DPP 2012
STANDAR
SPESIFIKASI TEKNIS
KONSTRUKSI JALAN REL, SIPIL, JEMBATAN
DAN BANGUNAN KERETA API
DIREKTORAT PRASARANA PERKERETAAPIAN
DIREKTORAT JENDERAL PERKERETAAPIAN
KEMENTERIAN PERHUBUNGAN
DPP 2012
DAFTAR ISI
BAB 1. UMUM
S.1. Peraturan – Peraturan..................................................................................... U.1-1
S.2. Definisi ............................................................................................................ U.2-1
S.3. Mobilisasi dan Demobilisasi ............................................................................ U.3-1
S.4. Survei ............................................................................................................. U.4-1
S.5. Ruang kerja..................................................................................................... U.5-1
S.6. Window Time .................................................................................................. U.6-1
S.7. Direksi Keet dan Gudang ............................................................................... U.7-1
S.8. Fasilitas Operasional Kerja.............................................................................. U.8-1
S.9. Pembersihan Lokasi Kerja............................................................................... U.9-1
S.10. Kesehatan dan Keselamatan Kerja (K3).......................................................... U.10-1
S.11. Dampak Lingkungan ....................................................................................... U.11-1
S.12. Jaminan dan Pengendalian Mutu .................................................................... U.12-1
S.13. Submittal......................................................................................................... U.13-1
S.14. Pemeriksaan dan Pengujian............................................................................ U.14-1
S.15. Organisasi Proyek........................................................................................... U.15-1
S.16. Rapat Proyek .................................................................................................. U.16-1
S.17. Pelaporan........................................................................................................ U.17-1
S.18. Serah Terima Pekerjaan.................................................................................. U.18-1
S.19. Masa Pemeliharaan ........................................................................................ U.19-1
BAB 2. SIPIL
S.1. Pekerjaan Pembongkaran............................................................................... S.1-1
S.2. Pembersihan Lahan ....................................................................................... S.2-1
S.3. Galian Umum ................................................................................................. S.3-1
S.4. Galian pada Tanah Keras/Batuan .................................................................. S.4-1
S.5. Galian untuk Bangunan Struktur...................................................................... S.5-1
S.6. Timbunan dengan Material Tanah Pilihan ...................................................... S.6-1
S.7. Timbunan di Belakang Bangunan Struktur ..................................................... S.7-1
S.8. Timbunan dengan Material Berbutir................................................................. S.8-1
S.9. Perbaikan Tanah Dasar dengan Material berbutir dan Geotekstile.................. S.9-1
S.10. Pemasangan Geotekstile sebagai Separator................................................... S.10-1
S.11. Perbaikan Tanah Dasar dengan Kapur .......................................................... S.11-1
S.12. Dinding Penahan Tanah dengan Pasangan Batu Kali .................................... S.12-1
S.13. Dinding Penahan Tanah dengan Pasangan Beton Bertulang ......................... S.13-1
S.14. Dinding Penahan tanah dengan Pasangan Batu ............................................ S.14-1
S.15. Saluran Air Pracetak ...................................................................................... S.15-1
S.16. Pasangan Batu Kosong dan Bronjong............................................................. S.16-1
S.17. Drainase Memanjang dan Melintang .............................................................. S.17-1
S.18. Gebalan Rumput ............................................................................................ S.18-1
S.19. Perlintasan Umum........................................................................................... S.19-1
S.20. Pekerjaan Perkerasan Jalan ........................................................................... S.20-1
DPP 2012
S.21. Pekerjaan Pemagaran dengan Beton ............................................................. S.21-1
S.22. Pagar Besi Hias .............................................................................................. S.23-1
BAB 3. TRACK
T.1. Pengadaan Rel .............................................................................................. T.1-1
T.2. Pengadaan Wesel dan Pemasangan ............................................................. T.2-1
T.3. Pengadaan Sistem Penambat ........................................................................ T.3-1
T.4. Pengadaan Pelat Sambung ............................................................................ T.4-1
T.5. IRJ .................................................................................................................. T.5-1
T.6. Bantalan Beton dan Sistem Penambat ........................................................... T.6-1
T.7. Bantalan Kayu ................................................................................................ T.7-1
T.8. Pengadaan dan Pengelasan Rel .................................................................... T.8-1
T.9. Kompromis Rel................................................................................................ T.9-1
T.10. Pengadaan Balas, Pengiriman dan Pengecekan ............................................ T.10-1
T.11. Pemasangan Track dan Pemecokan Awal ...................................................... T.11-1
T.12. Pemasangan Track pada Jembatan Tanpa Balas .......................................... T.12-1
T.13. Pengangkatan dan Listringan dan Pemecokan .............................................. T.13-1
T.14. Penggeseran Horisontal Track ....................................................................... T.14-1
T.15. Pekerjaan Bongkar Wesel .............................................................................. T.15-1
T.16. Blok Penahan (Sepur Badug) ......................................................................... T.16-1
T.17. Tamping dan Finishing dengan Mesin MTT .................................................... T.17-1
T.18. Pemasangan Rambu - Rambu ....................................................................... T.18-1
BAB 4. JEMBATAN DAN BOX CULVERT
J.1. Beton Struktur ................................................................................................. J.1-1
J.2. Beton Pratekan ............................................................................................... J.2-1
J.3. Baja Tulangan................................................................................................. J.3-1
J.4. Baja Struktur ................................................................................................... J.4-1
J.5. Pelaksanaan Perakitan ................................................................................... J.5-1
J.6. Pondasi Tiang Bor (Bored Pile) ....................................................................... J.6-1
J.7. Tiang Pancang ................................................................................................ J.7-1
J.8. Struktur Pangkal dan Pilar............................................................................... J.8-1
J.9. Andas Jembatan ............................................................................................. J.9-1
J.10. Railing Besi (Hand Rail) .................................................................................. J.10-1
J.11. Sheetpile Beton............................................................................................... J.11-1
J.12. Sheetpile Baja................................................................................................. J.12-1
BAB 5. BANGUNAN GEDUNG
G.1. Pekerjaan Pondasi .......................................................................................... G.1-1
G.2. Pekerjaan Konstruksi Baja .............................................................................. G.2-1
G.3. Pekerjaan Logam ............................................................................................ G.3-1
G.4. Pekerjaan Pasangan Batu - Bata .................................................................... G.4-1
G.5. Pekerjaan Plesteran/Acian Dinding ................................................................. G.5-1
G.6. Pekerjaan Dinding Keramik ............................................................................. G.6-1
G.7. Pekerjaan Alumunium Panel ........................................................................... G.7-1
DPP 2012
G.8. Pekerjaan Lantai Keramik ............................................................................... G.8-1
G.9. Pekerjaan Lantai Granite/Tile .......................................................................... G.9-1
G.10. Pekerjaan Paving Blok .................................................................................... G.10-1
G.11. Pekerjaan Water Proofing ............................................................................... G.11-1
G.12. Pekerjaan Kusen Aluminium ........................................................................... G.12-1
G.13. Pekerjaan Kayu............................................................................................... G.13-1
G.14. Pekerjaan Kaca............................................................................................... G.14-1
G.15. Pekerjaan Alat Penggantung dan Pengunci .................................................... G.15-1
G.16. Pekerjaan Langit-Langit Gypsum Board.......................................................... G.16-1
G.17. Pekerjaan Pengecatan .................................................................................... G.17-1
G.18. Pekerjaan Sanitair........................................................................................... G.18-1
G.19. Pekerjaan Atap Lembaran Baja Gelombang.................................................... G.19-1
G.20. Pekerjaan Railing Besi .................................................................................... G.20-1
G.21. Pekerjaan Silicone Sealant.............................................................................. G.21-1
G.22. Pekerjaan Sistem Elektrikal............................................................................. G.22-1
G.23. Pekerjaan Sistem Mekanikal ........................................................................... G.23-1
DPP 2012
BAB 1
UMUM
DPP 2012
U.1-1
U.1
PERATURAN – PERATURAN
1. PERATURAN-PERATURAN YANG TERKAIT
Dibawah ini adalah peraturan – peraturan yang dijadikan Pedoman dalam
pelaksanaan pekerjaan dalam penyusunan spesifikasi teknis apabila terdapat
perbedaan antara peraturan – peraturan dibawah ini dan spesifikasi teknis, maka
yang berlaku adalah sesuai yang tercantum dalam spesifikasi teknis ini:
 Standar Nasional Indonesia (SNI)
 Peraturan Menteri Perhubungan No 28 Tahun 2011 tentang Persyaratan Teknis
Jalur KA
 PD 10 (Peraturan Dinas)
 Hasil konsensus nasional rancangan SNI 1995, mengenai penambat elastis
(clip, insulator, alas rel dan shoulder)
 Peraturan Beton Bertulang Indonesia 1971
 Tata Cara Perhitungan Struktur Beton Untuk Bangunan Gedung (SKSNI T-15-
1991-03);
 Peraturan Bahan Jalan Rel Indonesia (draft)
 Peraturan Pelaksanaan Pembangunan Jalan Rel (draft)
 Peraturan setempat yang berlaku
 Peraturan tenaga kerja/hukum perburuhan yang berlaku
 Peraturan-peraturan lain yang berlaku
Standard pelaksanaan yang dikeluarkan oleh industri-industri bahan bangunan yang
dipakai di kegiatan ini.
DPP 2012
U.2-1
U.2
DEFINISI
ISTILAH DEFINISI
A : Ampere
AASHTO : American Association of State Highway
and Transportation Officials
ACI : American Concrete Institute
ANSI : American National Standard Institute
ASTM : American Society for Testing and
Material
AREA : American Railway Engineering
Association
AWS : American Welding Society
BS : `British Standards
JIS : Japanese Industrial Standards
CBR : California Bearing Ratio
UIC : International Union of Railways
Technical Specification
SNI : Standar Nasional Indonesia
PBI : Peraturan Beton Indonesia
Satker : Satuan Kerja
Konsultan : Penyedia Jasa Pengawasan
Konsultan Perencana : Penyedia Jasa Perencanaan
Konsultan MK : Penyedia Jasa Manajemen Konstruksi
Kontraktor : Penyedia Jasa Konstruksi
HB : Brinell Hardness
DPP 2012
U.3-1
U.3
MOBILISASI DAN DEMOBILISASI
1. RUANG LINGKUP
Pekerjaan ini meliputi pekerjaan pengiriman dan penarikan kembali semua sumber
daya, tenaga kerja, bahan, peralatan, perlengkapan, dan lain lain untuk mendukung
kegiatan pelaksanaan pekerjaan.
2. MOBILISASI
2.1 Mobilisasi terdiri dari pekerjaan persiapan dan pelaksanaan, termasuk, tapi
tidak terbatas pada kebutuhan-kebutuhan untuk mobilisasi personil, peralatan,
pemasokan, dan suplemen lainnya yang diperlukan ke lokasi proyek, untuk
pembangunan kantor, gudang dan fasilitas lainnya yang diperlukan untuk
bekerja di proyek, dan untuk seluruh pekerjaan dan operasi lainnya yang harus
dilakukan atau biaya yang diperlukan sebelum mulainya berbagai item
pekerjaan kontrak di lokasi proyek.
2.2 Mobilisasi adalah pengiriman ke lokasi pekerjaan sumber daya yang
dibutuhkan untuk pelaksanaan pekerjaan.
2.3 Mobilisasi dianggap selesai bila Kontraktor dapat melaksanakan dan diterima
oleh Konsultan mengenai pemenuhan masing-masing persyaratan yang terkait
yang disebutkan dalam kontrak.
3. DEMOBILISASI
3.1 Demobilisasi mencakup penyiapan pengajuan yang diperlukan sebelum
pengakhiran pekerjaan.Demobilisasi adalah penarikan kembali dari lokasi
pekerjaan sumber daya yang dibutuhkan untuk pelaksanaan pekerjaan.
3.2 Demobilisasi akan dianggap selesai jika seluruh peralatan, bahan, personil,
atau lainnya milik kontraktor telah dikeluarkan dari lokasi proyek, dan
persyaratan – persyaratan penyelesaian pekerjaan sebagaimana diatur dalam
kontrak telah terpenuhi.
DPP 2012
U.4-1
U.4
SURVEI
1. RUANG LINGKUP
Pekerjaan ini meliputi survei penelitian hasil desain konstruksi, survei topografi,
survei utilitas, penyelidikan tanah, survei hidrologi dan hidrolika, dan lain - lain yang
dibutuhkan untuk mendukung pelaksanaan pekerjaan.
2. SURVEI PENELITIAN HASIL DESAIN KONSTRUKSI
1) Sebelum pekerjaan dimulai, Kontraktor wajib melakukan penelitian terhadap
desain konstruksi yang terdapat dalam Kontrak.
2) Bila terdapat hal-hal yang meragukan dalam desain konstruksi, Kontraktor harus
berkoordinasi dengan Konsultan Perencana, Konnsultan dan PPK.
3) Perbaikan terhadap desain (review design) diusulkan oleh Kontraktor kepada
PPK untuk mendapat persetujuan.
3. SURVEI TOPOGRAFI
1) Kontraktor harus mengadakan pengukuran-pengukuran serta pemasangan
patok-patok yang diperlukan untuk pekerjaan pembangunan dan bertanggung
jawab penuh atas kebenaran dan ketepatan pengukuran tersebut sehingga
dapat dijadikan benchmark sebagai titik acuan elevasi dan posisi bangunan.
Patok-patok serta tanda patok harus dijaga sedemikian rupa sehingga
kedudukannya tetap serta tidak terganggu selama pekerjaan berlangsung.
2) Kesalahan-kesalahan yang terjadi sebagai akibat kelalaian di dalam menentukan
ukuran selama pelaksanaan menjadi tanggung jawab Kontraktor sepenuhnya.
Oleh karena itu sebelum pelaksanaan dimulai Kontraktor diwajibkan
mengadakan pemeriksaan menyeluruh terhadap gambar-gambar dan ketentuan
yang ada.
4. SURVEI UTILITAS
1) Kontraktor sebelum melaksanakan pekerjaan harus melakukan survei utilitas
yang berada di lokasi pekerjaan.
2) Kontraktor sebelum melaksanakan pekerjaan harus berkoordinasi dengan
PT.KAI untuk mengetahui kondisi utilitas yang ada di lokasi pekerjaan.
3) Hasil survei harus dibuat dokumentasi yang baik sebagai alat kerja.
DPP 2012
U.4-2
5. PENYELIDIKAN TANAH
1) Kontraktor sebelum melaksanakan pekerjaan harus melakukan penelitian
terhadap hasil penyelidikan tanah yang digunakan dalam proses desain.
2) Jika terdapat hal – hal yang belum diperhitungkan atau meragukan, Kontraktor
dapat melakukan penyelidikan tanah tambahan.
3) Dalam melakukan penyelidikan tanah, Kontraktor harus mendapat persetujuan
Konsultan dan PPK.
6. SURVEI HIDROLOGI DAN HIDROLIKA
Kontraktor harus melakukan survei hidrologi dan hidrolika untuk memastikan bahwa
akibat yang ditimbulkan selama pelaksanaan pekerjaan tidak menimbulkan dampak
negatif seperti banjir, penyumbatan, dan lain – lain.
DPP 2012
U.5-1
U.5
RUANG KERJA
1. RUANG KERJA (RIGHT OF WAY)
1) Ruang kerja akan menjadi lahan sementara atau permanen untuk melaksanakan
pekerjaan. Konsultan harus menentukan lebar efektif dan batas-batas ruang
kerja.
2) Kontraktor harus memperhatikan ruang kerja sebagaimana ditetapkan oleh
Konsultan.
3) Kontraktor bertanggung jawab untuk menyediakan ruang kerja tambahan yang
diperlukan untuk penyimpanan material, peralatan, dan lain – lain atas biaya
sendiri.
2. PERIJINAN
1) Setiap perijinan yang dibutuhkan untuk memindahkan material dan peralatan
menjadi tanggung jawab Kontraktor.
2) Kontraktor akan melakukan survei untuk mengetahui kondisi - kondisi dan
kesulitan yang mungkin ditemui dalam pengangkutan material, pengangkutan
peralatan, dan lain – lain.
3) Kontraktor harus menentukan jalan akses untuk mengangkut material, peralatan,
dan lain - lain.
3. PEMBERSIHAN LOKASI KERJA
1) Wilayah kerja harus dipelihara secara tertib dan bebas dari hambatan untuk
memberikan kondisi terbaik yang mungkin untuk berbagai operasi dan instalasi
yang diperlukan.
2) Limbah dan puing-puing harus dihilangkan dari lokasi kerja.
DPP 2012
U.6-1
U.6
WINDOW TIME
1. RUANG LINGKUP
Bagian ini mengatur penggunaan waktu untuk pelaksanaan pekerjaan terutama
pekerjaan yang berpengaruh bagi operasi kereta api.
2. RENCANA KERJA PELAKSANAAN DI LAPANGAN
1) Sebelum pelaksanaan pekerjaan, Kontraktor harus menyiapkan dan
menyampaikan Rencana Kerja kepada Konsultan.
2) Didalam rencana kerja harus tercantum mengenai program keselamatan yang
akan dilaksanakan oleh Kontraktor.
3) Kontraktor dan PPK serta Konsultan harus berkoordinasi dengan PT.KAI
sebelum melaksanakan pekerjaannya di track existing.
4) Pelaksanaan pekerjaan yang terletak di lokasi ruang manfaat jalan KA harus
berkoordinasi secara intensif kepada PT.KAI.
3. WINDOW TIME
1) Window Time adalah waktu yang digunakan diluar jam operasional kereta api.
2) Pekerjaan – pekerjaan yang telah diidentifikasi memerlukan window time adalah
sebagai berikut:
 Pergeseran Track (Track shifting)
 Peninggian Track (Track raising)
 Penyambungan Track (Connecting of track)
 Pemasangan Wesel (Setting of turnouts)
 Pembangunan Platform dan Sistem Drainase (Construction of new platform
and drainage system)
 Perlintasan Sebidang (Level crossing)
 Pekerjaan yang menyangkut perbaikan “Track Existing”
 Pekerjaan jembatan
 Relokasi dan Proteksi Utilitas (Relocation and protection of Utilities)
3) Kontraktor dalam melaksanakan pekerjaan yang memerlukan window time harus
menyampaikan rencana kerja dan kebutuhan waktu pekerjaan serta
berkoordinasi dengan Operator Prasarana untuk memperkirakan waktu yang
dibutuhkan.
4. PEMBATASAN KECEPATAN OPERASI KA
Kontraktor dan PPK / Konsultan harus berkoordinasi dengan PT.KAI untuk
pelaksanaan pembatasan kecepatan Kereta Api untuk menjaga operasi Kereta Api
yang aman selama pelaksanaan kegiatan konstruksi sesuai hasil pembahasan
Rencana Kerja.
DPP 2012
U.7-1
U.7
DIREKSI KEET DAN GUDANG
1. RUANG LINGKUP
Pekerjaan ini meliputi pembuatan Direksi Keet dan Gudang yang digunakan untuk
tempat pertemuan dan penyimpanan barang – barang sementara di lapangan.
2. PERSYARATAN TEKNIS
2.1. MATERIAL
1) Direksi keet dibuat dengan rangka kayu kelas III, dengan triplek tebal lebih
besar/sama dengan 4 mm, atap seng gelombang BJLS 25, lantai plesteran
dengan campuran 1 PC : 5 PC, tebal = 10 cm, kaca nako, daun pintu dari triplek,
dicat.
2) Di Direksi keet harus dilengkapi dengan :
No Item Volume
1 Papan Nama 1 bh
2 Meja 1 bh
3 Kursi 4 bh
4 Kalender 1 bh
5 Kotak Obat 1 set
6 Papan Tulis/White Board 1 bh
7 Papan Informasi 1 bh
8 Papan untuk menempel Gambar Kerja 1 bh
3) Setelah pekerjaan selesai, lokasi yang digunakan sebagai Direksi Keet dan
Gudang harus dibongkar dan dibersihkan.
DPP 2012
U8 -1
U.8
FASILITAS OPERASIONAL
1. RUANG LINGKUP
Fasilitas operasional kerja yang perlu dilengkapi oleh Kontraktor antara lain seperti
alat komunikasi, operasional kantor kontraktor, listrik/penerangan, dan lain – lain
sesuai kebutuhan di lapangan.
2. ALAT KOMUNIKASI
1) Kontraktor harus menyediakan peralatan komunikasi berupa HT dilengkapi
dengan RIG (bila perlu) yang diperlukan untuk komunikasi pemantauan operasi
KA pada saat bekerja dijalur atau dalam batas operasi KA.
2) Jika penguat/booster diperlukan, antena booster harus disediakan untuk
menjamin komunikasi yang baik/lancar antara alat komunikasi didalam seluruh
area pekerjaan, termasuk ke stasiun terdekat.
3. LISTRIK DAN PENERANGAN
1) Menyediakan dan memelihara semua penerangan sementara dan tenaga listrik
sementara yang diperlukan untuk konstruksi.
2) Menyediakan koneksi ke semua peralatan konstruksi yang memerlukan tenaga
listrik.
3) Menyediakan dan memelihara tenaga listrik sementara untuk peralatan mekanik
permanen memerlukan layanan tenaga listrik sampai tenaga listrik tetap dapat
digunakan.
4) Menyediakan penerangan lapangan sementara untuk keamanan sesuai dengan
arahan PPK / Konsultan.
5) Menyediakan grounding untuk semua perangkat sesuai standar yang berlaku.
6) menyediakan semua item yang diperlukan untuk penerangan.
7) Menyediakan dan menjaga semua peralatan layanan sementara sampai kerja
permanen terinstal dan diaktifkan.
8) Kesalahan-kesalahan yang terjadi sebagai akibat kelalaian di dalam penyediaan,
penggunaan dan perawatan peralatan akibat dari tenaga listrik selama proses
pelaksanaan pekerjaan menjadi tanggung jawab Kontraktor sepenuhnya. Oleh
karena itu sebelum pelaksanaan dimulai Kontraktor diwajibkan mengadakan
pemeriksaan menyeluruh terhadap syarat dan ketentuan yang ada.
4. TELEPON SEMENTARA
Kontraktor akan menyediakan layanan telepon sementara selama konstruksi untuk
kelancaran komunikasi.
DPP 2012
U8 -2
5. PETUNJUK PANGGILAN DARURAT
Kontraktor harus menyediakan daftar lokasi terdekat dan bekerja sama dengan
instansi terkait seperti polisi, rumah sakit atau pelayanan kesehatan di Direksi Keet,
untuk mengantisipasi apabila terjadi keadaan darurat.
DPP 2012
U.9-1
U.9
PEMBERSIHAN LOKASI KERJA
1) Selama proyek berlangsung, Kontraktor harus menjaga kebersihan dan mengatur
lokasi bahan bangunan dan alat kerja serta daerah kerja sehingga kelancaran
pelaksanaan pekerjaan tidak terlambat karenanya.
2) Pembersihan tumbuh-tumbuhan yang ada pada lokasi peruntukan kerja sesuai
petunjuk Gambar Kerja dan Pengawas Lapangan.
3) Sesudah proyek selesai dan sebelum melakukan penyerahan pekerjaan kepada
pemilik proyek, Kontraktor harus membersihkan seluruh daerah kerja dari segala
macam peralatan tersebut, sisa-sisa bahan bangunan, bekas bongkaran dan
bangunan-bangunan sementara, termasuk pengangkutannya tanpa tambahan biaya.
DPP 2012
U.10-1
U.10
KESEHATAN DAN KESELAMATAN KERJA (K3)
1. RUANG LINGKUP
Bagian ini mengatur mengenai pelaksanaan program Kesehatan dan Keselamatan
Kerja (K3) dalam pelaksanaan pekerjaan.
2. PEDOMAN DAN STANDAR
1) Undang-undang No. 1 tahun 1970 tentang Keselamatan Kerja
2) Keputusan Menteri Tenaga Kerja R.I. No. Kep. 1135/MEN/1987 tentang Bendera
Keselamatan Dan Kesehatan Kerja
3) Keputusan Menteri Tenaga Kerja R.I. No.: Kep.245/MEN/1990 tentang Hari
Keselamatan Dan Kesehatan Kerja Nasional
4) Peraturan Menteri Tenaga Kerja R.I. No. Per.05/MEN/1996 tentang Sistem
Manajemen Keselamatan dan Kesehatan Kerja
3. KESELAMATAN KERJA
1) Dari permulaan hingga penyelesaian pekerjaan dan selama masa pemeliharaan,
Kontraktor bertanggung jawab atas keselamatan dan keamanan pekerja,
material dan peralatan teknis serta konstruksi.
2) Kontraktor wajib menjaga keselamatan kerja di ruang kerja dengan melengkapi
dengan perlengkapan keselamatan kerja seperti safety line, rambu – rambu,
papan promosi keselamatan, dan lain – lain.
3) Kontraktor wajib menjamin keselamatan tenaga kerja yang terlibat dalam
pelaksanaan pekerjaan dari segala kemungkinan yang terjadi dengan memenuhi
aturan dan ketentuan kesehatan dan keselamatan kerja yang berlaku
(Jamsostek).
4) Kontraktor diwajibkan menyediakan obat-obatan menurut syarat-syarat
Pertolongan Pertama Pada Kecelakaan (PPPK) yang selalu dalam keadaan siap
digunakan di lapangan, untuk mengatasi segala kemungkinan musibah bagi
semua petugas dari pekerja lapangan.
5) Setiap pekerja diwajibkan menggunakan sepatu pada waktu bekerja dan di
lokasi harus disediakan Alat Pelindung Diri (APD) berupa safety belt, safety
helmet, masker/kedok las terutama untuk dipakai pada pekerjaan pemasangan
kuda-kuda baja dan pekerjaan yang beresiko tertimpa benda keras.
6) Kontraktor wajib menyediakan air bersih, kamar mandi dan WC yang layak dan
bersih bagi semua petugas dan pekerja. Membuat tempat penginapan di
lapangan pekerjaan untuk para pekerja tidak diperkenankan, kecuali atas ijin
PPK.
7) Apabila terjadi kecelakaan, Kontraktor segera mungkin memberitahukan kepada
Konsultan dan mengambil tindakan yang perlu untuk keselamatan korban-
korban kecelakaan itu.
DPP 2012
U.10-2
4. PROSEDUR OPERASI STANDAR (SOP) KESEHATAN DAN KESELAMATAN
KERJA (K3)
1) Kontraktor harus membuat SOP Kesehatan dan Keselamatan Kerja (K3).
2) SOP diajukan kepada Konsultan untuk dievaluasi.
3) Kontraktor harus menyampaikan laporan pelaksanaan SOP kepada Direktur
Keselamtan, Ditjen Perkeretaapian, Direktur Prasarana Ditjen Perkeretaapian,
PPK, dan Konsultan.
DPP 2012
U.13-1
U.11
DAMPAK LINGKUNGAN
1. PERTIMBANGAN LINGKUNGAN
1) Kontraktor akan membangun fasilitas, sehingga tidak satu pun pekerjaan
mempunyai dampak merugikan pada lingkungan, komunitas serta fasilitas kereta
api yang berdekatan.
2) Pertimbangan harus dilakukan sebagai berikut tetapi tidak terbatas pada:
a) Penggunaan bahan bakar ramah lingkungan untuk meminimalkan emisi
polusi udara
b) Pengendalian sulfur dioksida dan polutan udara lainnya
c) Pemisahan air limbah industri dan kota
d) Reklamasi air limbah
e) Pemulihan dan daur ulang bahan-bahan yang sesuai
f) Pengendalian kebisingan kendaraan
g) Pengendalian kebisingan dari industri dan fasilitas komersial
h) Batasan getaran
i) Pelestarian tanah alam sedapat mungkin.
j) Pelestarian situs arkeologi
2. PERLINDUNGAN LINGKUNGAN
1) Kontraktor harus menyadari dan mengikuti praktek-praktek perlindungan
lingkungan dan prosedur sebagaimana ditetapkan oleh otoritas dan instansi
terkait yang relevan.
2) Lanau dan lumpur yang diklasifikasikan sebagai limbah bahan tidak boleh
dibuang langsung ke perairan dekat pantai. Bahan ini akan dibuang di TPA yang
disetujui.
3) Limbah / sisa material dengan klasifikasi berbahan kimia berbahaya atau tidak
berbahaya akan dibuang dan/atau disimpan di TPA yang disetujui.
4) Tidak ada pembayaran terpisah akan dibuat untuk perlindungan lingkungan
hidup tetapi semua biaya yang daripadanya akan dimasukkan dalam harga
kontrak dibayarkan item.
3. PENGENDALIAN DAMPAK LINGKUNGAN
1) Kontraktor wajib mengikuti ketentuan yang ada dalam usaha pelaksanaan
pengendalian lingkungan.
2) Dampak lingkungan yang perlu diperhatikan antara lain:
 Banjir
 Longsor
 Debu
 Suara
U.11-1
DPP 2012
U.13-1
U.12
JAMINAN DAN PENGENDALIAN MUTU
1. RUANG LINGKUP
Bagian ini mencakup persyaratan untuk jaminan dan pengendalian mutu produk,
hasil kerja, dan penyiapan sertifikat pemenuhan persyaratan.
2. PERSYARATAN UMUM
1) Material dan peralatan yang digunakan dalam pekerjaan harus memenuhi
persyaratan yang berlaku dalam hal ukuran, pembuatan, jenis dan kualitas yang
ditentukan, kecuali secara spesifik ditentukan bebas dari persyaratan.
2) Konsultan dan PPK mempunyai hak untuk menolak material atau cara dan hasil
kerja yang tidak sesuai dengan persyaratan, pada setiap saat.
3) Kontraktor harus membongkar pekerjaan yang tidak diterima atau ditolak oleh
Konsultan dan PPK dan mengerjakan kembali sesuai persyaratan kontrak
dan/atau petunjuk dari Konsultan tanpa tambahan biaya.
4) Jika Kontraktor menolak untuk membongkar atau mengganti, PPK akan
melakukan pembongkaran atas biaya dari Kontraktor.
5) Pekerjaan yang dihasilkan harus sesuai dengan sasaran dan gambar desain
yang telah ditetapkan.
U.12-1
DPP 2012
U.13-1
U.13
SUBMITTAL
1. RUANG LINGKUP
Bagian ini mencakup persyaratan dan prosedur pengajuan dokumen yang diperlukan
selama pelaksanaan pekerjaan berupa jadwal pelaksanaan pekerjaan, ijin
pelaksanaan pekerjaan, material, sub kontraktor, gambar kerja (Shop Drawing),
metoda pelaksanaan pekerjaan, usulan review desain, perubahan pelaksanaan
pekerjaan (variation order) dan gambar pelaksanaan hasil pekerjaan (as built
drawing).
2. PERSYARATAN UMUM
1) Pengajuan submittal harus disertai surat penyampaian, yang berisi:
a. Nomor dan tanggal penyampaian / revisi penyampaian
b. Nama proyek, paket dan bagian pekerjaan
c. Nama Kontraktor, Subkontraktor, dan Pemasok/Supplier
d. Identifikasi dan spesifikasi produk dan material
e. Hal – hal yang diperlukan untuk identifikasi dan konfirmasi yang terkait
pengajuan
2) Dalam setiap pengajuan submittal, Kontraktor dianggap sudah mempelajari,
mengetahui dan memeriksa dokumen kontrak.
3) Pengajuan yang tidak disetujui akan diberikan catatan dan dikembalikan kepada
Kontraktor. Kontraktor harus melakukan perbaikan dan diajukan kembali.
3. JADWAL PELAKSANAAN PEKERJAAN.
1) Kontraktor harus menyampaikan jadwal Pelaksanaan Pekerjaan yang berisi
antara lain uraian item pekerjaan, urutan dan keterkaitan antar bagian pekerjaan,
bobot pekerjaan, bobot rencana mingguan dan bulanan serta mencantumkan
grafik kurva-S.
2) Jadwal pelaksanaan yang telah disetujui akan dijadikan panduan dalam
melakukan evaluasi secara periodik.
4. IJIN PELAKSANAAN PEKERJAAN.
1) Kontraktor harus mengajukan Ijin Pelaksanaan pekerjaan kepada Konsultan
sesuai format yang disediakan Konsultan.
2) Konsultan akan melakukan pengecekan di lapangan sesuai ijin pelaksanaan
yang diajukan.
3) Pada pekerjaan yang bersifat khusus, Kontraktor harus mengajukan metode
kerja dan mempresentasikan kepada PPK dan Konsultan.
DPP 2012
U.13-2
5. MATERIAL
1) Kontraktor harus menyampaikan contoh material/peralatan atau brosur material
yang akan digunakan untuk pekerjaan sesuai dengan gambar dan spesifikasi
teknis dan mendapat persetujuan dari PPK
2) Contoh material harus dalam ukuran dan kuantitas yang cukup untuk dilihat
secara visual, termasuk data lokasi dan teknis produksi dari pemasok.
3) PPK dapat meminta pengujian tambahan dan/atau pemeriksaan laboratorium
atas bahan, material dan/atau produk oleh pihak independen, bila diperlukan.
4) Kontraktor tidak boleh memesan bahan atau memulai pembuatan suatu produk
sebelum pengajuan disetujui dan ditandatangani oleh PPK dengan rekomendasi
Konsultan.
6. SUB KONTRAKTOR
1) Perusahaan Sub Kontraktor harus disetujui oleh PPK.
2) Kontraktor harus mengajukan usulan Sub Kontraktor kepada PPK.
3) PPK dibantu Konsultan melakukan pemeriksaan terhadap kemampuan yang
dimiliki Sub Kontraktor sesuai ketentuan dalam peraturan yang berlaku.
4) Pengajuan usulan harus dilengkapi dengan dokumen yang berisi company
profile, daftar pengalaman, jenis pekerjaan ddan hal – hal lain yang dianggap
perlu untuk penilaian.
7. GAMBAR KERJA (SHOP DRAWING)
1) Sebelum melaksanakan pekerjaan, Kontraktor harus mengajukan Gambar Kerja
(Shop Drawing).
2) Gambar Kerja (Shop Drawing) harus disetujui oleh Kontraktor, Konsultan, dan
PPK.
3) Pengajuan Gambar Kerja harus mengacu kepada gambar rancangan (desain)
dan spesifikasi teknis yang sudah disetujui oleh Direktur Prasarana Ditjen
Perkeretaapian.
4) Dalam melakukan pembuatan gambar kerja, Kontraktor harus melakukan
penelitian terhadap gambar rancangan (desain) yang sudah ditetapkan. Apabila
terjadi perbedaan antara kondisi lapangan dan gambar rancangan (desain) maka
Kontraktor dapat mengajukan usulan perubahan / review desain.
5) Kontraktor dalam melakukan penelitian desain (spesifikasi teknis dan gambar
rancangan) harus berkoordinasi dengan Konsultan Perencana.
6) Untuk mendapatkan hasil kerja yang optimal, Kontraktor diminta selalu
berkoordinasi dengan Konsultan dan pihak terkait.
7) Perhitungan volume untuk semua item pekerjaan mengacu kepada shop-
drawing yang telah disetujui.
8) Gambar kerja dibuat dalam bentuk Hard Copy dan Soft Copy (dalam bentuk
CAD dan PDF File)
DPP 2012
U.13-3
8. METODA PELAKSANAAN PEKERJAAN
Kontraktor harus mengajukan metode kerja dengan memperhatikan hal-hal sebagai
berikut:
1) Lokasi dan aksesibilitas tempat berlangsungnya pekerjaan.
2) Gambar kerja dan persyaratan teknis serta alokasi waktu untuk pekerjaan yang
bersangkutan.
3) Jumlah dan kapasitas sumber daya yang diperlukan untuk pekerjaan yang
bersangkutan.
4) Uraian detail aktifitas pekerjaan dengan mempertimbangkan kendala kondisi
yang ada selama pelaksanaan pekerjaan dalam bentuk gambar skematik,
bagan-alir bagian pekerjaan lain dengan menggunakan software seperti
Microsoft project, Primavera, dan lain – lain.
5) Uraian dan perhitungan struktur pengaman sementara yang diperlukan.
6) Aspek lingkungan dan sosial disekitar lokasi kerja.
7) Pengamanan utilitas dan/atau infrastruktur yang ada disekitar, baik dibawah atau
diatas lokasi kerja.
8) Pengamanan operasi KA.
9. USULAN PERUBAHAN DESAIN (REVIEW DESAIN)
Perubahan gambar rancangan (desain) dan spesifkasi teknis harus mendapat
persetujuan Konsultan dan PPK untuk perubahan kecil (minor). Jika perubahan yang
harus dilakukan besar (major) maka harus mendapat persetujuan Direktur Prasarana
Ditjen Perkeretaapian.
10. PERUBAHAN PEKERJAAN / VARIATION ORDER.
1) Jika ada perubahan pekerjaan Kontraktor harus mengajukan secara tertulis.
2) Pengajuan dilengkapi dengan gambar awal dan gambar perubahan secara detil.
3) Jika ada perubahan biaya dan waktu pelaksanaan yang ditimbulkan akibat
perubahan tersebut, maka perlu dibahas lebih lanjut dengan PPK untuk
memperoleh persetujuan dengan rekomendasi Konsultan.
11. GAMBAR HASIL PELAKSANAAN PEKERJAAN (AS BUILT DRAWING)
1) Kontraktor harus menyampaikan gambar “as-built” pada akhir pelaksanaan
konstruksi untuk mendapat persetujuan dari Konsultan dan PPK.
2) As Built Drawing disampaikan paling lambat 14 (empat belas) hari setelah serah
terima akhir.
3) Kontraktor harus menyampaikan gambar “as built drawing” yang telah disetujui
sebanyak:
 1 (satu) set asli
 5 (lima) set copy dijilid
 Rekaman soft copy dalam CD atau jenis lainnya dalam bentuk CAD dan PDF
file.
DPP 2012
U.16-1
U.14
PEMERIKSAAN DAN PENGUJIAN
1. KETENTUAN UMUM
1) Pengujian sampel di laboratorium harus dilakukan di laboratorium independent
yang telah disetujui oleh PPK / Konsultan.
2) Kontraktor harus melakukan pengujian yang diperlukan untuk menjamin kualitas
yang ditetapkan sesuai arahan Konsultan / PPK.
3) Segala biaya yang timbul akibat pelaksanaan pemeriksaan dan pengujian
ditanggung oleh Kontraktor.
2. PELAKSANAAN PEMERIKSAAN DAN PENGUJIAN
1) Kontraktor wajib memfasilitasi Konsultan dan PPK dalam pelaksanaan
pengujian.
2) Konsultan dan PPK dapat meminta tambahan pengujian jika perlu
3) Hasil pemeriksaan dan pengujian harus didokumentasi
4) Kontraktor harus menyiapkan personil untuk menyaksikan proses pemeriksaan
dan pengujian
5) Kontraktor harus menyiapkan alat uji yang diperlukan.
U
U.14-1U.14-1
U.14-1UU.14-1 U.14-1
U.14-1
DPP 2012
U.16-1
U.15
ORGANISASI PROYEK
1. RUANG LINGKUP
Bagian ini mencakup mengenai susunan organisasi pekerjaan dari mulai PPK,
penyedia jasa dan konsultan pengawas.
2. KUASA PENGGUNA ANGGARAN (KPA)
Pejabat yang ditetapkan oleh PA untuk menggunakan APBN.
3. PEJABAT PEMBUAT KOMITMEN (PPK)
Pejabat yang bertanggung jawab atas pelaksanaan Pengadaan Barang/Jasa.
4. BENDAHARA
Bendahara adalah personil yang bertugas dalam melakukan pembukuan keuangan.
5. SPM
SPM adalah personil yang bertugas melakukan verifikasi dokumen dalam rangka
persetujuan pembayaran.
6. PANITIA PENERIMA HASIL PEKERJAAN
Pejabat yang ditetapkan oleh PA/KPA yang bertugas memeriksa dan menerima hasil
pekerjaan.
7. KONSULTAN
Konsultan merupakan wakil PPK dilapangan yang bertanggung jawab terhadap
segala aktifitas dilapangan serta memberikan dukungan teknis kepada PPK sesuai
dengan bidang keahlian yang dimiliki serta mempunyai keahlian dibidangnya.
8. KONTRAKTOR
Kontraktor adalah suatu badan usaha yang melaksanakan pekerjaan yang
bertanggung jawab segala kegiatan konstruksi dilapangan serta mengkoordinasikan
semua kegiatannya dengan PPK dan Konsultan sehingga mencapai target serta
hasil sesuai dengan kontrak. Selama pekerjaan berlangsung Kontraktor harus
menempatkan perwakilannya dilapangan yang mempunyai hak dan wewenang
penuh terhadap hasil pekerjaan.
U-15-1
DPP 2012
U.16-2
9. STRUKTUR ORGANISASI PELAKSANA KEGIATAN
STRUKTUR ORGANISASI PELAKSANA KEGIATAN
10. STRUKTUR ORGANISASI KONTRAKTOR
1) Kontraktor diharapkan memiliki personil sesuai dengan fungsi – fungsi yang
terlibat dalam struktur organisasi dibawah ini.
2) Site Manager sebagai pengendali di lapangan harus memiliki pengetahuan
tentang manajemen sumber daya, teknis, operasional KA, dan kesehatan dan
keselamatan kerja (K3) serta pengendalian dampak lingkungan.
STRUKTUR ORGANISASI KONTRAKTOR
Tim Konsultan
PENGGUNA ANGGARAN
KONSULTAN MANAJEMEN KONSTRUKSI
PEJABAT PEMBUAT
KOMITMEN
BENDAHARA
& SPM
UNIT LAYANAN
PENGADAAN
PANITIA PENERIMA
HASIL PEKERJAAN
KONTRAKTOR
1
KONSULTAN
SUPERVISI
KONSULTAN
PERENCANA
KONTRAKTOR
3
KONTRAKTOR
2
Tim Pelaksana
Kegiata
n
PROJECT MANAGER
SITE MANAGERADMINISTRASI LOGISTIKKEUANGAN
DESIGN MANAGER TIM QA/QC
U.15-2
DPP 2012
U.16-1
U.16
RAPAT PROYEK
1. RUANG LINGKUP
Bagian ini mencakup persyaratan untuk pertemuan pra-konstruksi, koordinasi rutin
pertemuan dan kemajuan dan distribusi menit dan informasi terkait..
2. PERSYARATAN UMUM
1) Konsultan harus mengadakan Rapat Pra-konstruksi, Rapat Berkala, dan Rapat
Khusus" selama pelaksanaan pekerjaan.
2) Perwakilan kontraktor, subkontraktor dan pemasok harus menghadiri rapat yang
diselenggarakan oleh Konsultan dan PPK.
3) Konsultan adalah pemimpin rapat dan membuat risalah rapat untuk semua
proses yang dijalankan.
4) Hasil rapat harus didistribusikan kepada seluruh stakeholeder.
3. RAPAT PRA-KONSTRUKSI DENGAN AGENDA.
Dalam rapat Pra dibahas hal – hal sekurang – kurangnya:
1) Organisasi kerja
2) Program Kerja
3) Jadwal Pelaksanaan
4) Program Mutu
5) Prosedur pelaksanaan pekerjaan seperti pengajuan submittal, rencana
perubahan ruang lingkup, dan lain – lain.
6) Pelaksanaan Program Kesehatan dan Keselamatan Kerja (K3)
7) Pelaksaan Program Pengendalian Dampak Lingkungan
8) Rencana pelaksanaan pemeriksaan lapangan bersama
4. RAPAT KEMAJUAN PEKERJAAN
1) Jadwal rapat rutin, dan pertemuan untuk kemajuan pekerjaan.
2) Agenda Rapat :
a) Review dan persetujuan risalah rapat sebelumnya.
b) Observasi lapangan, kendala selama pekerjaan.
c) Masalah yang menghambat kemajuan pekerjaan.
d) Peninjauan ke pabrikasi dan jadwal pengiriman.
e) Tindakan korektif dan prosedur yang diperlukan untuk mempertahankan
target yang ditetapkan.
DPP 2012
U.16-2
f) Jadwal pekerjaan yang akan datang.
g) Jadwal Shop Drawing dan tanggal persetujuan.
h) Proposal perubahan untuk penyelesaian pekerjaan.
i) Dan lain – lain yang diperlukan.
DPP 2012
U.17-1
U.17
PELAPORAN
1. LAPORAN HARIAN
Kontraktor harus membuat Laporan Harian yang menggambarkan peristiwa-
peristiwa penting yang berkaitan dengan pekerjaan, jam kerja, jumlah buruh yang
dipekerjakan, waktu operasi peralatan, jam lembur, keterlambatan beserta
penyebabnya, kondisi meteorologi, bahan atau peralatan, kemajuan yang dibuat, dan
petunjuk, pemberitahuan dan rekomendasi yang dibuat oleh Konsultan Pengawas.
Laporan harian harus diajukan dan disetujui oleh Konsultan Pengawas.
2. LAPORAN MINGGUNAN
Kontraktor harus menyampaikan Laporan Mingguan kepada Konsultan pada hari
Selasa setiap minggu. Laporan mingguan ini menggambarkan peristiwa-peristiwa
berkaitan dengan keterlambatan beserta penyebabnya, kemajuan kerja yang dibuat,
jadwal/target satu minggu kedepan beserta perencanaan sumber daya yang akan
digunakan ( tenaga, material dan peralatan )
3. LAPORAN BULANAN
1) Kontraktor harus memberikan Laporan Kemajuan Bulanan kepada Konsultan
paling lambat tanggal 2 setiap bulannya. Laporan bulanan ini
menggambarkan peristiwa-peristiwa berkaitan dengan keterlambatan beserta
penyebabnya, kemajuan kerja yang dibuat, kondisi meteorologi, jadwal/target
satu bulan kedepan beserta perencanaan sumber daya yang akan digunakan
(tenaga, material dan peralatan)
2) Kontraktor harus menyampaikan “Laporan Kemajuan Bulanan” yang sudah
disetujui oleh Konsultan paling lambat tanggal 5 setiap bulannya kepada PPK.
DPP 2012
U.18-1
U.18
SERAH TERIMA HASIL PEKERJAAN
1. PERSIAPAN SERAH TERIMA HASIL PEKERJAAN
Kontraktor harus melakukan persiapan pelaksanaan serah terima hasil pekerjaan,
antara lain:
1) Melakukan pembersihan lapangan.
2) Melakukan pemeriksaan akhir kondisi hasil pelaksanaan pekerjaan.
3) Menyiapkan personil untuk pelaksanaan pemeriksaan dan pengujian.
4) Menyiapkan peralatan yang diperlukan untuk pemeriksaan dan pengujian.
5) Menyiapkan alat uji yang diperlukan untuk pemeriksaan dan pengujian.
6) Menyiapkan dokumen - dokumen untuk proses serah terima hasil pekerjaan
2. KETENTUAN PELAKSANAAN SERAH TERIMA HASIL PEKERJAAN
Ketentuan pelaksanaan serah terima hasil pekerjaan adalah sebagai berikut:
1) Menyampaikan surat permohonan kepada PPK untuk pelaksanaan serah terima
hasil pekerjaan.
2) Menyerahkan garansi pabrikan.
3) Melaksanakan pemeriksaan dan pengujian hasil pelaksanaan pekerjaan dengan
Konsultan dan tim PPK.
4) Menyampaikan pedoman pemeliharaan (maintenance manual).
5) Penyerahan pekerjaan terakhir hanya dapat dilaksanakan apabila seluruh
pekerjaan telah dapat berfungsi secara baik dan dapat diterima oleh PPK.
DPP 2012
U.19-1
U.19
MASA PEMELIHARAAN
1. RUANG LINGKUP
Masa Pemeliharaan adalah masa tanggung jawab perbaikan atas cacat atau rusak
hasil pekerjaan yang telah dilaksanakan dalam periode pemeliharaan yang telah
ditetapkan.
2. MASA PEMELIHARAAN
1) Masa Pemeliharaan adalah sesuai yang tercantum dalam dokumen kontrak.
mulai dari tanggal Sertifikat Penyelesaian Pekerjaan (ST 1)/PHO.
2) Sebelum akhir masa pemeliharaan berakhir Kontraktor harus mengajukan surat
permohonan pemeriksaan lapangan kepada PPK (Pejabat Pembuat Komitmen).
3) Setelah dilakukan evaluasi dan disimpulkan bahwa hasil pekerjaan dalam
kondisi baik maka PPK akan mengeluarkan Sertifikat Serah Terima Kedua (ST
2)/FHO.
3. KETENTUAN PELAKSANAAN PEMELIHARAAN
1) Kontraktor harus melakukan pemeriksaan secara rutin untuk menjaga kondisi
hasil pekerjaan tetap baik selama masa pemeliharaan.
2) Kontraktor harus membuat laporan bulanan hasil pemeriksaan rutin selama
masa pemeliharaan.
3) Setiap pelaksanaan pekerjaan di lapangan dalam rangka perbaikan hasil
pekerjaan harus diinformasikan kepada PPK.
4) Kontraktor harus memperbaiki hasil pekerjaan yang mengalami cacat atau rusak
selama masa pemeliharaan.
5) Biaya timbul akibat pelaksanaan perbaikan pekerjaan menjadi tanggung jawab
Kontraktor.

More Related Content

What's hot

Ustek pengawasan batu bolong
Ustek pengawasan batu bolongUstek pengawasan batu bolong
Ustek pengawasan batu bolong
Wong_Cosmic
 
Permen PUPR 26 2014 tentang Prosedur Operasional Standar Pengelolaan Sistem A...
Permen PUPR 26 2014 tentang Prosedur Operasional Standar Pengelolaan Sistem A...Permen PUPR 26 2014 tentang Prosedur Operasional Standar Pengelolaan Sistem A...
Permen PUPR 26 2014 tentang Prosedur Operasional Standar Pengelolaan Sistem A...
infosanitasi
 
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
Bintek
 

What's hot (20)

Ustek pengawasan batu bolong
Ustek pengawasan batu bolongUstek pengawasan batu bolong
Ustek pengawasan batu bolong
 
Permen PUPR 26 2014 tentang Prosedur Operasional Standar Pengelolaan Sistem A...
Permen PUPR 26 2014 tentang Prosedur Operasional Standar Pengelolaan Sistem A...Permen PUPR 26 2014 tentang Prosedur Operasional Standar Pengelolaan Sistem A...
Permen PUPR 26 2014 tentang Prosedur Operasional Standar Pengelolaan Sistem A...
 
PCM Contoh Paparan Presentasi.ppt
PCM Contoh Paparan Presentasi.pptPCM Contoh Paparan Presentasi.ppt
PCM Contoh Paparan Presentasi.ppt
 
Pengawasan proyek
Pengawasan proyekPengawasan proyek
Pengawasan proyek
 
Pondasi bendungan
Pondasi bendunganPondasi bendungan
Pondasi bendungan
 
Metode pelaksanaan jaringan irigasi
Metode pelaksanaan jaringan irigasiMetode pelaksanaan jaringan irigasi
Metode pelaksanaan jaringan irigasi
 
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
 
Analisa harga satuan jasa
Analisa harga satuan jasaAnalisa harga satuan jasa
Analisa harga satuan jasa
 
Rekomendasi Teknis Bidang Sumber Daya Air
Rekomendasi Teknis Bidang Sumber Daya AirRekomendasi Teknis Bidang Sumber Daya Air
Rekomendasi Teknis Bidang Sumber Daya Air
 
Metode pelaksanaan mep
Metode pelaksanaan mepMetode pelaksanaan mep
Metode pelaksanaan mep
 
Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...
Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...
Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...
 
1556525088perencanaan jembatan
1556525088perencanaan jembatan1556525088perencanaan jembatan
1556525088perencanaan jembatan
 
Stp drawing diagram & specs
Stp drawing diagram & specsStp drawing diagram & specs
Stp drawing diagram & specs
 
laporan-pendahhuluan-k-pdf.pdf
laporan-pendahhuluan-k-pdf.pdflaporan-pendahhuluan-k-pdf.pdf
laporan-pendahhuluan-k-pdf.pdf
 
Prinsip reschedule
Prinsip reschedule Prinsip reschedule
Prinsip reschedule
 
CONTOH LAPORAN KONSULTAN PENGAWAS
CONTOH LAPORAN KONSULTAN PENGAWASCONTOH LAPORAN KONSULTAN PENGAWAS
CONTOH LAPORAN KONSULTAN PENGAWAS
 
Metode pelaksanaan
Metode pelaksanaanMetode pelaksanaan
Metode pelaksanaan
 
PPT Perencanaan Waduk
PPT Perencanaan WadukPPT Perencanaan Waduk
PPT Perencanaan Waduk
 
Laporan Akhir Pengendalian Banjir.pdf
Laporan Akhir Pengendalian Banjir.pdfLaporan Akhir Pengendalian Banjir.pdf
Laporan Akhir Pengendalian Banjir.pdf
 
Itp & ceklist kolom erlangga 22160008
Itp & ceklist kolom erlangga 22160008Itp & ceklist kolom erlangga 22160008
Itp & ceklist kolom erlangga 22160008
 

Similar to 1. standar spesifikasi_teknis_umum

Manual Pesain Perkerasan
Manual Pesain PerkerasanManual Pesain Perkerasan
Manual Pesain Perkerasan
WSKT
 
191113081241HZFRIOOY_03.RKS MEP KANTOR JASA RAHARJA SULTENG.pdf
191113081241HZFRIOOY_03.RKS MEP KANTOR JASA RAHARJA SULTENG.pdf191113081241HZFRIOOY_03.RKS MEP KANTOR JASA RAHARJA SULTENG.pdf
191113081241HZFRIOOY_03.RKS MEP KANTOR JASA RAHARJA SULTENG.pdf
AbuVulkanikAlJawiy
 
MDP Perencanaan dispora22.pdf
MDP Perencanaan dispora22.pdfMDP Perencanaan dispora22.pdf
MDP Perencanaan dispora22.pdf
irsanto2
 
Rsni t 02-2005
Rsni t 02-2005Rsni t 02-2005
Rsni t 02-2005
iky
 
2002 12 sni 03-2847-2002 (beton)
2002 12 sni 03-2847-2002 (beton)2002 12 sni 03-2847-2002 (beton)
2002 12 sni 03-2847-2002 (beton)
franst
 
119599434 juknis-pelaksanaan-air-bersih
119599434 juknis-pelaksanaan-air-bersih119599434 juknis-pelaksanaan-air-bersih
119599434 juknis-pelaksanaan-air-bersih
Yudirwan Tanjung
 

Similar to 1. standar spesifikasi_teknis_umum (20)

Bag i-manual-desain-perkerasan
Bag i-manual-desain-perkerasanBag i-manual-desain-perkerasan
Bag i-manual-desain-perkerasan
 
Manual Pesain Perkerasan
Manual Pesain PerkerasanManual Pesain Perkerasan
Manual Pesain Perkerasan
 
Manual Desain Perkerasan Jalan - Baru (2012)
Manual Desain Perkerasan Jalan - Baru (2012)Manual Desain Perkerasan Jalan - Baru (2012)
Manual Desain Perkerasan Jalan - Baru (2012)
 
191113081241HZFRIOOY_03.RKS MEP KANTOR JASA RAHARJA SULTENG.pdf
191113081241HZFRIOOY_03.RKS MEP KANTOR JASA RAHARJA SULTENG.pdf191113081241HZFRIOOY_03.RKS MEP KANTOR JASA RAHARJA SULTENG.pdf
191113081241HZFRIOOY_03.RKS MEP KANTOR JASA RAHARJA SULTENG.pdf
 
Regulasi BRI Liga 1
Regulasi BRI Liga 1Regulasi BRI Liga 1
Regulasi BRI Liga 1
 
MDP Perencanaan dispora22.pdf
MDP Perencanaan dispora22.pdfMDP Perencanaan dispora22.pdf
MDP Perencanaan dispora22.pdf
 
Kirim Final revisi 520 Catu daya.pdf
Kirim Final revisi 520 Catu daya.pdfKirim Final revisi 520 Catu daya.pdf
Kirim Final revisi 520 Catu daya.pdf
 
Perencanaan teknis drainase_lingkungan_k
Perencanaan teknis drainase_lingkungan_kPerencanaan teknis drainase_lingkungan_k
Perencanaan teknis drainase_lingkungan_k
 
LEMBAR_KERJA_PESERTA_DIDIK_LKPD_TEKNIK_S.pdf
LEMBAR_KERJA_PESERTA_DIDIK_LKPD_TEKNIK_S.pdfLEMBAR_KERJA_PESERTA_DIDIK_LKPD_TEKNIK_S.pdf
LEMBAR_KERJA_PESERTA_DIDIK_LKPD_TEKNIK_S.pdf
 
Laporan Pendahuluan
Laporan Pendahuluan Laporan Pendahuluan
Laporan Pendahuluan
 
Standar perencanaan struktur baja untuk jembatan
Standar perencanaan struktur baja untuk jembatanStandar perencanaan struktur baja untuk jembatan
Standar perencanaan struktur baja untuk jembatan
 
Tesis Kebutuhan Perlengkapan Jalan
Tesis Kebutuhan Perlengkapan JalanTesis Kebutuhan Perlengkapan Jalan
Tesis Kebutuhan Perlengkapan Jalan
 
Rsni t 02-2005
Rsni t 02-2005Rsni t 02-2005
Rsni t 02-2005
 
2002 12 sni 03-2847-2002 (beton)
2002 12 sni 03-2847-2002 (beton)2002 12 sni 03-2847-2002 (beton)
2002 12 sni 03-2847-2002 (beton)
 
2002 12 sni 03-2847-2002 (beton) 2
2002 12 sni 03-2847-2002 (beton) 22002 12 sni 03-2847-2002 (beton) 2
2002 12 sni 03-2847-2002 (beton) 2
 
119599434 juknis-pelaksanaan-air-bersih
119599434 juknis-pelaksanaan-air-bersih119599434 juknis-pelaksanaan-air-bersih
119599434 juknis-pelaksanaan-air-bersih
 
Pedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air Minum
Pedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air MinumPedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air Minum
Pedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air Minum
 
Rencana Detail Tata Ruang Wilayah Kota
Rencana Detail Tata Ruang Wilayah KotaRencana Detail Tata Ruang Wilayah Kota
Rencana Detail Tata Ruang Wilayah Kota
 
SDP Genset
SDP GensetSDP Genset
SDP Genset
 
Dokumen lelang
Dokumen lelangDokumen lelang
Dokumen lelang
 

Recently uploaded (9)

10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt
 
MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++
 
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdfTEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
 
Strategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di IndonesiaStrategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di Indonesia
 
MODUL AJAR PENGANTAR SURVEY PEMETAAN.pdf
MODUL AJAR PENGANTAR SURVEY PEMETAAN.pdfMODUL AJAR PENGANTAR SURVEY PEMETAAN.pdf
MODUL AJAR PENGANTAR SURVEY PEMETAAN.pdf
 
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptxMateri Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
 
Manual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptxManual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptx
 
Metode numerik Bidang Teknik Sipil perencanaan.pdf
Metode numerik Bidang Teknik Sipil perencanaan.pdfMetode numerik Bidang Teknik Sipil perencanaan.pdf
Metode numerik Bidang Teknik Sipil perencanaan.pdf
 
4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf
4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf
4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf
 

1. standar spesifikasi_teknis_umum

  • 1. DPP 2012 STANDAR SPESIFIKASI TEKNIS KONSTRUKSI JALAN REL, SIPIL, JEMBATAN DAN BANGUNAN KERETA API DIREKTORAT PRASARANA PERKERETAAPIAN DIREKTORAT JENDERAL PERKERETAAPIAN KEMENTERIAN PERHUBUNGAN
  • 2. DPP 2012 DAFTAR ISI BAB 1. UMUM S.1. Peraturan – Peraturan..................................................................................... U.1-1 S.2. Definisi ............................................................................................................ U.2-1 S.3. Mobilisasi dan Demobilisasi ............................................................................ U.3-1 S.4. Survei ............................................................................................................. U.4-1 S.5. Ruang kerja..................................................................................................... U.5-1 S.6. Window Time .................................................................................................. U.6-1 S.7. Direksi Keet dan Gudang ............................................................................... U.7-1 S.8. Fasilitas Operasional Kerja.............................................................................. U.8-1 S.9. Pembersihan Lokasi Kerja............................................................................... U.9-1 S.10. Kesehatan dan Keselamatan Kerja (K3).......................................................... U.10-1 S.11. Dampak Lingkungan ....................................................................................... U.11-1 S.12. Jaminan dan Pengendalian Mutu .................................................................... U.12-1 S.13. Submittal......................................................................................................... U.13-1 S.14. Pemeriksaan dan Pengujian............................................................................ U.14-1 S.15. Organisasi Proyek........................................................................................... U.15-1 S.16. Rapat Proyek .................................................................................................. U.16-1 S.17. Pelaporan........................................................................................................ U.17-1 S.18. Serah Terima Pekerjaan.................................................................................. U.18-1 S.19. Masa Pemeliharaan ........................................................................................ U.19-1 BAB 2. SIPIL S.1. Pekerjaan Pembongkaran............................................................................... S.1-1 S.2. Pembersihan Lahan ....................................................................................... S.2-1 S.3. Galian Umum ................................................................................................. S.3-1 S.4. Galian pada Tanah Keras/Batuan .................................................................. S.4-1 S.5. Galian untuk Bangunan Struktur...................................................................... S.5-1 S.6. Timbunan dengan Material Tanah Pilihan ...................................................... S.6-1 S.7. Timbunan di Belakang Bangunan Struktur ..................................................... S.7-1 S.8. Timbunan dengan Material Berbutir................................................................. S.8-1 S.9. Perbaikan Tanah Dasar dengan Material berbutir dan Geotekstile.................. S.9-1 S.10. Pemasangan Geotekstile sebagai Separator................................................... S.10-1 S.11. Perbaikan Tanah Dasar dengan Kapur .......................................................... S.11-1 S.12. Dinding Penahan Tanah dengan Pasangan Batu Kali .................................... S.12-1 S.13. Dinding Penahan Tanah dengan Pasangan Beton Bertulang ......................... S.13-1 S.14. Dinding Penahan tanah dengan Pasangan Batu ............................................ S.14-1 S.15. Saluran Air Pracetak ...................................................................................... S.15-1 S.16. Pasangan Batu Kosong dan Bronjong............................................................. S.16-1 S.17. Drainase Memanjang dan Melintang .............................................................. S.17-1 S.18. Gebalan Rumput ............................................................................................ S.18-1 S.19. Perlintasan Umum........................................................................................... S.19-1 S.20. Pekerjaan Perkerasan Jalan ........................................................................... S.20-1
  • 3. DPP 2012 S.21. Pekerjaan Pemagaran dengan Beton ............................................................. S.21-1 S.22. Pagar Besi Hias .............................................................................................. S.23-1 BAB 3. TRACK T.1. Pengadaan Rel .............................................................................................. T.1-1 T.2. Pengadaan Wesel dan Pemasangan ............................................................. T.2-1 T.3. Pengadaan Sistem Penambat ........................................................................ T.3-1 T.4. Pengadaan Pelat Sambung ............................................................................ T.4-1 T.5. IRJ .................................................................................................................. T.5-1 T.6. Bantalan Beton dan Sistem Penambat ........................................................... T.6-1 T.7. Bantalan Kayu ................................................................................................ T.7-1 T.8. Pengadaan dan Pengelasan Rel .................................................................... T.8-1 T.9. Kompromis Rel................................................................................................ T.9-1 T.10. Pengadaan Balas, Pengiriman dan Pengecekan ............................................ T.10-1 T.11. Pemasangan Track dan Pemecokan Awal ...................................................... T.11-1 T.12. Pemasangan Track pada Jembatan Tanpa Balas .......................................... T.12-1 T.13. Pengangkatan dan Listringan dan Pemecokan .............................................. T.13-1 T.14. Penggeseran Horisontal Track ....................................................................... T.14-1 T.15. Pekerjaan Bongkar Wesel .............................................................................. T.15-1 T.16. Blok Penahan (Sepur Badug) ......................................................................... T.16-1 T.17. Tamping dan Finishing dengan Mesin MTT .................................................... T.17-1 T.18. Pemasangan Rambu - Rambu ....................................................................... T.18-1 BAB 4. JEMBATAN DAN BOX CULVERT J.1. Beton Struktur ................................................................................................. J.1-1 J.2. Beton Pratekan ............................................................................................... J.2-1 J.3. Baja Tulangan................................................................................................. J.3-1 J.4. Baja Struktur ................................................................................................... J.4-1 J.5. Pelaksanaan Perakitan ................................................................................... J.5-1 J.6. Pondasi Tiang Bor (Bored Pile) ....................................................................... J.6-1 J.7. Tiang Pancang ................................................................................................ J.7-1 J.8. Struktur Pangkal dan Pilar............................................................................... J.8-1 J.9. Andas Jembatan ............................................................................................. J.9-1 J.10. Railing Besi (Hand Rail) .................................................................................. J.10-1 J.11. Sheetpile Beton............................................................................................... J.11-1 J.12. Sheetpile Baja................................................................................................. J.12-1 BAB 5. BANGUNAN GEDUNG G.1. Pekerjaan Pondasi .......................................................................................... G.1-1 G.2. Pekerjaan Konstruksi Baja .............................................................................. G.2-1 G.3. Pekerjaan Logam ............................................................................................ G.3-1 G.4. Pekerjaan Pasangan Batu - Bata .................................................................... G.4-1 G.5. Pekerjaan Plesteran/Acian Dinding ................................................................. G.5-1 G.6. Pekerjaan Dinding Keramik ............................................................................. G.6-1 G.7. Pekerjaan Alumunium Panel ........................................................................... G.7-1
  • 4. DPP 2012 G.8. Pekerjaan Lantai Keramik ............................................................................... G.8-1 G.9. Pekerjaan Lantai Granite/Tile .......................................................................... G.9-1 G.10. Pekerjaan Paving Blok .................................................................................... G.10-1 G.11. Pekerjaan Water Proofing ............................................................................... G.11-1 G.12. Pekerjaan Kusen Aluminium ........................................................................... G.12-1 G.13. Pekerjaan Kayu............................................................................................... G.13-1 G.14. Pekerjaan Kaca............................................................................................... G.14-1 G.15. Pekerjaan Alat Penggantung dan Pengunci .................................................... G.15-1 G.16. Pekerjaan Langit-Langit Gypsum Board.......................................................... G.16-1 G.17. Pekerjaan Pengecatan .................................................................................... G.17-1 G.18. Pekerjaan Sanitair........................................................................................... G.18-1 G.19. Pekerjaan Atap Lembaran Baja Gelombang.................................................... G.19-1 G.20. Pekerjaan Railing Besi .................................................................................... G.20-1 G.21. Pekerjaan Silicone Sealant.............................................................................. G.21-1 G.22. Pekerjaan Sistem Elektrikal............................................................................. G.22-1 G.23. Pekerjaan Sistem Mekanikal ........................................................................... G.23-1
  • 6. DPP 2012 U.1-1 U.1 PERATURAN – PERATURAN 1. PERATURAN-PERATURAN YANG TERKAIT Dibawah ini adalah peraturan – peraturan yang dijadikan Pedoman dalam pelaksanaan pekerjaan dalam penyusunan spesifikasi teknis apabila terdapat perbedaan antara peraturan – peraturan dibawah ini dan spesifikasi teknis, maka yang berlaku adalah sesuai yang tercantum dalam spesifikasi teknis ini:  Standar Nasional Indonesia (SNI)  Peraturan Menteri Perhubungan No 28 Tahun 2011 tentang Persyaratan Teknis Jalur KA  PD 10 (Peraturan Dinas)  Hasil konsensus nasional rancangan SNI 1995, mengenai penambat elastis (clip, insulator, alas rel dan shoulder)  Peraturan Beton Bertulang Indonesia 1971  Tata Cara Perhitungan Struktur Beton Untuk Bangunan Gedung (SKSNI T-15- 1991-03);  Peraturan Bahan Jalan Rel Indonesia (draft)  Peraturan Pelaksanaan Pembangunan Jalan Rel (draft)  Peraturan setempat yang berlaku  Peraturan tenaga kerja/hukum perburuhan yang berlaku  Peraturan-peraturan lain yang berlaku Standard pelaksanaan yang dikeluarkan oleh industri-industri bahan bangunan yang dipakai di kegiatan ini.
  • 7. DPP 2012 U.2-1 U.2 DEFINISI ISTILAH DEFINISI A : Ampere AASHTO : American Association of State Highway and Transportation Officials ACI : American Concrete Institute ANSI : American National Standard Institute ASTM : American Society for Testing and Material AREA : American Railway Engineering Association AWS : American Welding Society BS : `British Standards JIS : Japanese Industrial Standards CBR : California Bearing Ratio UIC : International Union of Railways Technical Specification SNI : Standar Nasional Indonesia PBI : Peraturan Beton Indonesia Satker : Satuan Kerja Konsultan : Penyedia Jasa Pengawasan Konsultan Perencana : Penyedia Jasa Perencanaan Konsultan MK : Penyedia Jasa Manajemen Konstruksi Kontraktor : Penyedia Jasa Konstruksi HB : Brinell Hardness
  • 8. DPP 2012 U.3-1 U.3 MOBILISASI DAN DEMOBILISASI 1. RUANG LINGKUP Pekerjaan ini meliputi pekerjaan pengiriman dan penarikan kembali semua sumber daya, tenaga kerja, bahan, peralatan, perlengkapan, dan lain lain untuk mendukung kegiatan pelaksanaan pekerjaan. 2. MOBILISASI 2.1 Mobilisasi terdiri dari pekerjaan persiapan dan pelaksanaan, termasuk, tapi tidak terbatas pada kebutuhan-kebutuhan untuk mobilisasi personil, peralatan, pemasokan, dan suplemen lainnya yang diperlukan ke lokasi proyek, untuk pembangunan kantor, gudang dan fasilitas lainnya yang diperlukan untuk bekerja di proyek, dan untuk seluruh pekerjaan dan operasi lainnya yang harus dilakukan atau biaya yang diperlukan sebelum mulainya berbagai item pekerjaan kontrak di lokasi proyek. 2.2 Mobilisasi adalah pengiriman ke lokasi pekerjaan sumber daya yang dibutuhkan untuk pelaksanaan pekerjaan. 2.3 Mobilisasi dianggap selesai bila Kontraktor dapat melaksanakan dan diterima oleh Konsultan mengenai pemenuhan masing-masing persyaratan yang terkait yang disebutkan dalam kontrak. 3. DEMOBILISASI 3.1 Demobilisasi mencakup penyiapan pengajuan yang diperlukan sebelum pengakhiran pekerjaan.Demobilisasi adalah penarikan kembali dari lokasi pekerjaan sumber daya yang dibutuhkan untuk pelaksanaan pekerjaan. 3.2 Demobilisasi akan dianggap selesai jika seluruh peralatan, bahan, personil, atau lainnya milik kontraktor telah dikeluarkan dari lokasi proyek, dan persyaratan – persyaratan penyelesaian pekerjaan sebagaimana diatur dalam kontrak telah terpenuhi.
  • 9. DPP 2012 U.4-1 U.4 SURVEI 1. RUANG LINGKUP Pekerjaan ini meliputi survei penelitian hasil desain konstruksi, survei topografi, survei utilitas, penyelidikan tanah, survei hidrologi dan hidrolika, dan lain - lain yang dibutuhkan untuk mendukung pelaksanaan pekerjaan. 2. SURVEI PENELITIAN HASIL DESAIN KONSTRUKSI 1) Sebelum pekerjaan dimulai, Kontraktor wajib melakukan penelitian terhadap desain konstruksi yang terdapat dalam Kontrak. 2) Bila terdapat hal-hal yang meragukan dalam desain konstruksi, Kontraktor harus berkoordinasi dengan Konsultan Perencana, Konnsultan dan PPK. 3) Perbaikan terhadap desain (review design) diusulkan oleh Kontraktor kepada PPK untuk mendapat persetujuan. 3. SURVEI TOPOGRAFI 1) Kontraktor harus mengadakan pengukuran-pengukuran serta pemasangan patok-patok yang diperlukan untuk pekerjaan pembangunan dan bertanggung jawab penuh atas kebenaran dan ketepatan pengukuran tersebut sehingga dapat dijadikan benchmark sebagai titik acuan elevasi dan posisi bangunan. Patok-patok serta tanda patok harus dijaga sedemikian rupa sehingga kedudukannya tetap serta tidak terganggu selama pekerjaan berlangsung. 2) Kesalahan-kesalahan yang terjadi sebagai akibat kelalaian di dalam menentukan ukuran selama pelaksanaan menjadi tanggung jawab Kontraktor sepenuhnya. Oleh karena itu sebelum pelaksanaan dimulai Kontraktor diwajibkan mengadakan pemeriksaan menyeluruh terhadap gambar-gambar dan ketentuan yang ada. 4. SURVEI UTILITAS 1) Kontraktor sebelum melaksanakan pekerjaan harus melakukan survei utilitas yang berada di lokasi pekerjaan. 2) Kontraktor sebelum melaksanakan pekerjaan harus berkoordinasi dengan PT.KAI untuk mengetahui kondisi utilitas yang ada di lokasi pekerjaan. 3) Hasil survei harus dibuat dokumentasi yang baik sebagai alat kerja.
  • 10. DPP 2012 U.4-2 5. PENYELIDIKAN TANAH 1) Kontraktor sebelum melaksanakan pekerjaan harus melakukan penelitian terhadap hasil penyelidikan tanah yang digunakan dalam proses desain. 2) Jika terdapat hal – hal yang belum diperhitungkan atau meragukan, Kontraktor dapat melakukan penyelidikan tanah tambahan. 3) Dalam melakukan penyelidikan tanah, Kontraktor harus mendapat persetujuan Konsultan dan PPK. 6. SURVEI HIDROLOGI DAN HIDROLIKA Kontraktor harus melakukan survei hidrologi dan hidrolika untuk memastikan bahwa akibat yang ditimbulkan selama pelaksanaan pekerjaan tidak menimbulkan dampak negatif seperti banjir, penyumbatan, dan lain – lain.
  • 11. DPP 2012 U.5-1 U.5 RUANG KERJA 1. RUANG KERJA (RIGHT OF WAY) 1) Ruang kerja akan menjadi lahan sementara atau permanen untuk melaksanakan pekerjaan. Konsultan harus menentukan lebar efektif dan batas-batas ruang kerja. 2) Kontraktor harus memperhatikan ruang kerja sebagaimana ditetapkan oleh Konsultan. 3) Kontraktor bertanggung jawab untuk menyediakan ruang kerja tambahan yang diperlukan untuk penyimpanan material, peralatan, dan lain – lain atas biaya sendiri. 2. PERIJINAN 1) Setiap perijinan yang dibutuhkan untuk memindahkan material dan peralatan menjadi tanggung jawab Kontraktor. 2) Kontraktor akan melakukan survei untuk mengetahui kondisi - kondisi dan kesulitan yang mungkin ditemui dalam pengangkutan material, pengangkutan peralatan, dan lain – lain. 3) Kontraktor harus menentukan jalan akses untuk mengangkut material, peralatan, dan lain - lain. 3. PEMBERSIHAN LOKASI KERJA 1) Wilayah kerja harus dipelihara secara tertib dan bebas dari hambatan untuk memberikan kondisi terbaik yang mungkin untuk berbagai operasi dan instalasi yang diperlukan. 2) Limbah dan puing-puing harus dihilangkan dari lokasi kerja.
  • 12. DPP 2012 U.6-1 U.6 WINDOW TIME 1. RUANG LINGKUP Bagian ini mengatur penggunaan waktu untuk pelaksanaan pekerjaan terutama pekerjaan yang berpengaruh bagi operasi kereta api. 2. RENCANA KERJA PELAKSANAAN DI LAPANGAN 1) Sebelum pelaksanaan pekerjaan, Kontraktor harus menyiapkan dan menyampaikan Rencana Kerja kepada Konsultan. 2) Didalam rencana kerja harus tercantum mengenai program keselamatan yang akan dilaksanakan oleh Kontraktor. 3) Kontraktor dan PPK serta Konsultan harus berkoordinasi dengan PT.KAI sebelum melaksanakan pekerjaannya di track existing. 4) Pelaksanaan pekerjaan yang terletak di lokasi ruang manfaat jalan KA harus berkoordinasi secara intensif kepada PT.KAI. 3. WINDOW TIME 1) Window Time adalah waktu yang digunakan diluar jam operasional kereta api. 2) Pekerjaan – pekerjaan yang telah diidentifikasi memerlukan window time adalah sebagai berikut:  Pergeseran Track (Track shifting)  Peninggian Track (Track raising)  Penyambungan Track (Connecting of track)  Pemasangan Wesel (Setting of turnouts)  Pembangunan Platform dan Sistem Drainase (Construction of new platform and drainage system)  Perlintasan Sebidang (Level crossing)  Pekerjaan yang menyangkut perbaikan “Track Existing”  Pekerjaan jembatan  Relokasi dan Proteksi Utilitas (Relocation and protection of Utilities) 3) Kontraktor dalam melaksanakan pekerjaan yang memerlukan window time harus menyampaikan rencana kerja dan kebutuhan waktu pekerjaan serta berkoordinasi dengan Operator Prasarana untuk memperkirakan waktu yang dibutuhkan. 4. PEMBATASAN KECEPATAN OPERASI KA Kontraktor dan PPK / Konsultan harus berkoordinasi dengan PT.KAI untuk pelaksanaan pembatasan kecepatan Kereta Api untuk menjaga operasi Kereta Api yang aman selama pelaksanaan kegiatan konstruksi sesuai hasil pembahasan Rencana Kerja.
  • 13. DPP 2012 U.7-1 U.7 DIREKSI KEET DAN GUDANG 1. RUANG LINGKUP Pekerjaan ini meliputi pembuatan Direksi Keet dan Gudang yang digunakan untuk tempat pertemuan dan penyimpanan barang – barang sementara di lapangan. 2. PERSYARATAN TEKNIS 2.1. MATERIAL 1) Direksi keet dibuat dengan rangka kayu kelas III, dengan triplek tebal lebih besar/sama dengan 4 mm, atap seng gelombang BJLS 25, lantai plesteran dengan campuran 1 PC : 5 PC, tebal = 10 cm, kaca nako, daun pintu dari triplek, dicat. 2) Di Direksi keet harus dilengkapi dengan : No Item Volume 1 Papan Nama 1 bh 2 Meja 1 bh 3 Kursi 4 bh 4 Kalender 1 bh 5 Kotak Obat 1 set 6 Papan Tulis/White Board 1 bh 7 Papan Informasi 1 bh 8 Papan untuk menempel Gambar Kerja 1 bh 3) Setelah pekerjaan selesai, lokasi yang digunakan sebagai Direksi Keet dan Gudang harus dibongkar dan dibersihkan.
  • 14. DPP 2012 U8 -1 U.8 FASILITAS OPERASIONAL 1. RUANG LINGKUP Fasilitas operasional kerja yang perlu dilengkapi oleh Kontraktor antara lain seperti alat komunikasi, operasional kantor kontraktor, listrik/penerangan, dan lain – lain sesuai kebutuhan di lapangan. 2. ALAT KOMUNIKASI 1) Kontraktor harus menyediakan peralatan komunikasi berupa HT dilengkapi dengan RIG (bila perlu) yang diperlukan untuk komunikasi pemantauan operasi KA pada saat bekerja dijalur atau dalam batas operasi KA. 2) Jika penguat/booster diperlukan, antena booster harus disediakan untuk menjamin komunikasi yang baik/lancar antara alat komunikasi didalam seluruh area pekerjaan, termasuk ke stasiun terdekat. 3. LISTRIK DAN PENERANGAN 1) Menyediakan dan memelihara semua penerangan sementara dan tenaga listrik sementara yang diperlukan untuk konstruksi. 2) Menyediakan koneksi ke semua peralatan konstruksi yang memerlukan tenaga listrik. 3) Menyediakan dan memelihara tenaga listrik sementara untuk peralatan mekanik permanen memerlukan layanan tenaga listrik sampai tenaga listrik tetap dapat digunakan. 4) Menyediakan penerangan lapangan sementara untuk keamanan sesuai dengan arahan PPK / Konsultan. 5) Menyediakan grounding untuk semua perangkat sesuai standar yang berlaku. 6) menyediakan semua item yang diperlukan untuk penerangan. 7) Menyediakan dan menjaga semua peralatan layanan sementara sampai kerja permanen terinstal dan diaktifkan. 8) Kesalahan-kesalahan yang terjadi sebagai akibat kelalaian di dalam penyediaan, penggunaan dan perawatan peralatan akibat dari tenaga listrik selama proses pelaksanaan pekerjaan menjadi tanggung jawab Kontraktor sepenuhnya. Oleh karena itu sebelum pelaksanaan dimulai Kontraktor diwajibkan mengadakan pemeriksaan menyeluruh terhadap syarat dan ketentuan yang ada. 4. TELEPON SEMENTARA Kontraktor akan menyediakan layanan telepon sementara selama konstruksi untuk kelancaran komunikasi.
  • 15. DPP 2012 U8 -2 5. PETUNJUK PANGGILAN DARURAT Kontraktor harus menyediakan daftar lokasi terdekat dan bekerja sama dengan instansi terkait seperti polisi, rumah sakit atau pelayanan kesehatan di Direksi Keet, untuk mengantisipasi apabila terjadi keadaan darurat.
  • 16. DPP 2012 U.9-1 U.9 PEMBERSIHAN LOKASI KERJA 1) Selama proyek berlangsung, Kontraktor harus menjaga kebersihan dan mengatur lokasi bahan bangunan dan alat kerja serta daerah kerja sehingga kelancaran pelaksanaan pekerjaan tidak terlambat karenanya. 2) Pembersihan tumbuh-tumbuhan yang ada pada lokasi peruntukan kerja sesuai petunjuk Gambar Kerja dan Pengawas Lapangan. 3) Sesudah proyek selesai dan sebelum melakukan penyerahan pekerjaan kepada pemilik proyek, Kontraktor harus membersihkan seluruh daerah kerja dari segala macam peralatan tersebut, sisa-sisa bahan bangunan, bekas bongkaran dan bangunan-bangunan sementara, termasuk pengangkutannya tanpa tambahan biaya.
  • 17. DPP 2012 U.10-1 U.10 KESEHATAN DAN KESELAMATAN KERJA (K3) 1. RUANG LINGKUP Bagian ini mengatur mengenai pelaksanaan program Kesehatan dan Keselamatan Kerja (K3) dalam pelaksanaan pekerjaan. 2. PEDOMAN DAN STANDAR 1) Undang-undang No. 1 tahun 1970 tentang Keselamatan Kerja 2) Keputusan Menteri Tenaga Kerja R.I. No. Kep. 1135/MEN/1987 tentang Bendera Keselamatan Dan Kesehatan Kerja 3) Keputusan Menteri Tenaga Kerja R.I. No.: Kep.245/MEN/1990 tentang Hari Keselamatan Dan Kesehatan Kerja Nasional 4) Peraturan Menteri Tenaga Kerja R.I. No. Per.05/MEN/1996 tentang Sistem Manajemen Keselamatan dan Kesehatan Kerja 3. KESELAMATAN KERJA 1) Dari permulaan hingga penyelesaian pekerjaan dan selama masa pemeliharaan, Kontraktor bertanggung jawab atas keselamatan dan keamanan pekerja, material dan peralatan teknis serta konstruksi. 2) Kontraktor wajib menjaga keselamatan kerja di ruang kerja dengan melengkapi dengan perlengkapan keselamatan kerja seperti safety line, rambu – rambu, papan promosi keselamatan, dan lain – lain. 3) Kontraktor wajib menjamin keselamatan tenaga kerja yang terlibat dalam pelaksanaan pekerjaan dari segala kemungkinan yang terjadi dengan memenuhi aturan dan ketentuan kesehatan dan keselamatan kerja yang berlaku (Jamsostek). 4) Kontraktor diwajibkan menyediakan obat-obatan menurut syarat-syarat Pertolongan Pertama Pada Kecelakaan (PPPK) yang selalu dalam keadaan siap digunakan di lapangan, untuk mengatasi segala kemungkinan musibah bagi semua petugas dari pekerja lapangan. 5) Setiap pekerja diwajibkan menggunakan sepatu pada waktu bekerja dan di lokasi harus disediakan Alat Pelindung Diri (APD) berupa safety belt, safety helmet, masker/kedok las terutama untuk dipakai pada pekerjaan pemasangan kuda-kuda baja dan pekerjaan yang beresiko tertimpa benda keras. 6) Kontraktor wajib menyediakan air bersih, kamar mandi dan WC yang layak dan bersih bagi semua petugas dan pekerja. Membuat tempat penginapan di lapangan pekerjaan untuk para pekerja tidak diperkenankan, kecuali atas ijin PPK. 7) Apabila terjadi kecelakaan, Kontraktor segera mungkin memberitahukan kepada Konsultan dan mengambil tindakan yang perlu untuk keselamatan korban- korban kecelakaan itu.
  • 18. DPP 2012 U.10-2 4. PROSEDUR OPERASI STANDAR (SOP) KESEHATAN DAN KESELAMATAN KERJA (K3) 1) Kontraktor harus membuat SOP Kesehatan dan Keselamatan Kerja (K3). 2) SOP diajukan kepada Konsultan untuk dievaluasi. 3) Kontraktor harus menyampaikan laporan pelaksanaan SOP kepada Direktur Keselamtan, Ditjen Perkeretaapian, Direktur Prasarana Ditjen Perkeretaapian, PPK, dan Konsultan.
  • 19. DPP 2012 U.13-1 U.11 DAMPAK LINGKUNGAN 1. PERTIMBANGAN LINGKUNGAN 1) Kontraktor akan membangun fasilitas, sehingga tidak satu pun pekerjaan mempunyai dampak merugikan pada lingkungan, komunitas serta fasilitas kereta api yang berdekatan. 2) Pertimbangan harus dilakukan sebagai berikut tetapi tidak terbatas pada: a) Penggunaan bahan bakar ramah lingkungan untuk meminimalkan emisi polusi udara b) Pengendalian sulfur dioksida dan polutan udara lainnya c) Pemisahan air limbah industri dan kota d) Reklamasi air limbah e) Pemulihan dan daur ulang bahan-bahan yang sesuai f) Pengendalian kebisingan kendaraan g) Pengendalian kebisingan dari industri dan fasilitas komersial h) Batasan getaran i) Pelestarian tanah alam sedapat mungkin. j) Pelestarian situs arkeologi 2. PERLINDUNGAN LINGKUNGAN 1) Kontraktor harus menyadari dan mengikuti praktek-praktek perlindungan lingkungan dan prosedur sebagaimana ditetapkan oleh otoritas dan instansi terkait yang relevan. 2) Lanau dan lumpur yang diklasifikasikan sebagai limbah bahan tidak boleh dibuang langsung ke perairan dekat pantai. Bahan ini akan dibuang di TPA yang disetujui. 3) Limbah / sisa material dengan klasifikasi berbahan kimia berbahaya atau tidak berbahaya akan dibuang dan/atau disimpan di TPA yang disetujui. 4) Tidak ada pembayaran terpisah akan dibuat untuk perlindungan lingkungan hidup tetapi semua biaya yang daripadanya akan dimasukkan dalam harga kontrak dibayarkan item. 3. PENGENDALIAN DAMPAK LINGKUNGAN 1) Kontraktor wajib mengikuti ketentuan yang ada dalam usaha pelaksanaan pengendalian lingkungan. 2) Dampak lingkungan yang perlu diperhatikan antara lain:  Banjir  Longsor  Debu  Suara U.11-1
  • 20. DPP 2012 U.13-1 U.12 JAMINAN DAN PENGENDALIAN MUTU 1. RUANG LINGKUP Bagian ini mencakup persyaratan untuk jaminan dan pengendalian mutu produk, hasil kerja, dan penyiapan sertifikat pemenuhan persyaratan. 2. PERSYARATAN UMUM 1) Material dan peralatan yang digunakan dalam pekerjaan harus memenuhi persyaratan yang berlaku dalam hal ukuran, pembuatan, jenis dan kualitas yang ditentukan, kecuali secara spesifik ditentukan bebas dari persyaratan. 2) Konsultan dan PPK mempunyai hak untuk menolak material atau cara dan hasil kerja yang tidak sesuai dengan persyaratan, pada setiap saat. 3) Kontraktor harus membongkar pekerjaan yang tidak diterima atau ditolak oleh Konsultan dan PPK dan mengerjakan kembali sesuai persyaratan kontrak dan/atau petunjuk dari Konsultan tanpa tambahan biaya. 4) Jika Kontraktor menolak untuk membongkar atau mengganti, PPK akan melakukan pembongkaran atas biaya dari Kontraktor. 5) Pekerjaan yang dihasilkan harus sesuai dengan sasaran dan gambar desain yang telah ditetapkan. U.12-1
  • 21. DPP 2012 U.13-1 U.13 SUBMITTAL 1. RUANG LINGKUP Bagian ini mencakup persyaratan dan prosedur pengajuan dokumen yang diperlukan selama pelaksanaan pekerjaan berupa jadwal pelaksanaan pekerjaan, ijin pelaksanaan pekerjaan, material, sub kontraktor, gambar kerja (Shop Drawing), metoda pelaksanaan pekerjaan, usulan review desain, perubahan pelaksanaan pekerjaan (variation order) dan gambar pelaksanaan hasil pekerjaan (as built drawing). 2. PERSYARATAN UMUM 1) Pengajuan submittal harus disertai surat penyampaian, yang berisi: a. Nomor dan tanggal penyampaian / revisi penyampaian b. Nama proyek, paket dan bagian pekerjaan c. Nama Kontraktor, Subkontraktor, dan Pemasok/Supplier d. Identifikasi dan spesifikasi produk dan material e. Hal – hal yang diperlukan untuk identifikasi dan konfirmasi yang terkait pengajuan 2) Dalam setiap pengajuan submittal, Kontraktor dianggap sudah mempelajari, mengetahui dan memeriksa dokumen kontrak. 3) Pengajuan yang tidak disetujui akan diberikan catatan dan dikembalikan kepada Kontraktor. Kontraktor harus melakukan perbaikan dan diajukan kembali. 3. JADWAL PELAKSANAAN PEKERJAAN. 1) Kontraktor harus menyampaikan jadwal Pelaksanaan Pekerjaan yang berisi antara lain uraian item pekerjaan, urutan dan keterkaitan antar bagian pekerjaan, bobot pekerjaan, bobot rencana mingguan dan bulanan serta mencantumkan grafik kurva-S. 2) Jadwal pelaksanaan yang telah disetujui akan dijadikan panduan dalam melakukan evaluasi secara periodik. 4. IJIN PELAKSANAAN PEKERJAAN. 1) Kontraktor harus mengajukan Ijin Pelaksanaan pekerjaan kepada Konsultan sesuai format yang disediakan Konsultan. 2) Konsultan akan melakukan pengecekan di lapangan sesuai ijin pelaksanaan yang diajukan. 3) Pada pekerjaan yang bersifat khusus, Kontraktor harus mengajukan metode kerja dan mempresentasikan kepada PPK dan Konsultan.
  • 22. DPP 2012 U.13-2 5. MATERIAL 1) Kontraktor harus menyampaikan contoh material/peralatan atau brosur material yang akan digunakan untuk pekerjaan sesuai dengan gambar dan spesifikasi teknis dan mendapat persetujuan dari PPK 2) Contoh material harus dalam ukuran dan kuantitas yang cukup untuk dilihat secara visual, termasuk data lokasi dan teknis produksi dari pemasok. 3) PPK dapat meminta pengujian tambahan dan/atau pemeriksaan laboratorium atas bahan, material dan/atau produk oleh pihak independen, bila diperlukan. 4) Kontraktor tidak boleh memesan bahan atau memulai pembuatan suatu produk sebelum pengajuan disetujui dan ditandatangani oleh PPK dengan rekomendasi Konsultan. 6. SUB KONTRAKTOR 1) Perusahaan Sub Kontraktor harus disetujui oleh PPK. 2) Kontraktor harus mengajukan usulan Sub Kontraktor kepada PPK. 3) PPK dibantu Konsultan melakukan pemeriksaan terhadap kemampuan yang dimiliki Sub Kontraktor sesuai ketentuan dalam peraturan yang berlaku. 4) Pengajuan usulan harus dilengkapi dengan dokumen yang berisi company profile, daftar pengalaman, jenis pekerjaan ddan hal – hal lain yang dianggap perlu untuk penilaian. 7. GAMBAR KERJA (SHOP DRAWING) 1) Sebelum melaksanakan pekerjaan, Kontraktor harus mengajukan Gambar Kerja (Shop Drawing). 2) Gambar Kerja (Shop Drawing) harus disetujui oleh Kontraktor, Konsultan, dan PPK. 3) Pengajuan Gambar Kerja harus mengacu kepada gambar rancangan (desain) dan spesifikasi teknis yang sudah disetujui oleh Direktur Prasarana Ditjen Perkeretaapian. 4) Dalam melakukan pembuatan gambar kerja, Kontraktor harus melakukan penelitian terhadap gambar rancangan (desain) yang sudah ditetapkan. Apabila terjadi perbedaan antara kondisi lapangan dan gambar rancangan (desain) maka Kontraktor dapat mengajukan usulan perubahan / review desain. 5) Kontraktor dalam melakukan penelitian desain (spesifikasi teknis dan gambar rancangan) harus berkoordinasi dengan Konsultan Perencana. 6) Untuk mendapatkan hasil kerja yang optimal, Kontraktor diminta selalu berkoordinasi dengan Konsultan dan pihak terkait. 7) Perhitungan volume untuk semua item pekerjaan mengacu kepada shop- drawing yang telah disetujui. 8) Gambar kerja dibuat dalam bentuk Hard Copy dan Soft Copy (dalam bentuk CAD dan PDF File)
  • 23. DPP 2012 U.13-3 8. METODA PELAKSANAAN PEKERJAAN Kontraktor harus mengajukan metode kerja dengan memperhatikan hal-hal sebagai berikut: 1) Lokasi dan aksesibilitas tempat berlangsungnya pekerjaan. 2) Gambar kerja dan persyaratan teknis serta alokasi waktu untuk pekerjaan yang bersangkutan. 3) Jumlah dan kapasitas sumber daya yang diperlukan untuk pekerjaan yang bersangkutan. 4) Uraian detail aktifitas pekerjaan dengan mempertimbangkan kendala kondisi yang ada selama pelaksanaan pekerjaan dalam bentuk gambar skematik, bagan-alir bagian pekerjaan lain dengan menggunakan software seperti Microsoft project, Primavera, dan lain – lain. 5) Uraian dan perhitungan struktur pengaman sementara yang diperlukan. 6) Aspek lingkungan dan sosial disekitar lokasi kerja. 7) Pengamanan utilitas dan/atau infrastruktur yang ada disekitar, baik dibawah atau diatas lokasi kerja. 8) Pengamanan operasi KA. 9. USULAN PERUBAHAN DESAIN (REVIEW DESAIN) Perubahan gambar rancangan (desain) dan spesifkasi teknis harus mendapat persetujuan Konsultan dan PPK untuk perubahan kecil (minor). Jika perubahan yang harus dilakukan besar (major) maka harus mendapat persetujuan Direktur Prasarana Ditjen Perkeretaapian. 10. PERUBAHAN PEKERJAAN / VARIATION ORDER. 1) Jika ada perubahan pekerjaan Kontraktor harus mengajukan secara tertulis. 2) Pengajuan dilengkapi dengan gambar awal dan gambar perubahan secara detil. 3) Jika ada perubahan biaya dan waktu pelaksanaan yang ditimbulkan akibat perubahan tersebut, maka perlu dibahas lebih lanjut dengan PPK untuk memperoleh persetujuan dengan rekomendasi Konsultan. 11. GAMBAR HASIL PELAKSANAAN PEKERJAAN (AS BUILT DRAWING) 1) Kontraktor harus menyampaikan gambar “as-built” pada akhir pelaksanaan konstruksi untuk mendapat persetujuan dari Konsultan dan PPK. 2) As Built Drawing disampaikan paling lambat 14 (empat belas) hari setelah serah terima akhir. 3) Kontraktor harus menyampaikan gambar “as built drawing” yang telah disetujui sebanyak:  1 (satu) set asli  5 (lima) set copy dijilid  Rekaman soft copy dalam CD atau jenis lainnya dalam bentuk CAD dan PDF file.
  • 24. DPP 2012 U.16-1 U.14 PEMERIKSAAN DAN PENGUJIAN 1. KETENTUAN UMUM 1) Pengujian sampel di laboratorium harus dilakukan di laboratorium independent yang telah disetujui oleh PPK / Konsultan. 2) Kontraktor harus melakukan pengujian yang diperlukan untuk menjamin kualitas yang ditetapkan sesuai arahan Konsultan / PPK. 3) Segala biaya yang timbul akibat pelaksanaan pemeriksaan dan pengujian ditanggung oleh Kontraktor. 2. PELAKSANAAN PEMERIKSAAN DAN PENGUJIAN 1) Kontraktor wajib memfasilitasi Konsultan dan PPK dalam pelaksanaan pengujian. 2) Konsultan dan PPK dapat meminta tambahan pengujian jika perlu 3) Hasil pemeriksaan dan pengujian harus didokumentasi 4) Kontraktor harus menyiapkan personil untuk menyaksikan proses pemeriksaan dan pengujian 5) Kontraktor harus menyiapkan alat uji yang diperlukan. U U.14-1U.14-1 U.14-1UU.14-1 U.14-1 U.14-1
  • 25. DPP 2012 U.16-1 U.15 ORGANISASI PROYEK 1. RUANG LINGKUP Bagian ini mencakup mengenai susunan organisasi pekerjaan dari mulai PPK, penyedia jasa dan konsultan pengawas. 2. KUASA PENGGUNA ANGGARAN (KPA) Pejabat yang ditetapkan oleh PA untuk menggunakan APBN. 3. PEJABAT PEMBUAT KOMITMEN (PPK) Pejabat yang bertanggung jawab atas pelaksanaan Pengadaan Barang/Jasa. 4. BENDAHARA Bendahara adalah personil yang bertugas dalam melakukan pembukuan keuangan. 5. SPM SPM adalah personil yang bertugas melakukan verifikasi dokumen dalam rangka persetujuan pembayaran. 6. PANITIA PENERIMA HASIL PEKERJAAN Pejabat yang ditetapkan oleh PA/KPA yang bertugas memeriksa dan menerima hasil pekerjaan. 7. KONSULTAN Konsultan merupakan wakil PPK dilapangan yang bertanggung jawab terhadap segala aktifitas dilapangan serta memberikan dukungan teknis kepada PPK sesuai dengan bidang keahlian yang dimiliki serta mempunyai keahlian dibidangnya. 8. KONTRAKTOR Kontraktor adalah suatu badan usaha yang melaksanakan pekerjaan yang bertanggung jawab segala kegiatan konstruksi dilapangan serta mengkoordinasikan semua kegiatannya dengan PPK dan Konsultan sehingga mencapai target serta hasil sesuai dengan kontrak. Selama pekerjaan berlangsung Kontraktor harus menempatkan perwakilannya dilapangan yang mempunyai hak dan wewenang penuh terhadap hasil pekerjaan. U-15-1
  • 26. DPP 2012 U.16-2 9. STRUKTUR ORGANISASI PELAKSANA KEGIATAN STRUKTUR ORGANISASI PELAKSANA KEGIATAN 10. STRUKTUR ORGANISASI KONTRAKTOR 1) Kontraktor diharapkan memiliki personil sesuai dengan fungsi – fungsi yang terlibat dalam struktur organisasi dibawah ini. 2) Site Manager sebagai pengendali di lapangan harus memiliki pengetahuan tentang manajemen sumber daya, teknis, operasional KA, dan kesehatan dan keselamatan kerja (K3) serta pengendalian dampak lingkungan. STRUKTUR ORGANISASI KONTRAKTOR Tim Konsultan PENGGUNA ANGGARAN KONSULTAN MANAJEMEN KONSTRUKSI PEJABAT PEMBUAT KOMITMEN BENDAHARA & SPM UNIT LAYANAN PENGADAAN PANITIA PENERIMA HASIL PEKERJAAN KONTRAKTOR 1 KONSULTAN SUPERVISI KONSULTAN PERENCANA KONTRAKTOR 3 KONTRAKTOR 2 Tim Pelaksana Kegiata n PROJECT MANAGER SITE MANAGERADMINISTRASI LOGISTIKKEUANGAN DESIGN MANAGER TIM QA/QC U.15-2
  • 27. DPP 2012 U.16-1 U.16 RAPAT PROYEK 1. RUANG LINGKUP Bagian ini mencakup persyaratan untuk pertemuan pra-konstruksi, koordinasi rutin pertemuan dan kemajuan dan distribusi menit dan informasi terkait.. 2. PERSYARATAN UMUM 1) Konsultan harus mengadakan Rapat Pra-konstruksi, Rapat Berkala, dan Rapat Khusus" selama pelaksanaan pekerjaan. 2) Perwakilan kontraktor, subkontraktor dan pemasok harus menghadiri rapat yang diselenggarakan oleh Konsultan dan PPK. 3) Konsultan adalah pemimpin rapat dan membuat risalah rapat untuk semua proses yang dijalankan. 4) Hasil rapat harus didistribusikan kepada seluruh stakeholeder. 3. RAPAT PRA-KONSTRUKSI DENGAN AGENDA. Dalam rapat Pra dibahas hal – hal sekurang – kurangnya: 1) Organisasi kerja 2) Program Kerja 3) Jadwal Pelaksanaan 4) Program Mutu 5) Prosedur pelaksanaan pekerjaan seperti pengajuan submittal, rencana perubahan ruang lingkup, dan lain – lain. 6) Pelaksanaan Program Kesehatan dan Keselamatan Kerja (K3) 7) Pelaksaan Program Pengendalian Dampak Lingkungan 8) Rencana pelaksanaan pemeriksaan lapangan bersama 4. RAPAT KEMAJUAN PEKERJAAN 1) Jadwal rapat rutin, dan pertemuan untuk kemajuan pekerjaan. 2) Agenda Rapat : a) Review dan persetujuan risalah rapat sebelumnya. b) Observasi lapangan, kendala selama pekerjaan. c) Masalah yang menghambat kemajuan pekerjaan. d) Peninjauan ke pabrikasi dan jadwal pengiriman. e) Tindakan korektif dan prosedur yang diperlukan untuk mempertahankan target yang ditetapkan.
  • 28. DPP 2012 U.16-2 f) Jadwal pekerjaan yang akan datang. g) Jadwal Shop Drawing dan tanggal persetujuan. h) Proposal perubahan untuk penyelesaian pekerjaan. i) Dan lain – lain yang diperlukan.
  • 29. DPP 2012 U.17-1 U.17 PELAPORAN 1. LAPORAN HARIAN Kontraktor harus membuat Laporan Harian yang menggambarkan peristiwa- peristiwa penting yang berkaitan dengan pekerjaan, jam kerja, jumlah buruh yang dipekerjakan, waktu operasi peralatan, jam lembur, keterlambatan beserta penyebabnya, kondisi meteorologi, bahan atau peralatan, kemajuan yang dibuat, dan petunjuk, pemberitahuan dan rekomendasi yang dibuat oleh Konsultan Pengawas. Laporan harian harus diajukan dan disetujui oleh Konsultan Pengawas. 2. LAPORAN MINGGUNAN Kontraktor harus menyampaikan Laporan Mingguan kepada Konsultan pada hari Selasa setiap minggu. Laporan mingguan ini menggambarkan peristiwa-peristiwa berkaitan dengan keterlambatan beserta penyebabnya, kemajuan kerja yang dibuat, jadwal/target satu minggu kedepan beserta perencanaan sumber daya yang akan digunakan ( tenaga, material dan peralatan ) 3. LAPORAN BULANAN 1) Kontraktor harus memberikan Laporan Kemajuan Bulanan kepada Konsultan paling lambat tanggal 2 setiap bulannya. Laporan bulanan ini menggambarkan peristiwa-peristiwa berkaitan dengan keterlambatan beserta penyebabnya, kemajuan kerja yang dibuat, kondisi meteorologi, jadwal/target satu bulan kedepan beserta perencanaan sumber daya yang akan digunakan (tenaga, material dan peralatan) 2) Kontraktor harus menyampaikan “Laporan Kemajuan Bulanan” yang sudah disetujui oleh Konsultan paling lambat tanggal 5 setiap bulannya kepada PPK.
  • 30. DPP 2012 U.18-1 U.18 SERAH TERIMA HASIL PEKERJAAN 1. PERSIAPAN SERAH TERIMA HASIL PEKERJAAN Kontraktor harus melakukan persiapan pelaksanaan serah terima hasil pekerjaan, antara lain: 1) Melakukan pembersihan lapangan. 2) Melakukan pemeriksaan akhir kondisi hasil pelaksanaan pekerjaan. 3) Menyiapkan personil untuk pelaksanaan pemeriksaan dan pengujian. 4) Menyiapkan peralatan yang diperlukan untuk pemeriksaan dan pengujian. 5) Menyiapkan alat uji yang diperlukan untuk pemeriksaan dan pengujian. 6) Menyiapkan dokumen - dokumen untuk proses serah terima hasil pekerjaan 2. KETENTUAN PELAKSANAAN SERAH TERIMA HASIL PEKERJAAN Ketentuan pelaksanaan serah terima hasil pekerjaan adalah sebagai berikut: 1) Menyampaikan surat permohonan kepada PPK untuk pelaksanaan serah terima hasil pekerjaan. 2) Menyerahkan garansi pabrikan. 3) Melaksanakan pemeriksaan dan pengujian hasil pelaksanaan pekerjaan dengan Konsultan dan tim PPK. 4) Menyampaikan pedoman pemeliharaan (maintenance manual). 5) Penyerahan pekerjaan terakhir hanya dapat dilaksanakan apabila seluruh pekerjaan telah dapat berfungsi secara baik dan dapat diterima oleh PPK.
  • 31. DPP 2012 U.19-1 U.19 MASA PEMELIHARAAN 1. RUANG LINGKUP Masa Pemeliharaan adalah masa tanggung jawab perbaikan atas cacat atau rusak hasil pekerjaan yang telah dilaksanakan dalam periode pemeliharaan yang telah ditetapkan. 2. MASA PEMELIHARAAN 1) Masa Pemeliharaan adalah sesuai yang tercantum dalam dokumen kontrak. mulai dari tanggal Sertifikat Penyelesaian Pekerjaan (ST 1)/PHO. 2) Sebelum akhir masa pemeliharaan berakhir Kontraktor harus mengajukan surat permohonan pemeriksaan lapangan kepada PPK (Pejabat Pembuat Komitmen). 3) Setelah dilakukan evaluasi dan disimpulkan bahwa hasil pekerjaan dalam kondisi baik maka PPK akan mengeluarkan Sertifikat Serah Terima Kedua (ST 2)/FHO. 3. KETENTUAN PELAKSANAAN PEMELIHARAAN 1) Kontraktor harus melakukan pemeriksaan secara rutin untuk menjaga kondisi hasil pekerjaan tetap baik selama masa pemeliharaan. 2) Kontraktor harus membuat laporan bulanan hasil pemeriksaan rutin selama masa pemeliharaan. 3) Setiap pelaksanaan pekerjaan di lapangan dalam rangka perbaikan hasil pekerjaan harus diinformasikan kepada PPK. 4) Kontraktor harus memperbaiki hasil pekerjaan yang mengalami cacat atau rusak selama masa pemeliharaan. 5) Biaya timbul akibat pelaksanaan perbaikan pekerjaan menjadi tanggung jawab Kontraktor.