SlideShare a Scribd company logo
1 of 22
Download to read offline
Identifying Shorted Casings with
and without Test Leads
by
Jim Walton
Mears Group, Inc.
Integrity Solutions Division
Safety/OQ
• Pre-Job Meeting
• Clothing – Hard Hat, Safety Glasses, Work Boots,
Reflective Vest and other
• Equipment – Cones, Flags, Flares, First Aid Kit,
Flashers, Barricades and other
• Job Site Considerations
• Abnormal Operating Conditions
• Qualified Individuals
• Emergency Response Plan
• Job Safety Analysis
What methods should be utilized for identifying
shorted casings?
• Alternating Current Current Attenuation
(ACCA/CA/Electromagnetic)
• Close Interval Survey (CIS/CIPS)
• Direct Current Voltage Gradient (DCVG)
• Alternating Current Voltage Gradient (ACVG)
• Panhandle Eastern
• Casing Resistance
• Shifting the Casing potential
Principles of CA
• A specific signal/frequency is applied to the pipeline
• A magnetic field is created around the pipeline
• A receiving device at the ground surface receives the signal without
needing ground contact
• At areas of lower pipe to ground resistance (e.g. holidays or shorts) the
current attenuates at a higher rate
• Location, depth and distance must be established to acquire the
needed current measurement
• Distance between readings can vary (50 to 100 foot spacing is
common although distances much greater can be utilized in some
circumstances)
Current Attenuation Tools
PCM PPL with HDV
Principals of CIS
• A DC structure-to-electrolyte potential is collected during both the
CP “on” state and the CP instant “off” state
• Spacing is determined by depth of pipeline and 3 – 5 – 10 foot
spacing is common
• All influencing current should be interrupted
• All interrupters must be synchronized
• Sufficient ground contact must be achieved
CIS tools
Principles of DCVG
DCVG measures the voltage difference between two reference
electrodes. These differences can assist in pinpointing
holidays and corrosion cells on a pipeline. DCVG, because it
uses DC current, can also determine if the holiday is cathodic
(protected) or anodic (corroding) at the time the survey is being
performed.
• Asynchronous interruption (0.3sec on, 0.7sec off) is required
• Accurately locates indications of coating anomalies or shorts
• Predict relative importance/severity of anomaly.
• Must have sufficient current flow and voltage shift to obtain
accurate measurements.
DCVG tools
Principles of ACVG
ACVG uses the differences in the electrical field between two known
locations. One type of ACVG (the A-Frame) uses fixed pins on a frame
that are approximately 2’ apart. Since the distance never changes, each
data point is comparable.
Most ACVG devices will have a meter or a display that will show the
operator which way the holiday or indication is located. The severity of
the holiday is indicated by the strength of the signal at the holiday
location.
The signal strength increases until the probes are straddling and equal
distance from the holiday. Once the probes pass the holiday, the
direction changes and the strength of the signal decreases.
• Low frequency transmitter or special interrupt signal is required
• Accurately locates coating anomalies
• Predict relative importance/severity of anomaly
ACVG tools
ACVG tools
Sample Conditions of Cased Crossings
• Clear – No electrolyte in casing and complete electrical isolation
• No Anomalies – May have electrolyte in casing but no coating
holidays
• Electrolytic Condition – Electrolyte is present around a coating
holiday
• Metallic Short – There is metal to metal contact between the
casing and pipeline.
Shorted Casing Tests – Tool Methodology
• Current Attenuation (CA) – Take measurements before
and after the cased crossing.
• Alternating Current Voltage Gradient or Direct Current
Voltage Gradient (ACVG/DCVG) – Take measurements at
each end of the casing and over the cased crossing.
• CIS – Take on and off pipe to soil potentials and on and
off casing to soil potentials at the ends of the casing.
• Pipe to Casing Tests – Connect CA tool to pipeline and
casing and measure values outside the cased crossing.
Indirect Inspection Methods and types of Casing problems found
Indirect Method Type of Method Metallic Short Electrolytic Contact
P/S & C/S
Potentials
Electrical Potential  Low probability
P/S & C/S Shift Electrical Potential  
Pipe Current
Mapper
AC Current
Attenuation
 
PCM A-Frame AC Voltage Gradient  
Internal Resistance Electrical Resistance  Low probability
Panhandle Eastern Reverse Current
Applied to Casing
 Low probability
Pipe/Cable Locator Radio Signal  Low probability
Tinker & Rasor
Model CE-IT
Casing/Pipe
Capacitance
 Low probability
Guided Wave  
Provided Corrosion is Present
Portable Current Source
Tool Results
Results meant for Bare Casings
Coated Casings will require different criterion.
• Clear – Indirect Inspections will show no indications
across the casing.
• No Anomalies – ACVG/DCVG will show no indications;
CA over the length of the casing will show no indications;
CA utilized with pipe to casing connections may show
some loss of current outside the casing; Pipe to Soil and
Casing to Soil will be significantly different from each
other.
Tools Results (cont.)
• Electrolytic – ACVG/DCVG will find indications at the end(s) of the
casing and possibly over the casing (values normally <80dB). CA
over the length of the casing may show some loss (between 5 –
25%); CA utilized with pipe to casing connections should show some
loss of current outside the casing (between 20 – 80%); Pipe to Soil
and Casing to Soil will be different from each other but may be within
10 – 100 mV.
• Metallic - ACVG/DCVG will find indications at the end(s) of the casing
and possibly over the casing at the point of contact (values are
normally very high >80dB). CA over the length of the casing should
show significant loss (> 25% but may be less); CA utilized with pipe
to casing connections should show almost complete loss of current
outside the casing (> 80%); Pipe to Soil and Casing to Soil will
normally be identical (at least within 10 mV).
• Per DOT Part 192.921, DA can be used to assess the integrity of gas
transmission pipelines for the external, internal, and SCC threats.
• Per DOT Part 192.921, DA must be performed in accordance with
192.923, 192.925, 192.927, and 192.929, and specifically ECDA in
accordance with NACE RP0502.
From the NTSB Advisory Bulletin dated 01/03/2011
• Specifically, §192.921(a) requires the operator to select the method or
methods best suited to address the identified threats to the covered
segment (pipeline), which include internal inspection tool[s], pressure
test, direct assessment, or other technology that an operator
demonstrates can provide an equivalent understanding of the condition
of the pipeline.
• More than one assessment method may be required to address all
the threats to the covered pipeline segment.
DOT Code Requirements
The process assesses if a corrosion cell could exist
– Anode, Cathode, Metallic Path, Electrolytic Path
• If the coating is free of holidays, an external corrosion cell
cannot occur (absent disbonded coating issues).
• If a holiday is present, the highest risk of external corrosion
occurs with a metallic contact and electrolyte in the casing.
• If an electrolytic contact is present, a potentially corrosive
environment exists, however Cathodic Protection may be able
to polarize the pipeline.
Technical Basis
• Testing and field results have validated that the shorted casing
tests are applicable to cased pipelines with or without test
leads.
– Indirect Tests Find Metallic and Electrolytic Conditions
– Process Elements and Guided Wave Assess for Atmospheric Corrosion
• The process improves the safety of cased pipelines by
– identifying when potentially corrosive situations exist.
– mitigating the conditions.
– examining the integrity of the pipeline.
• Multiple applicable tools are key to having a good survey test
results across cased crossings.
• Coating condition & cathodic protection state are key in
making informed decisions about external corrosion.
• Of course any and all historical data is crucial to success.
Technical Basis
Questions
2 2
Jim Walton
Mears Group, Inc.
Integrity Solutions Division
1840 Hutton Drive, Suite 190
Carrollton, TX 75006
www.mearcorrosion.com
Office: 972-755-2633
Fax: 972-755-2637
Cell: 817-907-4444
email: jim.walton@mears.net

More Related Content

What's hot

Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSimple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSARAVANAN A
 
Electrical Meter Types
Electrical Meter TypesElectrical Meter Types
Electrical Meter Typesdartboard
 
Impressed Current Cathodic Protection System Design ICCP
Impressed Current Cathodic Protection System Design ICCPImpressed Current Cathodic Protection System Design ICCP
Impressed Current Cathodic Protection System Design ICCPTauseef bin Abdul Rashid
 
Cable fault location methods (Megger)
Cable fault location methods (Megger)Cable fault location methods (Megger)
Cable fault location methods (Megger)AHMED MOHAMED HEGAB
 
Advanced Cathodic Protection - CP Series - Eric Langelund
Advanced Cathodic Protection - CP Series - Eric LangelundAdvanced Cathodic Protection - CP Series - Eric Langelund
Advanced Cathodic Protection - CP Series - Eric Langelundnacetwincities
 
(Smaw) aws product development committee everyday pocket handbook for shiel...
(Smaw) aws product development committee   everyday pocket handbook for shiel...(Smaw) aws product development committee   everyday pocket handbook for shiel...
(Smaw) aws product development committee everyday pocket handbook for shiel...Raymizard Siregar
 
Survey & ts for ehv lines
Survey & ts for ehv linesSurvey & ts for ehv lines
Survey & ts for ehv linesMahesh Sontyal
 
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)Thorne & Derrick International
 
TTypes of cables
TTypes of cablesTTypes of cables
TTypes of cablesJAY THAKAR
 
Simple Current Transformer (CT) Testing for Switchyard Equipment.
Simple Current Transformer (CT) Testing for Switchyard Equipment.Simple Current Transformer (CT) Testing for Switchyard Equipment.
Simple Current Transformer (CT) Testing for Switchyard Equipment.SARAVANAN A
 
CATHODIC PROTECTION SYSTEM PRESENTATION
CATHODIC PROTECTION SYSTEM PRESENTATIONCATHODIC PROTECTION SYSTEM PRESENTATION
CATHODIC PROTECTION SYSTEM PRESENTATIONDerrick Okyere, MGhIE
 
Using High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash HazardsUsing High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash Hazardsmichaeljmack
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvAlexander Decker
 
The wire
The wireThe wire
The wiresdpable
 
Lv panel specification
Lv panel specificationLv panel specification
Lv panel specificationSajeewa Lakmal
 

What's hot (20)

Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSimple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
 
Electrical Meter Types
Electrical Meter TypesElectrical Meter Types
Electrical Meter Types
 
Procedure cable testing
Procedure cable testingProcedure cable testing
Procedure cable testing
 
Impressed Current Cathodic Protection System Design ICCP
Impressed Current Cathodic Protection System Design ICCPImpressed Current Cathodic Protection System Design ICCP
Impressed Current Cathodic Protection System Design ICCP
 
DCVG rev (d)
DCVG rev  (d)DCVG rev  (d)
DCVG rev (d)
 
Cable fault location methods (Megger)
Cable fault location methods (Megger)Cable fault location methods (Megger)
Cable fault location methods (Megger)
 
Advanced Cathodic Protection - CP Series - Eric Langelund
Advanced Cathodic Protection - CP Series - Eric LangelundAdvanced Cathodic Protection - CP Series - Eric Langelund
Advanced Cathodic Protection - CP Series - Eric Langelund
 
tower spotting
tower spottingtower spotting
tower spotting
 
(Smaw) aws product development committee everyday pocket handbook for shiel...
(Smaw) aws product development committee   everyday pocket handbook for shiel...(Smaw) aws product development committee   everyday pocket handbook for shiel...
(Smaw) aws product development committee everyday pocket handbook for shiel...
 
Survey & ts for ehv lines
Survey & ts for ehv linesSurvey & ts for ehv lines
Survey & ts for ehv lines
 
Welding Defects.pdf
Welding Defects.pdfWelding Defects.pdf
Welding Defects.pdf
 
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
 
TTypes of cables
TTypes of cablesTTypes of cables
TTypes of cables
 
Simple Current Transformer (CT) Testing for Switchyard Equipment.
Simple Current Transformer (CT) Testing for Switchyard Equipment.Simple Current Transformer (CT) Testing for Switchyard Equipment.
Simple Current Transformer (CT) Testing for Switchyard Equipment.
 
CATHODIC PROTECTION SYSTEM PRESENTATION
CATHODIC PROTECTION SYSTEM PRESENTATIONCATHODIC PROTECTION SYSTEM PRESENTATION
CATHODIC PROTECTION SYSTEM PRESENTATION
 
Using High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash HazardsUsing High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash Hazards
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kv
 
The wire
The wireThe wire
The wire
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Lv panel specification
Lv panel specificationLv panel specification
Lv panel specification
 

Similar to Identifying Casing Shorts With or Without Test Leads - Jim Walton

ACVG vs DCVG: Does It Matter? - Jim Walton
ACVG vs DCVG: Does It Matter? - Jim WaltonACVG vs DCVG: Does It Matter? - Jim Walton
ACVG vs DCVG: Does It Matter? - Jim Waltonnacetwincities
 
Overhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by AmprobeOverhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by AmprobeTranscat
 
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Thorne & Derrick International
 
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERDIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERRitesh Kumawat
 
external & internal corrosion monitoring
external & internal corrosion monitoringexternal & internal corrosion monitoring
external & internal corrosion monitoringsair ali khan
 
Detection of fault location in underground cable using arduino
Detection of fault location in underground cable using arduinoDetection of fault location in underground cable using arduino
Detection of fault location in underground cable using arduinoChirag Lakhani
 
Development of Over-Line Survey Systems for Monitoring Pipelines v1.0 - uploa...
Development of Over-Line Survey Systems for Monitoring Pipelines v1.0 - uploa...Development of Over-Line Survey Systems for Monitoring Pipelines v1.0 - uploa...
Development of Over-Line Survey Systems for Monitoring Pipelines v1.0 - uploa...David Simmonds
 
IQ_Partial_Discharge_Presentation_complete.ppt
IQ_Partial_Discharge_Presentation_complete.pptIQ_Partial_Discharge_Presentation_complete.ppt
IQ_Partial_Discharge_Presentation_complete.pptEddy Fernando Queca Cadiz
 
IQ_Partial_Discharge_Presentation.ppt
IQ_Partial_Discharge_Presentation.pptIQ_Partial_Discharge_Presentation.ppt
IQ_Partial_Discharge_Presentation.pptssuserf6b378
 
Tools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTranscat
 
Getting up close and personal with rc ds Bernard Gittins
Getting up close and personal with rc ds   Bernard GittinsGetting up close and personal with rc ds   Bernard Gittins
Getting up close and personal with rc ds Bernard GittinsNSW Environment and Planning
 
Decoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike TachickDecoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike Tachicknacetwincities
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DCMahesh Chandra Manav
 
Heat Exchangers inspection .pdf
Heat Exchangers inspection .pdfHeat Exchangers inspection .pdf
Heat Exchangers inspection .pdfNickeshShah
 

Similar to Identifying Casing Shorts With or Without Test Leads - Jim Walton (20)

ACVG vs DCVG: Does It Matter? - Jim Walton
ACVG vs DCVG: Does It Matter? - Jim WaltonACVG vs DCVG: Does It Matter? - Jim Walton
ACVG vs DCVG: Does It Matter? - Jim Walton
 
Overhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by AmprobeOverhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by Amprobe
 
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
 
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERDIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
 
external & internal corrosion monitoring
external & internal corrosion monitoringexternal & internal corrosion monitoring
external & internal corrosion monitoring
 
SLIDES
SLIDESSLIDES
SLIDES
 
Detection of fault location in underground cable using arduino
Detection of fault location in underground cable using arduinoDetection of fault location in underground cable using arduino
Detection of fault location in underground cable using arduino
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
 
Development of Over-Line Survey Systems for Monitoring Pipelines v1.0 - uploa...
Development of Over-Line Survey Systems for Monitoring Pipelines v1.0 - uploa...Development of Over-Line Survey Systems for Monitoring Pipelines v1.0 - uploa...
Development of Over-Line Survey Systems for Monitoring Pipelines v1.0 - uploa...
 
IQ_Partial_Discharge_Presentation_complete.ppt
IQ_Partial_Discharge_Presentation_complete.pptIQ_Partial_Discharge_Presentation_complete.ppt
IQ_Partial_Discharge_Presentation_complete.ppt
 
IQ_Partial_Discharge_Presentation.ppt
IQ_Partial_Discharge_Presentation.pptIQ_Partial_Discharge_Presentation.ppt
IQ_Partial_Discharge_Presentation.ppt
 
Tools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV Systems
 
Dc voltage
Dc voltageDc voltage
Dc voltage
 
Getting up close and personal with rc ds Bernard Gittins
Getting up close and personal with rc ds   Bernard GittinsGetting up close and personal with rc ds   Bernard Gittins
Getting up close and personal with rc ds Bernard Gittins
 
Fusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity CircuitsFusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity Circuits
 
Technotoy5
Technotoy5Technotoy5
Technotoy5
 
Technotoy5
Technotoy5Technotoy5
Technotoy5
 
Decoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike TachickDecoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike Tachick
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DC
 
Heat Exchangers inspection .pdf
Heat Exchangers inspection .pdfHeat Exchangers inspection .pdf
Heat Exchangers inspection .pdf
 

More from nacetwincities

Atmospheric Corrosion - Jason Lozano
Atmospheric Corrosion - Jason LozanoAtmospheric Corrosion - Jason Lozano
Atmospheric Corrosion - Jason Lozanonacetwincities
 
Unique CP Installations - Tom Mollica
Unique CP Installations - Tom MollicaUnique CP Installations - Tom Mollica
Unique CP Installations - Tom Mollicanacetwincities
 
Stray Current From DC Powered Transit Systems - Tom Mollica
Stray Current From DC Powered Transit Systems - Tom MollicaStray Current From DC Powered Transit Systems - Tom Mollica
Stray Current From DC Powered Transit Systems - Tom Mollicanacetwincities
 
The Cost Of Corrosion - Karen Speicher
The Cost Of Corrosion - Karen SpeicherThe Cost Of Corrosion - Karen Speicher
The Cost Of Corrosion - Karen Speichernacetwincities
 
Stray Current From DC Powered Transit Systems - Tom Mollica
Stray Current From DC Powered Transit Systems - Tom MollicaStray Current From DC Powered Transit Systems - Tom Mollica
Stray Current From DC Powered Transit Systems - Tom Mollicanacetwincities
 
Basic Electricity - CP Series - Eric Langelund
Basic Electricity - CP Series - Eric LangelundBasic Electricity - CP Series - Eric Langelund
Basic Electricity - CP Series - Eric Langelundnacetwincities
 
Basic Corrosion - CP Series - Eric Langelund
Basic Corrosion - CP Series - Eric LangelundBasic Corrosion - CP Series - Eric Langelund
Basic Corrosion - CP Series - Eric Langelundnacetwincities
 
Basic Cathodic Protection - CP Series - Eric Langelund
Basic Cathodic Protection - CP Series - Eric LangelundBasic Cathodic Protection - CP Series - Eric Langelund
Basic Cathodic Protection - CP Series - Eric Langelundnacetwincities
 
New Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary KrichauNew Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary Krichaunacetwincities
 
Integrity Related To Corrosion - Gary Krichau
Integrity Related To Corrosion - Gary KrichauIntegrity Related To Corrosion - Gary Krichau
Integrity Related To Corrosion - Gary Krichaunacetwincities
 
A History of Coatings - Ryan Swor
A History of Coatings - Ryan SworA History of Coatings - Ryan Swor
A History of Coatings - Ryan Swornacetwincities
 
Exothermic Welding & Pinbrazing - Kevin Jones
Exothermic Welding & Pinbrazing - Kevin JonesExothermic Welding & Pinbrazing - Kevin Jones
Exothermic Welding & Pinbrazing - Kevin Jonesnacetwincities
 
Bonding Dilemmas In Pipeline Facilities - Mike Tachick
Bonding Dilemmas In Pipeline Facilities - Mike TachickBonding Dilemmas In Pipeline Facilities - Mike Tachick
Bonding Dilemmas In Pipeline Facilities - Mike Tachicknacetwincities
 
Large Facility CP & Isolation Challenges - Mike Tachick
Large Facility CP & Isolation Challenges - Mike TachickLarge Facility CP & Isolation Challenges - Mike Tachick
Large Facility CP & Isolation Challenges - Mike Tachicknacetwincities
 
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020nacetwincities
 
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020nacetwincities
 
CP Material & Their Specific Uses - Charlie Poore - 2.5.2020
CP Material & Their Specific Uses - Charlie Poore - 2.5.2020CP Material & Their Specific Uses - Charlie Poore - 2.5.2020
CP Material & Their Specific Uses - Charlie Poore - 2.5.2020nacetwincities
 
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020nacetwincities
 

More from nacetwincities (18)

Atmospheric Corrosion - Jason Lozano
Atmospheric Corrosion - Jason LozanoAtmospheric Corrosion - Jason Lozano
Atmospheric Corrosion - Jason Lozano
 
Unique CP Installations - Tom Mollica
Unique CP Installations - Tom MollicaUnique CP Installations - Tom Mollica
Unique CP Installations - Tom Mollica
 
Stray Current From DC Powered Transit Systems - Tom Mollica
Stray Current From DC Powered Transit Systems - Tom MollicaStray Current From DC Powered Transit Systems - Tom Mollica
Stray Current From DC Powered Transit Systems - Tom Mollica
 
The Cost Of Corrosion - Karen Speicher
The Cost Of Corrosion - Karen SpeicherThe Cost Of Corrosion - Karen Speicher
The Cost Of Corrosion - Karen Speicher
 
Stray Current From DC Powered Transit Systems - Tom Mollica
Stray Current From DC Powered Transit Systems - Tom MollicaStray Current From DC Powered Transit Systems - Tom Mollica
Stray Current From DC Powered Transit Systems - Tom Mollica
 
Basic Electricity - CP Series - Eric Langelund
Basic Electricity - CP Series - Eric LangelundBasic Electricity - CP Series - Eric Langelund
Basic Electricity - CP Series - Eric Langelund
 
Basic Corrosion - CP Series - Eric Langelund
Basic Corrosion - CP Series - Eric LangelundBasic Corrosion - CP Series - Eric Langelund
Basic Corrosion - CP Series - Eric Langelund
 
Basic Cathodic Protection - CP Series - Eric Langelund
Basic Cathodic Protection - CP Series - Eric LangelundBasic Cathodic Protection - CP Series - Eric Langelund
Basic Cathodic Protection - CP Series - Eric Langelund
 
New Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary KrichauNew Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary Krichau
 
Integrity Related To Corrosion - Gary Krichau
Integrity Related To Corrosion - Gary KrichauIntegrity Related To Corrosion - Gary Krichau
Integrity Related To Corrosion - Gary Krichau
 
A History of Coatings - Ryan Swor
A History of Coatings - Ryan SworA History of Coatings - Ryan Swor
A History of Coatings - Ryan Swor
 
Exothermic Welding & Pinbrazing - Kevin Jones
Exothermic Welding & Pinbrazing - Kevin JonesExothermic Welding & Pinbrazing - Kevin Jones
Exothermic Welding & Pinbrazing - Kevin Jones
 
Bonding Dilemmas In Pipeline Facilities - Mike Tachick
Bonding Dilemmas In Pipeline Facilities - Mike TachickBonding Dilemmas In Pipeline Facilities - Mike Tachick
Bonding Dilemmas In Pipeline Facilities - Mike Tachick
 
Large Facility CP & Isolation Challenges - Mike Tachick
Large Facility CP & Isolation Challenges - Mike TachickLarge Facility CP & Isolation Challenges - Mike Tachick
Large Facility CP & Isolation Challenges - Mike Tachick
 
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
 
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
 
CP Material & Their Specific Uses - Charlie Poore - 2.5.2020
CP Material & Their Specific Uses - Charlie Poore - 2.5.2020CP Material & Their Specific Uses - Charlie Poore - 2.5.2020
CP Material & Their Specific Uses - Charlie Poore - 2.5.2020
 
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
 

Recently uploaded

BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756dollysharma2066
 
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...
NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...Khaled Al Awadi
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiMalviyaNagarCallGirl
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...lizamodels9
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Investment analysis and portfolio management
Investment analysis and portfolio managementInvestment analysis and portfolio management
Investment analysis and portfolio managementJunaidKhan750825
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCRsoniya singh
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 

Recently uploaded (20)

BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
 
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...
NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Investment analysis and portfolio management
Investment analysis and portfolio managementInvestment analysis and portfolio management
Investment analysis and portfolio management
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 

Identifying Casing Shorts With or Without Test Leads - Jim Walton

  • 1. Identifying Shorted Casings with and without Test Leads by Jim Walton Mears Group, Inc. Integrity Solutions Division
  • 2. Safety/OQ • Pre-Job Meeting • Clothing – Hard Hat, Safety Glasses, Work Boots, Reflective Vest and other • Equipment – Cones, Flags, Flares, First Aid Kit, Flashers, Barricades and other • Job Site Considerations • Abnormal Operating Conditions • Qualified Individuals • Emergency Response Plan • Job Safety Analysis
  • 3. What methods should be utilized for identifying shorted casings? • Alternating Current Current Attenuation (ACCA/CA/Electromagnetic) • Close Interval Survey (CIS/CIPS) • Direct Current Voltage Gradient (DCVG) • Alternating Current Voltage Gradient (ACVG) • Panhandle Eastern • Casing Resistance • Shifting the Casing potential
  • 4. Principles of CA • A specific signal/frequency is applied to the pipeline • A magnetic field is created around the pipeline • A receiving device at the ground surface receives the signal without needing ground contact • At areas of lower pipe to ground resistance (e.g. holidays or shorts) the current attenuates at a higher rate • Location, depth and distance must be established to acquire the needed current measurement • Distance between readings can vary (50 to 100 foot spacing is common although distances much greater can be utilized in some circumstances)
  • 6. Principals of CIS • A DC structure-to-electrolyte potential is collected during both the CP “on” state and the CP instant “off” state • Spacing is determined by depth of pipeline and 3 – 5 – 10 foot spacing is common • All influencing current should be interrupted • All interrupters must be synchronized • Sufficient ground contact must be achieved
  • 8. Principles of DCVG DCVG measures the voltage difference between two reference electrodes. These differences can assist in pinpointing holidays and corrosion cells on a pipeline. DCVG, because it uses DC current, can also determine if the holiday is cathodic (protected) or anodic (corroding) at the time the survey is being performed. • Asynchronous interruption (0.3sec on, 0.7sec off) is required • Accurately locates indications of coating anomalies or shorts • Predict relative importance/severity of anomaly. • Must have sufficient current flow and voltage shift to obtain accurate measurements.
  • 10. Principles of ACVG ACVG uses the differences in the electrical field between two known locations. One type of ACVG (the A-Frame) uses fixed pins on a frame that are approximately 2’ apart. Since the distance never changes, each data point is comparable. Most ACVG devices will have a meter or a display that will show the operator which way the holiday or indication is located. The severity of the holiday is indicated by the strength of the signal at the holiday location. The signal strength increases until the probes are straddling and equal distance from the holiday. Once the probes pass the holiday, the direction changes and the strength of the signal decreases. • Low frequency transmitter or special interrupt signal is required • Accurately locates coating anomalies • Predict relative importance/severity of anomaly
  • 13. Sample Conditions of Cased Crossings • Clear – No electrolyte in casing and complete electrical isolation • No Anomalies – May have electrolyte in casing but no coating holidays • Electrolytic Condition – Electrolyte is present around a coating holiday • Metallic Short – There is metal to metal contact between the casing and pipeline.
  • 14. Shorted Casing Tests – Tool Methodology • Current Attenuation (CA) – Take measurements before and after the cased crossing. • Alternating Current Voltage Gradient or Direct Current Voltage Gradient (ACVG/DCVG) – Take measurements at each end of the casing and over the cased crossing. • CIS – Take on and off pipe to soil potentials and on and off casing to soil potentials at the ends of the casing. • Pipe to Casing Tests – Connect CA tool to pipeline and casing and measure values outside the cased crossing.
  • 15. Indirect Inspection Methods and types of Casing problems found Indirect Method Type of Method Metallic Short Electrolytic Contact P/S & C/S Potentials Electrical Potential  Low probability P/S & C/S Shift Electrical Potential   Pipe Current Mapper AC Current Attenuation   PCM A-Frame AC Voltage Gradient   Internal Resistance Electrical Resistance  Low probability Panhandle Eastern Reverse Current Applied to Casing  Low probability Pipe/Cable Locator Radio Signal  Low probability Tinker & Rasor Model CE-IT Casing/Pipe Capacitance  Low probability Guided Wave   Provided Corrosion is Present
  • 17. Tool Results Results meant for Bare Casings Coated Casings will require different criterion. • Clear – Indirect Inspections will show no indications across the casing. • No Anomalies – ACVG/DCVG will show no indications; CA over the length of the casing will show no indications; CA utilized with pipe to casing connections may show some loss of current outside the casing; Pipe to Soil and Casing to Soil will be significantly different from each other.
  • 18. Tools Results (cont.) • Electrolytic – ACVG/DCVG will find indications at the end(s) of the casing and possibly over the casing (values normally <80dB). CA over the length of the casing may show some loss (between 5 – 25%); CA utilized with pipe to casing connections should show some loss of current outside the casing (between 20 – 80%); Pipe to Soil and Casing to Soil will be different from each other but may be within 10 – 100 mV. • Metallic - ACVG/DCVG will find indications at the end(s) of the casing and possibly over the casing at the point of contact (values are normally very high >80dB). CA over the length of the casing should show significant loss (> 25% but may be less); CA utilized with pipe to casing connections should show almost complete loss of current outside the casing (> 80%); Pipe to Soil and Casing to Soil will normally be identical (at least within 10 mV).
  • 19. • Per DOT Part 192.921, DA can be used to assess the integrity of gas transmission pipelines for the external, internal, and SCC threats. • Per DOT Part 192.921, DA must be performed in accordance with 192.923, 192.925, 192.927, and 192.929, and specifically ECDA in accordance with NACE RP0502. From the NTSB Advisory Bulletin dated 01/03/2011 • Specifically, §192.921(a) requires the operator to select the method or methods best suited to address the identified threats to the covered segment (pipeline), which include internal inspection tool[s], pressure test, direct assessment, or other technology that an operator demonstrates can provide an equivalent understanding of the condition of the pipeline. • More than one assessment method may be required to address all the threats to the covered pipeline segment. DOT Code Requirements
  • 20. The process assesses if a corrosion cell could exist – Anode, Cathode, Metallic Path, Electrolytic Path • If the coating is free of holidays, an external corrosion cell cannot occur (absent disbonded coating issues). • If a holiday is present, the highest risk of external corrosion occurs with a metallic contact and electrolyte in the casing. • If an electrolytic contact is present, a potentially corrosive environment exists, however Cathodic Protection may be able to polarize the pipeline. Technical Basis
  • 21. • Testing and field results have validated that the shorted casing tests are applicable to cased pipelines with or without test leads. – Indirect Tests Find Metallic and Electrolytic Conditions – Process Elements and Guided Wave Assess for Atmospheric Corrosion • The process improves the safety of cased pipelines by – identifying when potentially corrosive situations exist. – mitigating the conditions. – examining the integrity of the pipeline. • Multiple applicable tools are key to having a good survey test results across cased crossings. • Coating condition & cathodic protection state are key in making informed decisions about external corrosion. • Of course any and all historical data is crucial to success. Technical Basis
  • 22. Questions 2 2 Jim Walton Mears Group, Inc. Integrity Solutions Division 1840 Hutton Drive, Suite 190 Carrollton, TX 75006 www.mearcorrosion.com Office: 972-755-2633 Fax: 972-755-2637 Cell: 817-907-4444 email: jim.walton@mears.net