SlideShare a Scribd company logo
1 of 4
Download to read offline
ISSN 2349-7815
International Journal of Recent Research in Electrical and Electronics Engineering (IJRREEE)
Vol. 3, Issue 1, pp: (62-65), Month: January - March 2016, Available at: www.paperpublications.org
Page | 62
Paper Publications
Technical Aspects of EHV XLPE Cable End
Termination and on Site Brief Procedure
1
Sachin Kumar Gupta, 2
Arun Pachori
1
PG student, 2
Associate Professor, Dept of EE, Government Engineering College, Jabalpur, India
Abstract: The objective of this paper is to provide an source of information on EHV XLPE cable end termination
processes. It also describes the brief procedure of 220 KV XLPE single core (1 1200 Cu corrugated Al sheath)
cable termination at 400 KV GSS Heerapura (Rajasthan Vidyut Prasaran Nigam Ltd) Jaipur (Raj) India. The
realization of high density power transmission in major city areas requires the effective utilization of limited
underground space available so the different versions of the termination are designed for operation under severe
outdoor conditions and operation voltage up to 550 KV.
Keywords: XLPE CABLE, END TERMINATION, INSULATOR, CORE, OUTDOOR.
1. INTRODUCTION
The development of high voltage XLPE system goes back to the 1960’s since then production and material technology
have improved significantly providing reliable maintenance free products to utility industry. The different version of the
terminations are designed for operation under severe outdoor conditions and operation voltage up to 550 KV. The
terminations can also be used indoor where appropriate space is provided. Standard versions are designed for pollution
level III or IV for use in higher polluted areas insulators with longer creepage distance are used.
Outdoor termination with porcelain insulator (1a):
This termination type covers the full range from 72.5 KV to 420 KV. It is used for gas pressure cable, oil filled cable and
for XLPE cable. It is in use for many years and has the longest and satisfactory service history. The insulator may be in
brown or grey colour protective spark gaps are as an option.
1a 1b 1c
ISSN 2349-7815
International Journal of Recent Research in Electrical and Electronics Engineering (IJRREEE)
Vol. 3, Issue 1, pp: (62-65), Month: January - March 2016, Available at: www.paperpublications.org
Page | 63
Paper Publications
Outdoor termination with composite insulator (1b):
This termination type is for XLPE cable. The basic design is identical with that of the porcelain termination. The
composite insulator, however, is of much lower weight. This is advantageous with respect to lifting equipment needed for
installation and also for supporting constructions.
Dry type outdoor termination (1c):
The dry type termination for XLPE cable is completely free from any liquid or gaseous filling medium. Apart from the
environmental aspect, the dry design provides further advantages like easier installation and no need for filling equipment,
both contributing to significant savings for installation of the terminations.
2. OUTDOOR TERMINATION PROCESS OF 220 KV XLPE CABLE 1 1200 CU CORRUGATED
AL SHEATH
220 KV single circuit of 1200 sq mm 220 KV single core XLPE cable is established between 400 KV substation
Heerapura to 220 KV GIS substation Nala Power House Jaipur (appox 10 km) against specification No RVPN/ EHV/ TN-
278. General instruction preparatory works, Dimensions used, fitting procedure are strictly as per site work. During the
work relevant security and accident rules must be obeyed. The cable laying must be finished, the cable end is properly
sealed and for the proposed cable position the admissible bending radii must be taken into consideration during work.
Starting from the upper surface of the termination frame, mark the reference line on the outer plastic cable sheath. Mark
from the reference line the cutting position (over length=insulator length +900 mm) on the cable. Adjust the cable end in
straight jointing position and fix it. Remove the plastic cable sheath and corrugated aluminum sheath.
Taking into consideration the working length of the used round peeling device and an additional length of 10 mm for the
grinding process apply a mark with insulating tape on the insulation screen in direction to the cable so that the cable core
can be peeled with the peeling device to the transition D1/cone. The knife must be adjusted step by step so that the
insulation screen is completely removed. When grinding with emery the diameter of the cable core is reduced by approx
0.3 mm. The transition spot from D1 to D2 must be marked. The peeling process is to be carried out as described under
size D1 ,whereby the knife must be adjusted step by step so that diameter D2 as correlated to the stress cone is reached.
The transition from D1 to D2 elaborated conically by means of a rasp and abrasive cloth.
Make a cone for pushing over the stress cone at the end of the cable core. The prepared cable core may not show any
unclean areas like coarse, abrasion channels or marks of the rasp. Longitudinal variations at the end of the insulation
screen must be checked. The max. Allowed length is W=15mm. Apply one layer of semi conducting tape from the
corrugated aluminum sheath to the semi conducting layer of the cable. Wrap a centre lapping of self amalgamating tape
on the corrugated aluminium sheath and on the cable core. Push the cable gland including sealing ring over the cable core.
Push over the base plate with the pedestal insulators over the cable core fix them to the termination frame.
ISSN 2349-7815
International Journal of Recent Research in Electrical and Electronics Engineering (IJRREEE)
Vol. 3, Issue 1, pp: (62-65), Month: January - March 2016, Available at: www.paperpublications.org
Page | 64
Paper Publications
Clean the cable core and the stress cone inner bore, cover the stress cone inner bore and the surface of the cable core with
filling oil very well. Push the stress cone over the cable core up to the marked position by hand. Wash off the remainder
of the lubricant from stress cone and cable core.
Wrap one layer of semi conducting tape with 50% overlapping, copper woven fabric tape and self-amalgamating tape
from the tube of the sealing flange to the stress cone.
Cut the cable core exactly vertical at the cutting position (insulator length +3 mm). Push the mechanical connector on the
conductor up to the insulation and fix all screw by hand. Clean the base plate, the stress cone, the core and the insulator
carefully. Insert the sealing ring on the base plate. Push on the insulator and allow it to stand on the base plate. Screw the
insulator to the base plate and the aluminum top plate. Take care that no dirt can get into the open termination. Fit a stud
to the can and pour the oil into the insulator up to the oil level. The air chamber over the filling height, allow heat
expansion of the oil. Push the spacers over the conductor terminal bolt. Insert the sealing ring in the groove of the
conductor terminal. Screw the top nut on the bolt. Fit the cable gland and heat shrinkable sleeve.
ISSN 2349-7815
International Journal of Recent Research in Electrical and Electronics Engineering (IJRREEE)
Vol. 3, Issue 1, pp: (62-65), Month: January - March 2016, Available at: www.paperpublications.org
Page | 65
Paper Publications
3. CONCLUSION
The outdoor terminal should be suitable for heavily polluted atmospheric conditions with total creep age distance of 31
mm/KV and protected creep age distance of not more than 50% of the total creep age distance. The cable end terminals
for terminating the cable shall be fully compatible with the cable. Above termination is antifog, pre fabricated type based
on the EPR-based stress relief cone with an epoxy housing or pre-moulded type silicon based stress relief cone. The
termination base plate and the cable’s metallic sheath shall be electrically insulated from the supporting structure.
REFERENCES
[1] W. Weissenberg, U. Rengel, R. Scherer, “EHV XLPE Cable Systems up to 400 kV – More than 10 Years Field
Experience,” CIGRE 2004, paper B1-102, 2004.
[2] Ruben Vogelsang, Oldrich Sekula, Herbert Nyffenegger, & Werner Weissenberg, “Long-term experiences with
XLPE cable systems up to 550 kV,” CIGRE SC B1, 2009.
[3] R. V. Olshausen, & W. Weissenberg, “The electrical long-term performance of cross- linked polyethylene,” 30
WIRE 5/2001.
[4] W. Weissenberg, M. Kuschel, “Test methods for Silicone Rubber accessories used in high voltage cables up to 400
kV,” 6th Jicable, Paris, 2003.
[5] CIGRÉ Tech. Brochure # 379, “Update of service experience of HV underground & submarine cable systems,”
2009.
[6] J.-O. Boström, A. Campus, R. N. Hamton, & E. Marsden, “Reliable HV & EHV XLPE cables,” CIGRE, Paper 21-
105, 2002.
[7] HIGH VOLTAGE XLPE CABLE SYSTEMS Technical User Guide BRUGG CABLES E-Highway2050 WP3
workshop April 15th, 2014 Brussels.
[8] Underground Cable: an innovative and reliable Technology nkt cables.
[9] High voltage underground and subsea cable technology options for future transmission in Europe Ernesto Zaccone,
Chairman Europe a cable High Voltage Systems Group.
[10] LONG-LIFE XLPE INSULATED POWER CABLE jicable 07 Nigel HAMPTON, NEETRAC, Georgia Tech, USA,
Rick HARTLEIN, NEETRAC, Georgia Tech, USA, Hakan LENNARTSSON, Borouge Pty, Hong Kong, Harry
ORTON, OCEI, Vancouver, BC, Canada, h.Ram RAMACHANDRAN,The Dow Chemical Company, NJ, USA,
[11] D.H.Kim and E.J.Park,“An investigation of influence of semiconductive electrode materials in breakdown and
charge International Journal of Scientific Engineering and Technology (ISSN : 2277-1581) www.ijset.com, Volume
No.1, Issue No.2 pg:65-70 01 April 2012 accumulation in XLPE,” in Proc. IEEE Conf. Elect. Insulation
Dielect.Phenomena, Atlanta, GA, 1998, pp. 546–549.
[12] M.S.Mashikan, J.H. Groeger, S.J. Dale and E. Ildstad, “Role of semi conductive compounds in the premature aging
of XLPE cable insulation,” in Conf. record IEEE Int. Symp.n Elect. Insulation, Bos- ton,MA, June 5–8, 1988, pp.
314–320.
[13] Feasibility and technical aspects of partial undergrounding of extra high voltage power transmission lines Brussels,
December 2010 europa cables.

More Related Content

What's hot

400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...Thorne & Derrick International
 
Power cable technology in cesc ltd
Power cable technology in cesc ltdPower cable technology in cesc ltd
Power cable technology in cesc ltdAritra Sarkar
 
Performance of 400 kv line insulators under pollution.
Performance of 400 kv line insulators under pollution.Performance of 400 kv line insulators under pollution.
Performance of 400 kv line insulators under pollution.Ankit Sisodiya
 
High voltage cable insulation systems
High voltage cable insulation systemsHigh voltage cable insulation systems
High voltage cable insulation systemsSanket Tambakhe
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission lineFazlur Rahman
 
Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143sanjeet kumar
 
Basic Difference Between Wires and Cables
Basic Difference Between Wires and CablesBasic Difference Between Wires and Cables
Basic Difference Between Wires and CablesDr.Raja R
 
Underground cables
Underground cablesUnderground cables
Underground cablesAnu71
 
Transmission line insulators
Transmission line insulatorsTransmission line insulators
Transmission line insulatorsPrashant Sharma
 

What's hot (20)

Sheath bonding method for underground cables
Sheath bonding method for underground cablesSheath bonding method for underground cables
Sheath bonding method for underground cables
 
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
 
Types of cables
Types of cablesTypes of cables
Types of cables
 
Power cable technology in cesc ltd
Power cable technology in cesc ltdPower cable technology in cesc ltd
Power cable technology in cesc ltd
 
Performance of 400 kv line insulators under pollution.
Performance of 400 kv line insulators under pollution.Performance of 400 kv line insulators under pollution.
Performance of 400 kv line insulators under pollution.
 
High voltage underground cables
High voltage underground cablesHigh voltage underground cables
High voltage underground cables
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Tempsens- cable and wires
Tempsens- cable and wiresTempsens- cable and wires
Tempsens- cable and wires
 
Ug cables
Ug cablesUg cables
Ug cables
 
High voltage cable insulation systems
High voltage cable insulation systemsHigh voltage cable insulation systems
High voltage cable insulation systems
 
Under ground Cables
Under ground Cables Under ground Cables
Under ground Cables
 
Cable
CableCable
Cable
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 
Low tension power cable
Low tension power cableLow tension power cable
Low tension power cable
 
Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143
 
Basic Difference Between Wires and Cables
Basic Difference Between Wires and CablesBasic Difference Between Wires and Cables
Basic Difference Between Wires and Cables
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Transmission line insulators
Transmission line insulatorsTransmission line insulators
Transmission line insulators
 
Types of wires and cables
Types of wires and cablesTypes of wires and cables
Types of wires and cables
 
Basics of Wires and Cables
Basics of Wires and CablesBasics of Wires and Cables
Basics of Wires and Cables
 

Viewers also liked

Power Quality Improvement of DC Drive by Reduction of Circulating Current
Power Quality Improvement of DC Drive by Reduction of Circulating CurrentPower Quality Improvement of DC Drive by Reduction of Circulating Current
Power Quality Improvement of DC Drive by Reduction of Circulating Currentpaperpublications3
 
Non-Contact Temperature Measurement System Based on Embedded
Non-Contact Temperature Measurement System Based on EmbeddedNon-Contact Temperature Measurement System Based on Embedded
Non-Contact Temperature Measurement System Based on Embeddedpaperpublications3
 
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...paperpublications3
 
Green Buildings Overview and Analysis of Energy Efficient Building
Green Buildings Overview and Analysis of Energy Efficient BuildingGreen Buildings Overview and Analysis of Energy Efficient Building
Green Buildings Overview and Analysis of Energy Efficient Buildingpaperpublications3
 
Comparison of Tuning Methods of PID Controllers for Non-Linear System
Comparison of Tuning Methods of PID Controllers for Non-Linear SystemComparison of Tuning Methods of PID Controllers for Non-Linear System
Comparison of Tuning Methods of PID Controllers for Non-Linear Systempaperpublications3
 
A Review on Arrhythmia Detection Using ECG Signal
A Review on Arrhythmia Detection Using ECG SignalA Review on Arrhythmia Detection Using ECG Signal
A Review on Arrhythmia Detection Using ECG Signalpaperpublications3
 
Coin-Based Mobile Battery Charger Using Solar Panel
Coin-Based Mobile Battery Charger Using Solar PanelCoin-Based Mobile Battery Charger Using Solar Panel
Coin-Based Mobile Battery Charger Using Solar Panelpaperpublications3
 
Magnetic Levitation Time Machine
Magnetic Levitation Time MachineMagnetic Levitation Time Machine
Magnetic Levitation Time Machinepaperpublications3
 
A Power Control Scheme for UPQC for Power Quality Improvement
A Power Control Scheme for UPQC for Power Quality ImprovementA Power Control Scheme for UPQC for Power Quality Improvement
A Power Control Scheme for UPQC for Power Quality Improvementpaperpublications3
 
Analysis and Comparisons of Different Type of WCES- A Literature Review
Analysis and Comparisons of Different Type of WCES- A Literature ReviewAnalysis and Comparisons of Different Type of WCES- A Literature Review
Analysis and Comparisons of Different Type of WCES- A Literature Reviewpaperpublications3
 
Shunt Faults Detection on Transmission Line by Wavelet
Shunt Faults Detection on Transmission Line by WaveletShunt Faults Detection on Transmission Line by Wavelet
Shunt Faults Detection on Transmission Line by Waveletpaperpublications3
 
Presión atmosférica
Presión atmosféricaPresión atmosférica
Presión atmosféricaCesar Enoch
 
Patient Academy Onderzoek 7 maart 2017
Patient Academy Onderzoek 7 maart 2017Patient Academy Onderzoek 7 maart 2017
Patient Academy Onderzoek 7 maart 2017Marleen van Gelder
 
Studio Voylla makes Falaknuma Palace its muse!
Studio Voylla makes Falaknuma Palace its muse!Studio Voylla makes Falaknuma Palace its muse!
Studio Voylla makes Falaknuma Palace its muse!Voylla Fashion Pvt Ltd
 

Viewers also liked (15)

Power Quality Improvement of DC Drive by Reduction of Circulating Current
Power Quality Improvement of DC Drive by Reduction of Circulating CurrentPower Quality Improvement of DC Drive by Reduction of Circulating Current
Power Quality Improvement of DC Drive by Reduction of Circulating Current
 
Non-Contact Temperature Measurement System Based on Embedded
Non-Contact Temperature Measurement System Based on EmbeddedNon-Contact Temperature Measurement System Based on Embedded
Non-Contact Temperature Measurement System Based on Embedded
 
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
 
Green Buildings Overview and Analysis of Energy Efficient Building
Green Buildings Overview and Analysis of Energy Efficient BuildingGreen Buildings Overview and Analysis of Energy Efficient Building
Green Buildings Overview and Analysis of Energy Efficient Building
 
Comparison of Tuning Methods of PID Controllers for Non-Linear System
Comparison of Tuning Methods of PID Controllers for Non-Linear SystemComparison of Tuning Methods of PID Controllers for Non-Linear System
Comparison of Tuning Methods of PID Controllers for Non-Linear System
 
A Review on Arrhythmia Detection Using ECG Signal
A Review on Arrhythmia Detection Using ECG SignalA Review on Arrhythmia Detection Using ECG Signal
A Review on Arrhythmia Detection Using ECG Signal
 
Coin-Based Mobile Battery Charger Using Solar Panel
Coin-Based Mobile Battery Charger Using Solar PanelCoin-Based Mobile Battery Charger Using Solar Panel
Coin-Based Mobile Battery Charger Using Solar Panel
 
Magnetic Levitation Time Machine
Magnetic Levitation Time MachineMagnetic Levitation Time Machine
Magnetic Levitation Time Machine
 
A Power Control Scheme for UPQC for Power Quality Improvement
A Power Control Scheme for UPQC for Power Quality ImprovementA Power Control Scheme for UPQC for Power Quality Improvement
A Power Control Scheme for UPQC for Power Quality Improvement
 
Analysis and Comparisons of Different Type of WCES- A Literature Review
Analysis and Comparisons of Different Type of WCES- A Literature ReviewAnalysis and Comparisons of Different Type of WCES- A Literature Review
Analysis and Comparisons of Different Type of WCES- A Literature Review
 
Shunt Faults Detection on Transmission Line by Wavelet
Shunt Faults Detection on Transmission Line by WaveletShunt Faults Detection on Transmission Line by Wavelet
Shunt Faults Detection on Transmission Line by Wavelet
 
Trabajo b.s.o disney
Trabajo b.s.o disney Trabajo b.s.o disney
Trabajo b.s.o disney
 
Presión atmosférica
Presión atmosféricaPresión atmosférica
Presión atmosférica
 
Patient Academy Onderzoek 7 maart 2017
Patient Academy Onderzoek 7 maart 2017Patient Academy Onderzoek 7 maart 2017
Patient Academy Onderzoek 7 maart 2017
 
Studio Voylla makes Falaknuma Palace its muse!
Studio Voylla makes Falaknuma Palace its muse!Studio Voylla makes Falaknuma Palace its muse!
Studio Voylla makes Falaknuma Palace its muse!
 

Similar to Technical Aspects of EHV XLPE Cable End Termination and on Site Brief Procedure

A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationSubhrajit Ghosh
 
Project on Cable and its classification
Project on Cable and its classificationProject on Cable and its classification
Project on Cable and its classificationSOMNATH DAS
 
Comparative study of power cables and testing as per indian standards
Comparative study of power cables and testing as per indian standardsComparative study of power cables and testing as per indian standards
Comparative study of power cables and testing as per indian standardsIAEME Publication
 
Rubber cable
Rubber cableRubber cable
Rubber cable辉 李
 
IRJET- Review on Manufacturing Process Study of Coils used in Industrial and ...
IRJET- Review on Manufacturing Process Study of Coils used in Industrial and ...IRJET- Review on Manufacturing Process Study of Coils used in Industrial and ...
IRJET- Review on Manufacturing Process Study of Coils used in Industrial and ...IRJET Journal
 
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission LineDesign of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Lineijtsrd
 
Design of Elliptical Patch Antenna with Single & Double U-Slot for Wireless ...
Design of Elliptical Patch Antenna with Single & Double U-Slot  for Wireless ...Design of Elliptical Patch Antenna with Single & Double U-Slot  for Wireless ...
Design of Elliptical Patch Antenna with Single & Double U-Slot for Wireless ...IJMER
 
22 9752 cable paper id 0022 edit septian
22 9752 cable paper id 0022 edit septian22 9752 cable paper id 0022 edit septian
22 9752 cable paper id 0022 edit septianIAESIJEECS
 
Presentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsPresentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsMahesh Chandra Manav
 
Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Mahesh Chandra Manav
 
MV Cable Catalogue
MV Cable CatalogueMV Cable Catalogue
MV Cable CatalogueRajat Mehta
 
Jmv presentation smart power transmission projects cea
Jmv  presentation  smart power transmission projects  ceaJmv  presentation  smart power transmission projects  cea
Jmv presentation smart power transmission projects ceaMahesh Chandra Manav
 
Reconfigurable C and Ku band antenna Using Duelpatch
Reconfigurable C and Ku band antenna Using DuelpatchReconfigurable C and Ku band antenna Using Duelpatch
Reconfigurable C and Ku band antenna Using DuelpatchIRJET Journal
 
Developing an actual very high frequency antenna using genetic algorithms
Developing an actual very high frequency antenna using genetic algorithmsDeveloping an actual very high frequency antenna using genetic algorithms
Developing an actual very high frequency antenna using genetic algorithmseSAT Journals
 
New project report
New project reportNew project report
New project reportSai Printers
 
Analysis of Electric Field and Current Density on XLPE Insulator
Analysis of Electric Field and Current Density on XLPE Insulator Analysis of Electric Field and Current Density on XLPE Insulator
Analysis of Electric Field and Current Density on XLPE Insulator IJECEIAES
 
Sayan CESC HT Report.pdf
Sayan CESC HT Report.pdfSayan CESC HT Report.pdf
Sayan CESC HT Report.pdfSayanBasak15
 

Similar to Technical Aspects of EHV XLPE Cable End Termination and on Site Brief Procedure (20)

A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv Substation
 
Project on Cable and its classification
Project on Cable and its classificationProject on Cable and its classification
Project on Cable and its classification
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Comparative study of power cables and testing as per indian standards
Comparative study of power cables and testing as per indian standardsComparative study of power cables and testing as per indian standards
Comparative study of power cables and testing as per indian standards
 
Rubber cable
Rubber cableRubber cable
Rubber cable
 
IRJET- Review on Manufacturing Process Study of Coils used in Industrial and ...
IRJET- Review on Manufacturing Process Study of Coils used in Industrial and ...IRJET- Review on Manufacturing Process Study of Coils used in Industrial and ...
IRJET- Review on Manufacturing Process Study of Coils used in Industrial and ...
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission LineDesign of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
 
Design of Elliptical Patch Antenna with Single & Double U-Slot for Wireless ...
Design of Elliptical Patch Antenna with Single & Double U-Slot  for Wireless ...Design of Elliptical Patch Antenna with Single & Double U-Slot  for Wireless ...
Design of Elliptical Patch Antenna with Single & Double U-Slot for Wireless ...
 
22 9752 cable paper id 0022 edit septian
22 9752 cable paper id 0022 edit septian22 9752 cable paper id 0022 edit septian
22 9752 cable paper id 0022 edit septian
 
Presentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsPresentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lps
 
Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)
 
MV Cable Catalogue
MV Cable CatalogueMV Cable Catalogue
MV Cable Catalogue
 
OILFILLED.pdf
OILFILLED.pdfOILFILLED.pdf
OILFILLED.pdf
 
Jmv presentation smart power transmission projects cea
Jmv  presentation  smart power transmission projects  ceaJmv  presentation  smart power transmission projects  cea
Jmv presentation smart power transmission projects cea
 
Reconfigurable C and Ku band antenna Using Duelpatch
Reconfigurable C and Ku band antenna Using DuelpatchReconfigurable C and Ku band antenna Using Duelpatch
Reconfigurable C and Ku band antenna Using Duelpatch
 
Developing an actual very high frequency antenna using genetic algorithms
Developing an actual very high frequency antenna using genetic algorithmsDeveloping an actual very high frequency antenna using genetic algorithms
Developing an actual very high frequency antenna using genetic algorithms
 
New project report
New project reportNew project report
New project report
 
Analysis of Electric Field and Current Density on XLPE Insulator
Analysis of Electric Field and Current Density on XLPE Insulator Analysis of Electric Field and Current Density on XLPE Insulator
Analysis of Electric Field and Current Density on XLPE Insulator
 
Sayan CESC HT Report.pdf
Sayan CESC HT Report.pdfSayan CESC HT Report.pdf
Sayan CESC HT Report.pdf
 

Recently uploaded

Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksMagic Marks
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...Health
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086anil_gaur
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfsmsksolar
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 

Recently uploaded (20)

Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 

Technical Aspects of EHV XLPE Cable End Termination and on Site Brief Procedure

  • 1. ISSN 2349-7815 International Journal of Recent Research in Electrical and Electronics Engineering (IJRREEE) Vol. 3, Issue 1, pp: (62-65), Month: January - March 2016, Available at: www.paperpublications.org Page | 62 Paper Publications Technical Aspects of EHV XLPE Cable End Termination and on Site Brief Procedure 1 Sachin Kumar Gupta, 2 Arun Pachori 1 PG student, 2 Associate Professor, Dept of EE, Government Engineering College, Jabalpur, India Abstract: The objective of this paper is to provide an source of information on EHV XLPE cable end termination processes. It also describes the brief procedure of 220 KV XLPE single core (1 1200 Cu corrugated Al sheath) cable termination at 400 KV GSS Heerapura (Rajasthan Vidyut Prasaran Nigam Ltd) Jaipur (Raj) India. The realization of high density power transmission in major city areas requires the effective utilization of limited underground space available so the different versions of the termination are designed for operation under severe outdoor conditions and operation voltage up to 550 KV. Keywords: XLPE CABLE, END TERMINATION, INSULATOR, CORE, OUTDOOR. 1. INTRODUCTION The development of high voltage XLPE system goes back to the 1960’s since then production and material technology have improved significantly providing reliable maintenance free products to utility industry. The different version of the terminations are designed for operation under severe outdoor conditions and operation voltage up to 550 KV. The terminations can also be used indoor where appropriate space is provided. Standard versions are designed for pollution level III or IV for use in higher polluted areas insulators with longer creepage distance are used. Outdoor termination with porcelain insulator (1a): This termination type covers the full range from 72.5 KV to 420 KV. It is used for gas pressure cable, oil filled cable and for XLPE cable. It is in use for many years and has the longest and satisfactory service history. The insulator may be in brown or grey colour protective spark gaps are as an option. 1a 1b 1c
  • 2. ISSN 2349-7815 International Journal of Recent Research in Electrical and Electronics Engineering (IJRREEE) Vol. 3, Issue 1, pp: (62-65), Month: January - March 2016, Available at: www.paperpublications.org Page | 63 Paper Publications Outdoor termination with composite insulator (1b): This termination type is for XLPE cable. The basic design is identical with that of the porcelain termination. The composite insulator, however, is of much lower weight. This is advantageous with respect to lifting equipment needed for installation and also for supporting constructions. Dry type outdoor termination (1c): The dry type termination for XLPE cable is completely free from any liquid or gaseous filling medium. Apart from the environmental aspect, the dry design provides further advantages like easier installation and no need for filling equipment, both contributing to significant savings for installation of the terminations. 2. OUTDOOR TERMINATION PROCESS OF 220 KV XLPE CABLE 1 1200 CU CORRUGATED AL SHEATH 220 KV single circuit of 1200 sq mm 220 KV single core XLPE cable is established between 400 KV substation Heerapura to 220 KV GIS substation Nala Power House Jaipur (appox 10 km) against specification No RVPN/ EHV/ TN- 278. General instruction preparatory works, Dimensions used, fitting procedure are strictly as per site work. During the work relevant security and accident rules must be obeyed. The cable laying must be finished, the cable end is properly sealed and for the proposed cable position the admissible bending radii must be taken into consideration during work. Starting from the upper surface of the termination frame, mark the reference line on the outer plastic cable sheath. Mark from the reference line the cutting position (over length=insulator length +900 mm) on the cable. Adjust the cable end in straight jointing position and fix it. Remove the plastic cable sheath and corrugated aluminum sheath. Taking into consideration the working length of the used round peeling device and an additional length of 10 mm for the grinding process apply a mark with insulating tape on the insulation screen in direction to the cable so that the cable core can be peeled with the peeling device to the transition D1/cone. The knife must be adjusted step by step so that the insulation screen is completely removed. When grinding with emery the diameter of the cable core is reduced by approx 0.3 mm. The transition spot from D1 to D2 must be marked. The peeling process is to be carried out as described under size D1 ,whereby the knife must be adjusted step by step so that diameter D2 as correlated to the stress cone is reached. The transition from D1 to D2 elaborated conically by means of a rasp and abrasive cloth. Make a cone for pushing over the stress cone at the end of the cable core. The prepared cable core may not show any unclean areas like coarse, abrasion channels or marks of the rasp. Longitudinal variations at the end of the insulation screen must be checked. The max. Allowed length is W=15mm. Apply one layer of semi conducting tape from the corrugated aluminum sheath to the semi conducting layer of the cable. Wrap a centre lapping of self amalgamating tape on the corrugated aluminium sheath and on the cable core. Push the cable gland including sealing ring over the cable core. Push over the base plate with the pedestal insulators over the cable core fix them to the termination frame.
  • 3. ISSN 2349-7815 International Journal of Recent Research in Electrical and Electronics Engineering (IJRREEE) Vol. 3, Issue 1, pp: (62-65), Month: January - March 2016, Available at: www.paperpublications.org Page | 64 Paper Publications Clean the cable core and the stress cone inner bore, cover the stress cone inner bore and the surface of the cable core with filling oil very well. Push the stress cone over the cable core up to the marked position by hand. Wash off the remainder of the lubricant from stress cone and cable core. Wrap one layer of semi conducting tape with 50% overlapping, copper woven fabric tape and self-amalgamating tape from the tube of the sealing flange to the stress cone. Cut the cable core exactly vertical at the cutting position (insulator length +3 mm). Push the mechanical connector on the conductor up to the insulation and fix all screw by hand. Clean the base plate, the stress cone, the core and the insulator carefully. Insert the sealing ring on the base plate. Push on the insulator and allow it to stand on the base plate. Screw the insulator to the base plate and the aluminum top plate. Take care that no dirt can get into the open termination. Fit a stud to the can and pour the oil into the insulator up to the oil level. The air chamber over the filling height, allow heat expansion of the oil. Push the spacers over the conductor terminal bolt. Insert the sealing ring in the groove of the conductor terminal. Screw the top nut on the bolt. Fit the cable gland and heat shrinkable sleeve.
  • 4. ISSN 2349-7815 International Journal of Recent Research in Electrical and Electronics Engineering (IJRREEE) Vol. 3, Issue 1, pp: (62-65), Month: January - March 2016, Available at: www.paperpublications.org Page | 65 Paper Publications 3. CONCLUSION The outdoor terminal should be suitable for heavily polluted atmospheric conditions with total creep age distance of 31 mm/KV and protected creep age distance of not more than 50% of the total creep age distance. The cable end terminals for terminating the cable shall be fully compatible with the cable. Above termination is antifog, pre fabricated type based on the EPR-based stress relief cone with an epoxy housing or pre-moulded type silicon based stress relief cone. The termination base plate and the cable’s metallic sheath shall be electrically insulated from the supporting structure. REFERENCES [1] W. Weissenberg, U. Rengel, R. Scherer, “EHV XLPE Cable Systems up to 400 kV – More than 10 Years Field Experience,” CIGRE 2004, paper B1-102, 2004. [2] Ruben Vogelsang, Oldrich Sekula, Herbert Nyffenegger, & Werner Weissenberg, “Long-term experiences with XLPE cable systems up to 550 kV,” CIGRE SC B1, 2009. [3] R. V. Olshausen, & W. Weissenberg, “The electrical long-term performance of cross- linked polyethylene,” 30 WIRE 5/2001. [4] W. Weissenberg, M. Kuschel, “Test methods for Silicone Rubber accessories used in high voltage cables up to 400 kV,” 6th Jicable, Paris, 2003. [5] CIGRÉ Tech. Brochure # 379, “Update of service experience of HV underground & submarine cable systems,” 2009. [6] J.-O. Boström, A. Campus, R. N. Hamton, & E. Marsden, “Reliable HV & EHV XLPE cables,” CIGRE, Paper 21- 105, 2002. [7] HIGH VOLTAGE XLPE CABLE SYSTEMS Technical User Guide BRUGG CABLES E-Highway2050 WP3 workshop April 15th, 2014 Brussels. [8] Underground Cable: an innovative and reliable Technology nkt cables. [9] High voltage underground and subsea cable technology options for future transmission in Europe Ernesto Zaccone, Chairman Europe a cable High Voltage Systems Group. [10] LONG-LIFE XLPE INSULATED POWER CABLE jicable 07 Nigel HAMPTON, NEETRAC, Georgia Tech, USA, Rick HARTLEIN, NEETRAC, Georgia Tech, USA, Hakan LENNARTSSON, Borouge Pty, Hong Kong, Harry ORTON, OCEI, Vancouver, BC, Canada, h.Ram RAMACHANDRAN,The Dow Chemical Company, NJ, USA, [11] D.H.Kim and E.J.Park,“An investigation of influence of semiconductive electrode materials in breakdown and charge International Journal of Scientific Engineering and Technology (ISSN : 2277-1581) www.ijset.com, Volume No.1, Issue No.2 pg:65-70 01 April 2012 accumulation in XLPE,” in Proc. IEEE Conf. Elect. Insulation Dielect.Phenomena, Atlanta, GA, 1998, pp. 546–549. [12] M.S.Mashikan, J.H. Groeger, S.J. Dale and E. Ildstad, “Role of semi conductive compounds in the premature aging of XLPE cable insulation,” in Conf. record IEEE Int. Symp.n Elect. Insulation, Bos- ton,MA, June 5–8, 1988, pp. 314–320. [13] Feasibility and technical aspects of partial undergrounding of extra high voltage power transmission lines Brussels, December 2010 europa cables.