SlideShare a Scribd company logo
1 of 4
When dignitaries broke ground on the Access to the Region’s
Core (ARC) project in northern New Jersey in 2009, it was
supposed to be a celebration to signal the start of a bright new
future. Creating a commuter rail tunnel under the Hudson River
was not a particularly new or difficult idea, but it was viewed as
a critical need. The project was first proposed in 1995, and
every New Jersey governor after that time had publicly sup-
ported the need for the tunnel. The reasons were compelling:
The entire commuter rail system connecting
New York and New Jersey was supported by only one congested
100-year-old, two-track railroad tunnel into an overcrowded
Penn Station in midtown Manhattan; both tracks had reached
capacity and could no longer accommodate growth. Passengers
were making more than 500,000 trips through Penn Station
every day, with station congestion and overcrowding the norm.
The project was especially critical for New Jersey residents
because their commuter ridership to New York had more than
quadrupled in the past 20 years from10 million annual trips to
more than 46 million annual passenger trips. In the peak hours,
the New Jersey Transit Authority operated 20 of the 23 trains
heading into or out of New York. Building the ARC would
double the number of New Jersey Transit commuter trains, from
45 to about 90, that could come into Manhattan every morning
at rush hour.
· In the face of such congestion and perceived need, the ARC
project was conceived to include the following elements:
· Two new tracks under the Hudson River and the New Jersey
Palisades
· A new six-track passenger station, to be known as “New York
Pennsylvania Station Extension” (NYPSE) under 34th Street,
with passenger connection to Penn Station
· A new rail loop near the Lautenberg Secaucus Junction station
to allow two northern New Jersey line trains access to New
York City
· A midday rail storage yard in Kearny, New Jersey
Proponents also argued the environmental advantages of the
project, noting that the ARC project would eliminate 30,000
daily personal automobile trips, taking 22,000 cars off the roads
and resulting in 600,000 fewer daily vehicle miles traveled. The
project was expected to thus reduce greenhouse gas emissions
by nearly 66,000 tons each year.
The ARC project was anticipated to take eight years to
complete, coming into service in 2017. The cost of the project
was significant, as the Federal Transit Administration (FTA)
reported the project cost as $8.7 billion in their Annual Report.
In order to share the burden of the project costs, the funding as
originally proposed included the following sources:
· Federal government: $4.5 billion
· Port Authority of New York and New Jersey:
· $3.0 billion New Jersey Turnpike Authority: $1.25 billion
A final important feature of the funding plan limited the
exposure of the federal government for any project overruns,
meaning that the government was locked into its original
commitment amount only. Any cost overruns or project
slippages would have to be covered exclusively by the state of
New Jersey.
The contracts for various parts of the project began to be
awarded following competitive bidding in June 2009, and the
first tunneling contract was awarded in May 2010. Within little
more than three months, rumbles began being heard from the
New Jersey governor’s office on the viability of the project.
Governor Chris Christie ran and was elected on the promise of
reining in what many viewed as out- of-control spending by the
state’s legislature, coupled with some of the highest property
and business taxes in the country. As a self-described “budget
hawk,” Christie was increasingly troubled by rumors of cost
overruns in the ARC project. Worse, all projections for
completion of the project pointed to a much higher final price
tag than the original $8.7 billion estimate.
In early September 2010, Governor Christie ordered a
temporary halt in awarding new contracts for the project until
his office had a chance to study project cost projections more
thoroughly. This issue was highlighted when U.S.
Transportation Secretary
FIGURE 14.4 Artist’s Rendition of Underground Train Platform
at Penn Station for ARC Project Source: Star-Ledger
Ray LaHood, though a supporter of the tunnel, publicly
admitted that federal estimates showed the project could go
between $1 billion and $4 billion over budget. Christie
suspected that even those estimates might be low, putting his
state on the hook for a potentially huge new debt, at a time
when the economy was sour and the state was already
desperately seeking means to trim runaway spending. As
additional evidence of highly suspect initial cost estimates,
Christie’s supporters pointed to the recently completed “Big
Dig” project in Boston, which started with an initial price tag of
$2.5 billion and ultimately ended up costing well over $14
billion to complete.
Governor Christie first canceled the contract on October 7,
2010, citing cost overruns for which he said the state had no
way to pay. The following day, he agreed to temporarily
suspend his cancellation order so that he could try to resolve the
funding dilemma with federal transportation officials and other
project stakeholders. After a two-week period to analyze all
their options, the governor made the cancellation official.
Christie said that given the impact of the recession and the
probability of continuing cost overruns, the state could no
longer afford the tunnel’s escalating costs. More than a half-
billion dollars had already been spent on construction,
engineering, and land acquisition for a project that was
budgeted at $8.7 billion, but which the governor said could go
as high as $14 billion. “The only prudent move is to end this
project,” Governor Christie said at a Trenton news conference.
“I can’t put taxpayers on a never-ending hook.”30
Questions
1. How would you respond to the argument that it is impossible
to judge how successful a project like this one would have been
unless you actually do it?
2. Take a position, either pro or con, on Christie’s decision to
kill the ARC. Develop arguments to support your point of view.
3. In your opinion, how clearly must a large infra- structure
project like ARC have determined its need, costs, and so forth
before being approved? If the criteria are too stringent, what is
the implication for future projects of this type? Would any ever
be built?

More Related Content

Similar to When dignitaries broke ground on the Access to the Region’s Core (.docx

The Highline - City Hall
The Highline - City HallThe Highline - City Hall
The Highline - City HallErisaGjinaj
 
PWF Dulles Greenway Case Study
PWF Dulles Greenway Case StudyPWF Dulles Greenway Case Study
PWF Dulles Greenway Case StudyTim McDonald
 
Hawaii Governor David Ige - Leadership in Action - Transformation - Follow th...
Hawaii Governor David Ige - Leadership in Action - Transformation - Follow th...Hawaii Governor David Ige - Leadership in Action - Transformation - Follow th...
Hawaii Governor David Ige - Leadership in Action - Transformation - Follow th...Clifton M. Hasegawa & Associates, LLC
 
Honolulu Mayor Kirk Caldwell - Field of Dreams Build It They Will Come - The...
Honolulu Mayor Kirk Caldwell - Field of Dreams  Build It They Will Come - The...Honolulu Mayor Kirk Caldwell - Field of Dreams  Build It They Will Come - The...
Honolulu Mayor Kirk Caldwell - Field of Dreams Build It They Will Come - The...Clifton M. Hasegawa & Associates, LLC
 
15.9.24 steubenville herald star - icw
15.9.24   steubenville herald star - icw15.9.24   steubenville herald star - icw
15.9.24 steubenville herald star - icwhmhollingsworth
 
03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipeline03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipelineartba
 
2 q review
2 q review2 q review
2 q reviewJOCNews
 
Headings - 2015 Volume I
Headings - 2015 Volume IHeadings - 2015 Volume I
Headings - 2015 Volume IHeadings
 
Pre SOQ Workshop
Pre SOQ WorkshopPre SOQ Workshop
Pre SOQ Workshopmsialaska
 
Planning And Decision Making In Transport Infrastructure Dev.
Planning And Decision Making In Transport Infrastructure Dev.Planning And Decision Making In Transport Infrastructure Dev.
Planning And Decision Making In Transport Infrastructure Dev.ceal2005
 
Honolulu Rail Transit - Budget
Honolulu Rail Transit - BudgetHonolulu Rail Transit - Budget
Honolulu Rail Transit - BudgetRyan Ozawa
 
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010Economic benefits-of-hrrc-passenger-service stephan sheppard 2010
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010Barrington Institute
 
Where new york stands on 5 big transportation projects
Where new york stands on 5 big transportation projectsWhere new york stands on 5 big transportation projects
Where new york stands on 5 big transportation projectsJohn Clemenza
 
Connecting and transforming california
Connecting and transforming californiaConnecting and transforming california
Connecting and transforming californiaEvi Katsoulieri
 
Contruction Today August 2015
Contruction Today August 2015Contruction Today August 2015
Contruction Today August 2015Vicken Bedian, PE
 
Honolulu Authority for Rapid Transit (HART) - The Hard Reality - When All Els...
Honolulu Authority for Rapid Transit (HART) - The Hard Reality - When All Els...Honolulu Authority for Rapid Transit (HART) - The Hard Reality - When All Els...
Honolulu Authority for Rapid Transit (HART) - The Hard Reality - When All Els...Clifton M. Hasegawa & Associates, LLC
 

Similar to When dignitaries broke ground on the Access to the Region’s Core (.docx (20)

The Highline - City Hall
The Highline - City HallThe Highline - City Hall
The Highline - City Hall
 
PWF Dulles Greenway Case Study
PWF Dulles Greenway Case StudyPWF Dulles Greenway Case Study
PWF Dulles Greenway Case Study
 
Hawaii Governor David Ige - Leadership in Action - Transformation - Follow th...
Hawaii Governor David Ige - Leadership in Action - Transformation - Follow th...Hawaii Governor David Ige - Leadership in Action - Transformation - Follow th...
Hawaii Governor David Ige - Leadership in Action - Transformation - Follow th...
 
Honolulu Mayor Kirk Caldwell - Field of Dreams Build It They Will Come - The...
Honolulu Mayor Kirk Caldwell - Field of Dreams  Build It They Will Come - The...Honolulu Mayor Kirk Caldwell - Field of Dreams  Build It They Will Come - The...
Honolulu Mayor Kirk Caldwell - Field of Dreams Build It They Will Come - The...
 
Story_2_Kosciuszko_Bridge
Story_2_Kosciuszko_BridgeStory_2_Kosciuszko_Bridge
Story_2_Kosciuszko_Bridge
 
Congressman Oberstar Stimulus Proposal
Congressman Oberstar Stimulus ProposalCongressman Oberstar Stimulus Proposal
Congressman Oberstar Stimulus Proposal
 
15.9.24 steubenville herald star - icw
15.9.24   steubenville herald star - icw15.9.24   steubenville herald star - icw
15.9.24 steubenville herald star - icw
 
03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipeline03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipeline
 
Hahn Bill
Hahn BillHahn Bill
Hahn Bill
 
2 q review
2 q review2 q review
2 q review
 
Amtrak final paper
Amtrak final paperAmtrak final paper
Amtrak final paper
 
Headings - 2015 Volume I
Headings - 2015 Volume IHeadings - 2015 Volume I
Headings - 2015 Volume I
 
Pre SOQ Workshop
Pre SOQ WorkshopPre SOQ Workshop
Pre SOQ Workshop
 
Planning And Decision Making In Transport Infrastructure Dev.
Planning And Decision Making In Transport Infrastructure Dev.Planning And Decision Making In Transport Infrastructure Dev.
Planning And Decision Making In Transport Infrastructure Dev.
 
Honolulu Rail Transit - Budget
Honolulu Rail Transit - BudgetHonolulu Rail Transit - Budget
Honolulu Rail Transit - Budget
 
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010Economic benefits-of-hrrc-passenger-service stephan sheppard 2010
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010
 
Where new york stands on 5 big transportation projects
Where new york stands on 5 big transportation projectsWhere new york stands on 5 big transportation projects
Where new york stands on 5 big transportation projects
 
Connecting and transforming california
Connecting and transforming californiaConnecting and transforming california
Connecting and transforming california
 
Contruction Today August 2015
Contruction Today August 2015Contruction Today August 2015
Contruction Today August 2015
 
Honolulu Authority for Rapid Transit (HART) - The Hard Reality - When All Els...
Honolulu Authority for Rapid Transit (HART) - The Hard Reality - When All Els...Honolulu Authority for Rapid Transit (HART) - The Hard Reality - When All Els...
Honolulu Authority for Rapid Transit (HART) - The Hard Reality - When All Els...
 

More from philipnelson29183

·NEWSStates Take Aim at Social Welfare Programs  By Ti.docx
·NEWSStates Take Aim at Social Welfare Programs  By Ti.docx·NEWSStates Take Aim at Social Welfare Programs  By Ti.docx
·NEWSStates Take Aim at Social Welfare Programs  By Ti.docxphilipnelson29183
 
·Analyze HRM legal regulations and learn proper procedures for.docx
·Analyze HRM legal regulations and learn proper procedures for.docx·Analyze HRM legal regulations and learn proper procedures for.docx
·Analyze HRM legal regulations and learn proper procedures for.docxphilipnelson29183
 
[removed]1.value15.00 pointsProblem 5-3A Perpetual Alt.docx
[removed]1.value15.00 pointsProblem 5-3A Perpetual Alt.docx[removed]1.value15.00 pointsProblem 5-3A Perpetual Alt.docx
[removed]1.value15.00 pointsProblem 5-3A Perpetual Alt.docxphilipnelson29183
 
~GOODWRITER~You have now delivered the project to your customer..docx
~GOODWRITER~You have now delivered the project to your customer..docx~GOODWRITER~You have now delivered the project to your customer..docx
~GOODWRITER~You have now delivered the project to your customer..docxphilipnelson29183
 
__ captures a mother and child at the table in __ Paula Modersohn .docx
__ captures a mother and child at the table in __ Paula Modersohn .docx__ captures a mother and child at the table in __ Paula Modersohn .docx
__ captures a mother and child at the table in __ Paula Modersohn .docxphilipnelson29183
 
[removed]Which of the following would not be considered a subarea .docx
[removed]Which of the following would not be considered a subarea .docx[removed]Which of the following would not be considered a subarea .docx
[removed]Which of the following would not be considered a subarea .docxphilipnelson29183
 
__ de Dolores son médicos.Dolores tiene un tío que es __.A la ab.docx
__ de Dolores son médicos.Dolores tiene un tío que es __.A la ab.docx__ de Dolores son médicos.Dolores tiene un tío que es __.A la ab.docx
__ de Dolores son médicos.Dolores tiene un tío que es __.A la ab.docxphilipnelson29183
 
[removed]World’s Biggest Public Compan.docx
[removed]World’s Biggest Public Compan.docx[removed]World’s Biggest Public Compan.docx
[removed]World’s Biggest Public Compan.docxphilipnelson29183
 
Zhibei Wang04172020Page 5Authoritarian or Authoritati.docx
Zhibei Wang04172020Page 5Authoritarian or Authoritati.docxZhibei Wang04172020Page 5Authoritarian or Authoritati.docx
Zhibei Wang04172020Page 5Authoritarian or Authoritati.docxphilipnelson29183
 
Zinn Ch 14 - httpwww.historyisaweapon.comdefcon1zinnwarhea14.ht.docx
Zinn Ch 14 - httpwww.historyisaweapon.comdefcon1zinnwarhea14.ht.docxZinn Ch 14 - httpwww.historyisaweapon.comdefcon1zinnwarhea14.ht.docx
Zinn Ch 14 - httpwww.historyisaweapon.comdefcon1zinnwarhea14.ht.docxphilipnelson29183
 
Zeno of Elea.Heres the assignment Write a double-spaced paper .docx
Zeno of Elea.Heres the assignment Write a double-spaced paper .docxZeno of Elea.Heres the assignment Write a double-spaced paper .docx
Zeno of Elea.Heres the assignment Write a double-spaced paper .docxphilipnelson29183
 
Yo          los libros en la mochila.Ana y Salvador          la ta.docx
Yo          los libros en la mochila.Ana y Salvador          la ta.docxYo          los libros en la mochila.Ana y Salvador          la ta.docx
Yo          los libros en la mochila.Ana y Salvador          la ta.docxphilipnelson29183
 
Youve now read Johnathan Swifts brilliant (it is, trust me) satiri.docx
Youve now read Johnathan Swifts brilliant (it is, trust me) satiri.docxYouve now read Johnathan Swifts brilliant (it is, trust me) satiri.docx
Youve now read Johnathan Swifts brilliant (it is, trust me) satiri.docxphilipnelson29183
 
Youre gonna respond to Are too many people going to college by Ch.docx
Youre gonna respond to Are too many people going to college by Ch.docxYoure gonna respond to Are too many people going to college by Ch.docx
Youre gonna respond to Are too many people going to college by Ch.docxphilipnelson29183
 
Your team was invited to present to a high school IT class to explai.docx
Your team was invited to present to a high school IT class to explai.docxYour team was invited to present to a high school IT class to explai.docx
Your team was invited to present to a high school IT class to explai.docxphilipnelson29183
 
Your Paper (8 pages) should include the following areas1. Cover P.docx
Your Paper (8 pages) should include the following areas1. Cover P.docxYour Paper (8 pages) should include the following areas1. Cover P.docx
Your Paper (8 pages) should include the following areas1. Cover P.docxphilipnelson29183
 
Your organization is expanding globally and you will no longer have .docx
Your organization is expanding globally and you will no longer have .docxYour organization is expanding globally and you will no longer have .docx
Your organization is expanding globally and you will no longer have .docxphilipnelson29183
 
Your outline should be a detailed overview of the Service Learning .docx
Your outline should be a detailed overview of the Service Learning .docxYour outline should be a detailed overview of the Service Learning .docx
Your outline should be a detailed overview of the Service Learning .docxphilipnelson29183
 

More from philipnelson29183 (20)

·NEWSStates Take Aim at Social Welfare Programs  By Ti.docx
·NEWSStates Take Aim at Social Welfare Programs  By Ti.docx·NEWSStates Take Aim at Social Welfare Programs  By Ti.docx
·NEWSStates Take Aim at Social Welfare Programs  By Ti.docx
 
·Analyze HRM legal regulations and learn proper procedures for.docx
·Analyze HRM legal regulations and learn proper procedures for.docx·Analyze HRM legal regulations and learn proper procedures for.docx
·Analyze HRM legal regulations and learn proper procedures for.docx
 
[removed]1.value15.00 pointsProblem 5-3A Perpetual Alt.docx
[removed]1.value15.00 pointsProblem 5-3A Perpetual Alt.docx[removed]1.value15.00 pointsProblem 5-3A Perpetual Alt.docx
[removed]1.value15.00 pointsProblem 5-3A Perpetual Alt.docx
 
~GOODWRITER~You have now delivered the project to your customer..docx
~GOODWRITER~You have now delivered the project to your customer..docx~GOODWRITER~You have now delivered the project to your customer..docx
~GOODWRITER~You have now delivered the project to your customer..docx
 
__ captures a mother and child at the table in __ Paula Modersohn .docx
__ captures a mother and child at the table in __ Paula Modersohn .docx__ captures a mother and child at the table in __ Paula Modersohn .docx
__ captures a mother and child at the table in __ Paula Modersohn .docx
 
[removed]Which of the following would not be considered a subarea .docx
[removed]Which of the following would not be considered a subarea .docx[removed]Which of the following would not be considered a subarea .docx
[removed]Which of the following would not be considered a subarea .docx
 
__ de Dolores son médicos.Dolores tiene un tío que es __.A la ab.docx
__ de Dolores son médicos.Dolores tiene un tío que es __.A la ab.docx__ de Dolores son médicos.Dolores tiene un tío que es __.A la ab.docx
__ de Dolores son médicos.Dolores tiene un tío que es __.A la ab.docx
 
[removed]World’s Biggest Public Compan.docx
[removed]World’s Biggest Public Compan.docx[removed]World’s Biggest Public Compan.docx
[removed]World’s Biggest Public Compan.docx
 
[removed].docx
[removed].docx[removed].docx
[removed].docx
 
[removed]1Government.docx
[removed]1Government.docx[removed]1Government.docx
[removed]1Government.docx
 
Zhibei Wang04172020Page 5Authoritarian or Authoritati.docx
Zhibei Wang04172020Page 5Authoritarian or Authoritati.docxZhibei Wang04172020Page 5Authoritarian or Authoritati.docx
Zhibei Wang04172020Page 5Authoritarian or Authoritati.docx
 
Zinn Ch 14 - httpwww.historyisaweapon.comdefcon1zinnwarhea14.ht.docx
Zinn Ch 14 - httpwww.historyisaweapon.comdefcon1zinnwarhea14.ht.docxZinn Ch 14 - httpwww.historyisaweapon.comdefcon1zinnwarhea14.ht.docx
Zinn Ch 14 - httpwww.historyisaweapon.comdefcon1zinnwarhea14.ht.docx
 
Zeno of Elea.Heres the assignment Write a double-spaced paper .docx
Zeno of Elea.Heres the assignment Write a double-spaced paper .docxZeno of Elea.Heres the assignment Write a double-spaced paper .docx
Zeno of Elea.Heres the assignment Write a double-spaced paper .docx
 
Yo          los libros en la mochila.Ana y Salvador          la ta.docx
Yo          los libros en la mochila.Ana y Salvador          la ta.docxYo          los libros en la mochila.Ana y Salvador          la ta.docx
Yo          los libros en la mochila.Ana y Salvador          la ta.docx
 
Youve now read Johnathan Swifts brilliant (it is, trust me) satiri.docx
Youve now read Johnathan Swifts brilliant (it is, trust me) satiri.docxYouve now read Johnathan Swifts brilliant (it is, trust me) satiri.docx
Youve now read Johnathan Swifts brilliant (it is, trust me) satiri.docx
 
Youre gonna respond to Are too many people going to college by Ch.docx
Youre gonna respond to Are too many people going to college by Ch.docxYoure gonna respond to Are too many people going to college by Ch.docx
Youre gonna respond to Are too many people going to college by Ch.docx
 
Your team was invited to present to a high school IT class to explai.docx
Your team was invited to present to a high school IT class to explai.docxYour team was invited to present to a high school IT class to explai.docx
Your team was invited to present to a high school IT class to explai.docx
 
Your Paper (8 pages) should include the following areas1. Cover P.docx
Your Paper (8 pages) should include the following areas1. Cover P.docxYour Paper (8 pages) should include the following areas1. Cover P.docx
Your Paper (8 pages) should include the following areas1. Cover P.docx
 
Your organization is expanding globally and you will no longer have .docx
Your organization is expanding globally and you will no longer have .docxYour organization is expanding globally and you will no longer have .docx
Your organization is expanding globally and you will no longer have .docx
 
Your outline should be a detailed overview of the Service Learning .docx
Your outline should be a detailed overview of the Service Learning .docxYour outline should be a detailed overview of the Service Learning .docx
Your outline should be a detailed overview of the Service Learning .docx
 

Recently uploaded

Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 

Recently uploaded (20)

Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 

When dignitaries broke ground on the Access to the Region’s Core (.docx

  • 1. When dignitaries broke ground on the Access to the Region’s Core (ARC) project in northern New Jersey in 2009, it was supposed to be a celebration to signal the start of a bright new future. Creating a commuter rail tunnel under the Hudson River was not a particularly new or difficult idea, but it was viewed as a critical need. The project was first proposed in 1995, and every New Jersey governor after that time had publicly sup- ported the need for the tunnel. The reasons were compelling: The entire commuter rail system connecting New York and New Jersey was supported by only one congested 100-year-old, two-track railroad tunnel into an overcrowded Penn Station in midtown Manhattan; both tracks had reached capacity and could no longer accommodate growth. Passengers were making more than 500,000 trips through Penn Station every day, with station congestion and overcrowding the norm. The project was especially critical for New Jersey residents because their commuter ridership to New York had more than quadrupled in the past 20 years from10 million annual trips to more than 46 million annual passenger trips. In the peak hours, the New Jersey Transit Authority operated 20 of the 23 trains heading into or out of New York. Building the ARC would double the number of New Jersey Transit commuter trains, from 45 to about 90, that could come into Manhattan every morning at rush hour. · In the face of such congestion and perceived need, the ARC project was conceived to include the following elements: · Two new tracks under the Hudson River and the New Jersey Palisades · A new six-track passenger station, to be known as “New York Pennsylvania Station Extension” (NYPSE) under 34th Street, with passenger connection to Penn Station · A new rail loop near the Lautenberg Secaucus Junction station to allow two northern New Jersey line trains access to New York City
  • 2. · A midday rail storage yard in Kearny, New Jersey Proponents also argued the environmental advantages of the project, noting that the ARC project would eliminate 30,000 daily personal automobile trips, taking 22,000 cars off the roads and resulting in 600,000 fewer daily vehicle miles traveled. The project was expected to thus reduce greenhouse gas emissions by nearly 66,000 tons each year. The ARC project was anticipated to take eight years to complete, coming into service in 2017. The cost of the project was significant, as the Federal Transit Administration (FTA) reported the project cost as $8.7 billion in their Annual Report. In order to share the burden of the project costs, the funding as originally proposed included the following sources: · Federal government: $4.5 billion · Port Authority of New York and New Jersey: · $3.0 billion New Jersey Turnpike Authority: $1.25 billion A final important feature of the funding plan limited the exposure of the federal government for any project overruns, meaning that the government was locked into its original commitment amount only. Any cost overruns or project slippages would have to be covered exclusively by the state of New Jersey. The contracts for various parts of the project began to be awarded following competitive bidding in June 2009, and the first tunneling contract was awarded in May 2010. Within little more than three months, rumbles began being heard from the New Jersey governor’s office on the viability of the project. Governor Chris Christie ran and was elected on the promise of reining in what many viewed as out- of-control spending by the state’s legislature, coupled with some of the highest property and business taxes in the country. As a self-described “budget hawk,” Christie was increasingly troubled by rumors of cost overruns in the ARC project. Worse, all projections for completion of the project pointed to a much higher final price tag than the original $8.7 billion estimate.
  • 3. In early September 2010, Governor Christie ordered a temporary halt in awarding new contracts for the project until his office had a chance to study project cost projections more thoroughly. This issue was highlighted when U.S. Transportation Secretary FIGURE 14.4 Artist’s Rendition of Underground Train Platform at Penn Station for ARC Project Source: Star-Ledger Ray LaHood, though a supporter of the tunnel, publicly admitted that federal estimates showed the project could go between $1 billion and $4 billion over budget. Christie suspected that even those estimates might be low, putting his state on the hook for a potentially huge new debt, at a time when the economy was sour and the state was already desperately seeking means to trim runaway spending. As additional evidence of highly suspect initial cost estimates, Christie’s supporters pointed to the recently completed “Big Dig” project in Boston, which started with an initial price tag of $2.5 billion and ultimately ended up costing well over $14 billion to complete. Governor Christie first canceled the contract on October 7, 2010, citing cost overruns for which he said the state had no way to pay. The following day, he agreed to temporarily suspend his cancellation order so that he could try to resolve the funding dilemma with federal transportation officials and other project stakeholders. After a two-week period to analyze all their options, the governor made the cancellation official. Christie said that given the impact of the recession and the probability of continuing cost overruns, the state could no longer afford the tunnel’s escalating costs. More than a half- billion dollars had already been spent on construction, engineering, and land acquisition for a project that was budgeted at $8.7 billion, but which the governor said could go as high as $14 billion. “The only prudent move is to end this project,” Governor Christie said at a Trenton news conference.
  • 4. “I can’t put taxpayers on a never-ending hook.”30 Questions 1. How would you respond to the argument that it is impossible to judge how successful a project like this one would have been unless you actually do it? 2. Take a position, either pro or con, on Christie’s decision to kill the ARC. Develop arguments to support your point of view. 3. In your opinion, how clearly must a large infra- structure project like ARC have determined its need, costs, and so forth before being approved? If the criteria are too stringent, what is the implication for future projects of this type? Would any ever be built?