the key to success MES - Preparation is the key to success
MES - Preparation is the key to success NNE
 
MES (Manufacturing Execution System) Pocket Guide
MES (Manufacturing Execution System) Pocket GuideMES (Manufacturing Execution System) Pocket Guide
MES (Manufacturing Execution System) Pocket GuideVera Leonik-Shilyaeva
 
Using Syncade Workflow and AMS Device Manager for SIF Proof Testing on a Delt...
Using Syncade Workflow and AMS Device Manager for SIF Proof Testing on a Delt...Using Syncade Workflow and AMS Device Manager for SIF Proof Testing on a Delt...
Using Syncade Workflow and AMS Device Manager for SIF Proof Testing on a Delt...Emerson Exchange
 
Industry 4.0 pai
Industry 4.0 paiIndustry 4.0 pai
Industry 4.0 paiJayesh Pai
 
Out-of-the-box MES \ MOM solution
Out-of-the-box MES \ MOM solutionOut-of-the-box MES \ MOM solution
Out-of-the-box MES \ MOM solutionShashiAgasthya
 
Standards for virtual manufacturing and factory of the future position and s...
Standards for virtual manufacturing and factory of the future  position and s...Standards for virtual manufacturing and factory of the future  position and s...
Standards for virtual manufacturing and factory of the future position and s...Dr Nicolas Figay
 
Industry 4.0 Aligned Manufacturing MES Software
Industry 4.0 Aligned Manufacturing MES SoftwareIndustry 4.0 Aligned Manufacturing MES Software
Industry 4.0 Aligned Manufacturing MES SoftwareCantier Systems
 
Industry X.0 | Smart Factory | Session no.2
Industry X.0 | Smart Factory | Session no.2Industry X.0 | Smart Factory | Session no.2
Industry X.0 | Smart Factory | Session no.2Accenture Hungary
 
Industry 4.0: Merging Internet and Factories
Industry 4.0: Merging Internet and FactoriesIndustry 4.0: Merging Internet and Factories
Industry 4.0: Merging Internet and FactoriesFabernovel
 
Basics of mes
Basics of mesBasics of mes
Basics of mesumaydeo
 
Industry 4.0 and its technological needs
Industry 4.0 and its technological needsIndustry 4.0 and its technological needs
Industry 4.0 and its technological needsAlexandre Vallières
 

What's hot (20)

MES - Manufacturing Execution System Explained
MES - Manufacturing Execution System ExplainedMES - Manufacturing Execution System Explained
MES - Manufacturing Execution System Explained
 
Smart Manufacturing
Smart ManufacturingSmart Manufacturing
Smart Manufacturing
 
Smart Manufacturing
Smart ManufacturingSmart Manufacturing
Smart Manufacturing
 
2 Effective Manufacturing Erp Mes
2 Effective Manufacturing Erp Mes2 Effective Manufacturing Erp Mes
2 Effective Manufacturing Erp Mes
 
Industry 4.0 Smart factory Application Story
Industry 4.0 Smart factory Application StoryIndustry 4.0 Smart factory Application Story
Industry 4.0 Smart factory Application Story
 
PharmaSuite manufacturing execution system (MES) software, the new EBR solution
PharmaSuite manufacturing execution system (MES) software, the new EBR solutionPharmaSuite manufacturing execution system (MES) software, the new EBR solution
PharmaSuite manufacturing execution system (MES) software, the new EBR solution
 
MES - Preparation is the key to success
MES - Preparation is the key to success MES - Preparation is the key to success
MES - Preparation is the key to success
 
MES (Manufacturing Execution System) Pocket Guide
MES (Manufacturing Execution System) Pocket GuideMES (Manufacturing Execution System) Pocket Guide
MES (Manufacturing Execution System) Pocket Guide
 
Plant Integration and MES Solution for Industry
Plant Integration and MES Solution for IndustryPlant Integration and MES Solution for Industry
Plant Integration and MES Solution for Industry
 
ISA-95.pptx
ISA-95.pptxISA-95.pptx
ISA-95.pptx
 
Using Syncade Workflow and AMS Device Manager for SIF Proof Testing on a Delt...
Using Syncade Workflow and AMS Device Manager for SIF Proof Testing on a Delt...Using Syncade Workflow and AMS Device Manager for SIF Proof Testing on a Delt...
Using Syncade Workflow and AMS Device Manager for SIF Proof Testing on a Delt...
 
Industry 4.0 pai
Industry 4.0 paiIndustry 4.0 pai
Industry 4.0 pai
 
Out-of-the-box MES \ MOM solution
Out-of-the-box MES \ MOM solutionOut-of-the-box MES \ MOM solution
Out-of-the-box MES \ MOM solution
 
Standards for virtual manufacturing and factory of the future position and s...
Standards for virtual manufacturing and factory of the future  position and s...Standards for virtual manufacturing and factory of the future  position and s...
Standards for virtual manufacturing and factory of the future position and s...
 
Industry 4.0 Aligned Manufacturing MES Software
Industry 4.0 Aligned Manufacturing MES SoftwareIndustry 4.0 Aligned Manufacturing MES Software
Industry 4.0 Aligned Manufacturing MES Software
 
Industry X.0 | Smart Factory | Session no.2
Industry X.0 | Smart Factory | Session no.2Industry X.0 | Smart Factory | Session no.2
Industry X.0 | Smart Factory | Session no.2
 
Industry 4.0
Industry 4.0Industry 4.0
Industry 4.0
 
Industry 4.0: Merging Internet and Factories
Industry 4.0: Merging Internet and FactoriesIndustry 4.0: Merging Internet and Factories
Industry 4.0: Merging Internet and Factories
 
Basics of mes
Basics of mesBasics of mes
Basics of mes
 
Industry 4.0 and its technological needs
Industry 4.0 and its technological needsIndustry 4.0 and its technological needs
Industry 4.0 and its technological needs
 

Similar to manufacturingoperationmanagement-ISA 95.ppt

Manufacturing operation management
Manufacturing operation managementManufacturing operation management
Manufacturing operation managementMark Abkum
 
T061_isa95-04.pdf
T061_isa95-04.pdfT061_isa95-04.pdf
T061_isa95-04.pdfflorentflo2
 
Om lect 01(r0-may08)_operations strategy_mms_bharti_sies
Om lect 01(r0-may08)_operations strategy_mms_bharti_siesOm lect 01(r0-may08)_operations strategy_mms_bharti_sies
Om lect 01(r0-may08)_operations strategy_mms_bharti_siesvideoaakash15
 
Lean Operations Intro - Matrikulasi (std).ppt
Lean Operations Intro - Matrikulasi (std).pptLean Operations Intro - Matrikulasi (std).ppt
Lean Operations Intro - Matrikulasi (std).pptSyarahRizkia1
 
Conig® v1.5 Converged Information Governance
Conig® v1.5 Converged Information GovernanceConig® v1.5 Converged Information Governance
Conig® v1.5 Converged Information GovernanceYalcin Gerek
 
CONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information GovernanceCONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information GovernanceYalcin Gerek
 
How to become truly demand driven based on accurate customer orders rather th...
How to become truly demand driven based on accurate customer orders rather th...How to become truly demand driven based on accurate customer orders rather th...
How to become truly demand driven based on accurate customer orders rather th...Tristan Wiggill
 
Case study value of it strategy in hi tech industry
Case study value of it strategy in hi tech industryCase study value of it strategy in hi tech industry
Case study value of it strategy in hi tech industryiasaglobal
 
Oil-Refinery Planning & Scheduling Optimization
Oil-Refinery Planning & Scheduling OptimizationOil-Refinery Planning & Scheduling Optimization
Oil-Refinery Planning & Scheduling OptimizationAlkis Vazacopoulos
 
Lesson 3 - The Kimbal Lifecycle.pptx
Lesson 3 - The Kimbal Lifecycle.pptxLesson 3 - The Kimbal Lifecycle.pptx
Lesson 3 - The Kimbal Lifecycle.pptxcalf_ville86
 
Management Presentation on Managing Operations.
Management Presentation on Managing Operations.Management Presentation on Managing Operations.
Management Presentation on Managing Operations.Atif Imam
 
Standardization(work study & measurement)
Standardization(work study & measurement)Standardization(work study & measurement)
Standardization(work study & measurement)Nisarg Shah
 
Application Middleware Overview
Application Middleware OverviewApplication Middleware Overview
Application Middleware OverviewChristalin Nelson
 
Ch11 introto business
Ch11 introto businessCh11 introto business
Ch11 introto businessAjit Kumar
 
MFG4 2016 - Is Automation Right for Your Company - 4-2016
MFG4 2016 -  Is Automation Right for Your Company - 4-2016MFG4 2016 -  Is Automation Right for Your Company - 4-2016
MFG4 2016 - Is Automation Right for Your Company - 4-2016Craig Salvalaggio
 
CITGO Fueling Time Savings and Ensuring Quality with Automation – TechEd 2015
CITGO Fueling Time Savings and Ensuring Quality with Automation – TechEd 2015CITGO Fueling Time Savings and Ensuring Quality with Automation – TechEd 2015
CITGO Fueling Time Savings and Ensuring Quality with Automation – TechEd 2015Worksoft
 

Similar to manufacturingoperationmanagement-ISA 95.ppt (20)

Manufacturing operation management
Manufacturing operation managementManufacturing operation management
Manufacturing operation management
 
T061_isa95-04.pdf
T061_isa95-04.pdfT061_isa95-04.pdf
T061_isa95-04.pdf
 
Om lect 01(r0-may08)_operations strategy_mms_bharti_sies
Om lect 01(r0-may08)_operations strategy_mms_bharti_siesOm lect 01(r0-may08)_operations strategy_mms_bharti_sies
Om lect 01(r0-may08)_operations strategy_mms_bharti_sies
 
Lean Operations Intro - Matrikulasi (std).ppt
Lean Operations Intro - Matrikulasi (std).pptLean Operations Intro - Matrikulasi (std).ppt
Lean Operations Intro - Matrikulasi (std).ppt
 
Conig® v1.5 Converged Information Governance
Conig® v1.5 Converged Information GovernanceConig® v1.5 Converged Information Governance
Conig® v1.5 Converged Information Governance
 
CONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information GovernanceCONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information Governance
 
How to become truly demand driven based on accurate customer orders rather th...
How to become truly demand driven based on accurate customer orders rather th...How to become truly demand driven based on accurate customer orders rather th...
How to become truly demand driven based on accurate customer orders rather th...
 
Case study value of it strategy in hi tech industry
Case study value of it strategy in hi tech industryCase study value of it strategy in hi tech industry
Case study value of it strategy in hi tech industry
 
Demantra case study
Demantra case studyDemantra case study
Demantra case study
 
Oil-Refinery Planning & Scheduling Optimization
Oil-Refinery Planning & Scheduling OptimizationOil-Refinery Planning & Scheduling Optimization
Oil-Refinery Planning & Scheduling Optimization
 
Lesson 3 - The Kimbal Lifecycle.pptx
Lesson 3 - The Kimbal Lifecycle.pptxLesson 3 - The Kimbal Lifecycle.pptx
Lesson 3 - The Kimbal Lifecycle.pptx
 
Management Presentation on Managing Operations.
Management Presentation on Managing Operations.Management Presentation on Managing Operations.
Management Presentation on Managing Operations.
 
Sadchap01
Sadchap01Sadchap01
Sadchap01
 
Standardization(work study & measurement)
Standardization(work study & measurement)Standardization(work study & measurement)
Standardization(work study & measurement)
 
Application Middleware Overview
Application Middleware OverviewApplication Middleware Overview
Application Middleware Overview
 
Om ibs
Om   ibsOm   ibs
Om ibs
 
Ch11 introto business
Ch11 introto businessCh11 introto business
Ch11 introto business
 
SAP CBM
SAP CBMSAP CBM
SAP CBM
 
MFG4 2016 - Is Automation Right for Your Company - 4-2016
MFG4 2016 -  Is Automation Right for Your Company - 4-2016MFG4 2016 -  Is Automation Right for Your Company - 4-2016
MFG4 2016 - Is Automation Right for Your Company - 4-2016
 
CITGO Fueling Time Savings and Ensuring Quality with Automation – TechEd 2015
CITGO Fueling Time Savings and Ensuring Quality with Automation – TechEd 2015CITGO Fueling Time Savings and Ensuring Quality with Automation – TechEd 2015
CITGO Fueling Time Savings and Ensuring Quality with Automation – TechEd 2015
 

Recently uploaded

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

manufacturingoperationmanagement-ISA 95.ppt

  • 2. Distributed Control System - DCS 2 Objectives • Review the ISA 95 standards and how they are being used in companies like Eli Lilly & Company for shop floor to top floor integration – The standards provide a formal model for exchanged data between business systems and manufacturing systems – The models also include a definition of Manufacturing Operations Management, the activities on the shop floor that take production schedules and perform the actual work required to manufacture products • The Manufacturing Operations Management models are currently being used in the development of multiple new manufacturing facilities
  • 3. Distributed Control System - DCS 3 Manufacturing in the Supply Chain • “Make” is a significant part of the supply chain and collaborative manufacturing, but is often the last element to be actually integrated – Collaboration in “Make” is usually not a “Low Hanging Fruit” – But can offer very high ROI for high volume, or high cost products • However, Business IT and Manufacturing IT organizations are often at odds as they try to collaborate – They have different goals and different success criteria – They use the same terms for different elements and different terms for the same elements
  • 4. Distributed Control System - DCS 4 Collaborative Manufacturing Help • Fortunately there are multiple standards in place to help integrating business systems with manufacturing systems. – The ISA 95 Enterprise/Control System Integration standards, also an IEC/ISO standard – XML Schemas standards for collaborative manufacturing from the World Batch Forum • Will show how they are being applied to the development of manufacturing systems roadmap
  • 5. Distributed Control System - DCS 5 Different Points of View • Business Systems – Time Horizons • Long-term view – Model detail • Linear route structures – Control emphasis • Product cost and overall profitability – Modeling criteria: • Accounting reference points • Has inventory value changed significantly? If not, don’t model separately – View from the boardroom • Manufacturing Systems – Time Horizons • Real-time view – Model detail • Complex routes with rework paths – Control emphasis • Physical movement & accountability – Modeling criteria: • material movement reference points • Does product stop moving? If not, don’t model separately – View from the workcenter
  • 6. Distributed Control System - DCS 6 Philosophical Orientation • Enterprise Management systems: –How much is my stuff worth? • Manufacturing Operations Systems: –Where is my stuff?
  • 7. Distributed Control System - DCS 7 ISA 95 Provides Direction • The ANSI/ISA 95.00.01 “Enterprise - Control System Integration - Part 1: Models and Terminology” – Also Draft International Standard ISO/IEC 62264-1 • ANSI/ISA 95.00.02 “Enterprise - Control System Integration - Part 2: Object Attributes” • Draft ISA 95.00.03 “Enterprise - Control System Integration - Part 3: Activity Models of Manufacturing Operations Management”
  • 8. Distributed Control System - DCS 8 Business Planning & Logistics Plant Production Scheduling, Operational Management, etc Manufacturing Operations & Control Dispatching Production, Detailed Production Scheduling, Reliability Assurance, ... Batch Control Discrete Control Continuous Control Level 4 Level 3 Levels 2,1,0 ISA95.01 Levels Interface addressed in the ISA 95.01 and ISA 95.02 standard Area addressed in the ISA 95.03 standard
  • 9. Distributed Control System - DCS Business Planning & Logistics Plant Production Scheduling, Operational Management, etc Manufacturing Operations & Control Dispatching Production, Detailed Production Scheduling, Reliability Assurance, ... Business Logistics Management (ERP) 9 Interface addressed in the ISA 95.01 and ISA 95.02 standard Area addressed in the ISA 95.03 standard Batch Control Discrete Control Continuous Control Level 4 Level 3 Levels 2,1,0 ISA95.01 Levels Manufacturing Operations Management (MES)
  • 10. 10 ISA 95 Part 1 and Part 2 Exchanged Information Information that crosses the boundary between business systems and manufacturing systems
  • 11. Distributed Control System - DCS 11 Exchanged Information Categories Enterprise Information Plant Production Scheduling, Operational Management, etc Manufacturing Control Information Area Supervision, Production Planning, Reliability, Assurance, etc Product Definition Information (How to make a product) Production Capability Information (What is available for use) Production Schedule (What to make and use) Production Performance (What was made and used)
  • 12. Distributed Control System - DCS 12 4x4 Object Models • Four categories of resources – Personnel – Equipment – Material (and Energy) – Process Segments • Four Process, Product, & Production Models – Capability & Capacity Definition – Product Definition – Production Schedule – Production Performance
  • 13. Distributed Control System - DCS 13 Four Resource Object Models People Materials Equipment Personnel resources managed for production Equipment resources managed for production Material resources managed for production Process Segments Business view of production processes
  • 14. Distributed Control System - DCS 14 Capability, Product, Schedule, and Performance Information Product Definitions Production Schedule Production Performance What is available for use for production What is needed to make a product What to make and resources to use What was made and resources actually used Product Time Capability/Capacity
  • 15. Distributed Control System - DCS 15 Production Schedule People Materials Equipment Segments Production Schedule What to make - Priority and/or dates - What materials to use - What equipment to use - What personnel to use - Production parameters (e.g. Color, Options,…) Per location (Site, Area, …) Per week, day, shift, order, … • Production Schedule • Production Request • Segment Request • Expected Produced Material • Expected Consumed Material • Expected Personnel • Expected Equipment • Production Parameters • …
  • 16. Distributed Control System - DCS 16 Production Performance People Materials Equipment Segments Production Performance What was made - What material was actually produced - What materials were actually consumed - Equipment used - Personnel used - Production data (e.g. Purity, density,…) Per location (Site, Area, …) Per shift, hour, end of batch, … • Production Performance • Production Response • Segment Response • Produced Material Actual • Consumed Material Actual • Personnel Actual • Equipment Actual • Production Data • …
  • 17. Distributed Control System - DCS 17 XML Standard for B2M Exchanges • The World Batch Forum has developed XML Schemas that map to the ANSI/ISA-95 models • Defines how to represent the ISA-95 information in XML – Business To Manufacturing Markup Language – B2MML • One schema for each object model • Formal way to exchange information – www.wbf.org
  • 18. Distributed Control System - DCS 18 <Material <MaterialLot> <ID> W89 </ID> <Description> A lot of material </Description> <MaterialDefinitionID> WXE908 </MaterialDefinitionID> <Location> Tank 1 </Location> <Quantity UnitOfMeasure = "KL" > 4500 </Quantity> <MaterialLotProperty> <ID> dateTimeProduction </ID> <Value> 2001-01-06T00:14:23+11:30 </Value> </MaterialLotProperty> <MaterialLotProperty> <ID> Quality Status </ID> <Value> Good </Value> </MaterialLotProperty> </MaterialLot> </Material> An XML Example – Material Lot
  • 19. 19 ISA95 Part 3 Activity Models of Manufacturing Operations In Development Expected Release 2004
  • 20. Distributed Control System - DCS 20 INVENTORY OPERATIONS INVENTORY OPERATIONS MAINTENANCE OPERATIONS PRODUCTION OPERATIONS QUALITY ASSURANCE OPERATIONS Procurement (5.0) Production Scheduling (2.0) Material and Energy Control (4.0) Product Inventory Control (7.0) Product Cost Accounting (8.0) Quality Assurance (6.0) Research Development and Engineering Product Shipping Admin (9.0) Order Processing (1.0) Marketing & Sales Production Control (3.0) Maintenance Management (10.0)
  • 21. Distributed Control System - DCS 21 ISA 95.03 Manufacturing Operations Functions Production resource management Production capability Analysis Production data collection Production execution Production dispatching Production tracking Production performance Detailed production scheduling Production schedule Level 2 Process Control Product definition management Product definition Equipment and Process Specific Production Rules Equipment and Process Specific Data Operational Responses Operational Commands
  • 22. Distributed Control System - DCS 22 Major Activities Within Manufacturing Operations Quality Operations Maintenance Operations Production Operations Level 4 Level 3 Level 2 Management of Configuration Management of Information Management of Security Management of Documentation Management of Compliance Inventory Operations Other Enterprise Activities in Manufacturing Operations • Some actives are not specific to manufacturing • ISA-95.03 lists references to standards in these areas Activity detailed Activity not detailed Activity outside scope
  • 23. Distributed Control System - DCS 23 Implementations • Nestle – Project to use the XML schemas for schedule exchange • Arla Foods – Project to use XML for standard interfaces to multiple ERP systems and MES systems • Empersas Polar – Project to use XML schemas for schedule exchange • Eli Lilly – Projects to use ISA 95 models for manufacturing operations management architecture
  • 24. Distributed Control System - DCS 24 Building Collaborative Manufacturing Systems • Process Used to Develop Solution Architectures – Conceptual Topology – Functional Areas – Standards and Guidelines – Standard Applications – Logical Architecture Design – Physical Architecture Design
  • 25. Distributed Control System - DCS 25 ISA 95 Control Hierarchy Levels Level 4 Level 0 Level 1 Level 2 Level 3 Business Logistics Plant Production Scheduling, Shipping, Receiving, Inventory, etc Manufacturing Operations Management Dispatching, Detailed Production Scheduling, Production Tracking, ... Batch Production Control Discrete Production Control Continuous Production Control ISA – IEC/ISO Interface Standards IEC, OPC, & OMAC Interface Standards ISA Functional Model The production processes
  • 26. Distributed Control System - DCS What is the PCIMS ? PCIMS :Process Control Information Management System Each plant as an individual process area shall consist of an integrated production control system and the main units of integrated production system consist of : UCB : Unit Control Building which is the central location for controlling , PCB: process control building RIB which houses all I/O’s and the controllers
  • 27. Distributed Control System - DCS DCS is Distribution Control System Vendor ,Yokogawa centum CS3000 DCS consist of two main parts : HIS : Human Interface Station FCS : Field Control Station - it is operator station that is used to monitor and control the process . FCS is a stand alone unite capable of performing a full data acquisition control ,and all control function are executed there with all I/O’s analog & digital signal. What is the DCS ?
  • 28. Distributed Control System - DCS What is the PESS ? PESS : Programmable electronic safety system Vendor : ( Triconex ) which is used for emergency shutdown (ESD) function and other equipment tripping function .
  • 29. Distributed Control System - DCS What is MMS ? MMS : Machine Monitoring system Vendor : ( Bentlt Nevada ) Machine Motoring System , the Bently Nevada system is used to monitor the vibration of the shaft and the baring shaft temperature , and to send a signal as hard wire to the shut down system “ PESS” to trip the machine . Which is used in Comp package & critical big Pump..etc. Like :Tank gauging ,Flow computer for custody meter and Vibration monitoring “ System 1” Third party Equipment
  • 30. Distributed Control System - DCS What is RIB ? RIB is Remote Instrument Building The Remote Instrument Building RIB, which will house, the DCS controller as FCS ,HIS ,PESS / PLC controller and their cabinets and all other 3rd party equipment like Tank gauging ,Vibration monitoring , Flow computer , Power supply distribution panel ,Fire and Gas panel and Uninterruptible power supplies (UPS ) .
  • 31. Distributed Control System - DCS - DCS filed control station “ FCS “ Cabinets - Programmable electronic shut down system “PESS Cabinets - Machine monitoring system “ MMS Cabinets - Programmable logic control “PLC” Cabinets - Other equipment such as Tank Gauging , Custody metering Cabinets - Air unit - Fire and gas panel - All field instruments , wiring signals - Marshaling panels -Terminal blocks -Servers cabinets What is inside RIB’s
  • 32. Distributed Control System - DCS JB F TA HIS T B FCU FIO HIS HIS HIS Control Room V-net cable 10 base 5 Optical converter Fiber optic cable V-net cable 10 base 2 coaxial cable RIB FCS B/N TMR PLC Copper multi core shielded cable FTA or I/O's cable twisted multi core ,as TEL cable One pair copper cable Serial communication link Hard wire YNT FOPP YNT FOPP V-net converter 10 base 5 to 10 base 10 Black box
  • 33. Distributed Control System - DCS To do down loading , Tag equalizing between the HIS,s,Trending , and viewing DCS logic DCS OPC server V-net 10 Base 2 cable Control room YNT V-Net 10 Base 5 cable Fiber optic cable RIB YNT V-Net cable 10 base 5 FIO FCS HIS
  • 34. Distributed Control System - DCS RIB Control Room Fiber optic 100 MP/S Fiber optic 1GP/S 2 copper Fiber PLC, PESS PESS – PLC OPC server DCS OPC server One jacket fiber optic cable consist of 6 orange cable which consist of 4 wire The total is 12 pare wire inside one jacket
  • 35. Distributed Control System - DCS 35 Conclusions • Linked execution systems deliver results! – Reduced direct costs; increased productivity – Improved traceability; reduced “witch hunt” expense – Near-theoretical cycle times: customer responsiveness, reduced WIP inventory – Greater agility: smaller lot sizes, more premium products in the mix, happier customers, happier shareholders! • S95 defines the currency for manufacturing object and information exchange – Faster project implementation cycles – Flexibility to integrate and realign as corporate structures change
  • 36. Distributed Control System - DCS 36 Status • ISA95.00.01 & ISA.95.00.02 available • IEC/ISO 62264-1 available from IEC & ISO • ISA 95.00.03 in draft – Still under development in the committee • World Batch Forum – Developed XML Schemas for the exchanged information • Vendors – Many currently using ISA-95 models in development and current products • Users – Specifying ISA-95 in their RFPs