Good project management is no longer an option in today’s corporate world.
It is a critical tool to help your company stay on target and accomplish its goals.
In Primavera P6, after installation of server & database, the best practice to create & manager projects which I have come across is explained in this presentation.
It covers aspects such as structuring your projects (OBS, EPS, Resource Structure, WBS, Project Codes, Activity Codes/Cost Accounts , User Defined Fields) and Project Management Process ( what constitutes Planning, Controlling & Managing) .
Lesson 1 Project management process in p6 : Best practice by experience
1. PRIMAVERA P6
PROJECT MANAGEMENT PROCESS
Lesson 1
Best Practice from experience
COPYRIGHT (C) 2014 MYPLANNINGWORLD PTY. LTD. ALL RIGHTS RESERVED 1
2. Where to start, how to follow and what follows
COPYRIGHT (C) 2014 MYPLANNINGWORLD PTY. LTD. ALL RIGHTS RESERVED
2
Good project management is no longer an option
in today’s corporate world.
It is a critical tool to help your company stay on
target and accomplish its goals.
In Primavera P6, after installation of server &
database, the best practice which the presenter
has come across to create & manager projects is
explained in the foregoing chart.
5. COPYRIGHT (C) 2014 MYPLANNINGWORLD PTY. LTD. ALL RIGHTS RESERVED 5
As long as you are clear about the various functionalities of your organisation,
how is it broken down and whether the responsibilities are shared, overlapped or
standalone, you can even have a hybrid OBS for the purpose of managing
projects in P6.
EPS
Enterprise Project Structure can be used in many ways to handle multiple
projects or the different versions of the same project.
Primavera P6 is a very powerful tool to manage multiple projects in one go even
if you are running a single user installation. EPS takes its capabilities to even
more powerful state by allowing it to create & archive projects in the way we
are comfortable with.
The foregoing example just illustrates some of the ways we can use the EPS
functionality of P6.
7. COPYRIGHT (C) 2014 MYPLANNINGWORLD PTY. LTD. ALL RIGHTS RESERVED 7
RESOURCES
Question - How many types of resources are
there in any project?
Answer –Three sir, Manpower, Material &
Machineries
Result – Project failure!
Why?
See next slide
9. COPYRIGHT (C) 2014 MYPLANNINGWORLD PTY. LTD. ALL RIGHTS RESERVED 9
Mis-management or non-availability of
any of the above seven types of
resources can lead to failure of
project(s).
Some high-level thinkers in the
capacity of Project Managers consider
“Motivation” as a transparent resource
and constantly work on it throughout
the duration of the project.
No wonder, they succeed.
14. With this series of free training materials in Primavera P6, we intend to make
viewers aware about the potential of project planning & how it can be
implemented in real life situations.
As people improve their learning & understanding they will become more
aware about right & proper use of Project Management tools & techniques
such as P6.
If you like this material, please post in your comments on ourYouTube Channel,
Facebook Page, LinkedIn, Google orTwitter accounts.
Just tap Myplanningworld Pty. Ltd. or Madhu Barai and you should be able to
find us.
If not please head to www.myplanningworld.com/home
At your service,
Madhu Barai
Founding Director & Owner
Myplanningworld Consultancy Services
http://au.linkedin.com/in/madhubarai
COPYRIGHT (C) 2014 MYPLANNINGWORLD PTY. LTD. ALL RIGHTS RESERVED