SlideShare a Scribd company logo
1 of 6
Download to read offline
Abstract — This research is intended to enhance the original
Overall Equipment Effectiveness (OEE). Calculating
plant/equipment OEE can be very helpful for monitoring
trends (such as whether a given plant is improving OEE over
time) or as a rough measure of where a given plant lies in the
OEE benchmarking spectrum. OEE concept in TPM
implementation truly reduces manufacturing complex
problems into simple, intuitive presentation of information. It
helps to systematically improve the process with easy-to-obtain
measurements. The OEE is the process, which is acquired to
specify an equivalent weight setting of every single element,
even if, each concerning losses are totally different. Hence, the
study proposes a weighted graph approach, to identify
dissimilarity in weighting each OEE element. The proposed
concept is used to find the OEE for the plant, as well as to set
the target for the plant and the area to focus for their
improvement.
Index Terms— TPM, effectiveness, weighted signed graph,
OEE, performance improvement.
I. INTRODUCTION
N the highly competitive manufacturing environment
prevailing at the global level, plants of any country or
region should be benchmarked and maintained at world-
class level. Failing to do that, a plant may be exposed to
various difficulties. The results of implementation of Total
Productive Maintenance (TPM) program increased plant
efficiency and productivity significantly by means of
eliminating the major losses. The important goal of TPM is
the total elimination of all six major losses, including
breakdowns, equipment setup & adjustment losses, idling &
minor stoppages, reduced speed, defects & rework, spills,
process upset conditions, startup and yield losses. The
proposed algorithm gives the mathematical approach for
computing the plant effectiveness, i.e. Overall Equipment
Effectiveness (OEE). Measurement is an important
requirement for continuous improvement processes. It is
necessary to establish appropriate matrices for measurement
purposes. Measurement is an important requirement for
continuous improvement processes.
M. Maran, is with Department of Mechanical Engineering in Velammal
college of Technology – Madurai - India. Currently is doing research in
TPM and its assessment Methodology. (e-mail: gsmaran@yahoo.com).
G. Manikandan, completed his Ph.D from Anna University, Chennai,
India. he is with Department of Mechanical Engineering in Velammal
college of Technology – Madurai - India. Currently working in TQM and
its applications. (e-mail: gmk@vcet.ac.in).
K.Thiagarajan completed his Ph.D from University of Mysore, Mysore,
India. Currently working in the Department of Mathematics, Velammal
college of Technology, Madurai, India. Currently he is working on web
mining through automata, set theory and Fuzzy Logic. His area of
specialization is coloring of graphs and DNA Computing. (e-mail:
vidhyamannan@yahoo.com).
It is necessary to establish appropriate matrices for
measurement purposes. From a generic perspective, TPM
can be defined in terms of OEE, which in-turn can be
considered combination of the operation maintenance,
equipment management, and available resources. The goal
of TPM is to maximize equipment effectiveness, and OEE is
used as a measure.
OEE measurement is an effective way of analyzing the
efficiency of a single machine or an integrated
manufacturing system. OEE incorporates availability
performance rate and quality rate and gives results. In other
words, OEE addresses all losses caused by the equipment,
not being available when needed due to breakdowns or set-
up and adjustment losses, not running at the optimum rate
due to reduced speed or idling and minor stoppage Losses
and not producing first quality output due to defects and
rework or start-up losses. A key objective of TPM is cost
efficiency; maximizing Overall Equipment Effectiveness
through the elimination or minimization of all these six
losses by means of weighted signed graph method.
The proposed work optimizes the six losses associated with
the OEE by weighted signed graph approach. The
methodology of using signed graph for the betterment of the
TPM implementing organizations and other industries is
discussed. Finally, this approach gives them the direction to
work-on and fix their targets and OEE can be calculated as
follows,
Overall Equipment Effectiveness (OEE) = A X PR X Q,
Where,
A - Availability of the machine. Availability is proportion
of time a machine is actually available to out of time it
should be available
P- Performance Rate i.e., P=RE X SR
RE - Rate efficiency is actual average cycle time which is
slower than design cycle time because of jams, etc. Output
is reduced because of jams.
SR - Speed Rate is actual cycle time which is slower than
design cycle time; machine output is reduced because it is
running at a reduced speed.
Q - Quality rate, is percentage of good parts out of total
production, sometimes called yield.
In other words, OEE can be expressed as
OEE = Utilization (Availability) × Rate Loss
(Performance) × Yield (Quality)
All these figures are usually expressed in percentage and
higher OEE translates into higher equipment efficiency from
the equipment. Surprisingly, the OEE of most equipments
ranges from 40%-60%, whereas the benchmark is 85%,
world class [8]. As such, OEE has become the accepted
Overall Equipment Effectiveness Measurement
By Weighted Approach Method
M. Maran, G. Manikandan, and K.Thiagarajan
I
Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II,
IMECS 2012, March 14 - 16, 2012, Hong Kong
ISBN: 978-988-19251-9-0
ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online)
IMECS 2012
indicator to assess, how plants/factories actually manage
their most expensive asset, the equipment, to produce
saleable goods, with minimum losses and wastes.
The OEE is not that which gives one magic number; it
gives three numbers other than OEE, which are all useful
individually as the situation changes from day to day. In
addition, it helps to visualize performance in simple terms -
a very practical simplification. The OEE is probably the
most important tool in continuous improvement program in
manufacturing industry. Through the Pareto analysis the
operators can observe, where they lose most of the
production (The 6 Major Losses as mentioned in above).
Significant improvement can be evident within a short
period by means of eliminating the six equipment losses
with result of enhanced maintenance activities and
equipment management
Increasingly, companies working in process
manufacturing environments are discovering a surprisingly
effective framework from which to tackle the continuous
improvement challenge: the “Six Big Losses” approach.
Developed in the 1970’s by the Japan Institute of Plant
Maintenance (JIPM), the Six Big Losses framework enables
manufacturers to examine their efficiency problem with an
unprecedented level of granularity According to JIPM, the
OEE is based on three main aspects; each element concerns
with different losses as shown in the table 1.
II. OVER VIEW OF THE PAPER
Section I presents Introduction, Section II presents
weighted graph method of OEE, Section III deals with flow
diagram of the proposed scheme, Section IV presents ratings
for the factors of OEE & estimated results as well as
experimental results and Section V presents concurrent
application for industry. Finally Section VI presents
opportunity for further enrichment.
III. OEE - WEIGHTED APPROACH
In proposed system, OEE is considered as a signed
graph, where each factors BD, SA, MI, RS, RL & SL are
assigned with weight ratings based on the loss percentage.
Signed weight (++, +-, -+, --) is attached to each factors of
the graph based on the combination of above contributing
factors for A, P, Q & OEE. Depending upon the BD, SA,
MI, RS, RL & SL ratings A, P & Q are calculated. Similarly
based on A, P & Q ratings OEE is estimated.
WEIGHTED RATING FOR A, P & Q
In a weighted graph, A1, A2, A3 and A4 are considered
as the loss ratings, where A1< A2< A3< A4. (i.e., A1 is the
lowest loss level rating and A4 is the highest loss level
rating) [7].The ratings for the basic six parameters differ
from one another based on user. In the subsequent ranking
scheme, more weightage is given for BD i.e., up to 10%
loss, where as other parameters have less weightage of 2 to
3%.
1. BD - Breakdown (in %):
a. A1 = 0 to ≤ 1
b. A2 = > 1 to ≤ 5
c. A3 = > 5 to ≤ 10
d. A4 = > 10
2. SA - Setup adjustment (in %):
a. A1 = 0 to ≤ 0.5
b. A2 = > 0.5 to ≤ 1
c. A3 = > 1 to ≤ 2
d. A4 = > 2
3. MI - Minor / Idling stoppages (in %):
a. A1 = 0 to ≤ 1
b. A2 = > 1 to ≤ 2
c. A3 = > 2 to ≤ 3
d. A4 = > 3
4. RS - Reduced speed (in %):
a. A1 = 0 to ≤ 1
b. A2 = > 1 to ≤ 2
c. A3 = > 2 to ≤ 3
d. A4 = > 3
5. RL - Reject / Rework losses (in %):
a. A1 = 0 to ≤ 0.5
b. A2 = > 0.5 to ≤ 1
c. A3 = > 1 to ≤ 2
d. A4 = > 2
6. SL - Start-up losses (in %):
a. A1 = 0 to ≤ 0.5
b. A2 = > 0.5 to ≤ 1
c. A3 = > 1 to ≤ 2
d. A4 = > 2
IV. PROGRAM DEPENDENCE GRAPH
a) In the following program dependence graph, stage 1
calculation of availability with the inputs BD & SA
with constrain limit shown in Fig. 1.1 & 1.2.
b) In stage 2, calculation of performance with the inputs
of MI & RS with constrain limit shown in the fig 2.1
& 2.2.
c) In stage 3, calculation of quality with the inputs of
RL & SL with constrain limit shown in the fig 3.1 &
3.2.
d) Determination of OEE using formula OEE = Pi x Qi
x Ri x Si x Ti x Ui.
Performance
Aspects Relating Losses
1. Availability Rate
(A)
 Equipment failure
/breakdown losses
 Set-up and adjustment
losses
2. Performance
Efficiency (P)
 Idling and minor
stoppage losses
 Reduced speed losses
3. Quality Rate
(Q)
 Defect and rework
losses
 Start-up losses
Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II,
IMECS 2012, March 14 - 16, 2012, Hong Kong
ISBN: 978-988-19251-9-0
ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online)
IMECS 2012
STAGE 1 (Fig 1.1):
(Fig 1.2):
STAGE 1 - Calculation of Availability
(Input BD & SA)
STAGE 3 - Calculation of Quality
(Input RL & SL)
STAGE 2 - Calculation of Performance
(Input MI & RS)
OEE = Pi x Qi x Ri x Si x Ti x Ui
Determination of OEE Range
4
3
2
1
6
5
Start
END
Yes
No
IF
0 < BD ≤ 1.0
IF
1.0 < BD ≤ 5.0
P1
1
P2
1
IF
5.0 < BD ≤ 10.0
P3
1P4 1
No
Yes
No
Yes
IF
0 < SA ≤ 0.5
IF
0.5 < SA ≤ 1.0
Q1
2
Q2
2
IF
1.0 < SA ≤ 2.0
Q3
2Q4 2
No
Yes
No
Yes
No
Yes
Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II,
IMECS 2012, March 14 - 16, 2012, Hong Kong
ISBN: 978-988-19251-9-0
ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online)
IMECS 2012
STAGE 2 (Fig 2.1):
(Fig 2.2):
STAGE 3 (Fig 3.1):
(Fig 3.2):
IF
0 < MI ≤ 1.0
IF
1.0 < MI ≤ 2.0
R1
3
R2
3
IF
2.0 < MI ≤ 3.0
R3
3R4 3
No
Yes
No
Yes
No
Yes
IF
0 < RS ≤ 1.0
IF
1.0 < RS ≤ 2.0
S1
4
S2
4
IF
2.0 < RS ≤ 3.0
S3
4S4 4
No
Yes
No
Yes
No
Yes
IF
0 < RL ≤ 0.5
IF
0.5 < RL ≤ 1.0
T1
5
T2
5
IF
1.0 < RL ≤ 2.0
T3
5T4 5
IF
0 < SL ≤ 0.5
IF
0.5 < SL ≤ 1.0
U1
6
U2
6
IF
1.0 < SL ≤ 2.0
U3
6U4 6
No
Yes
No
Yes
No
Yes
Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II,
IMECS 2012, March 14 - 16, 2012, Hong Kong
ISBN: 978-988-19251-9-0
ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online)
IMECS 2012
SIGNED GRAPH METHOD FOR OEE
TABLE 2
AVAILABILITY RATING BASED ON BREAKDOWN AND SETUP ADJUSTMENT
BREAKDOWN
(BD)
SETUP ADJUSTMENT
(SA)
AVILABILITY (A)
+ + +
+ _ +
_ + _
_ _ _
TABLE 3
PERFORMANCE RATING BASED ON IDLING, MINIOR STOPPAGES AND
REDUCED SPEED
IDLING & MINIOR
STOPPAGES (IM)
REDUCED SPEED
(RS)
PERFORMANCE
(P)
+ + +
+ _ +
_ + _
_ _ _
TABLE 4
QUALITY RATING BASED ON DEFECT / REWORK AND STRAT-UP LOSSES
DEFECT /
REWORK (DR)
STRAT-UP LOSSES (SL) QUALITY (Q)
+ + +
+ _ +
_ + _
_ _ _
TABLE 5
OEE RATING BASED ON AVILABILITY, PERFORMANCE
& QULITY RATINGS
AVAILABILITY
(A)
PERFORMANCE
(P)
QUALITY
(Q)
OEE
+ + + ++
+ + _ +_
+ _ + +_
_ + + +_
+ _ _ +-*
_ + _ -+
_ _ + -+
_ _ _ --
* Availability is having major impact on the OEE. In most of
circumstances, A (+) ranking gives better OEE, in spite of both P (-) &
Q (-) ratings
TABLE 6
EXPRIMENTAL RESULTS
Here we assumed Values for A, P & Q, and for various vales of A,
P & Q, OEE was calculated
AVAILABILITY
(A)
PERFORMANCE
(P)
QUALITY
(Q)
OEE
95 98 99 92.2
95 98 97 90.3
95 97 94 86.6
90 98 98 86.4
93 96 96 85.7*
88 98 94 81.1
87 91 92 72.8
86 90 90 69.7
Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II,
IMECS 2012, March 14 - 16, 2012, Hong Kong
ISBN: 978-988-19251-9-0
ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online)
IMECS 2012
VI. REAL TIME APPLICATION
O.E.E. data collection, analysis and reporting provide the
principal basis for improving equipment effectiveness by
eliminating the major equipment-related losses. The
weighted OEE method is presented and the analytical
hierarchy process has been applied for setting the weight of
all the factors namely BD, SA, MI, RS, RL & SL. The
potential of the proposed method can be applied for new as
well as existing industries. OEE data very quickly leads to
root-cause identification and elimination of losses. Overall
Equipment Effectiveness continues to gain acceptance as an
effective method to measure production floor performance.
Capturing reliable production floor information is critical for
producing reliable OEE focused progress of the plant or
equipment. It will be optimal tool for plants implementing
TPM.
This weighted approach and OEE results will be
benchmarking tool to gauge manufacturing system,
especially maintenance management system. OEE helps
manufacturer to improve productivity and get better
visibility into their operations and also allow them to take
sound management decisions.
VII. CONCLUSION AND FUTURE WORKS
We may apply this methodology through algorithmic
approach to get computational work, the values of OEE
categorized through fuzzy logic method on A, P & Q to get
optimization.
No manual data collection or manual compilation for
OEE calculations is the first step in improving both the
accuracy of OEE reports as wells as reducing the cost to
produce the reports through neural network.The utility of
artificial neural network models lies in fact that, they can be
used to infer for future purposes.
VIII. LIST OF ACRONYMS
TPM Total Productive Maintenance
OEE Overall Equipment Effectiveness
PE Plant Effectiveness
A Availability
P Performance Rate
Q Quality Rate
JIPM Japan Institute of Plant Maintenance
BD Break-Down
SA Setup Adjustment
MI Minor / Idling stoppages
RS Reduced Speed
RL Reject / Rework Losses
SL Start-up LossesReferences
ACKNOWLEDGEMENT
The authors would like to thank Dr. Ponnammal
Natarajan, Former Director of Research, Anna University,
and Chennai, India. Currently Advisor, (Research and
Development), Rajalakshmi Engineering College, for her
intuitive ideas and fruitful discussions with respect to the
paper’s contribution.
REFERENCES
[1] B. Dal, P. Tugwell and R. Greatbanks (2000), “Overall
equipment effectiveness as a measure of operational
improvement”, International Journal of Operations &
Production Management, vol. 20, no. 12, pp. 1488–1520.
[2] Bin Yu, Munindar P.Singh, An Evidential model for
distributed reputation Management, AAMAS'02, July 15-
19,2002, Bologna, Italy.
[3] B. Yu and M. P. Singh. Trust and reputation management in a
small- world network. In Proceedings of the 4th International
Conference on MultiAgent Systems, pages 449-450, 2000.
[4] B.Yu and M.P.Singh. A social Mechanism of reputation
management in electronic communities. In proceedings of the
4th International Workshop on Cooperative Information
Agents, 2000.
[5] F.Harary Addision-Wesley, Reading "Graph Theory", Mass,
(1969).
[6] K.Thiagarajan, A.Raghunathan, Ponnammal Natarajan,
G.Poonkuzhali and Prashant Ranjan (2009), “Weighted Graph
Approach for Trust Reputation Management”, World
Academy of Science, Engineering and Technology 56 – 2009.
[7] Lungberg.O (1998), Mearsument of overall equipment
effectiveness as a basic for TPM activities. International
Journal of operation. And production management. 18 (5)
495-507.
[8] M. Lesshammar (1999)., “Evaluation and improvement of
manufacturing performance measurement systems – the
role of OEE”, International Journal of Operations and
Production Management, vol. 19, no. 1, pp. 55-78.
[9] S. Nakajima (1988) “Introduction to TPM”, Productivity
Press,Cambridge, MA.
[10] S.P.Srinivasan, P.Malliga, K.Thiagarajan, An Algorithmic
Graphical approach for Ground level logistics management of
Jatropha seed distribution.,Ultra Scientist of Physical
Sciences, Vol. 20, No:3,(M)(2008), Page(s): 605-612.
[11] Venkatesh, J. (2005), An Introduction to Total Productive
Maintenance (TPM), The Plant Maintenance Resource
Center, pp 2-3 and 15-27.
[12] Wireman, T., 1990. World Class Maintenance Management.
Industrial Press, New York.
[13] Yamashina, H., 1995. Japanese manufacturing strategy and
the role of total productive maintenance. Journal of Quality in
Maintenance Engineering 1 (1), 27–38.
Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II,
IMECS 2012, March 14 - 16, 2012, Hong Kong
ISBN: 978-988-19251-9-0
ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online)
IMECS 2012

More Related Content

What's hot

Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...IAEME Publication
 
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET-  	  Optimization of Machining Facility Layout by using Simulation: Cas...IRJET-  	  Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...IRJET Journal
 
IRJET- Forecast Modelling and Performance Load Volume Analytic Techniques of ...
IRJET- Forecast Modelling and Performance Load Volume Analytic Techniques of ...IRJET- Forecast Modelling and Performance Load Volume Analytic Techniques of ...
IRJET- Forecast Modelling and Performance Load Volume Analytic Techniques of ...IRJET Journal
 
Designing Unbalanced Assembly Lines: A Simulation Analysis to Evaluate Impact...
Designing Unbalanced Assembly Lines: A Simulation Analysis to Evaluate Impact...Designing Unbalanced Assembly Lines: A Simulation Analysis to Evaluate Impact...
Designing Unbalanced Assembly Lines: A Simulation Analysis to Evaluate Impact...IJERA Editor
 
Layout Case Study
Layout Case StudyLayout Case Study
Layout Case StudyNilam Kabra
 
Chapter engineering economics ppt, economics, semester, engineering electro...
Chapter   engineering economics ppt, economics, semester, engineering electro...Chapter   engineering economics ppt, economics, semester, engineering electro...
Chapter engineering economics ppt, economics, semester, engineering electro...srm
 
Job shop-scheduling uain heurstic bottle neck shift
Job shop-scheduling uain heurstic bottle neck shiftJob shop-scheduling uain heurstic bottle neck shift
Job shop-scheduling uain heurstic bottle neck shiftKassu Jilcha (PhD)
 
Technical efficiency measurement by data envelopment analysis an applicatio...
Technical efficiency measurement by data envelopment analysis   an applicatio...Technical efficiency measurement by data envelopment analysis   an applicatio...
Technical efficiency measurement by data envelopment analysis an applicatio...Geetika Sharma
 
IRJET- Effective Implementation of Planned Maintenance in a Gas Producing Pla...
IRJET- Effective Implementation of Planned Maintenance in a Gas Producing Pla...IRJET- Effective Implementation of Planned Maintenance in a Gas Producing Pla...
IRJET- Effective Implementation of Planned Maintenance in a Gas Producing Pla...IRJET Journal
 
Application of or for industrial engineers
Application of or for industrial engineersApplication of or for industrial engineers
Application of or for industrial engineersHakeem-Ur- Rehman
 
IRJET- Distribution Selection for Pump Manufacturing Companies
IRJET- Distribution Selection for Pump Manufacturing CompaniesIRJET- Distribution Selection for Pump Manufacturing Companies
IRJET- Distribution Selection for Pump Manufacturing CompaniesIRJET Journal
 
PREDICTION OF REPAIR & MAINTENANCE COSTS OF DIESEL ENGINE
PREDICTION OF REPAIR & MAINTENANCE COSTS OF DIESEL ENGINEPREDICTION OF REPAIR & MAINTENANCE COSTS OF DIESEL ENGINE
PREDICTION OF REPAIR & MAINTENANCE COSTS OF DIESEL ENGINEijmech
 
A review on non traditional algorithms for job shop scheduling
A review on non traditional algorithms for job shop schedulingA review on non traditional algorithms for job shop scheduling
A review on non traditional algorithms for job shop schedulingiaemedu
 

What's hot (15)

Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...
 
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET-  	  Optimization of Machining Facility Layout by using Simulation: Cas...IRJET-  	  Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
 
IRJET- Forecast Modelling and Performance Load Volume Analytic Techniques of ...
IRJET- Forecast Modelling and Performance Load Volume Analytic Techniques of ...IRJET- Forecast Modelling and Performance Load Volume Analytic Techniques of ...
IRJET- Forecast Modelling and Performance Load Volume Analytic Techniques of ...
 
Designing Unbalanced Assembly Lines: A Simulation Analysis to Evaluate Impact...
Designing Unbalanced Assembly Lines: A Simulation Analysis to Evaluate Impact...Designing Unbalanced Assembly Lines: A Simulation Analysis to Evaluate Impact...
Designing Unbalanced Assembly Lines: A Simulation Analysis to Evaluate Impact...
 
Layout Case Study
Layout Case StudyLayout Case Study
Layout Case Study
 
Chapter engineering economics ppt, economics, semester, engineering electro...
Chapter   engineering economics ppt, economics, semester, engineering electro...Chapter   engineering economics ppt, economics, semester, engineering electro...
Chapter engineering economics ppt, economics, semester, engineering electro...
 
Job shop-scheduling uain heurstic bottle neck shift
Job shop-scheduling uain heurstic bottle neck shiftJob shop-scheduling uain heurstic bottle neck shift
Job shop-scheduling uain heurstic bottle neck shift
 
Team5_-_Final_Report
Team5_-_Final_ReportTeam5_-_Final_Report
Team5_-_Final_Report
 
Technical efficiency measurement by data envelopment analysis an applicatio...
Technical efficiency measurement by data envelopment analysis   an applicatio...Technical efficiency measurement by data envelopment analysis   an applicatio...
Technical efficiency measurement by data envelopment analysis an applicatio...
 
IRJET- Effective Implementation of Planned Maintenance in a Gas Producing Pla...
IRJET- Effective Implementation of Planned Maintenance in a Gas Producing Pla...IRJET- Effective Implementation of Planned Maintenance in a Gas Producing Pla...
IRJET- Effective Implementation of Planned Maintenance in a Gas Producing Pla...
 
Application of or for industrial engineers
Application of or for industrial engineersApplication of or for industrial engineers
Application of or for industrial engineers
 
IRJET- Distribution Selection for Pump Manufacturing Companies
IRJET- Distribution Selection for Pump Manufacturing CompaniesIRJET- Distribution Selection for Pump Manufacturing Companies
IRJET- Distribution Selection for Pump Manufacturing Companies
 
PREDICTION OF REPAIR & MAINTENANCE COSTS OF DIESEL ENGINE
PREDICTION OF REPAIR & MAINTENANCE COSTS OF DIESEL ENGINEPREDICTION OF REPAIR & MAINTENANCE COSTS OF DIESEL ENGINE
PREDICTION OF REPAIR & MAINTENANCE COSTS OF DIESEL ENGINE
 
Bo24437446
Bo24437446Bo24437446
Bo24437446
 
A review on non traditional algorithms for job shop scheduling
A review on non traditional algorithms for job shop schedulingA review on non traditional algorithms for job shop scheduling
A review on non traditional algorithms for job shop scheduling
 

Viewers also liked

General_Cover_Letter
General_Cover_LetterGeneral_Cover_Letter
General_Cover_LetterPeggy Johnson
 
5.2 csolvingquads
5.2 csolvingquads5.2 csolvingquads
5.2 csolvingquadsvhiggins1
 
How to manufacture prestressed concrete beams and hollow core slabs?
How to manufacture prestressed concrete beams and hollow core slabs?How to manufacture prestressed concrete beams and hollow core slabs?
How to manufacture prestressed concrete beams and hollow core slabs?Prensoland S.A.
 
Unit 4 credit rating
Unit 4   credit ratingUnit 4   credit rating
Unit 4 credit ratingDeepika S.R.
 
6 GRADUATION PASS CERTIFICATE
6 GRADUATION PASS CERTIFICATE6 GRADUATION PASS CERTIFICATE
6 GRADUATION PASS CERTIFICATEMukut Barman
 
Consumer Behaviour Research for Surf Product
Consumer Behaviour Research for Surf ProductConsumer Behaviour Research for Surf Product
Consumer Behaviour Research for Surf ProductSumedh Rewatkar
 

Viewers also liked (10)

Chats en la educación
Chats en la educación Chats en la educación
Chats en la educación
 
General_Cover_Letter
General_Cover_LetterGeneral_Cover_Letter
General_Cover_Letter
 
5.2 csolvingquads
5.2 csolvingquads5.2 csolvingquads
5.2 csolvingquads
 
How to manufacture prestressed concrete beams and hollow core slabs?
How to manufacture prestressed concrete beams and hollow core slabs?How to manufacture prestressed concrete beams and hollow core slabs?
How to manufacture prestressed concrete beams and hollow core slabs?
 
Unit 4 credit rating
Unit 4   credit ratingUnit 4   credit rating
Unit 4 credit rating
 
6 GRADUATION PASS CERTIFICATE
6 GRADUATION PASS CERTIFICATE6 GRADUATION PASS CERTIFICATE
6 GRADUATION PASS CERTIFICATE
 
Consumer Behaviour Research for Surf Product
Consumer Behaviour Research for Surf ProductConsumer Behaviour Research for Surf Product
Consumer Behaviour Research for Surf Product
 
Problemas de programacion
Problemas de programacionProblemas de programacion
Problemas de programacion
 
Oberoimaxima
OberoimaximaOberoimaxima
Oberoimaxima
 
Kalpatarumulund1
Kalpatarumulund1Kalpatarumulund1
Kalpatarumulund1
 

Similar to Imecs2012 pp1280 1285

Optimization of Injection Molding Process-literature review
Optimization of Injection Molding Process-literature reviewOptimization of Injection Molding Process-literature review
Optimization of Injection Molding Process-literature reviewAlex Larsh
 
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean PrinciplesLead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean PrinciplesIRJET Journal
 
Design and Analysis of Chute System to obtain World Class OEE
Design and Analysis of Chute System to obtain World Class OEEDesign and Analysis of Chute System to obtain World Class OEE
Design and Analysis of Chute System to obtain World Class OEEijsrd.com
 
Gaining Insights into Patient Satisfaction through Interpretable Machine Lear...
Gaining Insights into Patient Satisfaction through Interpretable Machine Lear...Gaining Insights into Patient Satisfaction through Interpretable Machine Lear...
Gaining Insights into Patient Satisfaction through Interpretable Machine Lear...IRJET Journal
 
Hybrid Optimization Approaches to Economic Load Dispatch Problems – A Compara...
Hybrid Optimization Approaches to Economic Load Dispatch Problems – A Compara...Hybrid Optimization Approaches to Economic Load Dispatch Problems – A Compara...
Hybrid Optimization Approaches to Economic Load Dispatch Problems – A Compara...IRJET Journal
 
C041211117
C041211117C041211117
C041211117IOSR-JEN
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining CellIRJET Journal
 
IRJET- Comparison of GA and PSO Optimization Techniques to Optimal Planning o...
IRJET- Comparison of GA and PSO Optimization Techniques to Optimal Planning o...IRJET- Comparison of GA and PSO Optimization Techniques to Optimal Planning o...
IRJET- Comparison of GA and PSO Optimization Techniques to Optimal Planning o...IRJET Journal
 
IRJET- Literature Review on Manufacturing System Performance Improvement ...
IRJET-  	  Literature Review on Manufacturing System Performance Improvement ...IRJET-  	  Literature Review on Manufacturing System Performance Improvement ...
IRJET- Literature Review on Manufacturing System Performance Improvement ...IRJET Journal
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
IRJET- Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...
IRJET-  	  Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...IRJET-  	  Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...
IRJET- Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...IRJET Journal
 
IRJET- Optimum Design of Fan, Queen and Pratt Trusses
IRJET-  	  Optimum Design of Fan, Queen and Pratt TrussesIRJET-  	  Optimum Design of Fan, Queen and Pratt Trusses
IRJET- Optimum Design of Fan, Queen and Pratt TrussesIRJET Journal
 
Volume 2-issue-6-2177-2185
Volume 2-issue-6-2177-2185Volume 2-issue-6-2177-2185
Volume 2-issue-6-2177-2185Editor IJARCET
 
Optimization of supply chain logistics cost
Optimization of supply chain logistics costOptimization of supply chain logistics cost
Optimization of supply chain logistics costIAEME Publication
 
IRJET- A Novel Gabor Feed Forward Network for Pose Invariant Face Recogni...
IRJET-  	  A Novel Gabor Feed Forward Network for Pose Invariant Face Recogni...IRJET-  	  A Novel Gabor Feed Forward Network for Pose Invariant Face Recogni...
IRJET- A Novel Gabor Feed Forward Network for Pose Invariant Face Recogni...IRJET Journal
 
A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)OEEsystems International
 

Similar to Imecs2012 pp1280 1285 (20)

Optimization of Injection Molding Process-literature review
Optimization of Injection Molding Process-literature reviewOptimization of Injection Molding Process-literature review
Optimization of Injection Molding Process-literature review
 
H012535263
H012535263H012535263
H012535263
 
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean PrinciplesLead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
 
Design and Analysis of Chute System to obtain World Class OEE
Design and Analysis of Chute System to obtain World Class OEEDesign and Analysis of Chute System to obtain World Class OEE
Design and Analysis of Chute System to obtain World Class OEE
 
Gaining Insights into Patient Satisfaction through Interpretable Machine Lear...
Gaining Insights into Patient Satisfaction through Interpretable Machine Lear...Gaining Insights into Patient Satisfaction through Interpretable Machine Lear...
Gaining Insights into Patient Satisfaction through Interpretable Machine Lear...
 
Hybrid Optimization Approaches to Economic Load Dispatch Problems – A Compara...
Hybrid Optimization Approaches to Economic Load Dispatch Problems – A Compara...Hybrid Optimization Approaches to Economic Load Dispatch Problems – A Compara...
Hybrid Optimization Approaches to Economic Load Dispatch Problems – A Compara...
 
I012536474
I012536474I012536474
I012536474
 
C041211117
C041211117C041211117
C041211117
 
Over all Equipment Effectiveness (OEE) Measurement Analysis on Gas Power Plan...
Over all Equipment Effectiveness (OEE) Measurement Analysis on Gas Power Plan...Over all Equipment Effectiveness (OEE) Measurement Analysis on Gas Power Plan...
Over all Equipment Effectiveness (OEE) Measurement Analysis on Gas Power Plan...
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
IRJET- Comparison of GA and PSO Optimization Techniques to Optimal Planning o...
IRJET- Comparison of GA and PSO Optimization Techniques to Optimal Planning o...IRJET- Comparison of GA and PSO Optimization Techniques to Optimal Planning o...
IRJET- Comparison of GA and PSO Optimization Techniques to Optimal Planning o...
 
IRJET- Literature Review on Manufacturing System Performance Improvement ...
IRJET-  	  Literature Review on Manufacturing System Performance Improvement ...IRJET-  	  Literature Review on Manufacturing System Performance Improvement ...
IRJET- Literature Review on Manufacturing System Performance Improvement ...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
IRJET- Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...
IRJET-  	  Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...IRJET-  	  Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...
IRJET- Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...
 
IRJET- Optimum Design of Fan, Queen and Pratt Trusses
IRJET-  	  Optimum Design of Fan, Queen and Pratt TrussesIRJET-  	  Optimum Design of Fan, Queen and Pratt Trusses
IRJET- Optimum Design of Fan, Queen and Pratt Trusses
 
IMPROVEMENT OF QUALITY SIGMA LEVEL OF COPPER TERMINAL AT VERTICAL MACHINING C...
IMPROVEMENT OF QUALITY SIGMA LEVEL OF COPPER TERMINAL AT VERTICAL MACHINING C...IMPROVEMENT OF QUALITY SIGMA LEVEL OF COPPER TERMINAL AT VERTICAL MACHINING C...
IMPROVEMENT OF QUALITY SIGMA LEVEL OF COPPER TERMINAL AT VERTICAL MACHINING C...
 
Volume 2-issue-6-2177-2185
Volume 2-issue-6-2177-2185Volume 2-issue-6-2177-2185
Volume 2-issue-6-2177-2185
 
Optimization of supply chain logistics cost
Optimization of supply chain logistics costOptimization of supply chain logistics cost
Optimization of supply chain logistics cost
 
IRJET- A Novel Gabor Feed Forward Network for Pose Invariant Face Recogni...
IRJET-  	  A Novel Gabor Feed Forward Network for Pose Invariant Face Recogni...IRJET-  	  A Novel Gabor Feed Forward Network for Pose Invariant Face Recogni...
IRJET- A Novel Gabor Feed Forward Network for Pose Invariant Face Recogni...
 
A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)
 

Recently uploaded

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 

Imecs2012 pp1280 1285

  • 1. Abstract — This research is intended to enhance the original Overall Equipment Effectiveness (OEE). Calculating plant/equipment OEE can be very helpful for monitoring trends (such as whether a given plant is improving OEE over time) or as a rough measure of where a given plant lies in the OEE benchmarking spectrum. OEE concept in TPM implementation truly reduces manufacturing complex problems into simple, intuitive presentation of information. It helps to systematically improve the process with easy-to-obtain measurements. The OEE is the process, which is acquired to specify an equivalent weight setting of every single element, even if, each concerning losses are totally different. Hence, the study proposes a weighted graph approach, to identify dissimilarity in weighting each OEE element. The proposed concept is used to find the OEE for the plant, as well as to set the target for the plant and the area to focus for their improvement. Index Terms— TPM, effectiveness, weighted signed graph, OEE, performance improvement. I. INTRODUCTION N the highly competitive manufacturing environment prevailing at the global level, plants of any country or region should be benchmarked and maintained at world- class level. Failing to do that, a plant may be exposed to various difficulties. The results of implementation of Total Productive Maintenance (TPM) program increased plant efficiency and productivity significantly by means of eliminating the major losses. The important goal of TPM is the total elimination of all six major losses, including breakdowns, equipment setup & adjustment losses, idling & minor stoppages, reduced speed, defects & rework, spills, process upset conditions, startup and yield losses. The proposed algorithm gives the mathematical approach for computing the plant effectiveness, i.e. Overall Equipment Effectiveness (OEE). Measurement is an important requirement for continuous improvement processes. It is necessary to establish appropriate matrices for measurement purposes. Measurement is an important requirement for continuous improvement processes. M. Maran, is with Department of Mechanical Engineering in Velammal college of Technology – Madurai - India. Currently is doing research in TPM and its assessment Methodology. (e-mail: gsmaran@yahoo.com). G. Manikandan, completed his Ph.D from Anna University, Chennai, India. he is with Department of Mechanical Engineering in Velammal college of Technology – Madurai - India. Currently working in TQM and its applications. (e-mail: gmk@vcet.ac.in). K.Thiagarajan completed his Ph.D from University of Mysore, Mysore, India. Currently working in the Department of Mathematics, Velammal college of Technology, Madurai, India. Currently he is working on web mining through automata, set theory and Fuzzy Logic. His area of specialization is coloring of graphs and DNA Computing. (e-mail: vidhyamannan@yahoo.com). It is necessary to establish appropriate matrices for measurement purposes. From a generic perspective, TPM can be defined in terms of OEE, which in-turn can be considered combination of the operation maintenance, equipment management, and available resources. The goal of TPM is to maximize equipment effectiveness, and OEE is used as a measure. OEE measurement is an effective way of analyzing the efficiency of a single machine or an integrated manufacturing system. OEE incorporates availability performance rate and quality rate and gives results. In other words, OEE addresses all losses caused by the equipment, not being available when needed due to breakdowns or set- up and adjustment losses, not running at the optimum rate due to reduced speed or idling and minor stoppage Losses and not producing first quality output due to defects and rework or start-up losses. A key objective of TPM is cost efficiency; maximizing Overall Equipment Effectiveness through the elimination or minimization of all these six losses by means of weighted signed graph method. The proposed work optimizes the six losses associated with the OEE by weighted signed graph approach. The methodology of using signed graph for the betterment of the TPM implementing organizations and other industries is discussed. Finally, this approach gives them the direction to work-on and fix their targets and OEE can be calculated as follows, Overall Equipment Effectiveness (OEE) = A X PR X Q, Where, A - Availability of the machine. Availability is proportion of time a machine is actually available to out of time it should be available P- Performance Rate i.e., P=RE X SR RE - Rate efficiency is actual average cycle time which is slower than design cycle time because of jams, etc. Output is reduced because of jams. SR - Speed Rate is actual cycle time which is slower than design cycle time; machine output is reduced because it is running at a reduced speed. Q - Quality rate, is percentage of good parts out of total production, sometimes called yield. In other words, OEE can be expressed as OEE = Utilization (Availability) × Rate Loss (Performance) × Yield (Quality) All these figures are usually expressed in percentage and higher OEE translates into higher equipment efficiency from the equipment. Surprisingly, the OEE of most equipments ranges from 40%-60%, whereas the benchmark is 85%, world class [8]. As such, OEE has become the accepted Overall Equipment Effectiveness Measurement By Weighted Approach Method M. Maran, G. Manikandan, and K.Thiagarajan I Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II, IMECS 2012, March 14 - 16, 2012, Hong Kong ISBN: 978-988-19251-9-0 ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online) IMECS 2012
  • 2. indicator to assess, how plants/factories actually manage their most expensive asset, the equipment, to produce saleable goods, with minimum losses and wastes. The OEE is not that which gives one magic number; it gives three numbers other than OEE, which are all useful individually as the situation changes from day to day. In addition, it helps to visualize performance in simple terms - a very practical simplification. The OEE is probably the most important tool in continuous improvement program in manufacturing industry. Through the Pareto analysis the operators can observe, where they lose most of the production (The 6 Major Losses as mentioned in above). Significant improvement can be evident within a short period by means of eliminating the six equipment losses with result of enhanced maintenance activities and equipment management Increasingly, companies working in process manufacturing environments are discovering a surprisingly effective framework from which to tackle the continuous improvement challenge: the “Six Big Losses” approach. Developed in the 1970’s by the Japan Institute of Plant Maintenance (JIPM), the Six Big Losses framework enables manufacturers to examine their efficiency problem with an unprecedented level of granularity According to JIPM, the OEE is based on three main aspects; each element concerns with different losses as shown in the table 1. II. OVER VIEW OF THE PAPER Section I presents Introduction, Section II presents weighted graph method of OEE, Section III deals with flow diagram of the proposed scheme, Section IV presents ratings for the factors of OEE & estimated results as well as experimental results and Section V presents concurrent application for industry. Finally Section VI presents opportunity for further enrichment. III. OEE - WEIGHTED APPROACH In proposed system, OEE is considered as a signed graph, where each factors BD, SA, MI, RS, RL & SL are assigned with weight ratings based on the loss percentage. Signed weight (++, +-, -+, --) is attached to each factors of the graph based on the combination of above contributing factors for A, P, Q & OEE. Depending upon the BD, SA, MI, RS, RL & SL ratings A, P & Q are calculated. Similarly based on A, P & Q ratings OEE is estimated. WEIGHTED RATING FOR A, P & Q In a weighted graph, A1, A2, A3 and A4 are considered as the loss ratings, where A1< A2< A3< A4. (i.e., A1 is the lowest loss level rating and A4 is the highest loss level rating) [7].The ratings for the basic six parameters differ from one another based on user. In the subsequent ranking scheme, more weightage is given for BD i.e., up to 10% loss, where as other parameters have less weightage of 2 to 3%. 1. BD - Breakdown (in %): a. A1 = 0 to ≤ 1 b. A2 = > 1 to ≤ 5 c. A3 = > 5 to ≤ 10 d. A4 = > 10 2. SA - Setup adjustment (in %): a. A1 = 0 to ≤ 0.5 b. A2 = > 0.5 to ≤ 1 c. A3 = > 1 to ≤ 2 d. A4 = > 2 3. MI - Minor / Idling stoppages (in %): a. A1 = 0 to ≤ 1 b. A2 = > 1 to ≤ 2 c. A3 = > 2 to ≤ 3 d. A4 = > 3 4. RS - Reduced speed (in %): a. A1 = 0 to ≤ 1 b. A2 = > 1 to ≤ 2 c. A3 = > 2 to ≤ 3 d. A4 = > 3 5. RL - Reject / Rework losses (in %): a. A1 = 0 to ≤ 0.5 b. A2 = > 0.5 to ≤ 1 c. A3 = > 1 to ≤ 2 d. A4 = > 2 6. SL - Start-up losses (in %): a. A1 = 0 to ≤ 0.5 b. A2 = > 0.5 to ≤ 1 c. A3 = > 1 to ≤ 2 d. A4 = > 2 IV. PROGRAM DEPENDENCE GRAPH a) In the following program dependence graph, stage 1 calculation of availability with the inputs BD & SA with constrain limit shown in Fig. 1.1 & 1.2. b) In stage 2, calculation of performance with the inputs of MI & RS with constrain limit shown in the fig 2.1 & 2.2. c) In stage 3, calculation of quality with the inputs of RL & SL with constrain limit shown in the fig 3.1 & 3.2. d) Determination of OEE using formula OEE = Pi x Qi x Ri x Si x Ti x Ui. Performance Aspects Relating Losses 1. Availability Rate (A)  Equipment failure /breakdown losses  Set-up and adjustment losses 2. Performance Efficiency (P)  Idling and minor stoppage losses  Reduced speed losses 3. Quality Rate (Q)  Defect and rework losses  Start-up losses Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II, IMECS 2012, March 14 - 16, 2012, Hong Kong ISBN: 978-988-19251-9-0 ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online) IMECS 2012
  • 3. STAGE 1 (Fig 1.1): (Fig 1.2): STAGE 1 - Calculation of Availability (Input BD & SA) STAGE 3 - Calculation of Quality (Input RL & SL) STAGE 2 - Calculation of Performance (Input MI & RS) OEE = Pi x Qi x Ri x Si x Ti x Ui Determination of OEE Range 4 3 2 1 6 5 Start END Yes No IF 0 < BD ≤ 1.0 IF 1.0 < BD ≤ 5.0 P1 1 P2 1 IF 5.0 < BD ≤ 10.0 P3 1P4 1 No Yes No Yes IF 0 < SA ≤ 0.5 IF 0.5 < SA ≤ 1.0 Q1 2 Q2 2 IF 1.0 < SA ≤ 2.0 Q3 2Q4 2 No Yes No Yes No Yes Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II, IMECS 2012, March 14 - 16, 2012, Hong Kong ISBN: 978-988-19251-9-0 ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online) IMECS 2012
  • 4. STAGE 2 (Fig 2.1): (Fig 2.2): STAGE 3 (Fig 3.1): (Fig 3.2): IF 0 < MI ≤ 1.0 IF 1.0 < MI ≤ 2.0 R1 3 R2 3 IF 2.0 < MI ≤ 3.0 R3 3R4 3 No Yes No Yes No Yes IF 0 < RS ≤ 1.0 IF 1.0 < RS ≤ 2.0 S1 4 S2 4 IF 2.0 < RS ≤ 3.0 S3 4S4 4 No Yes No Yes No Yes IF 0 < RL ≤ 0.5 IF 0.5 < RL ≤ 1.0 T1 5 T2 5 IF 1.0 < RL ≤ 2.0 T3 5T4 5 IF 0 < SL ≤ 0.5 IF 0.5 < SL ≤ 1.0 U1 6 U2 6 IF 1.0 < SL ≤ 2.0 U3 6U4 6 No Yes No Yes No Yes Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II, IMECS 2012, March 14 - 16, 2012, Hong Kong ISBN: 978-988-19251-9-0 ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online) IMECS 2012
  • 5. SIGNED GRAPH METHOD FOR OEE TABLE 2 AVAILABILITY RATING BASED ON BREAKDOWN AND SETUP ADJUSTMENT BREAKDOWN (BD) SETUP ADJUSTMENT (SA) AVILABILITY (A) + + + + _ + _ + _ _ _ _ TABLE 3 PERFORMANCE RATING BASED ON IDLING, MINIOR STOPPAGES AND REDUCED SPEED IDLING & MINIOR STOPPAGES (IM) REDUCED SPEED (RS) PERFORMANCE (P) + + + + _ + _ + _ _ _ _ TABLE 4 QUALITY RATING BASED ON DEFECT / REWORK AND STRAT-UP LOSSES DEFECT / REWORK (DR) STRAT-UP LOSSES (SL) QUALITY (Q) + + + + _ + _ + _ _ _ _ TABLE 5 OEE RATING BASED ON AVILABILITY, PERFORMANCE & QULITY RATINGS AVAILABILITY (A) PERFORMANCE (P) QUALITY (Q) OEE + + + ++ + + _ +_ + _ + +_ _ + + +_ + _ _ +-* _ + _ -+ _ _ + -+ _ _ _ -- * Availability is having major impact on the OEE. In most of circumstances, A (+) ranking gives better OEE, in spite of both P (-) & Q (-) ratings TABLE 6 EXPRIMENTAL RESULTS Here we assumed Values for A, P & Q, and for various vales of A, P & Q, OEE was calculated AVAILABILITY (A) PERFORMANCE (P) QUALITY (Q) OEE 95 98 99 92.2 95 98 97 90.3 95 97 94 86.6 90 98 98 86.4 93 96 96 85.7* 88 98 94 81.1 87 91 92 72.8 86 90 90 69.7 Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II, IMECS 2012, March 14 - 16, 2012, Hong Kong ISBN: 978-988-19251-9-0 ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online) IMECS 2012
  • 6. VI. REAL TIME APPLICATION O.E.E. data collection, analysis and reporting provide the principal basis for improving equipment effectiveness by eliminating the major equipment-related losses. The weighted OEE method is presented and the analytical hierarchy process has been applied for setting the weight of all the factors namely BD, SA, MI, RS, RL & SL. The potential of the proposed method can be applied for new as well as existing industries. OEE data very quickly leads to root-cause identification and elimination of losses. Overall Equipment Effectiveness continues to gain acceptance as an effective method to measure production floor performance. Capturing reliable production floor information is critical for producing reliable OEE focused progress of the plant or equipment. It will be optimal tool for plants implementing TPM. This weighted approach and OEE results will be benchmarking tool to gauge manufacturing system, especially maintenance management system. OEE helps manufacturer to improve productivity and get better visibility into their operations and also allow them to take sound management decisions. VII. CONCLUSION AND FUTURE WORKS We may apply this methodology through algorithmic approach to get computational work, the values of OEE categorized through fuzzy logic method on A, P & Q to get optimization. No manual data collection or manual compilation for OEE calculations is the first step in improving both the accuracy of OEE reports as wells as reducing the cost to produce the reports through neural network.The utility of artificial neural network models lies in fact that, they can be used to infer for future purposes. VIII. LIST OF ACRONYMS TPM Total Productive Maintenance OEE Overall Equipment Effectiveness PE Plant Effectiveness A Availability P Performance Rate Q Quality Rate JIPM Japan Institute of Plant Maintenance BD Break-Down SA Setup Adjustment MI Minor / Idling stoppages RS Reduced Speed RL Reject / Rework Losses SL Start-up LossesReferences ACKNOWLEDGEMENT The authors would like to thank Dr. Ponnammal Natarajan, Former Director of Research, Anna University, and Chennai, India. Currently Advisor, (Research and Development), Rajalakshmi Engineering College, for her intuitive ideas and fruitful discussions with respect to the paper’s contribution. REFERENCES [1] B. Dal, P. Tugwell and R. Greatbanks (2000), “Overall equipment effectiveness as a measure of operational improvement”, International Journal of Operations & Production Management, vol. 20, no. 12, pp. 1488–1520. [2] Bin Yu, Munindar P.Singh, An Evidential model for distributed reputation Management, AAMAS'02, July 15- 19,2002, Bologna, Italy. [3] B. Yu and M. P. Singh. Trust and reputation management in a small- world network. In Proceedings of the 4th International Conference on MultiAgent Systems, pages 449-450, 2000. [4] B.Yu and M.P.Singh. A social Mechanism of reputation management in electronic communities. In proceedings of the 4th International Workshop on Cooperative Information Agents, 2000. [5] F.Harary Addision-Wesley, Reading "Graph Theory", Mass, (1969). [6] K.Thiagarajan, A.Raghunathan, Ponnammal Natarajan, G.Poonkuzhali and Prashant Ranjan (2009), “Weighted Graph Approach for Trust Reputation Management”, World Academy of Science, Engineering and Technology 56 – 2009. [7] Lungberg.O (1998), Mearsument of overall equipment effectiveness as a basic for TPM activities. International Journal of operation. And production management. 18 (5) 495-507. [8] M. Lesshammar (1999)., “Evaluation and improvement of manufacturing performance measurement systems – the role of OEE”, International Journal of Operations and Production Management, vol. 19, no. 1, pp. 55-78. [9] S. Nakajima (1988) “Introduction to TPM”, Productivity Press,Cambridge, MA. [10] S.P.Srinivasan, P.Malliga, K.Thiagarajan, An Algorithmic Graphical approach for Ground level logistics management of Jatropha seed distribution.,Ultra Scientist of Physical Sciences, Vol. 20, No:3,(M)(2008), Page(s): 605-612. [11] Venkatesh, J. (2005), An Introduction to Total Productive Maintenance (TPM), The Plant Maintenance Resource Center, pp 2-3 and 15-27. [12] Wireman, T., 1990. World Class Maintenance Management. Industrial Press, New York. [13] Yamashina, H., 1995. Japanese manufacturing strategy and the role of total productive maintenance. Journal of Quality in Maintenance Engineering 1 (1), 27–38. Proceedings of the International MultiConference of Engineers and Computer Scientists 2012 Vol II, IMECS 2012, March 14 - 16, 2012, Hong Kong ISBN: 978-988-19251-9-0 ISSN: 2078-0958 (Print); ISSN: 2078-0966 (Online) IMECS 2012